  • Section 64 of the Electricity Act, 2003 (the Act) read with Regulation 3 (6) of the Central Electricity Regulatory Commission
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Section 64 of the Electricity Act, 2003 (the Act) read with Regulation 3 (6) of the Central Electricity Regulatory Commission
Smart Summary

Structured Summary of the Opinion — Appeal No. 123 of 2011

Factual and Procedural Background

This appeal arises from an order dated 29.04.2011 of the Central Electricity Regulatory Commission (Central Commission) that declared the Date of Commercial Operation (COD) of the 400 kV Barh-Balia double circuit transmission line (constructed by Power Grid Corporation of India, "POWERGRID" — Respondent no.1) as effective from 01.07.2010. The Appellant is Punjab State Power Corporation Ltd. (successor to Punjab State Electricity Board). Respondents 2–17 are the beneficiaries in the Northern Region and the Central Commission is Respondent no.18.

National Thermal Power Corporation (NTPC) was constructing Barh Super Thermal Power Station (STPS). POWERGRID was responsible for the Barh-Balia transmission line and Balia sub-station; NTPC was responsible for the Barh sub-station and the switchgear at the Barh end. POWERGRID completed the transmission-line works (within its scope) and "idle charged" the line from the Balia end on 30.06.2010 and declared COD w.e.f. 01.07.2010. The Barh sub-station works and the switchgear at Barh end (NTPC's scope) were delayed; power did not flow on the line initially.

POWERGRID filed a petition for tariff determination on 01.10.2010. The Central Commission heard the matter (hearing on 25.01.2011) and issued the impugned order on 29.04.2011 determining tariff from 01.07.2010. The Appellant filed affidavits raising objections (04.03.2011, 15.03.2011 and 07.04.2011) asserting the line was idle and that certain COD conditions were unmet. Aggrieved by the Central Commission's order, the Appellant brought this appeal.

Legal Issues Presented

  1. Whether a new transmission line that has been charged from one end by the transmission licensee, while the switchgear, protection system and metering arrangement at the other (generating-station) end — works not within the transmission licensee's scope and not ready — and with no flow of power on the line, can be declared as having attained commercial operation (COD) for the purpose of raising transmission charges on the beneficiaries?

Arguments of the Parties

Appellant's Arguments (Punjab State Power Corporation Ltd.)

  • The Tariff Regulations require three conditions for COD of an element of transmission system: successful charging, trial operation and being in regular service. The petition filed by POWERGRID did not aver that trial operation and regular service had been carried out.
  • The Central Commission failed to consider the Appellant's three affidavits (04.03.2011, 15.03.2011, 07.04.2011) and relevant provisions of the Act, Tariff Regulations and the Indian Electricity Grid Code before declaring COD.
  • Under the Grid Code, metering and data collection (SEM installation and testing at both ends) is the function of the RLDC; the meters had not been installed at both ends (as of 16.05.2011 according to the Appellant), so the line could not have been commissioned.
  • The petition included minutes indicating that until COD of the first NTPC unit at Barh, transmission charges would be borne by NTPC. The Central Commission failed to account for that arrangement.
  • Typically an indemnification agreement provides compensation from the generating company to the transmission company if the transmission line is completed but the generating project is delayed; the Central Commission did not consider such commercial arrangements.

Respondent no.1's Arguments (Power Grid Corporation of India)

  • The petition (01.10.2010) disclosed that construction of the line was completed in June 2010. POWERGRID had informed regional committees and the position (claiming commercial operation w.e.f. 01.07.2010) was known to the Appellant.
  • The Appellant did not raise objections during the Central Commission proceedings until after the hearing (which concluded on 25.01.2011 and the matter was reserved). The Appellant's objections were filed only after the hearing and no re-hearing was sought.
  • The Tariff Regulations contain a proviso that, if an element is ready for regular service but is prevented from providing such service for reasons not attributable to the transmission licensee, the Commission may approve COD prior to actual regular service. POWERGRID submitted that the line was completed within its scope and sought COD under that proviso.
  • The switchgear and CTs/PTs for protection and metering at Barh end were NTPC's responsibility; POWERGRID's obligation (as CTU) was to provide main and check meters only after NTPC had established the control room/panel and was ready to energise from Barh end.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court structured its analysis by first examining the factual sequence and then applying the definition of "date of commercial operation (COD)" from the Tariff Regulations, 2009. The relevant definition requires that, for a transmission element, the COD is the date from which an element is in regular service after successful charging and trial operation; additionally, a proviso allows the Commission to approve COD prior to regular service only where the element is ready for regular service but is prevented from providing such service for reasons not attributable to the transmission licensee.

Applying that framework, the court observed:

  • The Barh-Balia line was charged only from the Balia end on 30.06.2010 and was idle because the Barh-end switchgear, protection and metering arrangements (NTPC's scope) were not ready on 01.07.2010. These components were reported to have been completed only in August 2011 and the first circuit was loaded on 02.08.2011 (second circuit on 19.08.2011).
  • Therefore, the three conditions in the Tariff Regulations — successful charging, successful trial operation, and being in regular service — were not fulfilled on 01.07.2010. Specifically, trial operation from both ends and regular service were not possible without the Barh-end switchgear and associated systems.
  • The court considered POWERGRID's reliance on the second proviso (allowing COD when an element is ready but prevented from providing service for reasons not attributable to the transmission licensee) and concluded that the proviso did not apply because the transmission line as a whole was not "ready for regular service": the Barh-end components were part of the transmission system and their non-installation meant the element was not ready.
  • The court questioned the existence of any trial operation report or proof of completed trial operation. On inquiry, POWERGRID could not produce evidence of trial operation prior to the COD declaration. The court therefore concluded trial operation had not been completed when COD was declared.
  • Procedurally, the court noted that the Appellant filed three affidavits after the hearing but before the impugned order, and those affidavits were not considered by the Central Commission. The impugned order records that "No reply has been filed by the respondents" in response to the public notice, which the court found inconsistent with the presence of the Appellant's affidavits. Given that an important issue (the absence of Barh-end switchgear and idle charging) had been raised before the order was passed, the court held that the Central Commission ought to have re-heard the matter or given further opportunity to the parties before deciding COD and tariff.
  • The court also pointed out that the petition filed by POWERGRID did not indicate that COD had been declared despite non-installation of switchgear at Barh end, and the impugned order did not discuss this material fact.

On this basis — factual insufficiency of the record to show all COD conditions met, inapplicability of the proviso, absence of evidence of trial operation, and procedural deficiencies in the Central Commission's consideration of the Appellant's objections — the court found the declaration of COD as of 01.07.2010 to be untenable.

Holding and Implications

Holding: The court answered the framed question in the negative and ruled in favour of the Appellant. The court ALLOWED THE APPEAL, set aside the impugned order dated 29.04.2011, and remanded the matter to the Central Commission to redetermine the COD and tariff of the 400 kV Barh-Balia double circuit line after hearing all concerned within three months from the date of the judgment.

Direct implications for the parties:

  • The Central Commission's determination of COD as 01.07.2010 (and the consequent tariff determination effective from that date) has been set aside; the Central Commission must re-examine and re-determine COD and tariff in a fresh proceeding giving parties an opportunity to be heard.
  • The decision relieves the beneficiaries (including the Appellant) from the immediate effect of the Central Commission's earlier tariff determination until the Commission conducts the mandated re-determination.
  • The court imposed a timeline: the Central Commission must complete redetermination within three months of the judgment.
  • No order as to costs was made.

Broader precedent: The opinion does not purport to lay down a new general rule beyond applying the Tariff Regulations to the facts; it enforces that all components necessary for a transmission element to be "ready for regular service" must be in place before COD is declared, and that the proviso allowing earlier COD applies only where the element is otherwise ready and only prevented from being put into service for reasons not attributable to the transmission licensee.


Disposition recorded in the opinion: Appeal allowed; impugned order set aside; matter remanded for re-determination of COD and tariff within three months; no costs.

To access the original judgment, please Sign In or Subscribe.

    Punjab State Power Corporation Ltd. v. Power Grid Corporation Of India Ltd.

    RAKESH NATH, TECHNICAL MEMBER Whether a new transmission line charged from one end by the transmission licensee without the switchgear, protection system and metering arrangement at the other end not in the scope of works of the transmission licensee being ready and without flow of power on the line could be declared as commissioned for the purpose of raising the transmission charges on the beneficiaries? The above question that has been posed in this Appeal is required to be answered by us.

    2. Punjab State Power Corporation Ltd., the successor in interest of Punjab State Electricity Board is the Appellant. Power Grid Corporation of India (POWERGRID), a transmission licensee, is the Respondent no.1. The power utilities of Northern Region Page No.4 of 24 Appeal No. 123 of 2011 and the beneficiaries of 400 kV Barh-Balia double circuit transmission line constructed by POWERGRID are the Respondents 2 to 17. The Central Electricity Regulatory Commission (Central Commission) is the Respondent no.18.

    3. The Appellant has challenged the impugned order dated 29.04.2011 of the Central Commission declaring the Date of Commercial Operation (COD) of 400 kV Barh-Balia double circuit transmission line of POWERGRID w.e.f. 01.07.2010.

    4. The brief background of the case is as under:- 4.1. National Thermal Power Corporation (NTPC) was constructing a Super Thermal Power Station at Barh in the State of Bihar. For evacuation of power from Stage I of Barh STPS comprising 3 units of 660 MW each, associated transmission system comprising sub-stations, transmission lines, etc., including 400 kV Barh-Balia Page No.5 of 24 Appeal No. 123 of 2011 double circuit line was taken up by POWERGRID. Construction of Balia Sub-station and the transmission line was under the scope of POWERGRID but the construction of Barh Sub-station and the switchgear of the line at Barh end was under the scope of NTPC. 4.2 Barh STPS Stage I of NTPC got delayed for some reason. However, POWERGRID completed the works of 400 kV Barh-Balia double circuit line and charged the line from Balia end on 30.06.2010 without the switchgear and metering and protection arrangements being ready at Barh end and declared the line as having achieved the Commercial Operation w.e.f. 01.07.2010. 4.3 On 01.10.2010, the Respondent no.1 filed a petition for determination of tariff for Barh-Balia transmission line even though the line was practically idle and unutilized because of pending works at Barh Sub-station of NTPC. The petition was heard on 25.01.2011. However, according to the Appellant till then they were not aware Page No.6 of 24 Appeal No. 123 of 2011 that the line was idle and no power was flowing through the line. 4.4 Subsequently when it came to the notice of the Appellant that line was idle and not loaded, they filed objections before the Central Commission by way of affidavits on 04.03.2011, 15.03.2011 and 07.04.2011. 4.5 The Central Commission by its order passed on 29.04.2011 decided the tariff for Barh-Balia line w.e.f. 01.07.2010 to be paid by the Appellant and other beneficiaries. Aggrieved by the order dated 29.04.2011, the Appellant has filed this Appeal.

    5. The Appellant has made the following submissions, assailing the impugned order. 5.1 The Tariff Regulations provide that for declaration of Date of Commercial Operation (COD), three conditions viz., successful charging, trial operation and regular service Page No.7 of 24 Appeal No. 123 of 2011 have to be fulfilled. The Central Commission failed to consider that the petition filed by the Respondent no.1 did not contain any averments regarding trial operation conducted on the transmission line and its regular service. In spite of this, the Central Commission passed the impugned order without considering the provisions of the Act, Regulations and Indian Electricity Grid Code and the objections filed by the Appellant through three affidavits filed on different dates. 5.2 The Central Commission under its conduct of Business Regulations should have considered the vital information submitted by the Appellant through affidavits, and only after considering the objections of the Respondent no.1, should have taken the decision regarding declaration of COD of the Barh-Balia line. 5.3 It was also the obligation of the Central Commission to satisfy itself of fulfillment of the conditions laid down in the Tariff Regulations for COD of the transmission line. Page No.8 of 24 Appeal No. 123 of 2011 5.4 According to the Indian Electricity Grid Code (Grid Code), metering and data collection is an exclusive function of Regional Load Dispatch Central (RLDC), the function being performed by the Respondent no.1. Before declaration of COD of the line, it was the obligation of the Respondent no.1 to ensure that Special Energy Meters (SEM) were duly installed and tested on both the ends of the line i.e. at Barh as well as at Balia end. According to the information available with the Appellant the said meters had not been installed as on 16.05.2011. In the absence of the meters, the line could not have been declared as commissioned. 5.5 The Central Commission also failed to appreciate that in the Petition filed by the Respondent no.1, the minutes of meeting dated 16.11.2009 of the 11th Commercial Committee Meeting of Eastern Region Power Committee were attached according to which Patna-Kahalgaon line Page No.9 of 24 Appeal No. 123 of 2011 was looped in-looped out at Barh Grid Sub-Station with appropriate cost of Rs.171 crores. It was recorded in the minutes that till the COD of the first unit at Barh STPS, the transmission charges would be borne by NTPC and thereafter by the concerned beneficiaries as per the Tariff Regulations of the Central Commission. 5.6 The Central Commission has failed to consider that in case where transmission line is to be constructed for evacuation of power from an identified power project, an indemnification agreement is generally signed between the generating company and transmission company with provision of compensation by the generating company to the transmission company if the transmission line is completed as per schedule and the generating project is delayed. Page No.10 of 24 Appeal No. 123 of 2011

    6. The Respondent no.1 in support of the impugned order has submitted the following:- 6.1 The petition for determination of tariff was filed by the Respondent no.1 before the Central Commission on 01.10.2010 duly disclosing that the construction of Barh- Balia line was completed in June, 2010. This was after several meetings with the Northern Regional Power Committee (NRPC), in which the Appellant is a Member, wherein the declaration under commercial operation effective 01.07.2010 was duly deliberated and intimated. The Appellant was, therefore, fully aware of the position taken by POWERGRID that notwithstanding the generating station and Barh Sub-station being not ready, POWERGRID was proceeding to claim the commercial operation w.e.f. 01.07.2010, having completed the construction of transmission elements which was within the scope of work of POWERGRID. Despite this the Appellant did not raise the objection in the proceedings Page No.11 of 24 Appeal No. 123 of 2011 before the Central Commission till the hearing held on 25.01.2011, when the Central Commission reserved the matter. 6.2 Much after the order was reserved by the Central Commission, the Appellant sent the objections to the petition on 04.03.2011, 15.03.2011 and 07.04.2011. The Appellant also did not file any application before the Central Commission for re-hearing the matter. 6.3 According to the Tariff Regulations, in case an element of the transmission system is ready for regular service but is prevented from providing such service for reasons not attributable to the transmission licensee, the Commission may approve the COD prior to the element coming into regular service. Accordingly, notwithstanding that Barh generating station of NPTC was not ready to generate electricity, the transmission line having been completed in all respects by POWERGRID is to be taken as under commercial operation. Page No.12 of 24 Appeal No. 123 of 2011 6.4 The switchgear at the Barh end of the Barh-Balia line and CTs/PTs required for protection and metering were to be installed by NTPC. Both main and check meters are only to be provided by POWERGRID as CTU in discharge of its statutory function. These meters could only be installed only after NTPC had established the control room/panel at Barh station and was ready to energise the line from Barh end.

    7. We have heard the Ld. Counsel for the Appellant and the Respondent no.1 on the above issue and carefully considered their rival contentions. In the light of their submissions, the only issue that is to be decided by us is as under:- Whether on idle charging of a new transmission line connecting a sub-station of a transmission licensee to a generating station of a generating company from one end when the switchgear and metering and protection system Page No.13 of 24 Appeal No. 123 of 2011 at the generating station end is not made ready by the generating company, could it be declared as having achieved the COD for recovery of transmission charges from the beneficiaries?

    8. Let us first examine the sequence of events of the case. 8.1 400 kV Barh-Balia double circuit transmission line was planned by the Respondent no.1 for evacuation of power output from Barh STPS of NTPC. While the construction of transmission line and switchgear at the Balia end was in the scope of works of the Respondent no.1, the switchgear and sub-station at Barh end was to be constructed by NTPC, as per the policy laid down by the Government of India. 8.2 The commissioning of Barh STPS by NTPC was delayed due to some reasons. In the meantime the works of Barh- Balia line in the scope of the Respondent no.1 were completed in June, 2010 and the line was idle charged Page No.14 of 24 Appeal No. 123 of 2011 from Balia end by the Respondent no.1 on 30.06.2010. Respondent no.1 declared the commercial operation of the line w.e.f. 01.07.2010. 8.3 On 01.10.2010 the Respondent no.1 filed a petition before the Central Commission for determination of tariff. The Central Commission heard the matter on 25.01.2011. 8.4 After the hearing was completed, the Appellant filed objections before the Central Commission by way of affidavits on 04.03.2011. 15.03.2011 and 07.04.2011. 8.5 The Central Commission passed the impugned order on 29.04.2011 determining the tariff applicable from 01.07.2010. 8.6 According to the Appellant, the works at the Barh end were completed by NTPC only in August, 2011 and the Page No.15 of 24 Appeal No. 123 of 2011 first circuit of Barh-Balia line was loaded on 02.08.2011 while the second circuit was loaded on 19.08.2011.

    9. Let us now examine the Tariff Regulations, 2009, defining the COD for transmission system. The relevant extract is reproduced below:- (12) date of commercial operation or COD means (b).. (c) In relation to the transmission system, the date declared by the transmission licensee from 0000 hour of which an element of transmission system is in regular service after successful charging and trial operation. Provided that the date shall be the first day of a calendar month and transmission charge for the element shall be payable and its availability shall be accounted for, from that date; Provided further that in case an element of the transmission system is ready for regular service but is prevented from providing such service for reasons not attributable to the transmission licensee, its suppliers or contractors, the Commission may approve the date of Page No.16 of 24 Appeal No. 123 of 2011 commercial operation prior to the element coming into regular service.

    10. A transmission system may comprise of one or more transmission lines and sub-station, inter-connecting transformer, etc. According to above definition an element of the transmission system which includes a transmission line, could be declared as attained COD if the following conditions are met.

    i) It has been charged successfully, ii) its trial operation has been successfully carried out, iii) it is in regular service.

    11. Thus, Barh-Balia line in order to achieve COD should have been charged successfully, its trial operation should have been completed and it should have been in regular service. While the line was idle charged only from Balia end on 30.06.2010, its charging from Barh end, its trial operation and regular service was not possible as the Page No.17 of 24 Appeal No. 123 of 2011 switchgear at Barh end of the line was not ready. Admittedly, the switchgear, protection system and metering arrangement of the transmission line at Barh end were not ready on 01.07.2010 and reported to have been completed only in August, 2011. Thus, all the conditions laid down in the Tariff Regulations for attaining COD had not been complied with.

    12. Ld. Counsel for the Respondent no.1 has argued that the second proviso to Regulation 3 (12) (c) of the Tariff Regulations stipulates that in case an element of the transmission system is ready for regular service but is prevented from providing such service for reasons not attributable to the transmission licensee, the Commission may approve COD prior to the element coming into service.

    13. In our opinion this proviso is not applicable in this case as Barh-Balia line was not ready for regular service due to non-installation of the switchgear at Barh end. Merely Page No.18 of 24 Appeal No. 123 of 2011 because the components of the transmission line in the scope of POWERGRID (R-1) were ready, the line could not be considered as completed and ready for use till the switchgear and protection and metering arrangements, etc; at the Barh end of the line were completed. Both ends of the switchgear protection and metering systems along with the overhead line are components of the transmission line. If for the sake of convenience of construction and operation and maintenance, the scope of work of the components of transmission line at the generating station end has been entrusted to the generating company, the transmission line could not be considered as completed unless all the components of the transmission are ready for use. The second proviso to the definition of COD, in our opinion, will be applicable if the transmission line is ready in all respect for regular use but is prevented for use due to some reasons beyond the control of transmission licensee, e.g. high voltage in the system. Page No.19 of 24 Appeal No. 123 of 2011

    14. We made a specific query to the Ld. Counsel for the Respondent no.1 about the trial operation procedure and trial operation report of Barh-Balia line but we could not get any specific reply in this regard. Thus, the Respondent no.1 could not produce any evidence to establish that the trial operation of the line was completed before declaration of COD on 01.07.2010. In our opinion, the trial operation of the transmission line could not have been completed till the switchgear and associated systems at Barh end were made ready for use.

    15. Ld. Counsel for the Respondent no.1 has stated that the Appellant did not raise any objection till the completion of hearing of the petition for determination of tariff before the Central Commission and only after completion of hearing they raised the objections by filing the affidavits.

    16. We notice that the Appellant had filed three affidavits on 04.03.2011, 15.03.2011 and 07.04.2011 before the Page No.20 of 24 Appeal No. 123 of 2011 Central Commission, between date of hearing on 25.01.2011 and the date of the impugned order on 29.04.2011. It is noticed that these affidavits were not considered by the Central Commission. This is evident from the recording in paragraph 6 of the impugned order which is reproduced below:

    6. No comments or suggestions have been received from the general public in response to the public notice published by the petitioner on 19/21.9.2010 as required under Section 64 of the Electricity Act, 2003 (the Act) read with Regulation 3 (6) of the Central Electricity Regulatory Commission (Procedure for making of application for determination of tariff, publication of the application and other related matters) Regulations, 2004. No reply has been filed by the respondents.

    17. In our opinion when an important issue regarding COD of the line was raised by the Appellant much before passing the impugned order in the matter, the Central Commission ought to have re-heard the matter by giving further opportunity to both the parties before deciding the issue. Page No.21 of 24 Appeal No. 123 of 2011

    18. We also notice from the petition filed by the Respondent no.1 before the Central Commission that the important fact of declaration of COD of Barh-Balia line without installation of the switchgear at Barh end was not indicated. This fact has also not been discussed anywhere in the impugned order. Thus, it appears that the Central Commission has decided the transmission tariff of Barh-Balia line w.e.f. 01.07.2010 without ascertaining that the line was ready for use after successful completion of trial operation.

    19. In view of above, the question framed by us is answered in negative and in favour of the Appellant. Accordingly, we set aside the impugned order and remand the matter to the Central Commission to redetermine the COD and tariff of 400 kV Barh-Balia double circuit line after hearing all concerned within 3 months of the date of this judgment. Page No.22 of 24 Appeal No. 123 of 2011

    20. Summary of our findings: According to Tariff Regulations, the COD of a transmission line shall be achieved when the following conditions are met.

    i) The line has been charged successfully, ii) its trial operation has been successfully carried out, and iii) it is in regular service. The above conditions in the case of 400 kV Barh-Balia line were not fulfilled on 01.07.2010, the date on which COD was declared by the Respondent no.1. Merely charging of the line from one end without the switchgear, protection and metering arrangements being ready at the other end, even if not in the scope of works of the transmission license, would not entitle the line for declaration of commercial operation. Page No.23 of 24 Appeal No. 123 of 2011

    21. In view of the above, the Appeal is allowed, the impugned order is set aside and matter is remanded back to the Central Commission for redeterming the COD and tariff of 400 kV Barh-Balia double circuit line after hearing all concerned within 3 months of the date of this judgment. No order as to costs. Pronounced in open court on 2nd Day of July, 2012. (Rakesh Nath) (Justice M. Karpaga Vinayagam) Technical Member Chairperson REPORTABLE/NON-REPORTABLE Page No.24 of 24

    Use AI to get other relevant cases.

    Comments

    Punjab State Power Corporation Ltd. v. Power Grid Corporation Of India Ltd.
    (Jul 2, 2012)