Loading..
Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Neutral Citations
2017 INSC 987
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 11(6) of the 1996 Act
  • Section 11(6) of the Arbitration and Conciliation Act, 1996
  • Section 31(7)(a) of the 1996 Act
  • The 1996 Act
  • Section 34 of the 1996 Act
  • Section 16 of the 1996 Act
  • The Arbitration Act, 1940 (for short “the 1940 Act”)
  • The Arbitration Act, 1996
  • The 1940 Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 37 of the 1996 Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2017 INSC 987
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 11(6) of the 1996 Act
  • Section 11(6) of the Arbitration and Conciliation Act, 1996
  • Section 31(7)(a) of the 1996 Act
  • The 1996 Act
  • Section 34 of the 1996 Act
  • Section 16 of the 1996 Act
  • The Arbitration Act, 1940 (for short “the 1940 Act”)
  • The Arbitration Act, 1996
  • The 1940 Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 37 of the 1996 Act
Smart Summary

Factual and Procedural Background

On 20-03-1991 the respondent, South-Eastern Railway (Union of India), invited tenders for earth-work and allied activities connected with a new goods terminal yard at Sankrail, Howrah District. The appellant’s tender dated 23-03-1991 for Rs 61,24,159 was accepted under a letter of acceptance issued on 17-06-1991, and a formal agreement incorporating the General Conditions of Contract (GCC) was executed on 22-08-1991.

Disputes soon arose regarding execution and alleged abandonment of the works. The Railway Administration issued notices dated 24-10-1991 and 15-11-1991 proposing termination/rescission, although time for completion was successively extended up to July 1993. The appellant ultimately abandoned the remaining works on 03-11-2003, blaming delays and hindrances attributed to the Railways.

The appellant raised monetary claims on 30-10-1996 and, by letter dated 22-06-1998, sought arbitration. Upon an application under Section 11(6) of the Arbitration and Conciliation Act, 1996 (“the 1996 Act”), the Chief Justice of the Calcutta High Court ordered constitution of an Arbitral Tribunal, which delivered an award on 20-09-2006.

The respondent’s Section 34 application to set aside the award was dismissed by a Single Judge. However, a Division Bench, by judgment dated 29-09-2011 (Union of India v. Chittaranjan Maity), set aside both the Single-Judge order and the award, directing a fresh reference. The present Supreme Court appeals challenge that Division Bench decision.

Legal Issues Presented

  1. Whether the Division Bench of the Calcutta High Court was justified in questioning the arbitrability of the disputes—on the ground of a purported “no-claim certificate”—for the first time in appellate proceedings.
  2. Whether the Arbitral Tribunal was legally competent to award pre-reference and pendente lite interest in light of Clause 16(2) of the GCC, which bars payment of interest on amounts payable under the contract.

Arguments of the Parties

Appellant's Arguments

  • The “no-claims certificate” contention was never raised under Section 11(6), before the Arbitral Tribunal, or before the Single Judge under Section 34; therefore the Division Bench could not examine arbitrability for the first time on appeal.
  • The arbitral award, including pre-award and pendente lite interest, was properly granted; interest from 17-07-1992 until realisation is permissible.

Respondent's Arguments

  • The appellant, having issued a “no-claims certificate,” forfeited all claims save the security deposit of Rs 15,000; hence no arbitrable dispute existed.
  • Even if claims survived, Clause 16(2) of the GCC expressly prohibits interest; thus the arbitral grant of interest is contrary to the contract and the 1996 Act.
  • Reliance on Ambica Construction is misplaced because that case is distinguishable and post-dates the governing legal framework.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
National Insurance Co. Ltd. v. Boghara Polyfab Pvt. Ltd., (2009) 1 SCC 267 Chief Justice under Section 11 can examine whether a claim is “live”; issue must be raised at that stage. Used to show respondent failed to raise “no-claim certificate” at the Section 11 stage, barring it from being considered later.
McDermott International Inc. v. Burn Standard Co. Ltd., (2006) 11 SCC 181 Objection to jurisdiction must be raised before the arbitrator; court’s supervisory role is minimal. Supported the conclusion that Division Bench should not have entertained the arbitrability objection for the first time on appeal.
State of Orissa v. G.C. Roy, (1992) 1 SCC 508 Arbitrator’s power to award pendente lite interest under the 1940 Act. Court noted it was decided under the repealed 1940 Act and therefore inapplicable to contracts governed by the 1996 Act with an express bar on interest.
Ambica Construction v. Union of India, (2017) 14 SCC 323 Bar on interest clauses do not necessarily preclude pendente lite interest. Court distinguished the decision as resting on 1940-Act jurisprudence and therefore not controlling under the 1996 Act.
Sayeed Ahmed & Co. v. State of U.P., (2009) 12 SCC 26 Under Section 31(7)(a) of the 1996 Act, if the agreement bars interest, the arbitrator cannot award pre-award interest. Relied upon to hold that the GCC bar prevented any pre-award (including pendente lite) interest.
Sree Kamatchi Amman Constructions v. Railways, (2010) 8 SCC 767 Clause 16 of Railway GCC prohibiting interest is enforceable; arbitrator cannot grant interest. Applied directly because the identical GCC clause governed the present contract.
Union of India v. Bright Power Projects (India) (P) Ltd., (2015) 9 SCC 695 When contract expressly bars interest, arbitrator lacks power to award it, even for pendente lite period. Further reinforced the bar on interest under Clause 16(2) GCC.

Court's Reasoning and Analysis

1. Arbitrability Issue: The Court observed that the respondent never questioned arbitrability or raised the “no-claims certificate” defence during Section 11(6) proceedings, before the Arbitral Tribunal, or in the Section 34 challenge. Citing Boghara Polyfab and McDermott International, it held that jurisdictional objections must be taken at the earliest opportunity and cannot be introduced for the first time in an appellate court. Consequently, the Division Bench exceeded its authority in reopening the issue.

2. Award of Interest: Section 31(7)(a) of the 1996 Act empowers an arbitrator to grant pre-award interest only “unless otherwise agreed by the parties.” Clause 16(2) of the GCC unequivocally bars interest on amounts payable to the contractor. Reliance on Ambica Construction was rejected because it applied 1940-Act principles. Affirming Sayeed Ahmed, Sree Kamatchi Amman Constructions and Bright Power Projects, the Court concluded that the Arbitral Tribunal lacked jurisdiction to award both pre-reference and pendente lite interest. Therefore, the interest component of Rs 12,44,546 was unsustainable.

3. Monetary Adjustment: The Tribunal had awarded Rs 11,13,136 (principal) plus interest. The respondent had deposited Rs 38,82,150 covering principal and interest; the appellant had already withdrawn 50 %. Given the circumstances, the Court directed that the respondent should not seek recovery of the excess amount already withdrawn by the appellant, balancing equities while eliminating the impermissible interest component.

Holding and Implications

PARTLY ALLOWED. The Supreme Court:

  • Set aside the Division Bench’s order insofar as it annulled the arbitral award on grounds of non-arbitrability.
  • Upheld the principal sum of Rs 11,13,136 but struck down the award of Rs 12,44,546 towards interest as barred by Clause 16(2) GCC and Section 31(7)(a) of the 1996 Act.
  • Directed that the respondent shall not recover the excess amount already withdrawn by the appellant; no order as to costs.

Implications: The decision reinforces two key principles under the 1996 Act: (i) jurisdictional or “no-claim” objections must be raised at the earliest—courts will not entertain them belatedly; and (ii) contractual clauses expressly barring interest are strictly enforced, depriving arbitrators of power to award pre-award or pendente lite interest. While the ruling offers finality to the parties, it does not create a new precedent but confirms existing jurisprudence on Sections 11 and 31(7)(a) of the 1996 Act.

    Sri Chittaranjan Maity v. Union Of India .

    S. Abdul Nazeer, J.— Leave granted. The appellant, in these appeals, has challenged the legality and correctness of the judgment and order dated 29-9-2011 in Union of India v. Chittaranjan Maity whereby the Division Bench of the High Court of Calcutta has set aside the judgment and order of the learned Single Judge in Union of India v. Chittaranjan Maity 2009 SCC OnLine Cal 184, (2009) 3 Cal LT 224.

    2. Brief facts necessary for the disposal of these appeals are as follows: on 20-3-1991, the respondent invited tender for the execution of balance of earth for formation of banks for laying railway line, roads, platforms and miscellaneous work in connection with new goods terminal yard of South-Eastern Railway at Sankrail in Howrah District. The appellant's tender dated 23-3-1991 for Rs 61,24,159 was accepted by issuance of letter of acceptance dated 17-6-1991. In this connection, an agreement was entered into between the appellant and the respondent on 22-8-1991. In the said agreement, General Conditions of the Contract (for short “GCC”) were incorporated and the parties were bound by the terms and conditions thereof.

    3. Various disputes and differences arose between the parties regarding execution of work and its purported abandonment. The respondent issued notice dated 24-10-1991, seeking termination of the agreement. Another notice dated 15-11-1991 was issued to the appellant under Clause 62(1) of GCC for rescission of the contract. However, at the request of the appellant through letter dated 2-4-1992, the validity of the contract was extended till 30-6-1992. The respondent further granted extension of time to complete the work up to July 1993. According to the appellant, the delay and/or hindrances occurred due to breaches committed by the Railway Administration. The remaining work was abandoned by the appellant w.e.f 3-11-2003.

    4. The appellant raised the claim before the respondent by his letter dated 30-10-1996. By a subsequent letter dated 22-6-1998, the appellant demanded reference of the dispute to the arbitration. Finally, the appellant filed an application under Section 11(6) of the Arbitration and Conciliation Act, 1996 (for short “the 1996 Act”) for appointment of an arbitrator for adjudication of the claims and disputes before the High Court of Calcutta. The Chief Justice of the High Court of Calcutta passed an order dated 6-12-2001, whereupon the General Manager, South-Eastern Railway, was directed to appoint arbitrators from their panel within four weeks from the said date. Pursuant to the said order, the Arbitral Tribunal was constituted which adjudicated the disputes and claims raised by the appellant, as also the respondent.

    5. The Arbitral Tribunal passed an award on 20-9-2006. The respondent moved an application, being AP No. 35 of 2006 under Section 34 of the 1996 Act, for setting aside the said award. The said application was dismissed 2009 SCC OnLine Cal 184, (2009) 3 Cal LT 224 by the Single Judge of the High Court. The respondent assailed the order of the learned Single Judge by filing an appeal in APO No. 213 of 2009, wherein it was contended that the appellant had issued a “no claims certificate” to the respondent, thereby forfeiting his right for any claim from the respondent in regard to which the dispute could not be adjudicated by the Arbitral Tribunal. As noticed above, the Division Bench has set aside the order of the learned Single Judge and also the award and directed holding of fresh reference by the Arbitral Tribunal.

    6. The learned Senior Counsel appearing for the appellant submits that the Division Bench failed to appreciate the question that issuance of “no claims certificate” by the appellant was not urged before the Chief Justice in the proceedings under Section 11(6) of the 1996 Act. The said plea was not even urged before the Arbitral Tribunal or before the learned Single Judge. The issue relating to existence of any live claim or the arbitrability of the dispute ought to have been urged in the proceedings under Section 11(6) of the 1996 Act or at least before the Arbitral Tribunal. The question as to whether there was any arbitral dispute or not, could not have been entertained by the Division Bench for the first time. It is further submitted that the Tribunal has rightly passed an award and granted pre-award and pendente lite interest from 17-7-1992 till the realisation of the award amount.

    7. On the other hand, the learned Additional Solicitor General appearing for the respondent submits that having regard to the “no claims certificate” issued by the appellant, the appellant has no right to make any claim except for security deposit of Rs 15,000 from the respondent. There was no arbitral dispute between the parties. Therefore, the claim itself was not maintainable. It is further argued that, at any rate, the appellant was not entitled for any interest having regard to the terms of the contract. He prays for dismissal of the appeals.

    8. Having regard to the contentions urged, the first question for our consideration is whether the Division Bench was justified in considering the arbitrability of the dispute for the first time in the appeal? It is evident from the materials on record that the dispute had arisen between the parties in relation to the contract in question. Therefore, the appellant filed an application before the Chief Justice of the High Court of Calcutta under Section 11(6) of the 1996 Act, for appointment of an arbitrator in terms of the contract which was allowed and an Arbitral Tribunal was constituted for adjudication of the dispute. The arbitrator after giving the parties opportunities of hearing and after considering the materials placed on record made and published the award. The amounts claimed and the amounts awarded against each item of the claim are briefly mentioned as follows:

    Claim Claimed amount (Rs) Awarded amount (Rs) 1. Balance amount payable 45,37,230 2,39,657 2. Claim for price variation due to rise in price of materials, labour and fuel 21,82,719.58 1,17,060 3. Claim for security deposit 15,000 15,000 4. Claim on account of advance payment towards labour supplier 51,000 15,300 5. Claim for advance payment to the earth supplier 1,80,000 54,000 6. Claim for remaining idle wage payment 1,80,000 54,000 7. Claim for overhead charges i.e staff salary and house rent 22,000 15,000 8. Claim for blockage of capital and business loss 12,75,000 6,03,119 9. Claim for interest 1,58,23,193.16 12,44,546

    9. The learned Single Judge had dismissed the application filed by the respondent for setting aside the said award. The issue relating to arbitrability of the dispute was not raised in the proceeding under Section 11(6) of the 1996 Act. One of the issues which can be considered by the Chief Justice under this provision is whether the claim is a live claim. This issue can also be kept open to be decided by the Arbitral Tribunal provided the said plea is urged before the Chief Justice. [See National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd. (2009) 1 SCC 267, p. 283, para 22.2]. The respondent had not raised the said plea before the Chief Justice. Be that as it may, the respondent has not urged the said plea either before the Arbitral Tribunal or before the learned Single Judge in the proceedings under Section 34 of the 1996 Act.

    10. This Court, in McDermott International Inc. v. Burn Standard Co. Ltd. (2006) 11 SCC 181, has held that the party questioning the jurisdiction of the arbitrator has an obligation to raise the said question before the arbitrator. It has been held as under:

    “51. After the 1996 Act came into force, under Section 16 of the Act the party questioning the jurisdiction of the arbitrator has an obligation to raise the said question before the arbitrator. Such a question of jurisdiction could be raised if it is beyond the scope of his authority. It was required to be raised during arbitration proceedings or soon after initiation thereof. The jurisdictional question is required to be determined as a preliminary ground. A decision taken thereupon by the arbitrator would be the subject-matter of challenge under Section 34 of the Act. In the event the arbitrator opined that he had no jurisdiction in relation thereto an appeal thereagainst was provided for under Section 37 of the Act.”

    11. It is also necessary to observe that intervention of the court is envisaged only in few circumstances like fraud or bias by the arbitrators, violation of natural justice. The court cannot correct the errors of the arbitrators. That is evident from para 52 of the judgment in McDermott International Inc. (2006) 11 SCC 181, which is as under:

    “52. The 1996 Act makes provision for the supervisory role of courts, for the review of the arbitral award only to ensure fairness. Intervention of the court is envisaged in few circumstances only, like, in case of fraud or bias by the arbitrators, violation of natural justice, etc. The court cannot correct errors of the arbitrators. It can only quash the award leaving the parties free to begin the arbitration again if it is desired. So, the scheme of the provision aims at keeping the supervisory role of the court at minimum level and this can be justified as parties to the agreement make a conscious decision to exclude the court's jurisdiction by opting for arbitration as they prefer the expediency and finality offered by it.”

    12. Therefore, the Division Bench was not justified while considering the arbitrability of the disputes for the first time, particularly, when the respondent has not urged the issue relating to “no claims certificate” before the Chief Justice, Arbitral Tribunal or before the learned Single Judge.

    13. The next question for consideration is whether the Arbitral Tribunal was justified in awarding interest on the delayed payments in favour of the appellant?

    14. The total interest awarded by the Arbitral Tribunal is Rs 12,44,546 which includes interest for the pre-reference period and also pendente lite interest. Section 31(7)(a) of the 1996 Act provides for payment of interest, as under:

    “31. (7)(a) Unless otherwise agreed by the parties, where and insofar as an arbitral award is for the payment of money, the Arbitral Tribunal may include in the sum for which the award is made interest, at such rate as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made.”

    In this section, a specific provision has been created, whereby if the agreement prohibits award of interest for the pre-award period (i.e pre-reference and pendente lite period), the arbitrator cannot award interest for the said period.

    15. Admittedly, GCC governing the contract between the parties, contains a clause which bars the payment of interest, which is as under:

    “16. (2) No interest will be payable upon the earnest money or the security deposit or amounts payable to the contractor under the contract, but government securities deposit in terms of sub-clause (1) of this clause will be repayable (with) interest accrued thereon.”

    16. Relying on a decision of this Court in Ambica Construction v. Union of India (2017) 14 SCC 323, the learned Senior Counsel for the appellant submits that mere bar to award interest on the amounts payable under the contract would not be sufficient to deny payment on pendente lite interest. Therefore, the arbitrator was justified in awarding the pendente lite interest. However, it is not clear from Ambica Construction (2017) 14 SCC 323 as to whether it was decided under the Arbitration Act, 1940 (for short “the 1940 Act”) or under the 1996 Act. It has relied on a judgment of Constitution Bench in State of Orissa v. G.C Roy (1992) 1 SCC 508. This judgment was with reference to the 1940 Act. In the 1940 Act, there was no provision which prohibited the arbitrator from awarding interest for the pre-reference, pendente lite or post-award period, whereas the 1996 Act contains a specific provision which says that if the agreement prohibits award of interest for the pre-award period, the arbitrator cannot award interest for the said period. Therefore, the decision in Ambica Construction (2017) 14 SCC 323 cannot be made applicable to the instant case.

    17. The learned Additional Solicitor General appearing for the respondent submits that the position of law for cases covered under the 1996 Act i.e if agreement prohibits award of interest then the grant of pre-award interest is impermissible for the arbitrator, has been reiterated by this Court in various judgments.

    18. In Sayeed Ahmed and Co. v. State of U.P (2009) 12 SCC 26, this Court noted that the 1940 Act did not contain any provision relating to the power of the arbitrator to award interest. However, now a specific provision has been created under Section 31(7)(a) of the 1996 Act. As per this section, if the agreement bars payment of interest, the arbitrator cannot award interest from the date of cause of action till the date of award. The Court has observed that in regard to the provision in the 1996 Act, the difference between pre-reference period and the pendente lite interest has disappeared insofar as award of interest by the arbitrator is concerned. Section 31(7)(a) recognises only two periods i.e pre-award and post-award period.

    19. In Sree Kamatchi Amman Constructions v. Railways (2010) 8 SCC 767, this Court was dealing with an identical case wherein Clause 16 of the GCC of Railways had required interpretation. This is the same Clause 16(2) of GCC prohibiting grant of interest which is also applicable in the facts of the present case. The Court held that where the parties had agreed that the interest shall not be payable, the Arbitral Tribunal cannot award interest between the date on which the cause of action arose to the date of the award.

    20. In Union of India v. Bright Power Projects (India) (P) Ltd. (2015) 9 SCC 695, a three-Judge Bench of this Court, after referring to the provisions of Section 31(7)(a) of the 1996 Act, held that when the terms of the agreement had prohibited award of interest, the arbitrator could not award interest for the pendente lite period. It has been held thus:

    “10. Thus, it had been specifically understood between the parties that no interest was to be paid on the earnest money, security deposit and the amount payable to the contractor under the contract. So far as payment of interest on government securities, which had been deposited by the respondent contractor with the appellant is concerned, it was specifically stated that the said amount was to be returned to the contractor along with interest accrued thereon, but so far as payment of interest on the amount payable to the contractor under the contract was concerned, there was a specific term that no interest was to be paid thereon.
    11. When parties to the contract had agreed to the fact that interest would not be awarded on the amount payable to the contractor under the contract, in our opinion, they were bound by their understanding. Having once agreed that the contractor would not claim any interest on the amount to be paid under the contract, he could not have claimed interest either before a civil court or before an Arbitral Tribunal.”

    Therefore, it is clear that the appellant is not entitled for any interest on the amount awarded by the Arbitral Tribunal.

    21. The Arbitral Tribunal had determined the amount payable to the appellant in a sum of Rs 11,13,136 and interest of Rs 12,44,546. A sum of Rs 38,82,150 was deposited by the respondent which includes the award amount, interest for the pre-reference period, pendente lite and post-award interest. We have held that the appellant is not entitled for any interest. The appellant has already withdrawn 50% of the amount deposited by the respondent, which is in excess of the award amount exclusive of interest. Having regard to the facts and circumstances of the case, we deem it proper to direct the respondent not to recover the excess amount withdrawn by the appellant. Ordered accordingly.

    22. The appeals are partly allowed and disposed of in the aforesaid terms without any order as to costs.

    Use AI to get other relevant cases.

    Comments

    Sri Chittaranjan Maity v. Union Of India .
    (Oct 3, 2017)