(i) H.P. State Forest Company Ltd., v. United India Assurance Co., Ltd., (2009) 2 SCC 252
(ii) Union of India and anr. v. IndusInd Bank Limited and Anris, 2017-1-LW 898. In both the Judgments, question in those cases was examined in the light of unamended Section 28 of the Indian Contract Act. Prior to the amendment of Section 28 of the Indian Contract Act, the Hon'ble Supreme Court drew a distinction between the curtailment of the period of limitation and extinction of the right itself in an agreement in view of Section 28 of the Indian Contract Act, in National Insurance Co., Ltd., v. Sujir Ganesh Nayak & Co., reported in AIR 1997 SC 2049. It was held that curtailment of the period of limitation is not permissible in view of Section 28 but extinction of the right itself unless exercised within the specified time is permissible and can be enforced. The above view was reiterated in Wild Life Institute Of India, Dehradun v. Vijay Kumar Garg reported in (1997) 10 SCC 528.
14. But after amendment to Section 28 of the Indian Contract Act, both the curtailment of the period of limitation and extinction of the right are not permissible. In support of the same, the learned Senior counsel appearing for the plaintiff also cited the Division Bench Judgment of the Delhi High Court in Chander Kant and Co., v. The Vice Chairman, DDA and Ors., reported in MANU/DE/2221/2009. In this Judgment, it has been held as follows :
8. The 1997 Amendment to the Section now also prohibits clauses which seek to extinguish the rights of any party thereto, or discharge any party from any liability under or in respect of any contract on the expiry of a specified period so as to restrict any party from enforcing his rights. The amendment gave effect to the 97th report of Law Commission of India. The effect of the amended Section 28 was considered by the learned single Judges of this Court in Hindustan Construction Company v. DDA; Kalyan Chand Goyal v. Delhi Development Authority (supra); J.K.Anand v. DDA and Anr. MANU/DE/0555/2001 : 2001 (59) DRJ 380 and Union Of India…Petitioner v. Simplex Concrete Piles India (P) Ltd.…, MANU/DE/1119/2003 : 2003 (3) Arb. LR 536 (Delhi) in which similar causes were held to be not valid in view of the amended provisions of Section 28 (b) of the Contract Act. In Explore Computers Pvt., Ltd., v. Cals Ltd., and Anr. (supra), Sanjay Kishan Kaul, J considered the decision of Supreme Court in National Insurance Co., Ltd., v. Sujir Ganesh Nayak and Co., (supra) and other decisions and held as follows :
48. The effect of the amendment of Section 28 thus made it clear that any clause extinguishing the right of a party or discharging any party from the liability in respect of any contract on expiry of specific period so as to restrict the time period would be void.
53. On a conspectus of the aforesaid judgments, two aspects have to be noted. The first is that it is the terms of the bank guarantee which have to be given due weight and the second is the distinction which is sought to be Page 2931 carved out in National Insurance Company case (supra) between a clause curtailing the period of limitation being void under Section 28 of the Contract Act and a clause which provides for forfeiture or waiver of a right if no action is commenced within the period stipulated by the agreement. Insofar as the second aspect is concerned, it cannot be lost sight of that the judgment in National Insurance Company Case (supra) was delivered on 23.03.1997 and thus related to the provisions of section 28 as it stood prior to the amendment because that was the substantive law in force at the time when the cause of action had arisen. The amendment to Section 28 was made with effect from 08.01.1997 and it is not disputed that the cause of action in respect of the subject matter in the present suit arose after the amendment. Sub Clause (b) of the amended Section 28 deals with the clauses which extinguish the rights of any party thereto or discharge any party from any liability being void under the said Section. Thus the scope of Section 28 has been widened whereby Clause (a) deals with the position prior to the amendment alone and Clause (b) is in addition.
54. In view of the amended Section coming into force, the distinction sought to be carved out earlier by the legal pronouncements would not hold good.
55. In my considered view it is not open for defendant No. 2 to contend that if any suit or claim is not filed within one month of the expiry of the bank guarantee, the right of the plaintiff to institute any legal proceedings itself is extinguished. Such a plea would fly in the face of the amended Section 28 as defendant No. 2 cannot be discharged from the liability nor can the rights of the plaintiff be extinguished by inclusion of the clause providing so. I am thus of the considered view that to the extent there is restriction on any suit or claim being filed by the plaintiff beyond a period of one month from the expiry of the bank guarantee, the said clause would not prohibit the plaintiff from instituting the suit as it would be barred by the provisions of the amended Section 28 of the Contract Act.
9. We are in respectful agreement with the view taken by the learned Judge. In our opinion, in view of the amendment, the distinction which was drawn earlier has been obliterated and the clauses providing for extinction or discharge of the rights of the parties on the expiry of the specified period are also covered by inserting Clause (b) in Section 28 of the Contract Act.
15. The learned Senior counsel appearing for the plaintiff also brought to the notice of this Court the Judgment of the Delhi High Court in Union of India v. Pt. Munshi Ram & Associates Pvt., Ltd., reported in MANU/DE/6111/2012 holding the law as explained by the Division Bench of the Delhi High Court in M/s. Chander Kant and Co., v. The Vice Chairman, DDA and Ors., is good as the decision in H.P.State Forest Company Ltd., v. United India Assurance Co., Ltd., reported in (2009) 2 SCC 252 by the Supreme Court appears to have proceeded on the basis that the amendment to Section 28 had been repealed. The operative portion of the above Judgment is : "11. In view of the above settled position in law, as far as the present case is concerned, although the date of start of the work was 22nd December 1995, the work was actually completed on 30th January 2001. The decision in P.Manohar Reddy & Bros. v. Maharashtra Krishna Valley Development Corporation (supra) was dealing with the case that arose under the Arbitration Act, 1940 and did not actually discuss tissue whether the amendment to section 28 of ca brought about the change to the legal position existing prior to the amendment. The execution of the contract in that case also appears to have been completed prior to the amendment. The decision in Himachal Pradesh State Forest Company Limited v. United India Insurance Company Limited (supra) appears to have proceeded on the basis that the amendment had been repealed. This is clear from para 11 of the said judgment which records that "During the resumed hearing, the learned counsel for the appellant candidly admitted that the amendment had been made but had thereafter been repealed and the matter would, thus, have to be examined under section 28of the contract act, as originally placed." In fact, there has been no repeal of the amendment. It was wrongly informed by learned counsel for the Appellant in that case that the amendment to Section 28 of the CA stood repealed. Consequently, the law as explained by the DBs of this Court in M/s. Chander Kant & Co., v. The Vice Chairman, DDA and D.D.A. v. Pandit Construction Company would hold good."
16. Thus it is clear that after amendment of Section 28 of the Contract Act both curtailment of the period of limitation for specific period and extinction of the right itself are not permissible and if there is any clause to that effect in an agreement it would be barred by the provisions of the amended section 28. In view of the above discussion, Clause 10 (3) of the insurance policy in this case is hit by the provisions of the amended Section 28 of the Contract Act.
17. The defendant in their letter, dated 05.11.2002 repudiated the claim of the plaintiff. The suit was filed by the plaintiff in August 2004. Under Article 44 (b) of the Limitation Act, the period of limitation is three years from the date of repudiation. Therefore, the suit has been filed well within time and therefore, both the issues are answered in favour of the plaintiff.
18. Issue No.6 : The learned counsel appearing for the defendant contends that as per the exceptions to the terms and conditions, the Insurance company is not liable for loss or damage caused by any of the insurer-employees. The learned Senior counsel appearing for the plaintiff per contra contends that the policy coverage includes the riots and strikes and further, there is no evidence that the damages have been caused by the employees of the plaintiff company. Exceptions form part of the terms and conditions of the policy and (i) and (ii) of the exceptions given in Ex.P.2-Insurance policy is extracted below : "1. The Company shall not be liable in respect of :
(i) loss or damage, whether direct or indirect, occasioned by happening through or arising from any consequence of war, invasion act of foreign enemy, hostilities (whether war be declared or not) civil war, mutiny, rebellion, revolution, insurrection, military or usurped power or riot, strike or civil commotion or loot or pillage in connection therewith or confiscation or detention by the order of any Government or Public Authority, earthquake, volcanic eruption, flood, storm, tempest, typhoon, hurricane, tornado, cyclone or other similar convulsions of nature and atmospheric disturbance.
(ii) loss or damage due to burglary or housebreaking or any attempt threat by any of the Insured's family or employees or any person lawfully on the premises, or where such loss or damage has been expedited or in any way assisted or brought about by any inmate or member of such household or business staff as principal or accessory." In the first page of the policy itself, it has been clearly mentioned as follows : "The word Riot and Strike appearing on the overleaf under exceptions stands deleted." Therefore, the word Riot and Strike in Exceptions (1) (i) has been deleted.
19. D.W.1 says in his evidence that generally the strike may be done by the employees or by general public. No doubt P.W.1 during his cross-examination states that they have given a police complaint and as per the translated version of the said FIR, the persons who worked with the plaintiff company had removed the materials on account of the pending salary to the employees and the said complaint was given by the plaintiff's Manager. P.W.1 refers as above the complaint and the translated version marked in C.S.No.763 of 2004. The same cannot be construed to be related to the suit claim. It is pertinent to note that the above documents are not marked in this suit and the author of the complaint, namely the Manager has also not been examined. In the absence of any concrete evidence, it cannot be said that the damages were caused only by the employees of the plaintiff company. In the light of the deletion of Riot and Strike from the exception in the policy, the coverage under the policy extends to the strike or theft and therefore, the defendant's claim of exclusion and coverage of the loss caused due to riot and strike is not sustainable. This issue is answered accordingly.
20. Issue No.7 : The plaintiff after informing the defendant about the damage forwarded the claim form and other relevant documents to the Surveyor appointed by the defendant Insurance Company as requested by the Surveyor in a meeting held on 10/12.02.1991. When the defendant asked the plaintiff to submit the requisite claim forms, the plaintiff on 23.04.1992 informed that the claim forms and supporting papers had already been submitted and sent a fresh copy of the claim form. The claim was made for a sum of Rs.9,08,144/-. Now the plaintiff claims in the suit the above amount together with interest thereon at 18% p.a., from 22.12.1999, which is the date of Survey Report.
21. The learned counsel appearing for the defendant contends that all documents filed by the plaintiff are only secondary evidence and are inadmissible as they have no probative value and there is absolutely no proof or account as to the claim. With respect to the claim, the plaintiff has categorically stated that he forwarded the claim form and other relevant documents to the Surveyor as requested by him in the meeting. The Surveyor appointed by the defendant also submitted his final survey report on 22.12.1999. The above facts have not been disputed with by the defendant. There is no quarrel with the report of the Surveyor that it is not binding on the parties but it can be taken as a guidance to decide the issue. When the Surveyor filed his final report after obtaining the claim form and relevant documents from the plaintiff, the defendant without filing the same is not entitled to say that the plaintiff has not filed the original documents and proof for his claim. Withholding the material documents, namely the Surveyor's Final Report including the documents filed by the plaintiff will lead to adverse inference as against the defendant. As far as probative value of the secondary evidence is concerned, the documents filed on the side of the plaintiff though copies, are only the letter correspondences and notices between the plaintiff and the defendant. While marking those documents, the defendant has not raised any objection. Therefore, the above Exhibits are admissible and the contention of the defendant is liable to be rejected. Considering the above the plaintiff is entitled to the claim as prayed for and the issue is answered accordingly. In fine this Civil Suit is decreed with costs, whereby the defendant is directed to pay the plaintiff a sum of Rs.16,86,306/- together with interest on the principal amount of Rs.9,08,144/- at 18% p.a., from the date of plaint till the date of realisation. 20.10.2017 Speaking order Index : Yes / No tsvn P.KALAIYARASAN, J tsvn Judgment in C.S.No.762 of 2004 20-10-2017