Factual and Procedural Background

The plaintiff is a company engaged in sugar production that generates part of its required electricity from its own generating sets. The plaintiff was liable to pay electricity duty under the Uttar Pradesh Electricity (Duty) Act, 1952. The vires of that Act had been challenged in writ proceedings and ultimately upheld by the Supreme Court on 19.8.1983. After that decision, Defendant No. 2 sent a letter dated 22.2.1984 calling upon the plaintiff to pay Rs. 14,13,786.84 as duty. On 24.3.1984 Defendant No. 2 addressed a letter to the Collector seeking collection of Rs. 12,91,411.07 (copy sent to the plaintiff), and the plaintiff's earlier representations about its liability were rejected.

Treating the 24.3.1984 letter as a certificate authorizing coercive recovery, the plaintiff filed a suit for a perpetual injunction restraining the State of Uttar Pradesh (Defendant No. 1) and the Assistant Electrical Inspector (Defendant No. 2) from recovering the stated amount as an arrear of land revenue for the period November 1970 to September 1983, without first examining what duty was actually due and without giving credit for Rs. 7,59,614.22 already paid. The trial court dismissed the suit on the ground that the plaintiff was required to deposit the amount under protest before filing the suit. The plaintiff appealed; the present opinion disposes of that appeal.

Legal Issues Presented

  1. Whether the letter dated 24.3.1984 amounted to a "certificate" under the Revenue Recovery statutory scheme enabling recovery as an arrear of land revenue.
  2. Whether the plaintiff was entitled to a perpetual injunction under Section 38 of the Specific Relief Act, 1963, to restrain recovery of the alleged electricity duty.
  3. Whether the statutory scheme (including provisions requiring payment under protest and bar provisions) and Section 41 of the Specific Relief Act preclude granting an injunction in these circumstances.
  4. Whether the plaintiff's conduct (including its prior knowledge, representations, partial payments, and failure to seek a declaration with appropriate court-fee) disentitles it to equitable relief by injunction.

Arguments of the Parties

Appellant's Arguments

  • Mr. Vishnu Sahai, counsel for the appellant, submitted that money is property and that by calling upon the plaintiff to pay the amount specified in the letter dated 24.3.1984, the plaintiff's right to property was threatened because the amount could be recovered as an arrear of land revenue.
  • The plaintiff asserted that the letter to the Collector had been treated as a certificate for recovery and that coercive recovery could follow; the plaintiff sought to prohibit such recovery by perpetual injunction.
  • The plaintiff contended that, properly applied to the facts, the statutory provisions would not render it liable to the full amount called for in the letter.

Respondent's Position (as described in the opinion)

  • The defendants maintained that the letter dated 24.3.1984 was not a certificate in the form required by the Revenue Recovery scheme and therefore did not authorize coercive recovery by the Collector.
  • Statutory procedure for recovery as an arrear of land revenue (under the Revenue Recovery Act read with the U.P. Zamindari Abolition and Land Reforms Act) requires a properly framed certificate and provides that a person denying liability must pay the amount under protest and then sue for repayment; thus an injunction is inappropriate.
  • The defendants implicitly relied on statutory bars and procedural requirements (deposit under protest, specified remedies) to argue the suit for injunction was premature and impermissible.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Decision of the Supreme Court dated 19.8.1983 (upholding validity of the Uttar Pradesh Electricity (Duty) Act, 1952) The Act was held valid, underpinning the defendant's claim for duty. Used as background: the Supreme Court's decision removed the vires challenge, after which the defendant sought recovery of duties from the plaintiff.
Unspecified precedents concerning the power of a court in an injunction suit to go into title even without a specific prayer for declaration The principle that, in appropriate cases, a court entertaining an application for injunction may examine title even without a prayer for declaration. The court noted these precedents are guidance to allow relief without technical refusal where the plaintiff's conduct is clean, but said they cannot be used to avoid procedural requirements (such as seeking a declaration and paying ad valorem court fee) when the plaintiff's conduct is not clean.

Court's Reasoning and Analysis

The court's reasoning proceeded in a step-wise manner, applying statutory requirements and equitable principles strictly to the facts pleaded:

  1. The trial court's judgment was vulnerable on the narrow ground that it proceeded on a finding that a certificate had been issued; however, this court would not interfere if the suit was dismissible on other grounds set out in the opinion.
  2. On the statutory formality issue, the court held that recovery of electricity duty as an arrear of land revenue must follow the Revenue Recovery scheme and the rules framed thereunder. A letter such as the 24.3.1984 communication to the Collector is not the "certificate" in the prescribed format contemplated by statute and the rules. Because the requisite proforma certificate and material information were not present, the plaintiff's apprehension of immediate coercive recovery based on that letter was premature.
  3. Concerning injunctive relief, the court examined Section 38 of the Specific Relief Act (discretionary power to grant prohibitory injunctions) and emphasised that subsection (3) lists specific circumstances that must be pleaded and proved when a person alleges invasion or threatened invasion of rights. The plaintiff failed to establish the necessary conditions under Section 38(3): it did not assert that the defendant was a trustee of the plaintiff's money; clause (b) (where pecuniary compensation would not be adequate) was not attracted because the plaintiff could seek recovery after illegal seizure; multiplicity of proceedings (clause (d)) was not shown.
  4. Even assuming Section 38(3) requirements might be met, Section 41 of the Specific Relief Act (which enumerates circumstances in which an injunction may be refused) imposed additional barriers. The statutory recovery procedure is non-judicial — a Collector acts upon receipt of a proper certificate and follows statutory steps (orders, demand/citation, coercive measures). The legislature has provided that a person denying his liability, when recovery is initiated under a certificate, may sue for repayment only after paying the amount under protest in writing (reference to Section 4 of the Revenue Recovery Act and Section 287-A of the U.P. Zamindari Abolition and Land Reforms Act). This reflects a public policy that those denying liability must first make payment under protest and then challenge recovery.
  5. The court held that granting a perpetual injunction could effectively restrain the Collector (who is not subordinate to the civil court) from initiating statutory recovery proceedings, which is prohibited by Section 41(b) of the Specific Relief Act. An equally efficacious remedy — paying under protest and then suing for repayment — was available to the plaintiff, so Clause (h) of Section 41 also precluded injunction.
  6. The plaintiff's conduct was independently fatal to its claim for equitable relief. The court observed the plaintiff admitted some liability and had made partial payments; it knew defendants had refused its earlier representations and that statutory conditions (payment under protest and payment of ad valorem court fee for declaration) applied. By suing on the premise that a certificate had been issued (when it had not) and by not seeking a declaration while avoiding the ad valorem court fee, the plaintiff's conduct amounted to an attempt to circumvent statutory requirements and disentitled it to equitable assistance (invoking Clause (i) of Section 41).
  7. The court emphasised that courts should scrutinise plaints in injunction suits to ensure the requirements of Section 38 are prima facie satisfied and that none of the prohibitions in Section 41 are attracted. Where allegations are incomplete or the plaintiff should have sought declaratory relief (and paid appropriate court fee), the plaint should be rejected after opportunity to amend. Here, because the 24.3.1984 letter was not a certificate and coercive recovery could not yet be initiated, the suit was premature and ought not to be entertained.

Holding and Implications

HOLDING: The appeal is dismissed. (Final line: "Appeal Dismissed.")

Immediate Consequences:

  • The dismissal upholds the conclusion that the plaintiff is not entitled to a perpetual injunction at this stage; the trial court's dismissal (that a deposit under protest was required before suing) is sustained on the alternative statutory and equitable grounds analysed by this court.
  • There is no order as to costs in the appeal.

Broader Implications and Guidance from the Court:

  • Court reaffirmed that recovery under the Revenue Recovery scheme is a statutory, quasi-administrative process requiring a proper certificate in the prescribed form before coercive steps can be taken; a mere communication to the Collector in an informal form is not such a certificate.
  • Court emphasised the limited and discretionary nature of injunctions under Section 38 of the Specific Relief Act and the importance of checking the prohibitions in Section 41 (including the statutory expectation that a person disputing liability must pay under protest and sue for recovery where provided by statute).
  • Courts are advised to scrutinise plaintiffs' conduct and the pleadings in injunction suits — if a plaintiff seeks injunctive relief without fulfilling statutory preconditions (or with conduct suggesting an attempt to avoid statutory requirements such as payment under protest or payment of ad valorem court fee for declarations), equitable relief should be refused and the plaint may be rejected with an opportunity to amend where appropriate.

This summary is prepared strictly from the content of the provided opinion and does not add or infer facts beyond the text supplied.

    Sir Shadilal Enterprises Ltd. v. State Of U.P And Others

    S.C Mohapatra and V.P Goel, JJ.:— Dismissal of suit seeking relief of perpetual injunction is grievance of plaintiff in this appeal.

    2. Plaintiff is a company incorporated under the Companies Act which carries on business of production of Sugar amongst others. For such production, it requires electricity. Part of electricity required is generated by plaintiff from its generating sets. For the said electricity generated, plaintiff is liable to pay duty as provided in the Uttar Pradesh Electricity (Duty) Act, 1952. Vires of this Act as challenged by plaintiff and others in various writ applications in this Court and thereafter, the litigation as carried to Supreme Court. After decision of Supreme Court on 19.8.1983 upholding validity of the Act, Defendant No. 2 called upon plaintiff in letter dated 22.2.1984 to pay Rs. 14,13,786.84 P. as duty under the Act. After one month, defendant no. 2 addressed a letter to Collector on 24.3.1984 to collect Rs. 12,91,411.07 paise from plaintiff, copy of which as sent to plaintiff to pay the same failing which the same could be recovered. Prior to this letter plaintiff as making representations about its liability which were rejected. Treating letter to Collector as Certificate for recovery of the amount mentioned therein under the coercive process, plaintiff filed the suit for perpetual injunction prohibiting State of Uttar Pradesh (Defendant No. 1) and Assistant Electrical Inspector (Defendant No. 2) from recovering the amount as stated in letter dated 24.3.1989 under coercive process or as arrear of land revenue towards Electricity duty for the period between November, 1970 and September, 1983 before examining the duty actually due and taking into account Rs. 7,59,614.22 paise paid. Trial Court dismissed the suit finding that before filing the suit plaintiff is required to deposit the amount under protest.

    3. Judgment of trial court is vulnerable on the short ground that it proceeded on the finding that a certificate has been issued. However, the same cannot be interfered with in case it is found that the suit is liable to be dismissed on other grounds.

    4. For deciding the appeal it is to be remembered that plaintiff based its suit asserting that a certificate for recovery of the amount has been issued. If this is found to be incorrect court should not exercise its judicial discretion to grant relief of perpetual injunction under Section 38 of the Specific Relief Act.

    5. It is not in dispute that arrears of electricity duty is to be recovered as arrear of Land Revenue. In the State, Land Revenue is recovered under the provisions of the Uttar Pradesh Zamindari Abolition and Land Reforms Act, Dues which are not Land Revenue but are to be recovered as arrear of Land Revenue are to be recovered under the Uttar Pradesh Public Monies (Recovery of Dues) Act, if the dues are public money as provided under the said Act. It is not disputed that arrears of electricity duty is not public money under the said Act. Therefore, this special statute is not attracted. Provisions of the Revenue Recovery Act which apply to all other dues recoverable as land revenue. Rules have been made by State Government under the Revenue Recovery Act. Authority authorised to collect the dues is required to issue a certificate to the Collector for recovery of the amount as arrear of land revenue in the prescribed form. A letter to Collector as in the letter dated 24.3.1984 is, thus, not a certificate as envisaged under the Statute. Plaintiff misconceived such letter to be a certificate and court also did not consider the provisions of the Statute. Apart from a Certificate being required to be issued in the proforma, all the material informations are required to be incorporated therein since a proceeding for initiation of coercive process is required to be clear in all respects. In letter dated 24.3.1984 details of the amount sought to be recovered have not been mentioned. Amount from November 1970 to September 1983 does not give a clear picture of the dues. However, it is not required to delve into the matter further as no certificate has been issued and as such apprehension of plaintiff that amount mentioned in the letter dated 24.3.1983 by coercive procedure is premature.

    6. Prohibiting injunction with mandatory injunction to decide the liability of plaintiff is a relief as provided in Section 38 of the Specific Relief Act, 1963. It is a discretionary power of court as provided under sub-section (1). No doubt such power is to be exercised judicially. As sub-section (1) provides discretion of court is restricted by providing that the same is subject to other provisions in the Chapter. Added to it, sub-section (3) provides for four circumstances under which prohibitory injunction can be granted here defendant invades or threatens to invade right of the plaintiff or enjoyment of property.

    7. Mr. Vishnu Sahai, learned counsel for appellant submitted that money is a property and by calling upon plaintiff to pay the amount as specified in letter dated 24.3.1984, right of the plaintiff to property is threatened to be invaded since the same could be recovered as arrear of land revenue.

    8. It is, however, to be remembered that inspite of invasion of a right atleast one of the requirements as provided in Section 38(3) of the Specific Relief Act is to be pleaded and proved. It is not the case of the plaintiff that defendant is a trustee of the money of the plaintiff. Since plaintiff is called upon to pay a specific amount, clause (b) of Section 38(3) is not attracted. No case has been made out by plaintiff that in case the amount is recovered from plaintiff by coercive process, the same is such invasion that compensation of money could not afford adequate relief. When money is recovered, plaintiff can file a suit for realisation of such money and damages for illegal recovery. Fourth clause is also not attracted as there is no question of avoiding any multiplicity of judicial proceeding.

    9. Even assuming that any of the requirements as envisaged under Section 38(3) of the Specific Relief Act is satisfied, plaintiff is to overcome the hurdles in Section 41 providing for refusal of injunction.

    10. There is no judicial proceeding pending. Only a letter has been addressed to Collector with copy to plaintiff. Recovery under the Revenue Recoveries Act is not a judicial proceeding as no lis is to be adjudicated. Only hen Collector receives a certificate he considers whether he could take steps. Such consideration is not adjudication. When Collector receives a certificate, he is to adopt the procedure as laid don in the U.P Zamindari Abolition and Land Reforms Act. Collector is to pass an order directing the Tahsildar to recover the dues as arrear of land revenue. Tahsildar is to issue a demand or citation as the case may be. In case the amount is not paid, question of coercive process arises. Legislature has in its intelligence provided in Section 4 of the Revenue Recovery Act that a person who denies his liability when a proceeding for recovery is initiated under a certificate can institute a suit for repayment of the amount after paying the amount under certificate under protest made in writing at the time of payment and signed by him or his agent. Under Section 287-A of the U.P Zamindari Abolition and Land Reforms Act similar provision has been made. Since electricity duty is to be recovered hen the same remains unpaid, under the Revenue Recoveries Act following the provisions of U.P Zamindari Abolition and Land Reforms Act, it can safely be concluded that public policy is that a person denying liability has to pay the amount sought to be recovered for which he denies liability under protest in writing and then file a suit for repayment. Section 330 of the U.P Zamindari Abolition and Land Reforms Act in that context provides for bar of suit save as otherwise provided under the Act. Hence, in vie of the legal provision no suit for injunction could be filed here an amount is to be recovered as Land Revenue.

    11. Granting relief of perpetual injunction could have the effect of restraining the Collector who is not subordinate to court from initiating a proceeding for recovery which is prohibited under Section 41(b). On this ground also relief sought cannot be granted. Clauses (c) to (g) and (i) are not attracted. Under clause (h) also an equally efficacious remedy is available by filing a regular suit after complying with the condition of protest payment. Hence no relief of injunction can be granted on this ground.

    12. Conduct of plaintiff is also an important matter for grant of relief of injunction. Clause (i) of Section 41 of the Specific Relief Act which provides that an injunction cannot be granted hen conduct of plaintiff or his agent has been such as to disentitle him to the assistance of the Court.

    13. In this case plaintiff does not dispute that it is liable to pay electricity duty. As revealed in the plaint it has paid some amount. Entire claim of plaintiff is that in case provisions are properly applied to the facts and circumstances, it could not be liable to pay the amount as called upon in letter dated 24.2.1984 There is no clear evidence that after receipt of letter dated 24.3.1984, it made any representation to defendants. In case prior to issue of letter dated 24.3.1984, plaintiff made any representation, it had knowledge that defendants have refused the same. In such circumstances, it as necessary for plaintiff to seek a declaration in the suit that it is not liable to pay any further amount than what has been paid. Plaintiff had knowledge that for seeking the declaration and consequential relief of injunction, it has to pay advalorem court fee. When a plaintiff having knowledge that defendant is disputing his right does not claim a declaration by adjudicating the validity of his claim to right, it is a subterfuge and conduct of plaintiff not being clean, relief of injunction cannot be granted in a suit for injunction only. Added to plaintiff having knowledge that in case he does not pay the dues, the same can be recovered as arrear of land revenue and to get his non-liability established he has to pay the amount under protest, his filing of the suit before issue of certificate by wrongly asserting that a certificate has been issued is an attempt to over-reach the law and therefore, plaintiff cannot get any assistance from the court.

    14. Courts which are approached for perpetual injunction should carefully read the plaint to be prima facie convinced that on the assertion in the plaint, requirements of Section 38 of the Specific Relief Act are satisfied and prohibitions as provided under Section 41 of the Act are not attracted. In case an authority is alleged to have exercised his statutory power, shortcomings in exercise of such powers are also to be clearly stated. Whenever court is satisfied that plaintiff has not clearly specified the necessary facts in detail, it ought to reject the plaint after giving opportunity to plaintiff to ra'ctify the same. In case plaintiff ought to have sought for a declaration of his non-liability and consequential relief of perpetual injunction, opportunity ought to be given to amend the plaint and pay the advalorem court fee if it is satisfied that plaintiff did not intend to take advantage of avoiding to pay the court fee or over-reaching the defendant to utilise the court for getting a benefit, which is otherwise barred or conditioned. When despite declaration, relief of injunction ought not to be granted, court could not consider the right of the plaintiff as court could not grant a decree which cannot be executed. Unless courts become vigilant at each stage of a suit, there is every chance for a plaintiff utilising the court which otherwise could not have been possible. Precedents providing that in a suit for injunction court can go into the question of title even without a prayer for declaration is only a guidance to help plaintiff to get the relief without the technical refusal of the same here conduct of plaintiff is clean. It cannot be utilised by plaintiff to avoid the normal rule to seek declaration and get consequential relief. Equitably considered also plaintiff's suit is pre-mature. A letter has only been issued by defendant No. 2 for taking steps to recover the amount as indicated therein. This letter is not a certificate as provided under the rules made under Revenue Recovery Act. On the basis of such a letter, coercive proceeding cannot be initiated by the Collector. Therefore, no immediate cause arises for grant of perpetual injunction as coercive process cannot be used for recovery of the amount. Once such process starts, plaintiff can file a suit by depositing the amount under protest. No case has been made out in the plaint that by such deposit plaintiff could be ruined, which cannot be compensated by payment of damages and, therefore, suit at this stage should be entertained. Liability of plaintiff is an academic question and we need not delve into such a question.

    15. In result, there is no merit in the appeal, which is dismissed., There shall be no order as to costs in this appeal.

    16. Appeal Dismissed.