Smart Summary

Factual and Procedural Background

The petitioner, CECL, filed a petition under Section 11 of the Arbitration and Conciliation Act, 1996 seeking appointment of a sole arbitrator to adjudicate disputes said to arise out of a Tripartite Agreement dated 29.01.2004, a Settlement Deed dated 17.03.2006 and other agreements between the parties. The Settlement Deed does not contain an arbitration clause; CECL relied on the arbitration clause in the Tripartite Agreement.

The factual matrix as described in the petition is: Intertoll was a joint venture which obtained a contract with NHAI by Contract Agreement dated 08.08.2002. Intertoll appointed CECL by a letter agreement dated 15.03.2003 to lay fibre-optic cable. On 29.01.2004 a Tripartite Agreement among CECL, Intertoll and RPG assigned CECL's rights under the 15.03.2003 letter agreement to RPG, and RPG was approved as sub-contractor by NHAI. CECL exited the JV and later entered a Consortium Agreement with RPG dated 21.03.2005 under which CECL would assist RPG. NHAI terminated the Contract Agreement with Intertoll on 21.11.2005, generating disputes between NHAI and Intertoll which were referred to arbitration. Intertoll and RPG executed a Settlement Deed dated 17.03.2006 settling their claims; that Settlement Deed contains no arbitration clause. By a Closure Agreement dated 06.09.2011 RPG purported to assign rights back to CECL.

CECL invoked the arbitration clause in the Tripartite Agreement and served a notice on 22.12.2011 proposing an arbitrator; Intertoll disputed existence of any arbitration agreement with CECL, denied that CECL stepped into RPG's shoes, suggested a different arbitrator and objected to non-compliance with contractual pre-conditions. CECL earlier filed Arb. P. 81/2012 under Section 11 which was withdrawn on 04.07.2013 with liberty to approach the Engineer under Clause 50.2 of the Tripartite Agreement. CECL also filed a petition under Section 9 (OMP No. 1282/2014) seeking preservation of monies; that petition was the subject of interim orders (one of which was vacated) and ultimately disposed on 29.01.2016 for failure to invoke the arbitration clause earlier. An appeal FAO(OS) 490/2014 was dismissed with costs in favour of Intertoll.

Legal Issues Presented

  1. Whether an arbitration agreement exists between CECL and Intertoll such that a tribunal can be appointed under Section 11 of the Arbitration and Conciliation Act, 1996.
  2. Whether an arbitration clause contained in the Tripartite Agreement (Clause 50.2) survived: (a) after assignment/substitution of parties by the Tripartite Agreement; (b) after the Settlement Deed dated 17.03.2006 which purportedly settled and discharged earlier contractual rights; and (c) after the Closure Agreement dated 06.09.2011 pursuant to which RPG purported to reassign rights to CECL.
  3. Whether CECL complied with the pre-conditions for invoking arbitration as set out in Clause 50.2 of the Tripartite Agreement.

Arguments of the Parties

Appellant's Arguments (CECL)

  • CECL asserted that an arbitration clause exists in the Tripartite Agreement dated 29.01.2004 and relied on that clause to seek appointment of an arbitrator under Section 11 of the Act.
  • Counsel for CECL submitted that post-Amendment (Arbitration and Conciliation (Amendment) Act, 2015) the court's examination under Section 11 is confined only to existence of an arbitration clause; there was no dispute about existence of such a clause (as per CECL), and therefore an arbitrator should be appointed.
  • CECL relied on the Closure Agreement dated 06.09.2011 to assert that RPG had assigned and/or relinquished its rights and entitlements to CECL, so CECL claimed to stand in RPG's place with rights under the Tripartite Agreement and Settlement Deed.

Respondent's Arguments (Intertoll)

  • Intertoll disputed that any valid arbitration agreement exists between Intertoll and CECL because Clause 50.2 of the Tripartite Agreement envisages arbitration only between the Employer (Intertoll) and the Contractor (RPG), not between Intertoll and CECL.
  • Intertoll pointed out that respondent nos. 2–4 were not parties to the Tripartite Agreement and that CECL was not a party to several agreements relied upon in CECL's notice; hence those agreements do not create arbitration obligations as between Intertoll and CECL.
  • Intertoll contended that the Closure Agreement of 06.09.2011 was executed without Intertoll's consent and therefore did not bind Intertoll; further, FIDIC conditions (which govern the Tripartite Agreement) do not permit assignment without the employer's prior consent, rendering any assignment ineffective against Intertoll.
  • Intertoll argued Clause 50.2 uses the word "could" with respect to settlement in accordance with the Act, indicating arbitration was not mandatory; accordingly, there was no obligatory arbitration agreement between CECL and Intertoll.
  • Intertoll submitted that CECL did not comply with the preconditions of Clause 50.2 (referral to the Engineer) and thus any Section 11 petition was premature.
  • Intertoll maintained that the Settlement Deed of 17.03.2006 novated and discharged the underlying contract between Intertoll and RPG, extinguishing prior rights and the arbitration clause (which the Settlement Deed itself did not contain).
  • Intertoll relied on earlier judicial findings (Single Judge 21.11.2014 in OMP 1282/2014 and Division Bench judgment in FAO(OS) 490/2014) to argue that the question of arbitrability between RPG and Intertoll had already been decided against arbitration; Intertoll also alleged suppression/non-disclosure of those decisions by CECL.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Union of India v. Kishorilal Gupta and Bros. (1960) 1 SCR 493 The principle that an arbitration clause is a collateral but integral part of a contract and generally perishes when the contract is extinguished or substituted by a new contract; where contracts are substituted the arbitration clause in the original contract does not survive, subject to exceptions where the original contract subsists for certain purposes. The Court applied this principle to hold that the arbitration clause in the Tripartite Agreement did not survive because the Settlement Deed substituted and extinguished the earlier contract rights between Intertoll and RPG.
Young Achievers v. Ims Learning Resources Private Limited: (2013) 10 SCC 535 Authority for the proposition that an arbitration clause in an agreement cannot survive if that agreement has been superseded/novated by a later agreement which does not contain an arbitration clause. The Court relied on this decision to reinforce the conclusion that the arbitration clause did not survive when the underlying rights were novated/discharged by the Settlement Deed, which itself had no arbitration clause.
Order of Single Judge dated 21.11.2014 in OMP No. 1282/2014 Factual and judicial finding (in the earlier Section 9 petition) that reassignment to CECL by a closure agreement was prima facie untenable because re-assignment long after earlier assignment to RPG was made without the consent of Intertoll. The Court noted this prior observation and treated it as relevant to the present controversy, observing that CECL had not disclosed this judgment in the present petition.
Division Bench judgment in FAO(OS) 490/2014 (decision dated 20.04.2015 as cited) Finding that the Settlement Deed dated 17.03.2006 and the subsequent agreement dated 06.09.2011 (both lacking arbitration clauses) meant that disputes relating to RPG's claims against Intertoll were not arbitrable. The Court treated this Division Bench decision as directly relevant and consistent with its conclusion that disputes between CECL and Intertoll were not arbitrable; it also noted that the appeal had been dismissed with costs awarded in Intertoll's favour.

Court's Reasoning and Analysis

The Court began by examining Clause 50.2 of the Tripartite Agreement (which sets out the procedure: reference to the Engineer, attempt at amicable settlement within 30 days, reference to the Employer, and if unresolved, settlement "could be settled in accordance with the arbitration and reconciliation act of 1996"). The Court observed that Clause 50.2 refers to disputes between the Employer and the Contractor and that, on a plain reading, it does not contemplate reference of disputes between CECL and Intertoll to arbitration because Intertoll is identified as Employer and RPG as Contractor.

The Court noted that CECL accepted Intertoll is not a party to the Closure Agreement and that the Closure Agreement was executed without Intertoll's consent; accordingly Intertoll could not be compelled to accept CECL as standing in RPG's place simply by virtue of that Closure Agreement.

The Court further reasoned that even if CECL had stepped into RPG's shoes, Intertoll could not be compelled to arbitrate because the agreement between Intertoll and RPG had been discharged by the Settlement Deed dated 17.03.2006. The Settlement Deed, the Court held, settled all outstanding issues emanating from the contract and extinguished the earlier rights of RPG and Intertoll in relation to the contract; the only contract surviving between those parties was the Settlement Deed, which does not contain an arbitration clause.

The Court then applied the legal principle from Union of India v. Kishorilal Gupta and Bros. that an arbitration clause perishes with the contract where the contract is extinguished and substituted by another contract. The Court also relied on Young Achievers v. Ims Learning Resources to the effect that an arbitration clause cannot survive novation/supersession by a later agreement lacking such a clause.

On these bases, the Court concluded that no arbitration agreement exists between CECL and Intertoll, and therefore it was unnecessary to consider the other objections raised by Intertoll (such as non-compliance with Clause 50.2 procedures or FIDIC-related assignment constraints).

The Court additionally criticized CECL's conduct for failing to disclose prior relevant decisions (the Single Judge order dated 21.11.2014 and the Division Bench's decision in FAO(OS) 490/2014) and treated that failure as relevant to the disposition of the petition.

Holding and Implications

HOLDING: The petition under Section 11 is DISMISSED.

Direct consequences ordered by the Court:

  • The petition is dismissed and CECL is ordered to pay costs of Rs. 1,00,000/- to respondent no. 1 (Intertoll) within two weeks.
  • The pending application related to the petition is disposed of.

Implications: As concluded by the Court, no arbitration agreement exists between CECL and Intertoll because the Tripartite Agreement's arbitration clause did not extend to CECL and, in any event, the underlying contract rights between RPG and Intertoll were extinguished by the Settlement Deed which lacks an arbitration clause. The decision resolves the dispute over whether an arbitral tribunal can be appointed between these parties in the present circumstances and results in dismissal of CECL's request for appointment of an arbitrator. The opinion does not purport to establish a novel legal principle beyond applying established authorities on survival of arbitration clauses upon novation/substitution; the ruling is outcome-determinative for the parties to this petition.

All statements in this summary are strictly drawn from the provided opinion and do not add or infer facts beyond that text.

To access the original judgment, please Sign In or Subscribe.

    C.E Construction Ltd. Petitioner v. Intertoll Ics Cecons O&M Company (P) Ltd. & Ors. S

    Vibhu Bakhru, J.:— The petitioner (hereafter referred to as ‘CECL’) has filed the present petition under Section 11 of the Arbitration and Conciliation Act, 1996 (hereafter ‘the Act’), inter alia, praying as under:-

    “a) Allow the present petition and appoint a Sole Arbitrator to adjudicate upon the disputes which have arisen between the Petitioner and the Respondents under the agreement dated 29.1.2004 and other agreements between the parties.”

    2. In paragraph 1 of the petition, CECL has described the disputes to have arisen out of a tripartite agreement dated 29.01.2004 (hereafter ‘the Tripartite Agreement’) and a settlement deed dated 17.03.2006 (hereafter c the Settlement Deed’) including other contracts executed between the parties. Admittedly, the Settlement Deed dated 17.03.2006 does not include an arbitration clause. During the course of the arguments, CECL sought to rely on the arbitration clause as contained in the Tripartite Agreement dated 29.01.2004, in support of its prayer for appointment of an arbitrator.

    3. At the outset, respondent no. 1 had disputed the existence of any arbitration agreement between respondent no. 1 and the petitioner. It was also pointed out that respondent nos. 2, 3 and 4 are not parties to the Tripartite Agreement.

    4. CECL does not dispute that respondent nos. 2, 3 and 4 are not parties to the Tripartite Agreement. Therefore, the question of appointing an arbitrator for any disputes between CECL and respondent nos. 2, 3 and 4 does not arise. Thus, the learned counsel for CECL and respondent no. 1 (Intertoll) were heard confined to the question as to the existence of arbitration agreement between the two parties in the context of the Tripartite Agreement 5. The controversy, whether an arbitration agreement exists between CECL and Intertoll, has to be considered in the context of the following facts:-

    5.1 Intertoll was constituted as a Joint Venture company between CECL, Intertoll ICS India Pvt. Ltd. and Intertoll (Pty) Ltd. Pursuant to tenders floated by the National Highways Authority of India (hereafter ‘NHAI’), Intertoll bid for the works of operation and maintenance of four laned highways on certain sections of National Highway-2 and National Highway-24. The bid submitted by Intertoll was accepted and on 08.08.2002, a “Contract Agreement” dated 08.08.2002 was entered into between NHAI and Intertoll. Thereafter, by a letter dated 15.03.2003-which is described as a back to back contract by CECL in the petition and hereafter referred to as ‘the letter agreement’ - CECL was appointed by Intertoll to execute the work of laying of fibre-optic cable system in connection with certain sections on NH-2, NH-24 and NH-8.

    5.2 Thereafter, on 29.01.2004, the Tripartite Agreement was executed between CECL, Intertoll and M/s. RPG Cables ltd. (hereafter ‘RPG’) whereby CECL assigned all its rights, titles and interest in the letter agreement dated 15.03.2003 in favour of RPG. In furtherance of the Tripartite Agreement, RPG was approved as a sub-contractor by NHAI

    5.3 CECL further submits that it also exited the JV agreement and ceased to be a constituent JV Partner in Intertoll CECL asserts that it has severed its relationship with Intertoll both as a constituent JV Partner and as a sub-contractor.

    5.4 CECL states that, thereafter, it entered into a Consortium Agreement dated 21.03.2005 with RPG whereby the said parties agreed that CECL would assist RPG in performing its work as a sub-contractor to Intertoll; that is, the work that was contracted to CECL under the letter agreement and subsequently assigned to RPG under the Tripartite Agreement.

    5.5 NHAI terminated the Contract Agreement dated 08.08.2002 with Intertoll on 21.11.2005 This led to certain disputes between NHAI and Intertoll, which were referred to arbitration.

    5.6 Intertoll and RPG entered into a Settlement Deed dated 17.03.2006 for settlement of all claims of RPG against Intertoll in respect of the letter agreement dated 15.03.2003 (which was assigned by CECL to RPG).

    5.7 Thereafter, RPG and CECL entered into an agreement dated 06.09.2011 - which is referred to in the petition, and hereafter, as the ‘Closure Agreement’ - whereby RPG relinquished all its rights, interest, entitlements and claims in the Consortium Agreement dated 21.03.2005 in favour of CECL and also assigned all its rights, issues, claims and entitlements arising from or emanating from the Settlement Deed dated 17.03.2006 and under the Tripartite Agreement dated 29.01.2004

    5.8 CECL invoked the arbitration clause contained in the Tripartite Agreement and sent a notice on 22.12.2011 requesting that Justice H.R Malhotra (Retired), a former judge of this Court, be appointed as an arbitrator in connection with inter se disputes arising out of the Tripartite Agreement, Settlement Deed dated 17.03.2006 and the Closure Agreement dated 06.09.2011 Intertoll responded to the aforesaid notice and, inter alia, disputed the existence of any arbitration agreement between Intertoll and CECL. Further, Intertoll also declined to accept that CECL has stepped into the shoes of RPG in terms of the Closure Agreement. However, without prejudice to its contentions, Intertoll also declined the request for appointment of Justice H.R Malhotra as a sole arbitrator and suggested the name of Justice J.K Mehra (Retired) as the sole arbitrator. Intertoll also raised an objection as to the fact that provisions of the arbitration clause under the Tripartite Agreement had not been followed.

    5.9 In view of the above, CECL filed a petition (being Arb. P. 81/2012) under Section 11 of the Act seeking appointment of an arbitrator. However, CECL withdrew the said petition on 04.07.2013 The order passed by this Court (dated 04.07.2013 in Arb. P. 81/2012) indicates that CECL had initially pressed its petition and had withdrawn the same after some arguments with liberty to approach the Engineer as contemplated under Clause 50.2 of the Tripartite Agreement.

    5.10 CECL asserts that in the meantime, Intertoll settled the disputes with NHAI on 06.08.2014 On 20.08.2014, Intertoll also withdrew its suit [CS(OS) 650/2011] filed against NHAI.

    5.11 On or about 17.10.2014, CECL also filed a petition under Section 9 of the Act (being OMP No. 1282/2014) arraying several parties including Intertoll (which was arrayed as respondent no. 8) as respondents. CECL alleged that Rs. 65 crores had been received by Intertoll from NHAI against surrender of claims of over Rs. 300 crores and, inter alia, sought for a direction that the money received from NHAI be preserved in a separate bank account 5.12 The petition does not disclose the fate of the aforementioned petition under Section 9 of the Act (OMP 1282/2014); although a copy of the order dated 29.01.2016 disposing of that petition has been filed along with the petition.

    5.13 However, it was pointed out by the learned counsel for Intertoll that initially an ad interim order dated 20.10.2014 was passed directing Intertoll to maintain status quo with regard to any funds received pursuant to the settlement with NHAI However, the said order dated 20.10.2014 was subsequently vacated by an order dated 21.11.2014 CECL had preferred an appeal against the said order before a Division Bench of this Court [being FAO(OS) 490/2014], which was also dismissed with cost of Rs. 1,00,000/- in favour of Intertoll.

    5.14 The said petition was finally disposed of on 29.01.2016 The Court while disposing of the petition observed that the petition was pending for more than 15 months but no steps had been taken by the petitioners to invoke the arbitration clause, therefore, the petition could not continue. However, the Court further observed that if the contention of petitioners (therein) is accepted in a petition under Section 11 of the Act and an Arbitral Tribunal is constituted, the petitioners would be entitled to move an application for interim order under Section 17 of the Act.

    Submissions

    5. Mr. Mohit Chaudhary, learned counsel appearing for CECL contended that by virtue of the Arbitration and Conciliation (Amendment) Act, 2015, the examination under Section 11 of the Act is confined only to existence of an arbitration clause. He submitted that in the present case, there is no dispute as to the existence of the arbitration clause and, therefore, an arbitrator is required to be appointed.

    6. Ms. Jasleen Oberoi, learned counsel appearing for Intertoll countered the submissions advanced by Mr. Chaudhary and opposed the present petition. Her contentions are summarised as under:

    7.1 First of all, she contended that there was no valid existing arbitration agreement between the parties. She pointed out that CECL had referred to disputes arising out of various agreements. However, Intertoll was not a party to the agreements referred to by CECL and although Intertoll was a party to the Tripartite Agreement, the arbitration clause contained therein did not envisage reference of disputes between CECL and Intertoll to arbitration. She further contended that the notice invoking arbitration dated 10.02.2016 also referred to various agreements to which Intertoll was not a party. She pointed out that Clause 50.2 of the Tripartite Agreement only contained an arbitration agreement for reference of the disputes between Intertoll and RPG and, therefore, no arbitration agreement existed between Intertoll and CECL.

    7.2 She further stated that the Closure Agreement dated 06.09.2011 relied upon by CECL in support of its contention that it had stepped into the shoes of RPG, was not with the consent of Intertoll and, therefore, did not bind Intertoll. She submitted that the Tripartite Agreement dated 29.01.2004 was governed by the General Conditions of Contract as issued by the Federation Internationale Des Ingenieurs Conseils, Third Edition 1987 (FIDIC). She contended that FIDIC conditions of contract did not permit the contractor to assign the contract without the prior consent of the employer and, thus, in the present case, Intertoll was not bound to accept that CECL had stepped into the shoes of RPG. She submitted that any assignment was thus non est as against Intertoll.

    7.3 Next, she submitted that the Tripartite Agreement did not contain an arbitration agreement at all since in terms of Clause 50.2, the unresolved disputes ‘could’ be settled in accordance with the Act. She submitted that the use of the word ‘could’ only indicated that the parties could decide to settle the disputes by arbitration and the same was not mandatory.

    7.4 She also submitted that CECL had not complied with the preconditions for invocation of the arbitration as set out in Clause 50.2 as it had not referred the disputes to the Engineer as contemplated thereunder and, therefore, in any event, the petition was pre-mature.

    7.5 She submitted that the agreement between Intertoll and RPG stood novated by the Settlement Deed dated 17.03.2006 The Tripartite Agreement dated 29.01.2004 only contemplated RPG replacing CECL as a sub-contractor for execution of the works under the letter agreement dated 15.03.2003 She stated that the contract itself stood discharged by the Settlement Deed dated 17.03.2006 and the said Settlement Deed did not contain an arbitration clause.

    7.6 Lastly, she submitted that the question whether an arbitration agreement existed between Intertoll and CECL, stood concluded by the judgement of the Single Judge dated 21.11.2014 passed in OMP 1282/2014 as well as the decision of the Division Bench dated 20.04.2015 rendered in FAO(OS) 490/2014. She also contended that the petitioner had not approached this Court with clean hands and had suppressed the Judgment of the Single Judge dated 21.11.2014 as well as decision of the Division Bench dated 20.04.2015

    Reasoning and Conclusion

    7. At the outset, it is necessary to refer to Clause 50.2 of the Tripartite Agreement which reads as under:-

    “If a dispute of any kind whatsoever arises between the Employer and the Contractor in connection with or arising out of the Contract whether in connection or arising out of the Contract whether the execution of the Works or after the Completion and whether before or after reputation (sic) or other termination, certificate or valuation by the Engineer the matter in dispute shall in the first place be referred to the Engineer with a copy to the Party. The Party shall attempt to settle the disputes amicably within a period of 30 days. If the disputes are not resolved in this manner then the aggrieved party can refer the dispute to the Employer for resolving the same after due discussions with the Chief Executive of the contracting parties.

    In case the dispute still remains unresolved then it could be settled in accordance with the arbitration and reconciliation act of 1996. The Performance under the Contract shall continue during the Arbitration proceedings and payment due to the Contractor by the Employer shall be withheld until they are the subject matter of the Arbitration Proceedings. The decision of the Arbitrator shall be final and binding upon the parties. The cost and expenses of the Arbitration Proceedings will be paid as determined by the Arbitrator.”

    8. Admittedly, Intertoll has been referred to as an Employer and RPG has been referred to as Contractor in the aforesaid clause. Thus, it is clear on a plain reading of the clause that the same does not contemplate reference of any disputes between CECL and Intertoll to arbitration. Mr. Chaudhary also did not dispute the aforesaid position. He, however, contended that by virtue of the Closure Agreement, RPG had assigned all its rights and entitlement under the Tripartite Agreement to CECL and, therefore, CECL was claiming to be a party through RPG. Admittedly, Intertoll is not a party to the Closure Agreement and the same was executed without any consent of Intertoll. Thus, prima facie, Intertoll cannot be compelled to accept CECL as a party to the arbitration agreement in place of RPG.

    9. However, even if it is accepted that CECL had stepped into the shoes of RPG, it could not compel Intertoll to refer the disputes to arbitration. This is so because the agreement between Intertoll and RPG had itself been discharged by virtue of the Settlement Deed dated 17.03.2006 A plain reading of the Settlement Deed indicates that Intertoll and RPG had agreed to settle all outstanding issues emanating from the contract in accordance with the terms as recorded in the Settlement Deed. It is clear from the above that all rights of RPG and Intertoll in relation to the contract - the letter agreement dated 15.03.2003 with CECL and subsequently substituted by RPG by way of the Tripartite Agreement-stood completely extinguished in terms of the Settlement Deed. The only contract that survived between the said parties was the Settlement Deed. Neither RPG nor Intertoll was required to perform any of the terms of the initial contract which stood discharged in terms of the Settlement Deed. And, as pointed out earlier, the Settlement Deed does not contain an arbitration clause.

    10. In Union of India v. Kishorilal Gupta and Bros.: (1960) 1 SCR 493, the Supreme Court had considered the question whether an arbitration clause in a contract survived the substitution of the contract by another contract. After discussing the various decisions, Justice Subba Rao speaking for majority held as under: -

    “10. The following principles relevant to the present case emerge from the aforesaid discussion: (1) An arbitration clause is a collateral term of a contract as distinguished from its substantive terms; but nonetheless it is an integral part of it; (2) however comprehensive the terms of an arbitration clause may be, the existence of the contract is a necessary condition for its operation; it perishes with the contract; (3) the contract may be non est in the sense that it never came legally into existence or it was void ab initio; (4) though the contract was validly executed, the parties may put an end to it as if it had never existed and substitute a new contract for it solely governing their rights and liabilities thereunder; (5) in the former case, if the original contract has no legal existence, the arbitration clause also cannot operate, for along with the original contract, it is also void; in the latter case, as the original contract is extinguished by the substituted one, the arbitration clause of the original contract perishes with it; and (6) between the two falls many categories of disputes in connection with a contract, such as the question of repudiation, frustration, breach etc. In those cases it is the performance of the contract that has come to an end, but the contract is still in existence for certain purposes in respect of disputes arising under it or in connection with it. As the contract subsists for certain purposes, the arbitration clause operates in respect of these purposes.

    11. We have held that the three contracts were settled and the third settlement contract was in substitution of the three contracts; and, after its execution, all the earlier contracts were extinguished and the arbitration clause contained therein also perished along with them. We have also held that the new contract was not a conditional one and after its execution the parties should work out their rights only under its terms. In this view, the judgment of the High Court is correct. This appeal fails and is dismissed with costs.”

    11. Applying the aforesaid principle, it is clear that the arbitration clause in the Tripartite Agreement dated 29.01.2004 does not survive. The Settlement Deed between RPG and Intertoll substituted their rights and obligations under the earlier contract.

    12. In Young Achievers v. Ims Learning Resources Private Limited.: (2013) 10 SCC 535, the parties therein had entered into another agreement which novated and superseded the earlier agreements. The agreements novating the earlier agreements did not contain an arbitration clause. In the aforesaid context, the Supreme Court held that “An arbitration clause in an agreement cannot survive if the agreement containing arbitration clause has been superseded/novated by a later agreement”.

    13. In view of the aforesaid, an arbitration agreement does not exist between CECL and Intertoll. In view of this conclusion, it is not necessary to consider other objections raised by Intertoll.

    14. However, before concluding, it would be necessary to mention that the conduct of CECL is less than fair. The question whether there exists an arbitrable dispute was also one of the issues which was agitated before this Court in OMP 1282/2014. In the order dated 21.11.2014, this Court had, inter alia, observed as under:-

    “(iii). That leaves me with the tripartite agreement dated 29.01.2004 The tripartite agreement was executed among, petitioner no. 1, respondent no. 8 and RPG. By virtue of this agreement, the sub-contract dated 15.03.2003 executed between petitioner no. 1 and respondent no. 8 was assigned in favour of RPG. It is stated that this contract dated 29.01.2004, contains an arbitration agreement which is incorporated in clause 50.2 of the agreement. A perusal of various provisions of the agreement would show that assignment in the first instance of the sub-contract dated 15.03.2003 was made in favour of RPG by petitioner no. 1 with the consent of respondent no. 8. Petitioner no. 1, seeks to re-agitate rights contained in the tripartite agreement by virtue of a closure agreement dated 06.09.2011 Respondent no. 8 is not a party to the said agreement. Re-assignment of rights which were assigned long ago in favour of RPG without the consent of respondent no. 8, seems prima facie untenable.”

    15. In the above mentioned matter, Intertoll was arrayed as respondent no. 8. The aforesaid decision was carried in appeal (in FAO(OS) 490/2014). In that case, the Division Bench had unequivocally held that the disputes between RPG and Intertoll were not arbitrable. The relevant extract of the said decision is quoted below:-

    “28. The agreement dated March 17, 2006 between respondent No. 8 and RPG Cables Ltd. makes a reference to a right in favour of RPG Cables Ltd. against respondent No. 8 with respect to such amount which respondent No. 8 would receive from NHAI pertaining to Optical Fiber Cables (OFC), but this agreement does not have any arbitration clause and assuming the appellant was assigned the rights of RPG Cables under the agreement dated March 17, 2006 when appellant and RPG Cables executed the agreement dated September 06, 2011, which agreement also does not have any arbitration clause, the dispute relating to claims of RPG Cables against respondent No. 8 would not an arbitrable dispute.”

    16. It is also relevant to note that that the aforesaid appeal was dismissed with cost of Rs. 1,00,000/- awarded in favour of Intertoll.

    17. Indisputably, the aforesaid decisions are relevant to the controversy in question but the same were not mentioned in the petition. Although, CECL had mentioned the aforesaid petition under Section 9 of the Act and also annexed the pleadings as well as the order dated 29.01.2016 disposing of the said petition, it failed to make any reference to the judgement dated 21.11.2014 as well as the proceedings before the Division Bench in FAO(OS) 490/2014.

    18. Thus, I consider this a fit case where the petition should be dismissed with costs. Accordingly, the petition is dismissed with cost of Rs. 1,00,000/-. The cost shall be paid to respondent no. 1 (Intertoll) within a period of two weeks from today. The pending application also stands disposed of.