Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 16(c) of the Specific Relief Act
  • Section 55 of the Contract Act, 1872
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Order 6 Rule 3 of the Code of Civil Procedure (CPC)
  • Specific Relief Act, Section 19(b)
  • Article 54 of the Limitation Act, 1963
  • Section 19(b) of the Specific Relief Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 16(c) of the Specific Relief Act
  • Section 55 of the Contract Act, 1872
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Order 6 Rule 3 of the Code of Civil Procedure (CPC)
  • Specific Relief Act, Section 19(b)
  • Article 54 of the Limitation Act, 1963
  • Section 19(b) of the Specific Relief Act
Smart Summary

Factual and Procedural Background

The plaintiff entered into an unregistered agreement dated 19-4-1992 with Defendants 1–11 to purchase 2.08 acres of land for Rs 65,000, paying an advance of Rs 2000 and agreeing to pay the balance of Rs 63,000 within nine months. On 03-02-1993 Defendants 12–15 entered into their own agreement (Ext. B-1) with Defendants 1–11 to buy the same property for Rs 80,000 and, on 19-4-1993, obtained a registered sale deed (Ext. B-3).

The plaintiff issued a notice on 29-4-1993 demanding execution of a sale deed; receiving no satisfactory response, he filed OS No. 63 of 1993 before the Sub-Court, Kuzhithurai, seeking specific performance. The trial court framed four issues, decreed specific performance in favour of the plaintiff, and invalidated the sale in favour of Defendants 12-15. Defendants 12-15 appealed; the High Court of Madras (Madurai Bench) affirmed the trial court (A.S. No. 646 of 1994). Defendants 12-15 then filed the present civil appeal before the Supreme Court, challenging the concurrent findings. The Supreme Court has now delivered the impugned judgment.

Legal Issues Presented

  1. Whether time was of the essence of the 19-4-1992 agreement and, if so, whether the plaintiff’s failure to pay the balance consideration within nine months barred specific performance.
  2. Whether the plaintiff had pleaded and proved continuous readiness and willingness as mandated by Section 16(c) of the Specific Relief Act, 1963.
  3. Whether Defendants 12–15 were bona fide purchasers protected under Section 19(b) of the Specific Relief Act.
  4. Consequent validity of the registered sale deed dated 19-4-1993 executed in favour of Defendants 12–15.

Arguments of the Parties

Appellants (Defendants 12–15)

  • Clause fixing nine months for payment made time the essence; non-payment by the plaintiff repudiated the contract (Section 55, Contract Act).
  • Pleadings did not strictly follow Order 6 Rule 3 CPC and Form 47; hence the mandatory requirement of readiness and willingness under Section 16(c) was not met.
  • They are bona fide purchasers for value without notice; the unregistered agreement in favour of the plaintiff did not appear in the encumbrance certificate, attracting Section 19(b) protection.
  • Cited several Supreme Court precedents emphasising the importance of time stipulations and proper pleadings in specific performance suits.

Respondent (Plaintiff)

  • Contended that defendants failed to measure the property, so the timeline for payment never began; therefore, time was not of the essence.
  • Maintained that the plaint did contain adequate averments of readiness and willingness and that both courts below correctly appraised the evidence.
  • Sought to uphold concurrent findings, arguing there was no miscarriage of justice warranting Supreme Court interference.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Gomathinayagam Pillai v. Palaniswami Nadar, AIR 1967 SC 868 Distinction between default and readiness/willingness; effect of time stipulations Relied on to show that failure to comply with a time-bound payment can defeat specific performance
Harold Wood Brick Co. Ltd. v. Ferris, (1935) 2 KB 198 Time as the essence of contracts Cited by appellants; referred to but not discussed in detail
Saradamani Kandappan v. S. Rajalakshmi, (2011) 12 SCC 18 Re-affirmation that in commercial transactions time can be of the essence Cited to buttress the argument on contractual timelines
Jugraj Singh v. Labh Singh, (1995) 2 SCC 31 Pleading requirements under Section 16(c) Used to argue that strict pleading standards were not satisfied
Ram Awadh v. Achhaibar Dubey, (2000) 2 SCC 428 Readiness and willingness must be proved throughout Invoked in support of appellants’ plea on Section 16(c)
Ouseph Varghese v. Joseph Aley, (1969) 2 SCC 539 Mandatory nature of Section 16(c) Relied upon in the same context
Abdul Khader Rowther v. P.K. Sara Bai, (1989) 4 SCC 313 Pleading and proof of readiness/willingness Referenced by appellants
Pushparani S. Sundaram v. Pauline Manomani James, (2002) 9 SCC 582 Effect of inadequate pleadings in specific performance suits Cited by appellants
Manjunath Anandappa v. Tammanasa, (2003) 10 SCC 390 Importance of compliance with Section 16(c) Cited; principle applied against the plaintiff
Chand Rani v. Kamal Rani, (1993) 1 SCC 519 When time is of the essence; quoted extracts from Halsbury’s Quoted by Court while analysing contractual clause
Hind Construction Contractors v. State of Maharashtra, (1979) 2 SCC 70 Construction of contracts where time stipulation exists with extension clauses Extract reproduced within Chand Rani quotation
Lamprell v. Billericay Union, (1849) 3 Exch 283; Webb v. Hughes, (1870) LR 10 Eq 281; Rickards (Charles) Ltd. v. Oppenheim, (1950) 1 KB 616 Classical English authorities on time stipulation Mentioned in passage quoted from Chand Rani

Court's Reasoning and Analysis

The Supreme Court first examined the agreement dated 19-4-1992 and held that the clause requiring payment within nine months clearly attracted the first part of Article 54 of the Limitation Act. The plaintiff issued notice only after one year and never paid the balance; hence, time was of the essence and the plaintiff was in breach.

Next, the Court scrutinised the plaint. Paragraph 6, though asserting willingness, did not replicate Clause 3 of Form 47 of Appendix A to the CPC. Consequently, the mandatory requirement of continuous readiness and willingness under Section 16(c) of the Specific Relief Act was not met.

The Court then turned to Section 19(b). Because the plaintiff’s agreement was unregistered and absent from the encumbrance certificate, Defendants 12-15 had no notice of it. They had verified title, paid full consideration, and obtained a registered sale deed; thus they qualified as bona fide purchasers protected from specific performance.

Finding that the trial court and High Court had overlooked these critical legal aspects, the Supreme Court set aside the concurrent findings, answered all material issues in favour of Defendants 12-15, and dismissed the suit.

Holding and Implications

Appeal Allowed; judgments and decrees of the High Court and trial court set aside; OS No. 63 of 1993 dismissed; no order as to costs.

Immediate effect: the plaintiff’s claim for specific performance fails and the sale in favour of Defendants 12-15 stands confirmed. The decision reinforces the necessity of (i) strict adherence to time stipulations when the contract so provides, (ii) precise pleadings and proof of readiness and willingness under Section 16(c), and (iii) the statutory protection accorded to bona fide purchasers under Section 19(b). No new legal doctrine is created, but existing principles are emphatically reaffirmed.

To access the original judgment, please Sign In or Subscribe.

    Padmakumari And Others v. Dasayyan And Others

    V. Gopala Gowda, J.— Leave granted. The concurrent finding of fact recorded by the High Court of Madras, Bench at Madurai, in Appeal Suit No. 646 of 1994 affirming First Appeal No. 646 of 1994 the judgment and decree dated 15-6-1994 passed in OS No. 63 of 1993 on the file of the Sub-Court, Kuzhithurai District is under challenge in this appeal by Defendants 12 to 15 urging various legal grounds.

    2. For the sake of convenience, the ranks of the parties assigned in the plaint filed before the trial court is adverted to in this judgment.

    3. Defendants 1 to 11 entered into an agreement of sale on 19-4-1992 in favour of the plaintiff and executed an unregistered agreement agreeing to sell the suit scheduled property measuring 2.08 acres of land belonging to them. The total sale consideration amount was Rs 65,000. Advance amount of Rs 2000 was agreed to be paid for execution of sale and the remaining balance consideration was agreed to be paid within nine months from the date of agreement of sale. Undisputedly, the remaining balance sale consideration was not paid on or before 18-4-1993.

    4*#. On 3-2-1993, Defendants 12 to 15 entered into an unregistered agreement (marked as Ext. B-1) with Defendants 1 to 11 to purchase the suit scheduled property. As per the said unregistered agreement, the property was agreed to be sold for Rs 80,000. Advance amount of Rs 10,000 was also paid to Defendants 1 to 11. On 19-4-1993, the suit scheduled property Sale Deed No. 75 of 1993 (marked as Ext. B-3) was executed by Defendants 1 to 11 in favour of Defendants 12 to 15. Out of the sale consideration of Rs 80,000 a sum of Rs 10,000 was paid as advance amount, a further sum of Rs 30,000 was paid at the time of execution of the sale deed, remaining Rs 40,000 was retained to be paid in favour of Defendants 1 to 11, free of interest, within one month from the date of disposal of IA No. 208 of 1990 in AS No. 95 of 1990 pending on the file of the District Court, Nagercoil. The appeal was filed challenging the decree for partition in OS No. 11 of 1978.

    5. The plaintiff got issued the legal notice (Ext. A-3) on 29-4-1993 to Defendants 1 to 15 demanding execution of the sale deed as per the agreement (Ext. A-1). Defendants 12 to 15 replied vide Ext. B-7. The other defendants did not reply to the demand made by the plaintiff, therefore, he was constrained to institute original suit on 14-6-1993 before the Sub-Court, Kuzhithurai. The written statements were filed by all the defendants denying the claim of the plaintiff inter alia contending that the time is the essence of the contract as per unregistered agreement of sale (Ext. A-1). As the plaintiff had agreed to pay remaining sale consideration of Rs 63,000 within nine months from the date of agreement, the same has not been paid. Since there is breach of contract on the part of the plaintiff and, therefore, he is not entitled for decree of specific performance in respect of the suit scheduled property.

    6. Further, it is pleaded that the plaintiff has not shown his readiness and willingness to perform his part of the contract, as required under Section 16(c) of the Specific Relief Act, therefore, Defendants 1 to 11 contended that the plaintiff is not entitled for a decree of specific performance of the suit scheduled property. Defendants 12 to 15 denied the plaint averments, however, specifically pleaded that they are the bona fide purchasers of the part of the suit scheduled property and they are protected under Section 19(b) of the Specific Relief Act. On the basis of the said pleadings the case went for trial. Before the trial court the plaintiff and the defendants were examined in support of their respective claim and counterclaim. The trial court on the basis of the pleadings and evidence adduced on record has formulated the following four issues:

    6.1. (i) Whether specific performance of the contract as sought by the plaintiff is allowable?

    6.2. (ii) Is sale deed dated 19-4-1993 valid?

    6.3. (iii) Have D-12 to D-15 purchased the suit property in good faith?

    6.4. (iv) What are the reliefs the plaintiff is entitled to?

    7. The trial court on the basis of pleadings and the evidence produced on record has appreciated and answered Issues (i) and (ii) in favour of the plaintiff. Issue (iii) was answered against Defendants 12 to 15 and, accordingly, answered Issue (iv) and passed the decree of specific performance in favour of the plaintiff in respect of the suit scheduled property with certain directions to him.

    8. Aggrieved by the said judgment and decree of the learned trial Judge, Defendants 12 to 15 preferred an appeal before the High Court raising certain grounds inter alia urging that findings and reasons recorded on the contentious Issues (i) to (iii) are erroneous in law and are liable to be set aside and prayed to set aside the judgment and decree of the trial court and disposal of the appeal suit instituted by them. On the basis of the rival legal contentions, the High Court has formulated certain points and the same have been answered in favour of the plaintiff by assigning reasons, rejecting the legal contentions urged in the appeal suit on behalf of Defendants 1 to 15. The concurrent finding recorded in the impugned judgment First Appeal No. 646 of 1994 of the High Court is under challenge in this appeal urging certain grounds and prayed to set aside the impugned judgment and decree.

    9. Mr Thomas P. Joseph, learned counsel for Defendants 12 to 15 (the appellants herein) questioned the correctness of the concurrent finding of fact recorded on the contentious issues raised by the defendants, which the High Court has answered in favour of the plaintiff, contending that as per the unregistered agreement there is a clause stipulating the time of nine months for payment of balance consideration of Rs 63,000 to Defendants 1 to 11 out of the total sale consideration of Rs 65,000, which has not been complied with by the plaintiff. Under Section 55 of the Contract Act, 1872 once the time is specified in the agreement, time is the essence of the contract and the parties shall adhere to the same. Non-adherence of the said contract rendered the contract repudiated, therefore, the plaintiff is not entitled for a decree of specific performance.

    10. The learned counsel for Defendants 12 to 15 relied upon the judgments of this Court in Gomathinayagam Pillai v. Palaniswami Nadar AIR 1967 SC 868, AIR para 4; Harold Wood Brick Co. Ltd. v. Ferris (1935) 2 KB 198, 1935 All ER Rep 603 (CA) and Saradamani Kandappan v. S. Rajalakshmi (2011) 12 SCC 18, SCC para 37 : AIR para 25.

    11. Another ground urged by the learned counsel for Defendants 12 to 15 is that the pleadings on behalf of the plaintiff must be strictly in conformity with Order 6 Rule 3 of the Code of Civil Procedure (“CPC”, for short) which provides the form of pleadings and placed strong reliance upon Clause 3 of Form 47 in Appendix A which reads thus:

    “3. The plaintiff has been and still is ready and willing specifically to perform the agreement on his part of which the defendant has had notice.”

    12. The learned counsel further places reliance upon the plaint averments at Para 6, which is quoted hereinafter, submitted that the said averments are not strictly in conformity with Order 6 Rule 3 CPC of Form 47 of the aforesaid clause, therefore, the plaintiff has not shown readiness and willingness which is the condition precedent as required under Section 16(c) of the Specific Relief Act, that has been ignored by both the courts below, therefore, the concurrent finding recorded by the High Court in the absence of this important aspect of the case has not only rendered the finding erroneous in law but the same are contrary to the judgments of this Court. The learned counsel placed strong reliance upon the following judgments in Jugraj Singh v. Labh Singh (1995) 2 SCC 31, SCC at para 3; Ram Awadh v. Achhaibar Dubey (2000) 2 SCC 428, Ouseph Varghese v. Joseph Aley (1969) 2 SCC 539, Abdul Khader Rowther v. P.K. Sara Bai (1989) 4 SCC 313, Pushparani S. Sundaram v. Pauline Manomani James (2002) 9 SCC 582 and Manjunath Anandappa v. Tammanasa (2003) 10 SCC 390, SCC paras 15, 17 and 18.

    13. The last legal contention urged by the learned counsel for Defendants 12 to 15 (the appellants herein) is that the courts below have erred in law in not noticing the right conferred upon Defendants 12 to 15 under Section 19(b) of the Specific Relief Act as they are bona fide purchasers since they, after proper verification and obtaining the clarification of the property in question, have paid full consideration to Defendants 1 to 11 towards the property in question, therefore, the concurrent finding of the High Court not noticing this important aspect of the matter while affirming the judgment and decree passed by the trial court rendered the finding erroneous in law and, therefore, the same are liable to be set aside.

    14. The learned counsel appearing on behalf of the plaintiff (Respondent 1 herein) sought to justify the impugned judgment and decree of the High Court contending that the High Court in exercise of its appellate jurisdiction examined the correctness of the finding rendered by the trial court on the contentious issues on proper appreciation of the pleadings and evidence on record and the same has been reaffirmed by the High Court by assigning valid and cogent reasons, hence, there is no ground for this Court to interfere with the same in exercise of its appellate jurisdiction as there is either miscarriage of justice or error in the judgment and decree and, therefore, he prayed to dismiss the appeal.

    15. The learned counsel for the plaintiff placing strong reliance upon paragraphs of the plaint in support of the contention that the plaintiff has averred relevant pleadings with regard to the non-compliance with the condition enumerated in the agreement of sale by Defendants 1 to 11 in non-measuring the suit scheduled property before calling upon the plaintiff to pay the balance sale consideration amounts to breach on the part of the defendants. This plea has not been specifically denied by them in their written statement as required under Order 8 Rule 5 CPC, therefore, he submitted that both the courts below have rightly examined the case on proper evaluation of the pleadings and evidence on record and rightly granted the decree in favour of the plaintiff and the same need not be interfered with by this Court in exercise of this Court's jurisdiction.

    16. With reference to the aforesaid rival legal contentions, we are required to examine the correctness of the concurrent finding recorded on the question of stipulation of period to perform the contract by the plaintiff to pay the balance consideration of Rs 63,000 on the basis of which he was awarded the decree of specific performance. We have carefully examined this aspect in the backdrop of the recitals contained in the unregistered agreement to sell the suit scheduled property to the plaintiff. As could be seen from the said agreement the plaintiff has agreed for payment of the balance sale consideration amount within nine months from the date of execution of the agreement to sell. The relevant recitals of Ext. A-1 are extracted hereunder for better appreciation of the contentions urged in this regard by the learned counsel on behalf of Defendants 12 to 15:

    “You are willing to purchase this schedule of property for Rs 65,000. As we were fully aware that there was no possibility to purchase this property for a higher price by anybody else, we also were willing to sell for the same amount and hence we received an advance of Rs 2000 from the total price. This amount of Rs 2000 is received to relieve us a little from our debt trap. You should pay the balance consideration of Rs 63,000 within 9 months.”

    (emphasis supplied)

    17. The above clause in the agreement to sell clearly indicates that the plaintiff has agreed to perform his part of the contract by paying balance consideration amount of Rs 63,000 within nine months. This clause falls within the first part of Article 54 of the Limitation Act, 1963. In support of this contention the learned counsel for Defendants 12 to 15 has placed strong reliance upon the judgments of this Court. It would suffice to refer to Gomathinayagam Pillai v. Palaniswami Nadar AIR 1967 SC 868. Para 9 of the said judgment reads as under: (AIR p. 873)

    “9. The trial Judge apparently confused two independent issues: one of default in performance of the contract by the respondent and the other of readiness and willingness of the respondent to carry out his part of the contract. As observed earlier, if time is not of the essence of the contract, default occurs when a party serves a notice making time of the essence and requires the other party within a reasonable time fixed by the notice to carry out the terms of the contract, and the party served with the notice fails to comply with the requisition. In this case no such notice was served, and from the mere delay in calling upon Appellants 1 and 2 to complete the contract, default on the part of the respondent cannot be inferred. But the trial court also came to the conclusion that the conduct of the respondent as evidenced by his statement and his witnesses proved that he was not ready and willing to perform his part of the contract. This the Court inferred from the delay of three months after 30-4-1959 and the evidence given by the respondent to explain that delay and other circumstances.”

    18. The other judgments relied upon by the learned counsel reiterate the same proposition. It would be worthwhile to extract para 22 of the judgment in Chand Rani v. Kamal Rani (1993) 1 SCC 519, which reads as follows:

    “22. In Hind Construction Contractors case (1979) 2 SCC 70, (1979) 2 SCR 1147 quoting Halsbury's Laws of England, this Court observed at SCR pp. 1154-55 as under:
    ‘7. … In the latest 4th Edn. of Halsbury's Laws of England in regard to building and engineering contracts the statement of law is to be found in Vol. 4, Para 1179, which runs thus:
    “1179. Where time is of the essence of the contract.—The expression time is of the essence means that a breach of the condition as to the time for performance will entitle the innocent party to consider the breach as a repudiation of the contract. Exceptionally, the completion of the work by a specified date may be a condition precedent to the contractor's right to claim payment. The parties may expressly provide that time is of the essence of the contract and where there is power to determine the contract on a failure to complete by the specified date, the stipulation as to time will be fundamental. Other provisions of the contract may, on the construction of the contract, exclude an inference that the completion of the works by a particular date is fundamental; time is not of the essence where a sum is payable for each week that the work remains incomplete after the date fixed, nor where the parties contemplate a postponement of completion.
    Where time has not been made of the essence of the contract or, by reason of waiver, the time fixed has ceased to be applicable, the employer may by notice fix a reasonable time for the completion of the work and dismiss the contractor on a failure to complete by the date so fixed.”
    8. It will be clear from the aforesaid statement of law that even where the parties have expressly provided that time is of the essence of the contract such a stipulation will have to be read along with other provisions of the contract and such other provisions may, on construction of the contract, exclude the inference that the completion of the work by a particular date was intended to be fundamental; for instance, if the contract were to include clauses providing for extension of time in certain contingencies or for payment of fine or penalty for every day or week the work undertaken remains unfinished on the expiry of the time provided in the contract such clauses would be construed as rendering ineffective the express provision relating to the time being of the essence of the contract. The emphasised portion of the aforesaid statement of law is based on Lamprell v. Billericay Union (1849) 3 Exch 283 (Exch p. 308), Webb v. Hughes (1870) LR 10 Eq 281 and Rickards (Charles) Ltd. v. Oppenheim (1950) 1 KB 616, (1950) 1 All ER 420 (CA).’”

    19. The said legal contention urged on behalf of Defendants 12 to 15 has been strongly rebutted by the learned counsel on behalf of the plaintiff contending that the question of payment of balance consideration amount of Rs 63,000 within nine months would have arisen after the terms and conditions of the contract agreed upon by Defendants 1 to 11 if they had measured the suit scheduled property. They have not discharged their part of the contract stipulated in the agreement to sell, therefore, it is urged by him that time was not the essence of the contract as Defendants 1 to 11 themselves have failed to perform their part of the agreement.

    20. The said contention urged on behalf of the plaintiff is unacceptable to us that the question of taking measurement would not arise before the plaintiff performed his part of the contract regarding the balance consideration within the period stipulated in the agreement. Undisputedly, that had not been done by the plaintiff in the instant case within the stipulated time and the notice was issued by the plaintiff only after one year, therefore, the plaintiff has not adhered to the time which is stipulated to pay the balance consideration amount to Defendants 1 to 11 which is a very important legal aspect which was required to be considered by the courts below at the time of determining the rights of the parties and passing the impugned judgment. The courts below have ignored this important aspect of the matter while answering the contentious Issues (i) and (ii) in favour of the plaintiff and granted decree of specific performance in respect of the suit scheduled property. The said finding of fact is contrary to the terms and conditions of the agreement, pleadings and the evidence on record. Accordingly, we answer the said issues in favour of Defendants 12 to 15 after setting aside the concurrent finding of fact recorded by the High Court.

    21. The second important legal contention raised by Defendants 12 to 15 is that the pleadings of the plaintiff are not in conformity with Order 6 Rule 3 CPC, Clause 3 of Form 47 in Appendix A, extracted hereinabove. A careful reading of Para 6 of the plaint makes it very clear that the averment as provided under Clause 3 is not in stricto sensu complied with by the plaintiff. The same is evidenced from the averments made at Para 6 of the plaint which reads thus:

    “6. The plaintiff is ready and willing to perform his part of the contract by paying the balance of sale consideration of Rs 63,000 and take the sale deed in accordance with the provisions of the agreement deed dated 19-4-1992.”

    22. Upon a careful reading of the abovesaid paragraph we have to hold that the plaintiff has not complied with the legal requirement which is mandatory as provided under Section 16(c) of the Specific Relief Act. Section 16(c) fell for consideration and has been interpreted by this Court in a number of cases, referred to supra, upon which reliance has rightly been placed and the said decisions are applicable to the fact situation in support of Defendants 12 to 15 and, therefore, we have to hold that the concurrent finding of fact recorded by the High Court on Issue (i) is erroneous in law and is liable to be set aside.

    23. The last contention urged is whether Defendants 12 to 15 (the appellants herein) are protected under Section 19(b) of the Specific Relief Act as they being the bona fide purchasers. The learned counsel for Defendants 12 to 15 has rightly invited our attention that the non-compliance with the contract regarding payment of balance consideration to Defendants 1 to 11 on the part of the plaintiff within nine months is an undisputed fact and further the agreement of sale is not registered, as is evidenced from the encumbrance certificate obtained by Defendants 12 to 15 before they entered into an agreement (Ext. B-1). Both the courts below have erroneously recorded an erroneous finding on the non-existent fact holding that the agreement of sale in favour of the plaintiff is a registered document which, in fact, is not true. The same is evidenced from the encumbrance certificate. More so, Defendants 12 to 15 before entering into the agreement with Defendants 1 to 11 have made proper verification from the competent authority to purchase the part of the suit scheduled property and got the agreement of sale (Ext. B-1) executed in their favour, from Defendants 1 to 11 and thereafter, they got the sale deed registered by paying sale consideration amount. As could be seen from the agreement of sale and registered sale deed, which is marked as Ext. B-3, it is very clear that Defendants 12 to 15 have paid the sale consideration amount of the property, therefore, the reliance placed upon Section 19(b) of the Specific Relief Act as they being the bona fide purchasers, the specific performance of contract cannot be enforced against the transferees. Defendants 12 to 15 being the transferees as they have purchased the suit scheduled property for value and have paid the money in good faith and without notice of the original contract.

    24**. In view of the aforesaid facts, the purchase of the suit scheduled property by Defendants 12 to 15 for a valuable consideration is established by the above defendants by adducing evidence on their behalf before the trial court. Both the courts below have omitted to consider this important piece of pleadings as also the material evidence on record thereby the concurrent finding recorded on the contentious issues has been rendered erroneous in law and is liable to be set aside. Accordingly, we answer the said issues in favour of Defendants 12 to 15.

    25. For the reasons stated supra, Defendants 12 to 15 (the appellants herein) must succeed. Accordingly the appeal is allowed, the impugned judgments and decrees of the High Court and the trial court are hereby set aside and the suit is dismissed. There shall be no order as to costs.

    Use AI to get other relevant cases.

    Comments

    Padmakumari And Others v. Dasayyan And Others
    (Apr 7, 2015)