Loading..
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Punjab Town and Improvement Trust Act, 1922
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Punjab Town and Improvement Trust Act, 1922
Smart Summary

Summary of National Consumer Disputes Redressal Commission Order

Matter: First Appeal Nos. 995 & 1268 of 2017 (Against Order dated 07.03.2017 in Complaint No. 155/2014, State Commission, Punjab). Date of NCDRC Order: 10 April 2019. Bench: Dr. S.M. Kantikar (Presiding Member) and Mr. Dinesh Singh (Member).

Factual and Procedural Background

The complainant, Pooja Garg, was allotted a residential plot by the Jalandhar Improvement Trust in a development scheme advertised on 08.08.2011. The allotment letter dated 23.12.2011 required payment of specified sums (including a condition-precedent deposit of Rs. 9,31,700/- within 30 days) and execution of an agreement to sale within 30 days. The complainant paid earnest money and multiple subsequent instalments, totaling Rs. 38,99,638/- (close to 88% of the total plot cost of Rs. 44,37,950/-).

Litigation concerning acquisition of part of the project land (32 acres out of 94.97 acres) was pending in the High Court from 23.02.2011, and the High Court later granted an interim order (26.09.2012) staying dispossession of the landowners. The Improvement Trust did not execute the agreement to sale within the 30-day period despite receiving the requisite deposit and continued to take further instalments. Possession of the fully developed plot was not delivered by the assured date of 22.07.2014.

The complainant filed Consumer Complaint No. 155 of 2014 in the State Commission on 18.09.2014 alleging deficiency in service and unfair trade practice and sought refund of deposits with interest, compensation and costs. The State Commission allowed the complaint by order dated 07.03.2017 directing refund of Rs. 38,99,638/- with 9% interest from the date of filing of the complaint, payment of Rs. 3,00,000/- as compensation, and Rs. 20,000/- as costs (para 16 of the State Commission's order).

Two appeals arose from that order: F.A. No. 995/2017 filed by the Jalandhar Improvement Trust seeking to set aside the State Commission's order, and F.A. No. 1268/2017 filed by Pooja Garg seeking enhancement of the rate of interest. The NCDRC heard both sides, reviewed the record, and on 07.02.2019 passed an interim order partially modifying the State Commission's order and reserved a reasoned judgment, with execution stayed until pronouncement of reasons. The reasoned judgment was delivered on 10.04.2019.

Legal Issues Presented

  1. Whether the Jalandhar Improvement Trust's conduct in advertising and allotting a plot that was situated in land under pending litigation, retaining earnest money and further deposits while failing to execute the agreement to sale and to deliver possession within the assured period, constituted deficiency in service and unfair trade practice under the Consumer Protection Act, 1986.
  2. Whether the relief awarded by the State Commission (refund of deposited amount with interest, compensation and costs) should be maintained, modified or upset — specifically, whether the rate of interest on refund should be altered (complainant seeking enhancement; trust seeking to set aside the order).

Arguments of the Parties

Complainant (Pooja Garg) — Contentions

  • She paid Rs. 38,99,638/- (including condition-precedent deposit of Rs. 9,31,700/-) in respect of an allotted plot but the Improvement Trust failed to execute the agreement to sale within the stipulated 30 days and failed to deliver possession of a fully developed plot within the stipulated 2½ years period.
  • The Improvement Trust's failure amounted to deficiency in service and unfair trade practice; she sought refund of deposited amount with interest, compensation and costs.

Jalandhar Improvement Trust — Contentions

  • The complainant failed to make instalment payments in time (contention of the Trust).
  • Part of the land where the subject plot was situated was subject to High Court litigation; the High Court granted stay on dispossession of the landowners, which prevented the Trust from delivering possession or lawfully executing the agreement in respect of that plot.
  • The Trust later allotted an alternative plot to the complainant and therefore the complainant was not entitled to refund, compensation or costs.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Archit Gupta v. Jalandhar Improvement Trust and another Referenced as a prior consumer matter in which similar relief was granted; used as guiding authority in the State Commission's decision. The State Commission's allowance of the complaint referred to this earlier decision (para 16). The NCDRC noted that "In view of the discussion held in Consumer Complaint No. 88 of 2015 (Archit Gupta v. Jalandhar Improvement Trust and another), this complaint is also allowed" and proceeded to affirm relief with specified modifications.

Court's Reasoning and Analysis

The Commission's analysis was structured around a chronological reconstruction and legal appraisal of the conduct of the Improvement Trust in light of the transactions and the pending High Court litigation. The key steps in the reasoning were:

  1. Chronology established that the High Court litigation concerning part of the project land (32 acres) was filed on 23.02.2011 and that the Trust advertised the entire project (94.97 acres) for allotment on 08.08.2011 without informing the public that a portion was under litigation (paras 9(i)–(iv), 11(i)–(v)).
  2. The complainant duly deposited the condition-precedent amount of Rs. 9,31,700/- within 30 days (19.01.2012), followed by further instalments amounting to a total deposit of Rs. 38,99,638/-. Despite this, the agreement to sale was not executed within the stipulated 30-day period and possession was not delivered by the assured date of 22.07.2014 (paras 7(ii), 9(iii)–(iv), 11(vi)–(xi)).
  3. The Trust continued to accept subsequent instalments during the pendency of the litigation and interim stay (para 11(viii)–(ix)), demonstrating that it retained consumer funds while being unable lawfully to execute the contract or hand over possession.
  4. The Trust's defence — that the complainant failed to present for execution or that it was constrained by the stay — was addressed: the Commission observed that once the complainant had deposited the condition-precedent sum, it was unreasonable to assert she failed to present herself, and that in any event the Trust could not lawfully have executed the agreement or delivered possession during the pendency of litigation and interim stay (para 11(ix)–(xii)).
  5. The Commission found that the Trust's conduct in advertising and allocating plots without disclosing litigation, retaining earnest money and subsequent deposits, taking belated and arbitrary steps to offer an alternative plot only after long delay, and failing to execute agreements and deliver possession constituted (a) deficiency in service under section 2(1)(g) & (o) and (b) deceptive and unfair acts within the meaning of section 2(1)(r) of the Consumer Protection Act, 1986 (paras 15–16, 19).
  6. The complainant was deemed to have two available remedies — to wait for delivery of the originally allotted plot (or accept alternative plot) and additionally claim compensation for delay, or to opt for refund of deposits with interest, compensation and costs. The complainant chose refund and compensation (paras 17–18).
  7. As to the rate of interest on refund, the Commission emphasized objective, non-arbitrary criteria: it adopted the rate applicable to house building loans in a scheduled nationalized bank (State Bank of India) for the corresponding period, using the higher rate if floating/variable rates existed (paras 21, 140–141). This replaced the State Commission's simple 9% interest direction.
  8. The Commission retained the lumpsum compensation (Rs. 3,00,000/-) and cost (Rs. 20,000/-) as awarded by the State Commission, finding no reason to interfere (paras 22–23, 142).
  9. Remedial directions included refund with interest computed as above, payment of compensation and costs within four weeks of pronouncement of the reasoned judgment, and a warning that delay in compliance would attract higher/penal interest and additional compensation/costs to be determined on further application (paras 25, 143–145).
  10. The Commission also recorded a cautionary admonition to the Improvement Trust and its chief executive for systemic flaws and directed that para 27 be brought to the notice of the appropriate state government secretary for administrative follow-up (paras 27–28).

Holding and Implications

Primary Ruling: The NCDRC found that the Jalandhar Improvement Trust was guilty of deficiency in service and unfair trade practice in the allotment and handling of the complainant's plot and funds, and it upheld the substantive relief in favor of the complainant while partially modifying the State Commission's order as to the rate of interest and procedural directions.

Key consequences and directions:

  • The principal amount of Rs. 38,99,638/- deposited by the complainant shall be refunded with interest from the respective dates of deposit until realization. The rate of interest to be applied shall be the house-building loan rate of a scheduled nationalized bank (State Bank of India) for the corresponding periods; where floating/varying/different rates applied, the higher rate is to be used for computation (paras 140–141).
  • In addition, compensation of Rs. 3,00,000/- (for loss and injury, harassment, hardship, uncertainty and helplessness) and costs of litigation of Rs. 20,000/- as awarded by the State Commission shall remain unchanged (para 142).
  • All payments are to be made within four weeks from the date of pronouncement of the reasoned judgment (para 143). Failure to comply timely will attract higher/penal interest and other compensation/costs to be determined by the Commission if required (paras 144–145).
  • The State Commission is directed to undertake execution in accordance with law after expiry of the four-week period (para 26), and a copy of this Order is to be sent to the State Commission within ten days (para 29).
  • The Commission issued a stern advisory to the Improvement Trust and its chief executive regarding systemic flaws and directed administrative notification to the state govt. secretary responsible for the Trust (paras 27–28).

No broader precedent was held beyond application of consumer law to the facts; the decision affirmed refund with interest computed by reference to an objective bank lending rate, upheld lumpsum compensation and costs, and provided enforcement and administrative follow-up directions.

    Jalandhar Improvement Trust And Another Through Its Chairman (S) v. Pooja Garg (S).

    NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

    NEW DELHI

    FIRST APPEAL NO. 995 OF 2017

    (Against the Order dated 07/03/2017 in Complaint No. 155/2014 of the State Commission Punjab)

    1. JALANDHAR IMPROVEMENT TRUST & ANR.

    THROUGH ITS CHAIRMAN,MODEL TOWN

    ROAD,JALANDHAR CITY

    JALANDHRA CITY

    PUNJAB

    2. JALANDHAR IMPROVEMENT TRUST,

    THROUGH ITS CHAIRMAN,JALANDHAR,

    JALANDGAR

    PUNJAB ...........Appellant(s) Versus

    1. POOJA GARG

    W/O SHRI VIJAY GARG,C/O,M/S MOHAN LAL TARSEM

    CHAND,KARYANA MERCHANT,DHURI

    GATE,SANGRUR ...........Respondent(s)

    FIRST APPEAL NO. 1268 OF 2017

    (Against the Order dated 07/03/2017 in Complaint No. 155/2014 of the State Commission Punjab)

    WITH

    IA/9718/2017(Condonation of delay)

    1. POOJA GARG

    W/O. SH. VIJAY GARG, C/O. M/S. MOHAN LAL TARSEM

    CHAND KARYANA MARCHANT DHURI GATE

    SANGRUR

    PUNJAB ...........Appellant(s) Versus

    1. JALANDHAR IMPROVEMENT TRUST & ANR.

    THROUGH ITS EXECUTIVE OFFICER (RESIDENTIAL

    PLOT IN SURYA ENCLAVE ENCLAVE EXTENSION)

    JALANDHAR

    2. EXECUTIVE OFFICER

    JALANDHAR IMPROVEMENT TRUST

    JALANDHAR

    PUNJAB ...........Respondent(s)

    BEFORE:

    HON'BLE MR. DR. S.M. KANTIKAR,PRESIDING MEMBER HON'BLE MR. DINESH SINGH,MEMBER

    For the Appellant : For Pooja Garg : Mr. Karan Dewan, Advocate Mr. Sanjeev Goyal, Advocate

    For the Respondent : For Jalandhar Improvement : Mr. Dharam Vir Sharma, Sr. Advocate

    1

    with Trust & Anr. Ms. Madhu Bala Sandhu, Advocate Mr. Tushar Sharma, Advocate

    Dated : 10 Apr 2019

    ORDER

    HON'BLE MR. DINESH SINGH, MEMBER

    1. The matter relates to 2 f. a. s filed apropos the Order dated 07.03.2017 of the State Commission.

    2. The State Commission vide its Order dated 07.03.2017 had allowed the complaint:

    16. In view of the discussion held in Consumer Complaint No. 88 of 2015 (Archit Gupta v. Jalandhar Improvement Trust and another), this complaint is also allowed and following directions are issued to the opposite parties:-

    i) to refund the sum of Rs.38,99,638/-, along with interest at the rate of 9% per annum from the date of filing of the complaint till the date of payment;

    ii) to pay Rs.3,00,000/-, as compensation; and

    iii) to pay Rs. 20,000/-, as costs, out of which Rs.10,000/- shall be deposited by the opposite parties in the 'Consumer Legal Aid Account' of this Commission and the remaining Rs. 10,000/- shall be paid to the complainant. (para 16 of the State Commission's Order)

    3. F.A. no. 995 of 2017 has been filed by the Jalandhar Improvement Trust (improvement trust) for setting-aside the Order dated 07.03.2017 of the State Commission. F.A. no. 1268 of 2017 has been filed by one Pooja Garg (complainant) for enhancement of rate of interest on the amount deposited by her with the improvement trust.

    4. We heard the learned counsels for the improvement trust and for the complainant, and perused the material on record.

    5. Brief facts, shorn of unnecessary detail, are that the complainant was allotted a plot in a development scheme of the improvement trust. The complainant had deposited Rs. 38,99,638/- (against the total cost of Rs. 44,37,950/-) with the improvement trust. The sum and substance of the complainant's contention was that the improvement trust was deficient and deceptive & unfair in performing its duties as it failed to duly execute the agreement to sale and to duly deliver possession of the fully developed subject plot within the respective stipulated time-frames. The complainant filed a complaint before the State Commission alleging deficiency in service and unfair trade practice on the part of the improvement trust and praying for refund of her deposited amount with interest and compensation and cost of litigation.

    2

    The sum and substance of the improvement trust's contention was that the complainant failed to make the payment of the instalments in time. Hon'ble High Court granted stay on dispossession of the land owners with respect to part of the land wherein the subject plot was situated. The improvement trust subsequently allotted an alternative plot to the complainant. The complainant is not entitled for refund of her deposited amount or compensation or cost of litigation.

    6. The f. a. no. 995 of 2017 filed by the improvement trust (Jalandhar Improvement Trust & Anr. vs. Pooja Garg) was within limitation. The delay of 18 days in filing the cross-appeal by the complainant [f. a. no. 1268 of 2017 (Pooja Garg vs. Jalandhar Improvement Trust & Anr.)] was overlooked.

    7. On 07.02.2019, after hearing arguments of both sides and perusing the material on record,

    we passed the following Order:

    Dated: 07.02.2019

    ORDER

    Heard the learned senior counsel for the Improvement Trust and the learned counsel for the complainant, and perused the material on record. The impugned Order of the State Commission is partially modified as below:

    The principal amount (total Rs. 38,99,638/-) deposited by the complainant with the Improvement Trust shall be refunded with interest from the respective date / s of deposit till the date / s of realization. The rate of interest shall be the rate for house building loan in the corresponding period of a scheduled nationalized bank (take, State Bank of India). If 'floating'/varying/different rates of interest were prescribed in the corresponding period, the higher rate shall be taken for this instant computation.

    In addition, compensation for loss and injury, harassment and difficulty, uncertainty and helplessness, shall remain Rs. 3,00,000/-, and cost of litigation shall remain Rs. 20,000/- (as awarded by the State Commission).

    All payments shall be made within four weeks of the date of pronouncement of the reasoned judgment.

    Failure in timely compliance shall attract higher/penal interest and other compensation/costs (which shall be determined by this Commission in the facts and specificities of that contingency if it so arises).

    Reasoned judgment to follow.

    Till the pronouncement of the reasoned judgment execution proceedings shall remain stayed.

    3

    We are giving our reasons hereinafter.

    8. The State Commission had allowed the complaint vide its impugned Order dated 07.03.2017. The State Commission had heard both sides, appraised the evidence, and passed a reasoned Order. In addition to deficiency in service, the State Commission had also given clear findings of unfair trade practice.

    9. The relevant chronology, material to adjudicate this matter, is as below:

    (i) Acquisition of land under the Punjab Town and Improvement Trust Act, 1922 was undertaken by the improvement trust for implementation of its subject development scheme. The land acquisition proceedings with respect to a part of the project land (32 acres) was challenged in Hon'ble High Court on 23.02.2011. Subsequently Hon'ble High Court vide its order dated 26.09.2012 granted stay on dispossession of the land owners. (Declaration of award was not stayed.) Award for acquisition of land for the total area of 94.97 acre was passed on 31.05.2011. Advertisement for booking freehold residential plots in the said development scheme of the improvement trust on the total area of 94.97 acre of the project land was issued on 08.08.2011. The complainant applied for allotment of a plot and deposited earnest money (Rs. 4,25,000/-) on 05.09.2011. The complainant was allotted the subject plot in the development scheme vide its letter dated 23.12.2011. The subject plot was situated in the part of the land (32 acres) that was in litigation before Hon'ble High Court and on which Hon'ble High Court subsequently granted stay on dispossession of the land owners. As per the terms and conditions of the allotment, the complainant had to deposit 1/4thprice of the subject plot plus cess charges and site plan and agreement fee & photograph fee (Rs. 9,31,700/-) within 30 days and an agreement to sale was to be then executed between the improvement trust and the complainant within the said 30 days. Clause 5, clause 6 and clause 7 of the allotment letter dated 23.12.2011 read as below:

    5) Agreement to sale shall be executed within 30 days from the issuance of this letter on the stamp paper of Rs. 500/- in the name of Chairman Improvement Trust Jalandhar and shall come to the office of Trust along with two witnesses for the computerized photograph.

    6) If you did not complete the conditions as mentioned above within 30 days from the issuance of allotment letter of the plot under subject and if you did not deposit 1/4 th amount of the plot in time, then the Trust the full right to forfeit the plot without issuance of any letter and the initial amount deposited by the allottee shall deemed to be forfeited.

    7) Development facilities under the scheme shall be completed within the period of installments time of two and half years and you can take the possession after executing the agreement to sell with the trust.

    (as per the translated copy furnished by the improvement trust)

    (ii) The complainant deposited the requisite Rs. 9,31,700/- with the improvement trust on 19.01.2012 i.e. within 30 days from the issuance of the allotment letter dated 23.12.2011. Agreement to sale was not executed by the improvement trust within the stipulated period of 30 days.

    4

    (iii) The complainant subsequently deposited Rs. 7,01,250/-, Rs. 7,01,250/-, Rs. 3,34,000/- and Rs. 8,06,438/- with the improvement trust on 04.07.2012, 17.12.2012, 14.01.2013 and 03.06.2013. In all, the complainant deposited Rs. 4,25,000/- (earnest money) + Rs. 9,31,700/- (deposited within 30 days of allotment) + Rs. 25,42,938/- (subsequent instalments) totalling Rs. 38,99,638/- against the total cost of Rs. 44,37,950/- of the subject plot, that is, the complainant deposited close to 88% of the total cost. The agreement to sale, which was to be executed within 30 days of the allotment (23.12.2011), i.e. by 22.01.2012, on the complainant depositing an amount of Rs. 9,31,700/- (which she deposited on 19.01.2012), was not executed at all, and moreso not executed even after the complainant had further deposited an amount of Rs. 25,42,938/- spread between 04.07.2012 to 03.06.2013.

    (iv) As per the terms and conditions of the allotment, possession of the subject plot was to be delivered by the improvement trust within 2 ½ years (co-terminus with the time-frame for payment of the subsequent instalments after the making of the deposit of the Rs. 9,31,700/- which was the condition precedent for execution of the agreement to sale). The possession had to be delivered after 30 days plus 2 ½ years, that is, on or before 22.07.2014. The possession of the duly and fully developed subject plot was not delivered within the assured period.

    (v) A consumer complaint no. 155 of 2014 was filed by the complainant before the State Commission on 18.09.2014, that is, after about 32 months of the stipulated date of execution of the agreement to sale (22.01.2012) and after about 2 months of the assured date of delivery of possession of the subject plot (22.07.2014).

    (vi) The improvement trust subsequently expressed its inability to deliver possession of the subject plot to the complainant in view of the stay on dispossession granted by Hon'ble High Court and allotted an alternative plot to the complainant vide its letter dated 12.06.2015:

    Office of Jalandhar Improvement Trust, Jalandhar

    To

    Smt. Pooja Garg wife of Sh. Vijay Garg,

    C/o M/s Mohan Lal Tarsem Chand Karyana Merchant

    Dhuri Gate, Sangrur.

    Letter No. JIT/1183 Dated: 12.06.2015

    Subject: Regarding Plot No. 159-D, Development Scheme 94.97 acres. You are informed vide this letter that the place / Khasra where your plot No. 159-D is situated is under stay granted from the Hon'ble Punjab and Haryana High Court and therefore, you cannot be given possession of the same. Therefore, you are allotted plot No. 212-D in place of Plot No. 159-D on the same terms and conditions as given in the allotment letter. The possession of the same is with the Trust. Sd/-

    5

    Executive Engineer, Jalandhar Improvement Trust, Jalandhar (as per the translated copy furnished by the improvement trust)

    (vii) The said letter dated 12.06.2015 was issued after about 41 months of the stipulated date of execution of the agreement to sale (22.01.2012), and after about 11 months of the assured date of possession (22.07.2014), and after about 9 months of the complaint being filed before the State Commission (18.09.2014).

    (viii) The concerned writ petitions were dismissed by Hon'ble High Court vide its judgment dated 22.12.2015.

    (ix) The improvement trust issued a general public notice for allotment of alternative plots to all affected on 20.01.2016.

    10. We note the chronology:

    Land acquisition proceedings for the subject development scheme initiated for total area of 94.97 acre 2010
    Date of filing of writ petitions with respect to part of the land in the development scheme (i.e. w.r.t. 32 acres out of the total 94.97 acres) wherein the subject plot was also situated 23.02.2011
    Date of land acquisition award 31.05.2011
    Date of general public advertisement / notice for booking of plots 08.08.2011
    Date of application with earnest money made by the complainant to the improvement trust 05.09.2011
    Date of issuance of allotment letter by the improvement trust to the complainant 23.12.2011
    Date of interim order of Hon’ble High Court for stay on dispossession of the land owners 26.09.2012
    Dates of deposits by the complainant with the improvement trust 05.09.2011 (earnest money);

    6

    (total deposited = Rs. 38,99,638/-; total cost = Rs. 44,37,950/-) 19.01.2012 (deposit as

    condition

    precedent to

    agreement to sale);

    04.07.2012;

    17.12.2012;

    14.01.2013;

    03.06.2013

    (subsequent installments)

    Assured date of execution of agreement to sale 22.01.2012
    Date of expiry of 2 ½ years after the 30 days for execution of agreement to sale for delivery of possession of duly and fully developed subject plot to the complainant 22.07.2014
    Date of filing of complaint in the State Commission (c.c. no. 155 of 2014) 18.09.2014
    Date of allotment of alternative plot 12.06.2015
    Date of dismissal of writ petitions 22.12.2015
    Date of general public notice for allotment of alternative plots 20.01.2016
    Date of State Commission’s impugned Order 07.03.2017

    11. We specifically note the following:

    (i) The litigation apropos land acquisition went before Hon'ble High Court on 23.02.2011.

    (ii) Without taking into consideration (without the requisite due administrative prudence and without the requisite due application of mind and without the requisite due diligence), and albeit ignoring, the pending litigation before Hon'ble High Court, the total area (94.97 acres), inclusive of the part area (32 acres) under litigation before Hon'ble High Court, was advertised on

    7

    08.08.2011 to the general public for making application and depositing earnest money for allotment of plots.

    (iii) It was not informed in the advertisement dated 08.08.2011 to the general public that part of the project land (32 acres) was under litigation before Hon'ble High Court.

    (iv) The part area under litigation was included in the said advertisement, without any distinction being made between the land under litigation and the land not under litigation.

    (v) The complainant was allotted the subject plot on 23.12.2011 in that part of the project land that was under litigation since 23.02.2011 and on which Hon'ble High Court then also subsequently passed an interim order on 26.09.2012 for stay on dispossession of the land owners.

    (vi) The complainant dutifully made deposit of the requisite amount of Rs. 9,31,700/- with the improvement trust on 19.01.2012 towards 1/4thprice of the subject plot plus cess charges and site plan and agreement fee & photograph fee, within the stipulated period of 30 days, which was the condition precedent to execution of the agreement to sale.

    (vii) The agreement to sale was not executed by the improvement trust within the stipulated period of 30 days.

    (viii) The improvement trust continued to take the subsequent installments from the complainant during the pendency of the litigation before Hon'ble High Court and then also during the Hon'ble High Court's interim order being passed and being in place.

    (ix) As already said, the improvement trust did not execute the agreement to sale within the stipulated period of 30 days as per the terms and conditions in the allotment letter after receiving the requisite amount of Rs. 9,31,700/- from the complainant within the stipulated time. The fact of the matter is that the improvement trust could not execute the agreement to sale having regard to the pending litigation in Hon'ble High Court and then, specifically, having regard to the subsequent interim order of stay on dispossession (such latter act would have been unlawful and contemptuous). The improvement trust's defence that the complainant did not come forth to execute the agreement to sale fails on two points, one, that when the complainant had duly made deposit of the requisite Rs. 9,31,700/- that was the condition precedent to execution of the agreement to sale, it belies any reason or logic that she did not come forth for execution of the document, and, two, the improvement trust was not in a position to execute any agreement to sale etc. on the subject plot first in the light of the pending litigation and then, specifically, in the light of the subsequent interim order of Hon'ble High Court.

    (x) Possession of the duly and fully developed subject plot was not delivered to the complainant by 22.07.2014 i.e. the stipulated 2 ½ year period after the initial 30 day period for execution of the agreement to sale. The fact of the matter here too is that the improvement trust could not have delivered possession because till the expiry of the said 2 ½ years after 30 days the litigation was still pending and Hon'ble High Court's interim order of stay on dispossession had also come in place. Neither could the improvement trust have been able to in any manner enter into and develop the subject plot (the land owners were in possession, not the improvement trust). On the plain facta of the litigation pending before Hon'ble High Court, and then of Hon'ble High Court's interim order also being passed and coming in place, the whole defence of

    8

    the improvement trust fails on reason of, one, it was not lawfully feasible to develop the subject plot in 2 ½ years after 30 days, two, it was not lawfully feasible to hand over possession in 2 ½ years after 30 days.

    (xi) The complainant went to the State Commission on 18.09.2014 i.e. after about 32 months of the stipulated date for execution of the agreement to sale (22.01.2012) and after about 2 months of the assured date of delivery of possession (22.07.2014).

    (xii) During the pendency of the writ petitions before Hon'ble High Court and during the pendency of the proceedings before the State Commission, the improvement trust allotted an alternative plot to the complainant vide its letter dated 12.06.2015. This was, one, after about 41 months of the stipulated date of execution of the agreement to sale, two, after about 11 months of the assured date of delivery of possession, three, arbitrary and one-sided, four, heavily belated (on the face of it itself).

    (xiii) The complainant had deposited Rs. 38,99,638/-, which was close to 88% of the total cost of Rs. 44,37,950/-, and there is nothing on record to show that she was not ready and willing to deposit the balance cost with interest or penal interest if any, provided that the subject plot was duly and fully developed within the assured period and was not unreasonably delayed (reasonable delay here would connote such delay as a reasonable man of normal intelligence would not normally agitate).

    12. The material facts and consequences relating to availability of land / litigation apropos acquisition of land were not brought to the notice of the general public (including the complainant) at the time of advertising the subject development scheme. In the absence of the facts and the consequences thereof being specifically and explicitly brought to their notice, the buyers - consumers would reasonably (and correctly) understand that all aspects of project planning, execution and completion, inclusive of availability of land, at the due time, are the responsibility of the improvement trust and have been / are being / would be duly taken care of by the improvement trust, without cost or time overruns.

    13. The improvement trust was required and expected to have the due pragmatic and realistic assessment and preparation of the project planning, execution and completion. It was the prime responsibility of the improvement trust to ensure that it was in a position to deliver the possession of subject plot / s to the buyer / s. Planning, execution and completion were its responsibility, and not of the consumer.

    (Normal) impediments or problems that arise in planning, execution and completion were its responsibility, and not of the consumer.

    Specifically, availability of land, at the due time, being a fundamental basic requirement of a residential project, were decidedly the improvement trust's primary responsibility, and not of the consumer.

    Cost or Time overruns were its responsibility, not of the consumer.

    14. We may make it explicit that mere allotting an alternative plot (arbitrarily, one-sidedly, belatedly) vide letter dated 12.06.2015 does not in any manner dilute the improvement trust's

    9

    responsibilities towards project planning, execution and completion, including availability of land, at the due time, without cost or time overruns, and of executing the agreement to sale within the stipulated period, and of delivering the duly and fully developed subject plot within the assured period, without unreasonable delay, which responsibilities qua the complainant arose on issuance of the allotment letter and retaining the earnest money (Rs. 4,25,000/-) and taking the payment of the Rs. 9,31,700/- for execution of the agreement to sale of the subject plot.

    15. Not executing the agreement to sale on the complainant making good her part of depositing the amount of Rs.9,31,700/- towards 1/4thprice of the subject plot plus cess charges and site plan and agreement fee & photograph fee within the stipulated period of 30 days and not delivering possession of the subject plot within the assured period of 2 ½ years after the 30 day period for execution of the agreement to sale and unreasonable delay beyond the assured date of delivery of possession constitute deficiency in service within the meaning of section 2 (1)(g) and

    (o) of the Act 1986.

    16. Advertising allotment of plot / s on land under litigation before Hon'ble High Court and not disclosing this fact upfront in its advertisement to the general public and (then) not being in a position to (lawfully) take possession and develop the land and (still) retaining the earnest money of Rs. 4,25,000/-, taking deposit of Rs. 9,31,700/- re the condition precedent to execution of the agreement to sale, taking further deposits of Rs. 25,42,938/- (in instalments) and (then) arbitrarily, one-sidedly and belatedly allotting an alternative plot after about 41 months of the stipulated date of execution of the agreement to sale and after about 11 months of the assured date of delivery of possession are deceptive and unfair acts and constitute unfair trade practice within the meaning of section 2(1)(r) of the Act 1986.

    17. Two rights accrued to the consumer - complainant:

    one: the option to either wait for the subject plot to be delivered (if and when the litigation ended in favour of the improvement trust), or to take possession of an alternative plot offered by the improvement trust at her considered wisdom and discretion, and in addition seek just and equitable compensation under the Act 1986 for unreasonable delay and loss and injury. two: to claim refund of the principal amount, with interest thereon, lumpsum compensation and cost of litigation.

    That is, the consumer - complainant had both options available, one, to obtain possession of the subject plot or alternative plot at her considered wisdom and discretion if and when offered by the improvement trust and to in addition seek just and equitable compensation under the Act 1986 for unreasonable delay in possession and the loss and injury, and, two, to opt for a fair amount from the improvement trust comprising refund of the deposited amount, with interest thereon, lumpsum compensation and cost of litigation.

    18. It is seen that of the two options available to the consumer - complainant, she opted for a fair amount from the improvement trust. The said amount has to be equitable and just.

    19. To sum up, we find, both, deficiency in service within the meaning of section 2(1)(g) & (o), and unfair trade practice within the meaning of section 2(1)(r), to be well and truly evident on the part of the improvement trust.

    10

    In remedy, it is just, equitable, appropriate and necessary to direct the improvement trust to refund the principal amount deposited by the complainant with the improvement trust with interest as well as to pay lumpsum compensation and cost of litigation to the complainant.

    20. In so far as refund of the amount deposited with the improvement trust is concerned, there can be no two opinions. The refund in full has necessarily to be made by the improvement trust to the complainant.

    21. In respect of the interest on the amount deposited, it is always desirable and preferable, to the extent feasible and appropriate in the facts and specificities of a case, that some objective logical criteria be identified and adopted to determine an apt rate of interest. The rate of interest cannot be arbitrary or whimsical, some reasonable and acceptable rationale has to be evident, subjectivity has to be minimized.

    We feel it appropriate that, considering that the subject plot in question is a residential plot, in a residential development scheme, the rate of interest for house building loan for the corresponding period in a scheduled nationalized bank (take, State Bank of India) would be appropriate and logical, and, if 'floating' / varying / different rates of interest were / are prescribed, the higher rate of interest should be taken for this instant computation.

    22. The lumpsum compensation in addition for loss and injury, for mental agony and physical harassment, hardship and difficulty, uncertainty and helplessness, can be neither meagre nor exorbitant, it has to be just and equitable, commensurate with the loss and injury. We feel the lumpsum compensation awarded by the State Commission does not require interference by this Commission in the given facts and specificities of the case.

    23. In respect of cost of litigation, too, just and equitable cost is necessary (this by its very nature, needs no elaboration).

    We feel that the cost of litigation awarded by the State Commission needs no interference by this Commission.

    24. We may also note that once the amount awarded for deficiency in service and unfair trade practice is adjudicated and determined, the onus is on the improvement trust to be prompt and dutiful in making the necessary payments within the stipulated time. Creating yet further harassment, difficulty and helplessness for the ordinary simple consumer by delaying payments or making reduced payments etc. (if the adjudication is not stayed or quashed or modified by a higher authority / court) will be an unacceptable situation, to be viewed seriously - the harassment, difficulty and helplessness of the consumer should end promptly and fully, the chapter should close. Therefore, if the improvement trust delays the adjudicated payments beyond the time stipulated, it would and should attract higher / penal interest and other compensation / costs, which will be determined by this Commission if the contingency so arises.

    25. We firm-up the award as below:

    (i) The principal amount (total Rs. 38,99,638/-) deposited by the complainant with the improvement trust shall be refunded with interest from the respective date / s of deposit till the date / s of realization. The rate of interest shall be the rate for house building loan in the

    11

    corresponding period of a scheduled nationalized bank (take, State Bank of India). If 'floating' / varying / different rates of interest were prescribed in the corresponding period, the higher rate shall be taken for this instant computation.

    (ii) In addition, compensation for loss and injury, harassment and difficulty, uncertainty and helplessness, shall remain Rs. 3,00,000/-, and cost of litigation shall remain Rs. 20,000/- (as awarded by the State Commission).

    All payments shall be made within four weeks of the date of pronouncement of the reasoned judgment.

    Failure in timely compliance shall attract higher / penal interest and other compensation / costs (which shall be determined by this Commission in the facts and specificities of that contingency if it so arises).

    26. Needless to add that the State Commission shall undertake execution as per the law after expiry of the four weeks' period from the date of pronouncement of this Order.

    27. Furthermore, specifically for indulging in unfair trade practice, we put the improvement trust through its chief executive to stern advice of caution. We are consciously refraining from imposing cost on the improvement trust / its chief executive / its functionaries on this count (i.e. re unfair trade practice) considering that the improvement trust is a government organization intended for overall public good. We would but advise the senior officer / s in the state government responsible for the functioning of the improvement trust to take note of the fundamental flaws in its functioning as brought out in this judgment and to take the necessary appropriate steps for systemic improvements for future.

    28. We request learned senior counsel for the improvement trust, and we direct the chief executive of the improvement trust, to bring para 27 of this Order to the notice of the secretary- in-charge in the state government (civil secretariat) charged with the responsibility of the functioning of the improvement trust.

    29. A copy of this Order may be sent to the State Commission by the Registry within ten days in reference to para 26.

    ......................

    DR. S.M. KANTIKAR

    PRESIDING MEMBER

    ......................

    DINESH SINGH

    MEMBER