Stuart, C.J and Tyrrell, J.:— On the 5th January, 1878, Chedi Lal and Shib Datt executed a bond for Rs. 200, which they received, from the plaintiff as an advance for cultivating indigo. Under the terms of the bond the obligors undertook to supply 1,334 maunds of indigo plant at a price of Rs. 15 per 100 maunds, and it was stipulated in the bond, that on failure of such delivery the obligors would be liable to payment of damages calculated at twice the sum advanced as consideration of the bond. As a collateral security, for due performance of the obligation, the obligors hypothecated their immoveable property described in the bond. That property has since been purchased by Sewa Ram. On the allegation that the executants of the bond had wholly failed to perform the contract, the present suit was instituted by plaintiff against Shib Dat and, the heirs of Chedi Lal, who has since died. Sewa Ram, the purchaser of the hypothecated property, has also been impleaded as a defendant in the suit. The object of the suit was the recovery of Rs. 200, the consideration of the bond, and Rs. 400 as liquidated damages for breach of contract, by enforcement of lien against the hypothecated property.
No evidence was produced by the plaintiff to prove any actual less. The Munsif regarded the damages claimed as excessive, and proceeding under s. 74 of the Contract Act, calculated damages as one rupee percent, per mensem on the principal sum advanced, and decreed the claim to the extent of Rs. 283-5-8.
The lower appellate Court regarded the method of assessing damages adopted by the Munsif as erroneous, and, taking into consideration the provisions of the fourth clause of s. 5, Regulation VI of 1823, held that, under the circumstances of the case, Rs. 100 was the reasonable amount of damages to be awarded to the plaintiff, and modified the Munsif's decree accordingly.
The present second appeal has been preferred by the, plaintiff who contends that the defendants were bound to pay the whole amount of the stipulated damages; that the assessment of damages by the lower appellate Court at only Rs. 100 was conjectural and unsound; and that in any case damages should have been equal to the loss actually sustained by the plaintiff on account of the breach of contract committed by the defendants.
The learned pleader who appeared in support of the appeal admitted that his contention could receive no support from the provisions of the fourth, clause of s. 5, Regulation VI, of 1823, and he confined his argument to the general principles to law relating to the assessment of damages. Whatever the distinction between liquidated damages and penalty may be, the terms of s. 74 of the Contract Act are broad enough to include both classes of cases, and the words of the section clearly give a wide discretion to the Courts in the assessment of damages, even in cases where the parties to the contract have in anticipation of the breach expressly determined by agreement what shall be the sum payable as damages for the breach. The section appears to have been introduced to obviate the difficulties which exist in distinguishing liquidated, damages from penalty under the English Law, and the effect of it is, that the Courts are not bound to award the entire amount of damages agreed upon by the parties anticipation of the breach of contract. The only restriction is that the Court cannot decree damages exceeding the amount previously agreed upon by the parties. The discretion of the Court in the matter of reducing the amount of damages agreed upon is left unqualified by any specific limitations, though of course the expression “reasonable compensation” used in the section necessarily implies that the discretion so Vested must be exercised with care, caution, and on sound principles.
With reference to the particular circumstances of this case the question is, what amount should be regarded as “reasonable compensation” for the breach of contract complained of? The fundamental, ground of law, on which damages are awarded, is to place the injured party in the same position in which he would have been had he not sustained the injury of which he complains. As a general, principle, therefore, the damages decreed must be commensurate with the injury sustained. When the injury consists of the breach of a contract, the Court, acting upon the principle above enunciated, would assess damages with a view of restoring to the plaintiff such advantage as he might reasonably be expected to have derived from the contract had the breach never occurred.
There are of course cases in which, ex necessitate rei, it is impossible to fix the exact amount of damages actually resulting from a breach of contract, and it is principally, if not exclusively, in such cases that the Courts of Equity do not interfere with the contract of the parties who, in anticipation of the breach of contract, have stipulated that a fixed sum shall be regarded as the measure of compensation to be paid by the person, who violates the contract. Rut the present is not a case in which it would be impracticable or impossible to ascertain the actual damages sustained, by the plaintiff. It is easy to determine the amount of pecuniary advantage which the plaintiff might have derived if the defendant had performed his contract and supplied 1,334 maunds of indigo plant at the stipulated period. It is consequently practicable to fix the extent of the loss which the plaintiff has sustained, and this in our opinion must be the measure of damages in this case, so long as the amount so ascertained does not exceed the sum agreed upon.
The method of assessing damages would be to ascertain the quantity of indigo which would have been pressed out of the stipulated amount of indigo plant, to ascertain the price at which indigo might have been fairly sold in the market during the season to which the contract relates, and to deduct from such price the ordinary charges of producing and selling the quantity, of indigo in question. More than the amount so ascertained the plaintiff in our opinion is not entitled in equity to recover, and if that amount is decreed to him it would be a “reasonable compensation” for the breach of contract on which the suit is based.
With reference to these observations we decree this appeal, and setting aside the decree of the lower appellate Court remand the case to that Court under s. 562, Civil Procedure Code, the costs of this appeal to abide the result.
Cause remanded.