Case Summary: National Consumer Disputes Redressal Commission — Consumer Case Nos. 975 & 976 of 2016

Factual and Procedural Background

These matters concern two consumer complaints (C.C. No. 976 of 2016 and C.C. No. 975 of 2016) filed by Vrajendra Jogjivandas Thakkar (and transactions involving his family members) against CCI Projects (P) Ltd. Each complaint arises from booking of a residential flat in the "White Spring Building" project in Borivali (East), Mumbai, pursuant to agreements dated 30.10.2012.

In C.C. No. 976 of 2016, Vrajendra J. Thakkar (HUF) had flat No. 6A allotted for a consideration of Rs. 9,038,850/-. The allotment was transferred by the HUF to the complainant's mother who gifted it to the complainant. In C.C. No. 975 of 2016, Smt. Hemali Vrajendra Thakkar had flat No. 6B allotted for the same consideration; that allotment was subsequently transferred and gifted so that the complainant effectively became the transferee.

The agreements specified a possession delivery date of August 2014 (subject to automatic extension for certain contingencies under Clause 17). The complainant and/or predecessor-in-interest paid significant sums (noted aggregate payments of Rs. 8,586,912/- in one account and the total sale consideration less certain 5% withheld on possession in another communication). Possession was not delivered by the contractual date, and the complainant filed consumer complaints seeking possession, interest, alternative allotment or refund, compensation, and litigation costs.

The opposite party admitted bookings and execution of the agreements but contended (i) it had made an unconditional offer to refund amounts with interest at 9% per annum per Clause 18 of the agreement, and (ii) delays were due to contingencies including amendments to Development Control Rules (DCR), delayed processing of the Commencement Certificate, government restrictions on sand procurement and a contractor leaving the site. On 10.7.2017 the Commission directed the complainants to pay admitted balance and deposit disputed amounts with the Commission; possession was thereafter delivered in compliance with that direction.

Legal Issues Presented

  1. Whether any of the demands (in particular a demand for interest of Rs. 104,207/- in the Debit Note dated 19.7.2017) raised by the opposite party prior to delivery of possession were unjustified.
  2. Whether the complainant is entitled to compensation for delay in delivery of possession of the flats.

Arguments of the Parties

Complainant's Arguments

  • The complainant had paid all instalments on or before their respective due dates and/or as demanded; there is no allegation or evidence of delayed payment of any particular instalment.
  • The complainant specifically disputed the demand of Rs. 104,207/- claimed as interest in the Debit Note dated 19.7.2017, asserting absence of particulars or break-up for that claimed interest.

Opposite Party's Arguments

  • The opposite party admitted bookings and the agreements, and stated that because of delay in possession it had offered an unconditional refund with interest at 9% per annum under Clause 18 of the agreement.
  • It contended the delay in delivery of possession was attributable to contingencies covered by Clause 17 of the agreement, notably (a) the notification amending Development Control Rules (DCR) which delayed processing of the Commencement Certificate until March 2012, (b) intermittent government restrictions on procurement of sand on environmental grounds, and (c) the contractor leaving the site when work was stopped pending regulatory changes.
  • The opposite party issued demand communications (including a demand letter dated 6.11.2016 and a Debit Note dated 19.7.2017) seeking payment of certain arrears and interest.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Commission undertook a fact-by-fact analysis limited to the matters placed on record and the terms of the agreements dated 30.10.2012. The court's reasoning proceeded in the following sequence:

  1. On the demand for Rs. 104,207/- as interest (Debit Note dated 19.7.2017): the court observed the Debit Note did not provide details or a break-up of the amount claimed as interest. The learned counsel for the opposite party could not point to any provision in the agreement permitting recovery of interest for delayed payment of ancillary charges (development charges, club house charges, electrical and gas deposit charges, society formation and legal charges, water/sewerage deposits, advance maintenance charges and service tax). Since these charges had either been paid or deposited with the Commission before possession was delivered, the court concluded the opposite party was not entitled to recover any amount on that account.
  2. On justification for delay in delivery of possession under the contract: the opposite party's own case acknowledged that (a) the amended DCR was notified in January 2012, (b) the Commencement Certificate was approved in March 2012, and (c) construction resumed in September/October 2012. The agreements with buyers were executed on 30.10.2012. The court inferred from these chronology facts that the delay attributed to modification of Development Control Regulations could not justify the delay in delivering possession in terms of the relevant clause of the agreement (the opinion refers to Clause 14 in this context).
  3. On the embargo/ban on sand procurement: the opposite party placed no documentary evidence to substantiate the claim of intermittent government restrictions on procurement of sand. The court held that absent documentary proof the plea could not be accepted. Further, the court noted that even if there were regional mining embargoes, it was for the builder to procure sand from alternative sources available at the relevant time; thus such an embargo could not excuse delay under the agreements.
  4. The court concluded that the opposite party failed to bring its case within the purview of Clause 17 of the buyers' agreement (i.e., failed to establish that the contingencies excusing delay applied).

Holding and Implications

DISPOSITION: The complaints were disposed of by the Commission with specific financial directions.

Core Rulings (Direct Relief to Parties)

  • The Commission ordered that the balance (if any) of the amount deposited by the complainant with the Commission before taking possession, together with proportionate interest accrued, shall be released to the opposite party after deducting: (i) the interest amount of Rs. 104,207/- (in both complaints) and (ii) an amount equivalent to the compensation payable under the directions below.
  • The amount of Rs. 104,207/- (in both cases) shall be released to the complainant along with proportionate interest accrued on that amount.
  • The opposite party was directed to pay compensation in the form of simple interest at 8% per annum on the amount paid by the complainant, from 1.9.2014 until the date possession was actually delivered. The compensation so payable would be adjusted to the extent available out of the amount payable to the complainant as noted above.
  • The opposite party was directed to pay Rs. 25,000/- as the cost of litigation to the complainant in each complaint.
  • All payments required by the order were to be made within three months from the date of the order.

Implications

The direct effect of the decision is the financial reallocation described above: (a) the complainant receives Rs. 104,207/- plus proportionate interest, (b) the opposite party receives any remaining deposited balance after specified deductions, (c) the opposite party pays interest as compensation at 8% p.a. from 1.9.2014 until actual delivery of possession, and (d) a litigation cost of Rs. 25,000/- per complaint is awarded to the complainant. Payments were ordered to be completed within three months.

The opinion does not purport to set out any broader legal precedent; it resolves the disputes on the contractual facts, documentary record and arguments before the Commission. The court expressly found the opposite party did not satisfy the contractual exceptions relied upon to excuse delay.

To access the original judgment, please Sign In or Subscribe.

    Vrajendra Jogjivandas Thakkar Complainant(S) v. Cci Projects (P) Ltd. Opp. Party(S).

    NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

    NEW DELHI

    CONSUMER CASE NO. 975 OF 2016

    1. VRAJENDRA JOGJIVANDAS THAKKAR

    701, 2-B, Surbhi Complex, Sai Nagar, M.G.X Road No-1, Kandivali (W), Mumbai ...........Complainant(s) Versus

    1. CCI PROJECTS (P) LTD.

    Rivali Park CCI Compound, Western Express Highway, Borivali (E), Mumbai - 400066 ...........Opp.Party(s)

    CONSUMER CASE NO. 976 OF 2016

    WITH

    IA/3049/2017(Directions),IA/5342/2017(Directions),IA/6177/2017(Condonation of Delay in Filing The Evidence)

    1. VRAJENDRA JOGJIVANDAS THAKKAR ...........Complainant(s) Versus

    1. CCI PROJECTS (P) LTD.

    Rivali Park CCI Compound, Western Express Highway, Borivali (E), Mumbai - 400066 ...........Opp.Party(s)

    BEFORE:

    HON'BLE MR. JUSTICE V.K. JAIN,PRESIDING MEMBER

    For the Complainant : Mr. Dilip Singh, Advocate For the Opp.Party : Mr. Anil Agarwalla, Advocate Mr. Jagdeep Anand, Advocate

    Dated : 23 Jan 2018

    ORDER

    JUSTICE V.K. JAIN (ORAL)

    In C.C. No.976 of 2016, Vrajendra J. Thakkar, HUF booked a residential flat with the opposite party in a project, namely, 'White Spring Building' which the opposite party was to construct in Village Magathane, Dattapada Road, Borivali (East), Mumbai, for a consideration of Rs.9038850/- and flat No.6A in the proposed building was allotted to him. The parties then entered into an agreement dated 30.10.2012, incorporating their respective obligations in respect of the aforesaid transaction The allotment was later transferred by the HUF to the mother of the complainant who thereafter gifted the same to the complainant. In terms of Clause 17 of the agreement dated 30.10.2012, the possession was to be delivered by August, 2014 though the date for delivery of possession was to automatically stand extended in the event of any of the contingencies specified in the said Clause. The complainant and/or his predecessor-in-interest made payment of a sum of Rs.8586912/- to the opposite party but the

    1

    possession of the flat was not delivered to him. He, therefore, approached this Commission by way of this consumer complaint, seeking the following reliefs:-

    "a. OP be directed to handover the legal possession of flat to complainant within one month

    AND

    b. OP be directed to pay to Complainant 18% interest per annum on Rs.85 86,911/- from September '2014 on the consideration amount already paid to OP till OP handover the possession of the flat to Complainant. OR

    c. if granting prayer a) & b) is legally not possible then in alternative OP be directed to hand over any other newly constructed flat to complainant consisting same area, at the same rate in same locality in tower with same facility. OR

    d. OP be directed to refund the Complainant Rs.2,00,00,000/- (Rupees Two Crore) the current market value of the said flat. AND

    e. AND OP be directed to pay to complainant 18% interest per annum on Rs.85,86,911/- from September 2014 on the consideration amount already paid to OP till OP refund complainant Rs.2,00,00,000/- the current market value of the said flat. AND f. OP be directed to pay to complainant Rs.5,00,000/- as compensation for causing mental stress, harassment and agony. AND

    g. OP be directed to pay to Complainant Rs.1,00,000/- as litigation cost. h. Any other relief as Hon'ble Commission deem fit and proper."

    2. In C.C. No.975 of 2016, Smt. Hemali Vrajendra Thakkar, wife of the complainant booked a residential flat with the opposite party in the same project and flat No.6B was allotted to her for the same consideration of Rs.9038850/-. She also entered into an agreement dated 30.10.2012 with the opposite party and the said agreement contained clauses identical clauses contained in the agreement subject matter of CC No. 976 of 2016. Later on, the aforesaid allotment was transferred by the wife of the complainant to her mother-in-law, namely, Kundanben Jagjivandar Thakkar, who in turn gifted the same to the complainant. Since the possession of the above referred flat was not offered to him, the complainant is before this Commission with identical prayers.

    3. The complaint has been resisted by the opposite party which has admitted the bookings made by the complainant and his wife as well as the execution of the agreements with them on 30.10.2012. It has interalia been stated in the written version filed by the opposite party that since the possession of the flats was delayed, the opposite party had made an unconditional offer to refund the entire amount received from the complainant alongwith interest @ 9% per annum in terms of Clause 18 of the agreement dated 30.10.2012 . It is further alleged in the written version filed by the opposite party that since the possession was delayed for the reasons squarely covered in Clause 17 of the agreement dated 30.10.2012, the delay in offering the possession was justified. It is alleged that after the opposite party had applied for the Commencement Certificate for the upper habitable floors, the same was not processed since changes in Development Control Rules were in the offing. The notification amending

    2

    Development Control Rules came to be issued only in January, 2012 and thereafter, the Commencement Certificate was approved in March 2012, where upon the opposite party could start the work in September/October, 2012. It is also alleged that the work was intermittently delayed due to the off and on Government restrictions on procurement of sand on account of environmental concerns and on account of the contractor having left the site when the work was stopped on account of delay due to amendment of the Development Control Regulations.

    4. Vide order dated10.7.2017, this Commission interalia directed as under:-

    "The learned counsel for the complainants on instructions states that the complainants are ready to pay the balance admitted amount, if any, to the OP and deposit the amount being disputed by them with this Commission in order to obtain possession of the flats which have already been offered to them by the opposite party. The request made by the complainants is just and reasonable. Subject to the complainants paying the balance admitted amount, if any, to the OP and depositing the amount being disputed by them with this Commission within four weeks from today, the possession of the flats allotted to the complainants, complete in all respects shall be delivered to the complainants within four weeks thereafter. The OP shall convey the balance amount being claimed by it from the complainants, to them through counsel within one week from today. The amount deposited with the Commission shall be kept in interest bearing FDR with the Nationalized Bank."

    In compliance of the aforesaid direction, the possession of the flats has already been delivered to the complainant, after he has paid the admitted amount to the opposite party and deposited the disputed amount with this Commission.

    5. It would thus be seen that two issues arises for consideration in this case. the first issue being as to whether any of the demands raised by the opposite party before delivering possession of the flats to the complainant was unjustified and the second being as to whether the complainant is entitled to any compensation for the delay in delivery of possession of the flat to him

    6. After some arguments, the learned counsel for the complainant states on instructions that the complainant is disputing only the demand on account of interest in payment of the flat, contained in the Debit Note dated 19.7.2017. A perusal of the demand letter dated 6.11.2016 issued by the opposite party to the complainant shows that the entire sale consideration except 5% of the consideration payable on delivery of possession, development charges, club house charges, electrical and gas deposit charges, society formation and legal charges, water/sewerage deposits charges and advance maintenance charges for 12 months and service tax were duly paid to the opposite party. There is no evidence or even allegation of delay in payment of any particular instalment to the opposite party. According to the complainant, he had paid all the instalments on or before the due date, as and when the same were demanded by the opposite party. The Debit Note dated 19.7.2017 also does not give any details or break-up of the amount claimed as interest for the delay in payment for the delay in flats. In the absence of such particulars, the demand for payment of Rs.104207/- towards interest on account of delay in payment of the flat cannot be justified. It would be appropriate to note here that the

    3

    learned counsel for the opposite party has not been able to draw my attention to any provision in the agreement for payment of interest on the delayed payment of development charges, club house charges, electrical and gas deposit charges, society formation and legal charges, water/sewerage deposit charges, advance maintenance charges and service tax arrears. In any case, all these charges have either been paid or deposited with this Commission before the possession of the flats was delivered to the complainant. Therefore, in my opinion, the opposite party is not entitled to recover any amount towards interest for the delay in payment of the flats.

    7. As far as justification for the delay in delivery of the possession is concerned, this is the case of the opposite party itself is that the amended Development Control Rules came to be notified in January 2012. This is also the case of the opposite party that after receipt of the Commencement Certificate in March 2012, they had actually resumed the construction work in September/October 2012. The agreements with the flat buyers were executed on 30.10.2012. It is, therefore, evident that the delay on account of modification of the Development Control Regulations would give no justification for the delay in delivery of possession in terms of Clause 14 of the agreements dated 30.10.2012.

    8. As far as the alleged embargo on procurement of sand is concerned, no document has been placed on record by the opposite party. In the absence of any documentary evidence, the plea taken in this regard cannot be accepted. In any case, even if there was an embargo on mining in a particular place in Maharashtra, it was for the builder to procure sand from an alternative source wherever the sand could be available at the relevant time. The embargo on mining therefore, can give no justification for the delay in delivery of possession in terms of the agreement executed between the parties.

    9. I, therefore, hold that the opposite party has failed to bring its case within the purview of Clause 17 of the Buyers Agreement, executed between the parties.

    10. For the reasons stated hereinabove, the complaints are disposed of with the following directions:-

    The balance, if any, out of the amount deposited by the complainant with this Commission before taking possession of the flat and proportionate interest which may have accrued on that amount, after deducting (i) the interest amount of Rs.104207/- (in both the complaints) and (ii) an amount equivalent to compensation payable to the complainant in terms of direction (3) below, shall be released to the opposite party.

    1.

    The amount of Rs.104207/- shall (in both the cases) be released to the complainant along with proportionate interest which may have accrued on that amount.

    2.

    The opposite party shall pay compensation in the form of simple interest @ 8% per annum on the amount which had been paid by that date, to the complainant, w.e.f. 1.9.2014 till the date on which the possession was actually delivered to him. The compensation to the extent available shall be adjusted out of the amount payable to the complainant in terms of direction (1) above.

    3.

    The opposite party shall also pay Rs.25,000/- as the cost of litigation in each complainant 4.

    4

    to the complainant. The payment by the OP in terms of this order shall be made within three months from today.

    5.

    ......................J

    V.K. JAIN

    PRESIDING MEMBER

    5