Factual and Procedural Background

The petitioner Company was awarded a contract by the respondent Gujarat Urban Development Company Ltd., a Government of Gujarat undertaking, for providing, supplying, lowering, lying, and joining RCC pipeline for the Rajpipla underground drainage project at a contract price of approximately Rs. 14 crores. The contract included a dispute resolution mechanism under Clause 20. The petitioner executed only a small portion of the work, citing opposition from the local population regarding the pipeline diameters, while the respondent alleged the petitioner was unwilling to complete the contract and sought to be relieved. The petitioner requested the respondent to constitute a Dispute Adjudication Board (DAB) as per Clause 20.2 of the contract, but no DAB was constituted within the stipulated 28 days or thereafter. Subsequently, the petitioner issued a notice demanding appointment of an arbitrator and claiming certain monetary sums. No response was received, leading to the filing of the present petition for appointment of an arbitrator.

Legal Issues Presented

  1. Whether the petitioner is entitled to the appointment of an arbitrator under the arbitration clause of the contract after the failure to constitute the Dispute Adjudication Board.
  2. Whether disputes unrelated to the contract between the petitioner and respondent can be included in the arbitration proceedings.

Arguments of the Parties

Respondent's Arguments

  • The respondent contended that the petitioner was unwilling to complete the contract and requested to be relieved.
  • The respondent's counsel pointed out that the petitioner mixed disputes relating to non-awarding of contract to another entity, Gujarat Water Supply and Sewerage Board, which are not relevant to the arbitration between the petitioner and the respondent.

Petitioner's Arguments

  • The petitioner argued that the remaining work could not be completed due to local opposition regarding pipeline diameters.
  • The petitioner sought appointment of an arbitrator after failure to constitute the DAB and clarified it would confine claims to disputes arising out of the works contract with the respondent, excluding unrelated claims.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court examined the dispute resolution mechanism in the contract, particularly Clause 20, which requires the constitution of a Dispute Adjudication Board (DAB) within 28 days of notice by the contractor. Since the respondent failed to constitute the DAB despite the petitioner's request, the mechanism for amicable settlement and DAB decision became inapplicable. Clause 20.8 explicitly provides that in the absence of a DAB, disputes may be referred directly to arbitration under Clause 20.6. The court noted that the petitioner rightly invoked the arbitration clause after the failure of the DAB process. The court also accepted the petitioner's clarification to exclude unrelated disputes from the arbitration. Finding no other ground to decline the appointment, the court proceeded to appoint a sole arbitrator.

Holding and Implications

The petition for appointment of an arbitrator is granted and disposed of.

The court appointed Shri Bankim Mehta, retired Judge of the court, as the Sole Arbitrator to resolve the disputes arising out of the contract between the petitioner and respondent. The decision directly facilitates the continuation of dispute resolution through arbitration as per the contract terms, without setting any new precedent beyond the immediate parties.

    Kunal Structure (India) Pvt. Ltd. Petitioner(S) v. Gujarat Urban Development Company Ltd. (S)

    ORAL ORDER

    Petitioner seeks appointment of an arbitrator to resolve the disputes between the petitioner Company and the respondent Gujarat Urban Development Company Ltd., a Government of Gujarat undertaking. It is not in dispute that the petitioner was awarded a contract for providing, supplying, lowering, lying and joining RCC pipeline by the respondent Company for proposed sewer lines item rate contract for Rajpipla underground drainage project for a contract price of Rs. 14 crores (rounded off). It is also not in dispute that the agreement contained a dispute resolution mechanism. Clause 20 pertained to claims disputed and arbitration.

    The petitioner could execute a very small portion of the work assigned. According to the petitioner, the remaining portion could not be completed because of the opposition of the local population on the diameters of the pipeline to be installed. However, the respondent contends that the petitioner was unwilling to complete the contract and asked to be relieved. Insofar as my purpose is concerned, this dispute is not germane.

    Clause 20.2 of the agreement pertained to appointment of the Dispute Adjudication Board and envisaged constitution of such a Board at the request of the contractor who would raise a dispute with the respondent. In terms of clause 20.2, the Board would have to be constituted by the respondent within 28 days of receipt of the notice. Clause 20.4 further envisaged getting decision by the Dispute Adjudication Board. Clause 20.6 contained arbitration clause in following manner:

    “Unless settled amicably, any dispute in respect of which the DBA's decision (if any) has not become final and binding shall be finally settled by international arbitration. Unless otherwise agreed by both parties:

    (a) the dispute shall be finally settled under the Rules of Arbitration of the International Chamber of Commerce.

    (b) The dispute shall be settled by three arbitrators appointed in accordance with these Rules, and

    (c) The arbitration shall be conducted in the language for communication defined in Sub-Clause 1.4 (Law and Language).

    The arbitrator(s) shall have full power to open up, review and revise any certificate, determination, instruction, opinion, or valuation of (or on behalf of) the Employer. And any decision of the DBA, relevant to this dispute.

    Neither party shall be limited in the proceedings before the arbitrator(s) to the evidence or arguments previously put before the DAB to obtain its decision, or to the reasons for dissatisfaction given in its notice of dissatisfaction. Any decision of the DBA shall be admissible in evidence in the arbitration. Arbitration may be commenced prior to or after completion of the Works. The obligations of the parties and the DBA shall not be altered by reasons of any arbitration being conducted during the progress of the Works.”

    Clause 20.8 pertained to expiry of Dispute Adjudication Board's appointment and provided, inter alia, that if a dispute arises between the parties and there is no DAB in place, whether by reason of expiry of the DBA's appointment or otherwise, clause 20.4 regarding obtaining Dispute Adjudication Board's decision and clause 20.5 regarding amicable settlement shall not apply and the dispute may be referred directly to arbitration under clause 20.6

    In the present case, the petitioner did urge the respondent to constitute the DAB under notice dated 4.4.2013 Admittedly, no DAB was constituted for a period of 28 days or any time thereafter. Thereupon the petitioner issued a notice for appointment of an arbitrator on 8.5.2014 in which the petitioner raised several disputes and demanded a sum of Rs. 2.10 crores (rounded off) by way of loss of profit, and Rs. 1.40 crores (rounded off) on account of overhead establishment charges in addition to return of Rs. 70 lacs of security deposit failing which the petitioner sought appointment of an arbitrator.

    When no reply was received by the petitioner to this notice, this petition came to be filed.

    Learned counsel Shri Chauhan for the respondent drew my attention to various claims made in this arbitration petition where the petitioner has mixed up disputes regarding non-awarding of contract to Gujarat Water Supply and Sewerage Board. I entirely agree that such disputes cannot form part of arbitration between the petitioner and the respondent. Counsel for the petitioner stated that he would not press those issues and disputes in so far as the petitioners request for appointment of arbitrator is concerned. He clarified that the petitioner would confine its claims only those arising out of the works contract between the petitioner and the respondent company.

    I do not see any other ground on which the request for appointment of an arbitrator can be declined. The dispute resolution mechanism without resorting to arbitration having failed for want of constituting the DAB, the petitioner could resort to arbitration clause which is what has been done in the present case.

    In the result, I request Shri Bankim Mehta, retired Judge of this Court to act as Sole Arbitrator to resolve the disputes between the petitioner and th respondent arising out of the contract in question. The petition is disposed of accordingly.