  • Section 3A of the Kerala Conservation of Paddy Land and WetLand Act, 2008,
  • ARTICLE 226 CONSTITUTION OF INDIA
  • W.P.(C).No.40499/2016 9 2008 Act.
  • Section 5 of the 2008 Act.
  • Land Tax Act,
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Section 3A of the Kerala Conservation of Paddy Land and WetLand Act, 2008,
  • ARTICLE 226 CONSTITUTION OF INDIA
  • W.P.(C).No.40499/2016 9 2008 Act.
  • Section 5 of the 2008 Act.
  • Land Tax Act,
Smart Summary

Factual and Procedural Background

The petitioners purchased approximately 14.997 Ares of property in Resurvey No.107/1-1-2, Block No.23 of Marampally Village on 19.7.2012, as evidenced by a registered sale deed. The property had originally been purchased by the petitioners' predecessors-in-interest in 1977 when it was located in Vazhakkulam Village. Following a bifurcation of Vazhakkulam Village into Vazhakkulam and Marampally Villages, a re-survey was conducted and new survey numbers were assigned. However, during this re-survey, the property was incorrectly recorded as 'Nilam' in the Village and Re-survey records and in the draft data bank prepared for the area. Despite an earlier application by the predecessors-in-interest to correct this entry in the revenue records and draft data bank, no effective action was taken by the respondents.

After purchasing the property, the petitioners applied to the 2nd respondent to correct the property's description in the revenue records. The 2nd respondent advised them to apply under Section 3A of the Kerala Conservation of Paddy Land and WetLand Act, 2008 (the 2008 Act) for consideration after finalisation of the data bank. The petitioners challenged this order through a writ petition. During the pendency of the writ petition, they submitted an application to the 4th respondent Local Level Monitoring Committee (LLMC). The writ petition was disposed of with a direction to the 4th respondent to consider the application after a site inspection within two months. The 4th respondent submitted a report indicating that the property was wrongly included as 'Nilam' in the draft data bank, noting the presence of a double storied building and mature trees, and that the property was bounded by residential houses and a transport road. The petitioners sought a declaration that the property was not 'Nilam' and requested correction of the data bank entry.

Legal Issues Presented

  1. Whether the property in question, erroneously included as 'Nilam' in the Land Data Bank under the Kerala Conservation of Paddy Land and WetLand Act, 2008, can be declared as not being paddy land or wetland for the purposes of the Act.
  2. Whether the Court can direct the exclusion of the property from the notified Land Data Bank once it is established that the inclusion was erroneous.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court examined the statutory scheme of the Kerala Conservation of Paddy Land and WetLand Act, 2008, which aims to prevent indiscriminate reclamation and conversion of paddy lands and wetlands in Kerala due to ecological concerns and declining rice cultivation. The Act establishes a Local Level Monitoring Committee (LLMC) responsible for preparing a data bank of cultivable paddy land and wetlands based on satellite imagery and revenue records. The data bank is to include only cultivable paddy land and wetlands existing at the commencement of the Act.

The Court noted that the property in question was erroneously included in the data bank as 'Nilam' due to classification in revenue records, despite evidence that the land was not paddy land or wetland at the relevant time. The LLMC's report confirmed that the land had been converted prior to 2008 and was not cultivable paddy land or wetland. The Court observed that once the data bank is finalized and notified in the Gazette, the LLMC cannot unilaterally correct errors as it becomes functus officio. Therefore, the Court held that only it, exercising jurisdiction under Article 226 of the Constitution of India, can declare such entries erroneous and direct statutory authorities to modify the data bank accordingly.

Based on the material on record, the Court found that the land should be excluded from the Land Data Bank, as it does not qualify as paddy land or wetland under the 2008 Act.

Holding and Implications

The writ petition is allowed. The Court declared that the petitioners' property situated in Block No.23 of Resurvey No.107/1-1-2 is neither paddy land nor wetland for the purposes of inclusion in the Land Data Bank under the 2008 Act.

The 4th respondent LLMC is directed to exclude the property from the Land Data Bank. If the data bank is still in draft form, the property shall be excluded prior to finalisation and notification. If the data bank has already been finalized and notified in the Gazette, the 4th respondent must issue a corrigendum notification excluding the land and publish it in the Gazette.

Pending such notification, the 4th respondent shall issue a certificate to the petitioners within one week of receiving a copy of the judgment, certifying the exclusion of the land. This certificate can be used by the petitioners to seek permission under the Kerala Land Utilisation Order for other uses of the land.

The finalisation of the data bank or issuance of the corrigendum notification must be completed within six weeks of receipt of the judgment copy. Following notification, the petitioners may approach the Land Tax authority for reassessment and reclassification of the land as 'puriyadom' in the Basic Tax Register.

No new precedent was established; the decision directly affects the parties by correcting the erroneous inclusion of their property in the Land Data Bank.

    SALIM C.K. v. STATE OF KERALA

    The petitioners purchased an extent of 14.997 Ares of property in Resurvey No.107/1-1-2 in Block No.23 of Marampally Village on 19.7.2012, as per sale deed registered as document No.4163/2012 in Perumbavoor SRO. The predecessors-in-interest of the petitioners had purchased the said property in 1977, when the property was situated in the then Vazhakkulam Village. Pursuant to a bifurcation of Vazhakkulam Village as Vazhakkulam and Marampally Villages, a re-survey was conducted, and fresh survey numbers allotted. At the time of re-survey, however, the description of the property was shown as 'Nilam' in the Village and Re-survey records. The same description was mentioned in the draft data bank prepared for the area as well. Although the predecessor-in-interest of the petitioners preferred an application seeking correction of the entry in the revenue records as well as the draft data bank, no effective steps were taken by the respondents towards that end. W.P.(C).No.40499/2016 2

    2. On the petitioners purchasing the property, they preferred an application [Ext.P10] before the 2nd respondent, for correcting the description of the property in the revenue records. The 2nd respondent, by Ext.P11 order dated 12.4.2016, advised the petitioners to prefer an application under Section 3A of the Kerala Conservation of Paddy Land and WetLand Act, 2008, [hereinafter referred to as the "2008 Act"] so that the same could be considered after finalisation of the data bank. The petitioners impugned Ext.P11 order through W.P.(C).No.20490/2016. During the pendency of the writ petition, the petitioners submitted Ext.P12 application before the 4th respondent Local Level Monitoring Committee. The writ petition was thereafter disposed by Ext.P13 judgment, with a direction to the 4th respondent to consider the application preferred by the petitioners, after conducting a site inspection, within two months from the date of receipt of a copy of the judgment. Pursuant to the said judgment, the 4th respondent drew up a report, which was communicated to the petitioners as Ext.P16. In Ext.P16 report, the 4th respondent suggests that the property belonging to the petitioners was wrongly included in the draft data bank as 'Nilam'. It is indicated that, there is an old W.P.(C).No.40499/2016 3 double storied building, and trees that are more than 20 years old standing on the property. The report shows the property as bounded by residential houses on three sides, and the Perumbavoor Aluva transport road on the northern side. In the writ petition, the petitioners are aggrieved by the inaction on the part of the respondents in taking steps to correct the entry in the data bank, by declaring that the property in question is not 'Nilam'.

    3. I have heard Sri. P.B.Krishnan, the learned counsel appearing for the petitioners as also Sri. Surin George Ipe, the learned Government Pleader for the respondents.

    4. On a consideration of the facts and circumstances of the case as also the submissions made across the bar, I find that the 2008 Act was enacted to check the indiscriminate and uncontrolled reclamation and massive conversion of paddy land and wetland that was taking place in the State of Kerala. Noticeably, over the years, the farmers had demonstrated a preference for cultivation of cash crops over paddy cultivation, and this had led to the area under rice cultivation declining drastically from above eight lakh hectares in the early W.P.(C).No.40499/2016 4 1970's to nearly two lakh hectares in early 2000. It was found that the said conversion had also resulted in ecological degradation. It was therefore thought that the wider interests of society mandated that the paddy lands in the State should be preserved.

    5. A perusal of the statutory provisions under the 2008 Act and Rules would indicate that the object of conservation of paddy land and wetland is sought to be achieved through a complete prohibition on reclamation of wetland and removal of sand therefrom, as also through restrictions against the conversion and reclamation of paddy land except in accordance with the provisions of the 2008 Act. The limited purposes for which paddy land can be reclaimed are spelt out in the 2008 Act, and cover only 'public purposes' meaning thereby, purposes for schemes undertaken or financed by the Centre-State Governments, Government-Quasi-Government Institutions, Local Self Government Institutions, Statutory Bodies and other schemes as may be specified by the Government from time to time. There is also provision for accommodating requests from persons owning small extents of land, for reclamation of the same, for construction of residential buildings therein. Thus, the object of the enactment is W.P.(C).No.40499/2016 5 sought to be achieved through a policy that insists on preservation of the paddy lands as existed on the date of coming into force of the 2008 Act, and taking steps to keep in check, attempts at reclamation of the said paddy lands and wetlands.

    6. As a first step for identifying the paddy lands and wetlands that were in existence as on the date of coming into force of the 2008 Act, it was envisaged that a Local Level Monitoring Committee [LLMC], that was constituted in terms of the Act, would be entrusted with the task of preparing a data bank with the details of cultivable paddy land and wetland, within the area of jurisdiction of the Committee, with the help of the map prepared by the State Land Use Board or Centre-State Science and Technology Institutions on the basis of satellite pictures by incorporating the survey numbers and extent in the data bank, and to get it notified by the Panchayat/Municipality/Corporation concerned, and thereafter exhibit the same for the information of the public, in the respective Panchayat/Muncipality/Corporation Office and in the Village Offices. It must be noticed immediately, that the data bank that was contemplated under the provisions of the Act, was to contain details W.P.(C).No.40499/2016 6 only of cultivable paddy land and wetland within the area of jurisdiction of the LLMC concerned, and was not intended to contain details of any other category of land. A perusal of the Kerala Conservation of Paddy Land and WetLand Rules, and in particular, Rule 4, would indicate that, as a first step for collecting the data for preparation of the data bank, the revenue records pertaining to the lands within the area of jurisdiction of the LLMC, had to be perused, and the details of such lands as were shown as paddy lands and wetlands in the revenue records, collected, and the lands inspected by the Village Officer and the Agricultural Officer concerned, and it was only on their satisfaction, with regard to the nature of the land being a paddy land or a wetland, that the same was to be included in the draft data bank that was to be initially prepared. Thereafter, the draft data bank had to be considered by the LLMC, and on a review of the details in the said draft data bank, after obtaining the reports from the National Remote Sensing Agencies, State Land Use Boards, Centre-State Science and Technology Institutions or the Information Kerala Mission, a final data bank had to be prepared. Thereafter, the finalised land data bank had to be forwarded to the Secretary, Local Self Government, who is obliged to notify the said finalised data bank, W.P.(C).No.40499/2016 7 by publication in the Kerala Gazette, and issue directions to publish the same in the Panchayat/Municipality/Corporation Offices and also the Village Offices concerned.

    7. While the statutory scheme noticed above contemplates the inclusion of only paddy lands and wetlands in the Land Data Bank, it would appear that, as a matter of fact, many lands that were not paddy lands or wetlands as on the date of coming into force of the 2008 Act, came to be included in the Land Data Bank solely because the said lands were classified as paddy land or wetland in the revenue records. The instant case appears to be one of that nature, where the land in question was erroneously included in the land data bank. Ext.P16 order of the Agricultural Officer, who is the Convenor of the 4th respondent LLMC, clearly indicates that the land is not a paddy land or wetland, but has in fact been converted prior to 2008. In such cases the problem that arises is that consequent to the erroneous inclusion of lands in the Land Data Bank, a statutory presumption arises that the land in question is either a paddy land or a wetland. Such a presumption arises because the statutory scheme envisages that the LLMC should include only paddy lands and wetlands in the W.P.(C).No.40499/2016 8 Land Data Bank prepared in terms of Section 5 of the 2008 Act. On an error being noticed in the final notified data bank, the LLMC cannot suo motu or on an application correct the same since it becomes functus officio once the final data bank is notified in the Gazette. It follows, therefore, that once it is established that the entry in the notified data bank is erroneous then only this Court, in exercise of its power under Article 226 of the Constitution of India can declare, based on the material produced before it, that the entry of any particular property in the data bank is erroneous and that the said property should be excluded from the said data bank. Consequential directions can then be given to the statutory authorities to give effect to the declaration by modifying the entries in the data bank. In the instant case, the material on record would indicate that the land in question is to be excluded from the data bank.

    8. The upshot of the above discussions is that, the writ petition is allowed, by declaring that the property of the petitioners covered by Ext.P9 document and situated in Block No.23 of Resurvey No.107/1-1-2 is not either paddy land or wetland, for the purposes of inclusion in the Land Data Bank prepared in accordance with the W.P.(C).No.40499/2016 9 2008 Act. The 4th respondent is directed to exclude the said land of the petitioners from the Land Data Bank. If the data bank is at the draft stage, the land shall be excluded before finalising the data bank, and notifying the same. If, on the other hand, the data bank has already been finalised, and notified through publication in the Gazette, then the 4th respondent shall issue a corrigendum notification showing the exclusion of the land from the data bank, and publish the said corrigendum notification in the Gazette. In the meanwhile, the 4th respondent shall, after excluding the lands from the data bank, issue a certificate to the petitioner within a week from the date of receipt of a copy of this judgment, certifying that the lands in question have been excluded from the data bank. The petitioner can utilise the said certificate for approaching the authorities under the Kerala Land Utilisation Order for getting permission to utilise the land for other purposes. The other actions, such as finalising of the Data bank or issuance of the corrigendum notification, shall be taken by the 4th respondent, within a period of six weeks from the date of receipt of a copy of this judgment. On the notification/corrigendum notification being published in W.P.(C).No.40499/2016 10 the Gazette, the petitioner may along with the orders, if any, obtained under the Kerala Land Utilisation Order, approach the authority under the Land Tax Act, for the purpose of getting a fresh assessment done, based on the revised classification of the land as 'puriyadom', and a consequent change of the description of the land as 'puriyadom' in the Basic Tax Register. The writ petition is disposed as above. A.K.JAYASANKARAN NAMBIAR JUDGE prp/

    Use AI to get other relevant cases.