Shree Chandrashekhar, J.:— Seeking a direction upon the respondent-SAIL to pay Rs. 1,15,80,772.67/- with interest @ 18% per annum and litigation cost, the present writ petition has been filed.
2. It is stated that a contract was awarded by Bokaro Steel Plant to M/s. Tata Iron and Steel Company Growth Shop for dismantling, erection, start-up, commissioning and performance guarantee test of Bokaro Hot Strip Mill, BSL. The work of supply of material and equipments was completed by TISCO Growth Shop and erection of the Bokaro Hot Strip Mill was to be carried by M/s. Tata Construction and Projects Ltd. (TCPL). Subsequently, M/s. TCPL issued the work order for the erection part to the petitioner-Company on 20.05.1997 The petitioner has asserted that M/S TCPL did not make payment for the work done and therefore, it made a representation to the Managing Director, BSP on 15.03.2003 to intervene in the matter.
3. From the aforesaid facts, it is apparent that the grievance of the petitioner is against M/s. TCPL which is a private company. In the writ petition, the petitioner has failed to aver that the respondent-SAIL is a party to the contract awarded to the petitioner by M/s. TCPL or, that the work order was issued by M/s. TCPL on the direction of the respondents. There is no privity of contract between the petitioner and the respondents.
4. Considering the aforesaid facts, the writ petition is held not maintainable and, accordingly, it is dismissed.