Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Attorney(S)
Acts
  • section 23 read with section 51A of the Indian Electricity Act, 1910
  • Recovery wp179-11 (corrected).doc 14 of Rebate Benefits) Act, 2002
  • COMPANIES ACT 1956
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Attorney(S)
Acts
  • section 23 read with section 51A of the Indian Electricity Act, 1910
  • Recovery wp179-11 (corrected).doc 14 of Rebate Benefits) Act, 2002
  • COMPANIES ACT 1956
Smart Summary

Structured Summary of the Provided Opinion

Factual and Procedural Background

The petitioner (a company incorporated under the Companies Act, 1956) operates a factory at Cuncolim Industrial Estate producing HC Ferro Manganese and Silico Manganese. The State Government issued a Notification dated 30 September 1991 providing for a 25% rebate in power tariff for bonafide industrial activities. The petitioner applied for power supply on 26 November 1992 and power supply was made available on 17 November 1993.

The 1991 Notification was rescinded by a subsequent Notification dated 31 March 1995. Guidelines were issued on 12 December 1995 relating to modalities of the rebate. Further Notifications were issued on 15 May 1996 and 1 August 1996. On 31 March 1998 a circular suspended release of the 25% rebate. Writ petitions were filed challenging the circular; the petition filed by the present petitioner was Writ Petition No.241 of 1998. A notification dated 24 July 1998 suspended the 1996 Notifications, and the writs were amended.

A Division Bench disposed of a group of petitions (including that of the petitioner) on 21 January 1999 (G.R.Ispat Ltd v. Chief Electrical Engineer & Ors), directing that the benefit of the 1991 Notification be made applicable to the petitioner from the date of power supply and that the 1995 rescission would not affect entitlement for rebate accrued prior to 1 April 1995.

Later litigation culminated in the challenge to Act VIII of 2002 being negatived by the Supreme Court on 3 May 2010 (Civil Appeal No.4220/2002 - M/s M.R.F. Ltd v. Manohar Parrikar & Ors and connected appeals). Pursuant to these developments the State issued Notification No.120/4/CEE/TECH dated 27 January 2011 concerning manner and time-limit for refund. On 21 February 2011 the Executive Engineer, Electricity Division IV, Margao, Goa issued the demand notice impugned in this petition seeking recovery of Rs.1,08,66,027/- (the differential sum).

The petitioner approached this Court under Article 226 of the Constitution impugning that demand notice. The Chief Electrical Engineer filed an affidavit in reply asserting that the petitioner had claimed rebate for five years from the date of supply by virtue of the 1996 Notifications and that the petitioner had already been given a total rebate of Rs.1,53,09,077/-, leaving a differential of Rs.1,08,66,027/- sought to be recovered under Act VIII of 2002. The petitioner filed a rejoinder reiterating reliance on the 21 January 1999 Division Bench judgment and the guidelines dated 12 December 1995.

Legal Issues Presented

  1. Whether the impugned demand notice dated 21 February 2011 seeking recovery of Rs.1,08,66,027/- is contrary to law and liable to be quashed.
  2. Whether the petitioner was entitled to the 25% rebate under the Notification dated 30 September 1991 from the date of power supply for a period of five years, so as to preclude any obligation to refund amounts claimed in the demand notice.
  3. Whether the Notifications of 15 May 1996 and 1 August 1996 (and related guidelines of 12 December 1995) can be relied upon to show that the 1991 Notification survived rescission, and if those 1996 Notifications are void ab initio whether that affects the petitioner's entitlement.
  4. Whether principles of finality of judgment and res judicata prevent the respondents from relying on judgments in proceedings to which the petitioner was not a party.
  5. Whether the 25% rebate should be computed only with reference to energy charges (as per the guidelines) or include other tariff components (energy charges and demand charges etc.).

Arguments of the Parties

Petitioner's Arguments (Mr. V.B. Nadkarni, senior counsel)

  • The demand notice is contrary to law; the petitioner cannot be called upon to refund any monies because there was no excess rebate or wrongful benefit given to it.
  • If entitled to the 25% rebate under the 1991 Notification from the date of supply, that rebate applies for five years and cannot be taken away midstream by the State.
  • The petitioner is bound by the Division Bench judgment delivered on 21 January 1999 (in the petitioner's own case) and the State cannot rely on judgments in proceedings where the petitioner was not a party.
  • The petitioner relied on the guidelines dated 12 December 1995 (including clauses that the 25% rebate may be worked out with reference to energy charges and adjusted against bills rather than refunded in cash) to support that the rebate was properly applied and billed.
  • Even if there were later changes in tariff rates during the five-year period, the rebate should be computed to give the petitioner the full benefit (including on energy charges and demand charges), not restricted to energy charges alone.

Respondents' Arguments (Chief Electrical Engineer / State; Mr. Kantak, Advocate General)

  • The State's affidavits contend that, in view of the Notifications of 15 May 1996 and 1 August 1996, the petitioner claimed rebate for five years from the date of supply and was entitled to rebate of 25% as per 1988 tariff from the date of supply until 31 March 1995, which amounted to Rs.43,45,050/-, and the petitioner has been given a total rebate of Rs.1,53,09,077/-. The differential sum of Rs.1,08,66,027/- is recoverable under Act VIII of 2002.
  • The respondents relied upon subsequent judgments (including Manohar Parrikar and Alcon Cement decisions) and Act VIII of 2002 to justify the demand and to contend that the petition lacks merit and must be dismissed.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
G.R.Ispat Ltd v. Chief Electrical Engineer & Ors (W.P. No.199/98 and connected matters, judgment dated 21 Jan 1999) The Division Bench directed that the benefit of the 1991 Notification shall be made applicable from the date of power supply and that rescission of 1995 will not affect entitlement for rebate accrued prior to 1 Apr 1995. The petitioner relied on this decision to claim entitlement from supply date. The Court noted the reliance but concluded that later developments (including voiding of the 1996 Notifications) undermined reliance on the rationale sustaining the 1991 Notification.
M/s M.R.F. Ltd v. Manohar Parrikar & Ors (Civil Appeal No.4220/2002 and connected appeals; Supreme Court, order dated 3 May 2010) The Supreme Court negatived the challenge to Act VIII of 2002; the opinion records that the Supreme Court set out circumstances leading to the conclusion that the 1996 Notifications were void ab initio. The Court relied on the Supreme Court's conclusions to hold that, because the 1996 Notifications were void ab initio, the earlier reliance on them to keep the 1991 Notification alive could not stand; this underpins dismissal of the petition.
Manohar Parrikar v. State of Goa & Ors (W.P. No.316/1998, decided 24 Apr 2001) Cited as one of the subsequent judgments in the litigation around rebate and the 1996 Notifications. The Court noted reliance by parties on this decision but explained that, in light of the finding that the 1996 Notifications were void ab initio, those subsequent judgments cannot be used to sustain the 1991 Notification; the Court therefore did not permit reliance on them to aid the petitioner.
Alcon Cement Company Ltd & Anr v. State of Goa & Anr (W.P. No.277/99 and connected matters, decided 24 Apr 2001) Cited by counsel as part of a group of decisions concerning the rebate scheme and its implementation. The opinion records that these decisions were cited but the Court found them not to assist the petitioner once the 1996 Notifications were held void ab initio by higher authority.
Narendra Kumar Maheshwari v. Union of India & Ors, 1990 (Supp) SCC 440 Cited by petitioner’s counsel; the opinion does not set out the particular principle relied upon from this citation. The Court recorded the citation as relied upon by petitioner’s counsel but did not specifically rely on this decision in its reasoning and indicated it was unnecessary to refer to each cited authority.
MRF Ltd, Kottayam v. Asstt. Commissioner (Assessment) Sales Tax & Ors, (2006) 8 SCC 702 Cited by counsel; the opinion does not specify the particular rule extracted from this case. Cited by petitioner’s counsel; the Court did not adopt detailed reliance on it and did not make it part of the ratio of the present judgment.
U.P. Power Corporation Ltd & Anr v. Sant Steels & Alloys (P) Ltd & Ors, (2008) 2 SCC 777 Cited by counsel; specific principle not stated in the opinion. Recorded as relied upon by petitioner’s counsel; the Court stated it was unnecessary to refer to each decision once the principal conclusions were reached.
Tarini Charan Bhattacharjee & Ors v. Kedar Nath Haldar, AIR 1928 Cal 777 Cited by petitioner’s counsel in support of res judicata/finality principles; the opinion notes the citation. The Court observed that reliance on such authorities about res judicata was misplaced on the facts because the application of those principles did not assist the petitioner given the voiding of the 1996 Notifications.
Sarat Chandra Pal v. Barlow & Co, AIR 1928 Cal 782 Cited by counsel; the opinion does not detail the rule taken from this authority. Recorded as cited; the Court did not find it helpful to the petitioner's case on these facts.
State of West Bengal v. Hemant Kumar Bhattacharjee & Ors, AIR 1966 SC 1061 Cited by counsel; the opinion does not specify the exact principle relied upon. Cited but not specifically relied upon in the Court's analysis; the Court focused on the controlling questions of validity of notifications and the Supreme Court's conclusions.
Daryao & Anr v. State of U.P. & Ors, AIR 1961 SC 1457 Cited by counsel; the opinion does not set out the particular proposition taken from it. Listed among citations relied upon by petitioner’s counsel; the Court did not treat these authorities as determinative in view of the dispositive findings regarding the notifications.
Kopargaon S.S.K. Ltd v. State of Maharashtra & Ors, (2009) 3 SCC 273 Cited by counsel; the opinion does not explain the specific principle extracted. Cited; the Court did not adopt a detailed reliance on this decision in its judgment.
Gangai Vinayagar Temple & Ors v. Meenakshi Ammal & Ors, (2009) 9 SCC 757 Cited by counsel; the opinion does not identify the particular rule cited. Cited; the Court did not find these auxiliary authorities necessary to resolve the petition once the key issues were addressed.
M/s Northern India Iron & Steel Co v. State of Haryana, AIR 1976 SC 1100 Cited by counsel; the opinion does not specify the exact proposition relied upon. Cited but not specifically applied; the Court determined the petition on other grounds.
Assistant Commissioner (CT) LTU & Anr v. Amara Raja Batteries Ltd, (2009) 8 SCC 209 Cited by counsel; the opinion does not elaborate the principle taken from it. Recorded among the list of citations but not central to the Court's resolution of the petition.
Commissioner of Income Tax, Bangalore v. Vasudeo V. Dempo, 1993 Supp (1) SCC 612 Cited by counsel; the opinion does not state the specific rule referred to. Cited; the Court did not rely on it in reaching the outcome and indicated many citations were unnecessary to traverse in detail.
Khet Singh v. Union of India, (2002) 4 SCC 380 Cited by counsel; the opinion does not set out the particular proposition relied upon. Included in the list of authorities cited by petitioner’s counsel; the Court did not make it part of its operative reasoning.

Court's Reasoning and Analysis

The Court first observed that the present petition raised the same contentions as companion writ petitions which had been decided in a companion judgment. After examining the petition, the affidavits and all annexures, the Court concluded that the petitioner's case was not different from those of other petitioners and that the submissions advanced were without substance for the reasons recorded in the companion judgments.

Crucially, the Court analysed the sequence of Notifications and judicial decisions. Although this Court (by Division Bench) in the petitioner's earlier proceeding had accepted survival of the 1991 Notification on the basis of the 1996 Notifications and the government guidelines, the Court noted that subsequent judicial pronouncements (including those culminating in the Supreme Court's decision referred to in M/s M.R.F. Ltd v. Manohar Parrikar & Ors) held that the 1996 Notifications were void ab initio. Because the earlier finding of survival of the 1991 Notification had relied on the 1996 Notifications, the invalidation of the 1996 instruments undermined the basis for treating the 1991 Notification as surviving its 1995 rescission.

The Court rejected the petitioner's contention that principles of finality of judgment and res judicata precluded respondents from relying on judgments in cases where the petitioner was not a party. The Court explained that those principles could not assist the petitioner because the legal foundation for survival of the 1991 Notification (i.e., reliance on the 1996 Notifications) had been removed by holding those 1996 Notifications void ab initio; therefore, the law as declared by the higher authority binds the petitioner irrespective of its party status in the other proceedings.

The Court also addressed the petitioner's reliance on the guidelines of 12 December 1995, observing that such guidelines were only administrative directions on implementation and could not revive or sustain Notifications that had been held to be of no legal effect. In short, once the controlling Notifications were held invalid, the guidelines did not avail the petitioner.

For these reasons the Court concluded there was no merit in the writ petition and that the petition had to be dismissed. The Court discharged the Rule but made no order as to costs.

Holding and Implications

Holding: The writ petition is DISMISSED. The Rule is discharged, without any order as to costs.

Implications:

  • The direct effect on the parties is that the petitioner's challenge to the demand notice dated 21 February 2011 (seeking recovery of Rs.1,08,66,027/-) has failed and the Court declined to quash that demand in this petition.
  • The Court relied upon the legal conclusion that the 1996 Notifications were void ab initio (as set out by higher authority), which negated the earlier basis for treating the 1991 Notification as surviving its 1995 rescission. The opinion indicates that, in these circumstances, reliance on administrative guidelines alone cannot sustain rebate entitlement where the underlying statutory instruments have been invalidated.
  • The opinion does not purport to lay down any new legal precedent beyond applying the existing higher-court conclusions to the petitioner’s facts. The Court specifically recorded that many authorities cited were unnecessary to traverse in detail once the dispositive legal position was identified.

This summary is based exclusively on the content of the provided opinion. No information beyond that text has been added.

To access the original judgment, please Sign In or Subscribe.

    M/S. KARTHIK ALLOYS LTD.,REP. BY ITS DIRECTOR MR. A. RAMU v. STATE OF GOA THROUGH ITS SECRETARY (POWER) AND ANR.,

    . Rule. Respondents waive service. By consent Rule made returnable forthwith.

    2 The petitioner by this petition under Article 226 of the wp179-11 (corrected).doc Constitution of India has impugned the demand notice dated 21st February 2011, a copy of which is at Annexure A by which the Executive Engineer, Electricity Division IV, Margao, Goa, is seeking to recover amount of Rs.1,08,66,027/- in the manner set out in the said demand notice.

    3 The petitioner is a company incorporated under the Companies Act, 1956 and had set up its factory at Cuncolim Industrial Estate for manufacture of HC Ferro Maganese and Silico Manganese. It is stated that on 30th September 1991, a Notification was issued by the State Government in exercise of the powers conferred by section 23 read with section 51A of the Indian Electricity Act, 1910 providing for concessional tariffs for power supply to bonafide industrial activities by way of rebate of 25% in the tariffs chargeable. In furtherance of this Notification, the petitioner applied for supply of power to its factory on 26th November 1992. The power supply was made available on 17th November 1993. By a subsequent Notification dated 31st March 1995, the State was pleased to rescind the 1991 Notification. It is submitted that although this scheme of 25% rebate in power tariff wp179-11 (corrected).doc for period of 25 years was introduced in 1991, the modalities of the rebate benefit could not be worked out until 12th December 1995. On this, certain guidelines were issued by Under Secretary (Power), Government of Goa. Reliance is placed on these guidelines and then contended that the two further Notifications, one of 15th May 1996 and 1st August 1996 were issued. On 31st March 1998, the Chief Electrical Engineer issued a circular, whereby release of 25% rebate was suspended with immediate effect. Some writ petitions were filed in this Court challenging the Circular dated 31st March 1998 and one of the writ petitions was filed by the petitioner herein. That was numbered as Writ Petition No.241 of 1998. There was another notification dated 24th July 1998, which suspended with immediate effect, the Notifications of 1996 and, therefore, the writ petition was amended. All petitions including the one filed by the present petitioner came to be heard and disposed off by the Division Bench on 21st January 1999 (G.R.Ispat Ltd Vs. Chief Electrical Engineer & Ors) and the common judgment directs that the benefit of the Notification dated 30th September 1991 shall be made applicable to the present petitioner from the date of power supply. The rescinding wp179-11 (corrected).doc Notification of 1995 will not affect the petitioners entitlement and it would be receiving the rebate benefit as accrued prior to 1st April 1995.

    4 The challenge to the Division Bench judgment and further events which are identical to one noted in judgments in the companion matters, are then referred to and it is urged that the challenge to the Act VIII of 2002 was negatived by the Supreme Court on 3rd May 2010 (Civil Appeal No.4220/2002- M/s.M.R.F Ltd Vs. Manohar Parrikar & Ors and other connected appeals). In pursuance of this judgment of the Honble Supreme Court, the State Government issued a Notification No.120/4/CEE/TECH dated 27th January 2011, notifying the manner and time limit for the refund. Annexure F is a true copy of this Notification. It is in pursuance of this Notification that the impugned demand notice has been issued. That is challenged in the instant petition on several grounds.

    5 Upon the petition being served on the State an affidavit in reply is filed by the Chief Electrical Engineer, Margao, Goa. wp179-11 (corrected).doc While referring to the notifications and the challenge to the Government actions, so also the orders of this Court and the Honble Supreme Court, it is contended that the contention of the petitioner that there is no benefit of rebate under Notifications dated 15th May 1996 and 1st August 1996, is not correct. It is submitted that in view of these two Notifications, the petitioner was claiming rebate for five years from the date of power supply

    i.e 17th September 1993. Pointing out the difference in the wording of the two notifications, it is submitted that the petitioner is entitled to rebate of 25% as per 1988 tariff from the date of power supply

    i.e 17th November 1993 till 31st March 1995. This amount works out to Rs.43,45,050/-. The petitioner is given a total rebate of Rs.1,53,09,077/-. The differential sum of Rs.1,08,66,027/- is sought to be recovered in terms of the Act VIII of 2002 and the impugned demand notice. Therefore, the challenge to the demand notice should fail.

    6 A rejoinder affidavit is filed by the petitioner in which it seeks to deal with the affidavit in reply and submits that the judgment of this Court in Writ Petition No.241 of 1998 and wp179-11 (corrected).doc companion matters delivered on 21st January 1999 would apply with full force. The petitioner is not party to the subsequent writ petitions being Writ Petition Nos.277/1999 or 264/1999 which are disposed off by this Court on 24th April 2001. In these circumstances, the State cannot place reliance on any of the subsequent judgments to deny the petitioners benefits. In paras 16, 17, 18 and 21 in the rejoinder affidavit, this is what is stated:

    16. In this petition, at paragraph 6 thereof, it has been specifically set out that the Government on 12/12/1995 had issued guidelines including the manner in which the grant of rebate was to be adjusted.

    17. The relevant clauses of the said guidelines viz.Clauses (iv), (v) and (vi) were also set out. Clause (v) thereof stipulated that a 25% rebate may be worked out with reference to the energy charges as per which the billing may be done and Clause (vi) stipulated that the amount of 25% rebate worked out as above may be adjusted against the subsequent/current bills and may not be refunded in cash.

    18. At ground (IV) of the petition the entire set of reliefs claimed in Writ Petition No.316/1998 filed by Shri Manohar Parrikar have been set out, prayer (b) whereof was for a declaration that the guidelines as framed by letter dated 12/12/1995 is illegal to the extent it goes beyond the scope of 1991 Notification; and prayer (c) thereof was for an order or direction to quash and set aside the guidelines dated 12/12/1995 to the extent they go beyond the 1991 Notification. wp179-11 (corrected).doc

    21. It is pertinent to note that the afore-referred guidelines dated 12/12/1995 were framed by the Government as tacitly stated therein at Clause (iv) thereof viz since the scheme has been withdrawn with effect from 01.04.1995 the industrial units who have been supplied electricity upto and inclusive of 31/03/1995 shall become eligible for the rebate for a period of 5 years.

    7 Therefore, the petitioner cannot be called upon to pay back or refund the rebate. The petitioner is entitled to 25% rebate for the period of 17th November 1993 to 27th July 1998 as held in the case of G.R.Ispat Ltd Vs. Chief Electrical Engineer & Ors, (W.P.No.199/98 and connected matters, dated 21st January 1999), and particularly because of the guidelines issued on 12th December 1995. The billing has been done accordingly and the energy charges have been paid. There is, therefore, no question of any refund and if beyond entitlement of the petitioner any excess amount is paid, then, the petitioner undertake to refund the same within such period as the Court may direct. These are the statements made in the affidavit in rejoinder by one B.Srinivasa, Director of the petitioner-Company.

    8 It is on this material, that we have heard the learned wp179-11 (corrected).doc counsel appearing for the parties.

    9 Mr.V.B.Nadkarni, learned senior counsel appearing on behalf of the petitioner submitted that the demand notice is contrary to law. He submits that the petitioner cannot be called upon to refund any monies as there is no question of any excess rebate or wrong benefit being given to the petitioner. He submits that if the petitioner was entitled to benefit of 25% rebate in power tariff under the Notification dated 30th September 1991 from the date of power supply to them, then, that benefit in terms of the notification is for five years. That benefit cannot be taken away midstream and all of a sudden by the State. The State is bound by the Division Bench judgment of this Court delivered in the petitioners case to which it is a party. The State cannot rely on any other judgments or orders and that too in proceedings to which the petitioner is not a party. By doing so, the respondents are violating the mandate of this Courts judgments and orders, so also directions. There is no question of the petitioner being denied the benefit and, therefore, this Court should quash and set aside the demand notice as prayed. wp179-11 (corrected).doc

    10 Mr.Nadkarni then submitted that the petitioner is not responsible if the benefit of the 1991 Notification was not extended immediately. The benefit has been extended much beyond the notification of 1991 and, therefore, the State itself issued the guidelines on 12th December 1995. In the petitioners case, the power supply was commenced in terms of the request of the petitioner, from 17th November 1993. Once that is the position, then, the benefit of five years rebate at the rate of 25% in the power tariff should be granted, or else, this Court will be permitting the respondents to flout and violate the judgment and order of this Court which has gained finality. Mr.Nadkarni has, therefore, submitted that the impugned demand notice is violative of the mandate of Article 14 and Article 19(1)(g) of the Constitution of India.

    11 Mr.Nadkarni then submits that the petitioner has not gained any benefit under the 1996 notification as falsely contended. He submits that even the subsequent judgments in the case of Manohar Parrikar Vs. State of Goa & Ors(W.P.No. wp179-11 (corrected).doc 316/1998 decided on 24th April 2001) and Alcon Cement Company Vs. State of Goa (W.P.No.277 of 1999 and other connected matters decided on 24th April 2001) will not apply to the petitioner as it was never being made party to the said proceedings. Once, the judgments have been understood as inter parties, then, all the more, no reliance can be placed on the same.

    12 Mr.Nadkarni submits that the next issue that is raised for determination is that the 25% rebate is not restricted to the tariffs chargeable under Government Notification dated 27th June 1988. The subsequent changes in the tariff rates also became applicable during the five years benefit period and, therefore, the rebate needed to be computed and granted accordingly. The petitioner must be granted full rebate and that would include benefit in terms of payment of energy charges so also demand charges. If the 25% rebate is restricted to the energy charges, then, that would go contrary to the notification. For all these reasons, he submits that the petition be allowed. wp179-11 (corrected).doc

    13 On the other hand, Mr.Kantak, learned Advocate General supported the demand notice and invited our attention to the affidavits filed in the reply. He relied upon the judgments of this Court in the writ petitions filed in 1998 viz the judgment delivered in Manohar Parrikars case (supra) and that in Alcons case (supra). He also relies upon the Act VIII of 2002 and submits that the petition is devoid of any merits and must be dismissed.

    14 Mr.Nadkarni, learned senior counsel appearing for the petitioner has relied on the following decisions in support of the above submissions:

    1. 1990 (Supp) Supreme Court Cases 440 (Narendra Kumar Maheshwari Vs. Union of India & Ors);

    2. (2006) 8 Supreme Court Cases 702 (MRF Ltd, Kottayam Vs. Asstt. Commissioner (Assessment) Sales Tax & Ors);

    3. (2008) 2 Supreme Court Cases 777(U.P.Power Corporation Ltd & Anr Vs. Sant Steels & Alloys (P) Ltd & Ors);

    4. W.P.No.277/99 (Alcon Cement Company Ltd & Anr Vs. State of Goa & Anr) and W.P.No.364/99 (M/s.M.R.F Ltd & Anr Vs. State of Goa & Anr) decided on 24th April 2001; wp179-11 (corrected).doc

    5. AIR 1928 Calcutta 777 (Tarini Charan Bhattacharjee & Ors Vs. Kedar Nath Haldar);

    6. AIR 1928 Calcutta 782 (Sarat Chandra Pal Vs. Barlow & Co);

    7. AIR 1966 Supreme Court 1061 (State of West Bengal Vs. Hemant Kumar Bhattacharjee & Ors);

    8. AIR 1961 Supreme Court 1457 (Daryao & Anr Vs. State of U.P & Ors);

    9. (2009) 3 Supreme Court Cases 273 (Kopargaon S.S.K. Ltd Vs. State of Maharashtra & Ors);

    10. (2009) 9 Supreme Court Cases 757 (Gangai Vinayagar Temple & Ors Vs. Meenakshi Ammal & Ors);

    11. AIR 1976 Supreme Court 1100 (M/s.Northern India Iron & Steel Co Vs. State of Haryana);

    12. (2009) 8 Supreme Court Cases 209 (Assistant Commissioner (CT) LTU & Anr Vs. Amara Raja Batteries Ltd);

    13. 1993 Supp (1) Supreme Court Cases 612 (Commissioner of Income Tax, Bangalore Vs. Vasudeo V. Dempo);

    14. (2002) 4 Supreme Court Cases 380 (Khet Singh Vs. Union of India)

    15 After carefully perusing the petition and the affidavits filed on record, so also all annexures, we are of the opinion that the petitioners case in this petition is not different from the other wp179-11 (corrected).doc petitioners whose petitions we have decided by the companion judgment. Same contentions have been raised by Mr.Nadkarni, learned senior counsel appearing for the petitioner and we have found no substance therein. The reasons that have persuaded us not to accept these contentions and submissions, are elaborately recorded in the judgments in the companion writ petitions. For the same reasons, we reject the contentions of the petitioner in this petition.

    16 The argument of Mr.Nadkarni is that principles of finality of judgment and res judicata would not enable the respondents to place reliance on a judgment of this Court in Manohar Parrikars case (supra). It is also not well founded. His reliance on the judgments of the Honble Supreme Court in that regard is not apposite in this case. Firstly, the petitioner has in the petition, as a part of the factual narration, pointed out that the Writ Petition No.241 of 1998 was disposed off, so also, the Special Leave Petition therefrom was disposed off. In para 15 they make a reference to Manohar Parrikars case. They also make a reference to Goa (Prohibition of Further Payments and Recovery wp179-11 (corrected).doc of Rebate Benefits) Act, 2002 and the issue of its constitutional validity. The petitioner was party to the writ petitions filed in the Honble Supreme Court challenging the said Act. These petitions have also been dismissed by the Supreme Court on 3rd May 2010. We have made reference to the observations in this very judgment of the Honble Supreme Court to reject the contentions of the other petitioners. There is no question of principle of finality of judgment and res judicata applying because this Court in the judgment delivered on 21st January 1999 in the petitioners writ petitions and other cases relied on the fact that the notification dated 30th September 1991 survived after it was rescinded in 1995. For its survival, this Court relied upon the phraseology and wording of the subsequent Notifications dated 15th May 1996 and 1st August 1996. It also made reference to the guidelines. However, in Manohar Parrikars case (supra), this Court held that the 1996 Notifications were void ab initio and were of no legal effect. Once they were held to be void ab initio, then, there is no question of they being relied upon to hold that the 1991 notification survives. Admittedly, the 1991 Notification has been rescinded by Notification dated 31st March 1995. That rescission wp179-11 (corrected).doc has not been questioned. Once the Notification of 1991 stands rescinded and all findings of its survival being based on 1996 notification, then, irrespective of the fact whether the petitioner is party to the decision in Manohar Parrikars case (supra) or not, the law laid down therein binds them as well as us. The Honble Supreme Court has set out the circumstances which led to the conclusion that these notifications are void ab initio. Therefore, the judgments on the principle of finality of decisions and res judicata relied upon by Mr.Nadkarni are not applicable in these facts. Similarly, his reliance on the decisions on the point of res judicata and particularly decision of Full Bench of Calcutta High Court reported in AIR 1928 Calcutta 777 (Tarini Charan Bhattacharjee & Ors Vs. Kedar Nath Haldar) is misplaced. The principles are too well settled. What is important is their application. Therefore, even these decisions are of no assistance to the petitioner. We need not refer to each of the decision cited, once we are of the aforementioned opinion.

    17 Then, the reliance placed on the decisions on the status of guidelines is also misplaced. The guidelines in this case are of wp179-11 (corrected).doc no assistance because all that they indicate is how the Notifications are to be implemented. Once both the 1991 and 1996 Notifications are no longer in the field, then, reliance on the guidelines alone cannot be of any assistance. Therefore, the decisions in that behalf also need not be noted and referred to in any further details.

    18 In the light of the above conclusion, we are of the view that there is no merit in this writ petition and it deserves to be dismissed. Rule is accordingly discharged but without any orders as to costs. (S.C.DHARMADHIKARI, J) (F.M.REIS, J)