Loading..
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
Smart Summary

Factual and Procedural Background

This appeal under Section 37 of the Arbitration and Conciliation Act, 1996, challenges the judgment of a Single Judge of the High Court of Himachal Pradesh dated 15.9.2014. The Single Judge had allowed an application filed by respondent No.1 under Section 9 of the Act, restraining the appellant from invoking bank guarantees furnished by respondent No.1.

The respondent No.1 had entered into two separate contracts with the appellant for the design, engineering, manufacturing, testing, erection, commissioning, and allied works for a 132/33KV sub-station near Shimla. Separate formal agreements were executed pursuant to two letters of award dated 18.01.2011, one relating to the supply portion and the other to erection, commissioning, and civil works.

At the start of the works, the appellant advanced certain amounts to respondent No.1, who secured these advances by furnishing unconditional bank guarantees issued by respondent No.2 bank. Additionally, respondent No.1 furnished performance guarantees for the contracts. The total amount of the bank guarantees furnished amounted to ₹1,64,41,713/-.

Respondent No.1 filed an application under Section 9 of the Act seeking, inter alia, an injunction restraining the appellant from invoking the bank guarantees and staying the operation of a letter levying liquidated damages. The Single Judge granted the injunction restraining the invocation of the bank guarantees and directed their renewal until the completion of the arbitral proceedings or revocation by the arbitrator or court.

Legal Issues Presented

  1. Whether the Single Judge erred in granting an injunction restraining the appellant from invoking unconditional bank guarantees furnished by respondent No.1.
  2. Whether a single application for interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, is maintainable in respect of two separate arbitration agreements.
  3. Whether the plea of fraud raised by respondent No.1 was sufficiently pleaded and established to justify restraining invocation of the bank guarantees.
  4. Whether the contentions of special equities or irretrievable injury/injustice in favor of respondent No.1 justified the grant of injunction.

Arguments of the Parties

Appellant's Arguments

  • The learned Single Judge failed to consider that no exceptional case for injunction was made out by respondent No.1.
  • There was no legal ground for restraining the appellant from invoking the bank guarantees, especially since substantial amounts were found due from respondent No.1.
  • A single application for interim relief in respect of two separate arbitration agreements was not maintainable and should have been dismissed on this ground alone.

Respondent No.1's Arguments

  • Supported the order passed by the Single Judge restraining invocation of the bank guarantees.
  • Claimed that the appellant had played fraud and that the threatened action of levying compensation amounted to gross misrepresentation, suppression, and distortion of material facts, thereby justifying special equities in their favor.
  • Asserted that hindrances created by the appellant caused delay in project execution and that there were huge quantity variations for which payment was due but not made.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Hindustan Construction Co. Ltd. vs. State of Bihar and others (1999) 8 SCC 436 Bank guarantees are unconditional contracts allowing the beneficiary to realize the amount irrespective of disputes, except in cases of established fraud or irretrievable injury. The court relied on this principle to emphasize the unconditional nature of bank guarantees and the limited grounds to restrain their invocation.
U.P. Cooperative Federation Ltd. v. Singh Consultants & Engineers Pvt. Ltd. (1988) 1 SCC 174 Unconditional bank guarantees must be honored on demand except in cases of fraud or irretrievable injury. Applied to affirm that the bank must pay as per the guarantee terms without regard to disputes between supplier and customer.
Bolivinter Oil SA v. Chase Manhattan Bank [1984] 1 All E.R. 351 An injunction against invocation of bank guarantee is only granted when clear fraud is proved, with bank's knowledge. Quoted to illustrate the high threshold for restraining invocation of bank guarantees.
U.P. State Sugar Corporation v. Sumac International Ltd. (1997) 1 SCC 568 Beneficiary entitled to realize unconditional bank guarantees irrespective of disputes; courts slow to grant injunctions restraining realization. Reiterated the principle that bank guarantees are independent contracts.
BSES Limited vs. Fenner India Ltd. (2006) 2 SCC 726 Two exceptions to unconditional invocation: (i) clear fraud known to bank, (ii) special equities like irretrievable injury/injustice. Applied to analyze whether exceptions were made out by respondent No.1.
Himadri Chemicals Industries Ltd. vs. Coal Tar Refining Co. (2007) 8 SCC 110 Summarized principles for injunction against bank guarantee invocation emphasizing independence and unconditionality. Guided the court in applying the settled principles to the facts of the case.
Meghmala and others vs. G. Narasimha Reddy and others (2010) 8 SCC 383 Fraud should not be condoned; fraud avoids judicial acts and unravels everything. Used to assess the nature and sufficiency of fraud allegations by respondent No.1.
S.P. Chengalvaraya Naidu v. Jagannath (AIR 1994 SC 853) Fraud unravels all judicial acts; fraud must be specifically pleaded and proved. Supported the court's requirement for explicit fraud pleadings and evidence.
Other cited precedents include State of Maharashtra & Ors. vs. Prabhu (1994) 2 SCC 481, United India Insurance Co. Ltd. vs. Rajendra Singh & Ors AIR 2000 SC 1165, and others General principles on fraud, equity, and injunctions in contractual and judicial proceedings. Collectively reinforced the court’s stance on fraud and injunctions in the context of bank guarantees.

Court's Reasoning and Analysis

The court examined the nature and purpose of bank guarantees, emphasizing that they constitute independent and unconditional contracts between the bank and the beneficiary. The court reiterated the settled legal position that invocation of such guarantees cannot be restrained except in two narrowly defined exceptions: (i) where there is an established egregious fraud known to the bank, and (ii) where irretrievable harm or injustice would result from the invocation.

Applying these principles, the court found that the Single Judge's reasons for granting the injunction—primarily that respondent No.1 owed substantial amounts and that the guarantees would be kept alive—did not align with the legal standards established by the Supreme Court.

Regarding the fraud plea raised by respondent No.1, the court noted that the allegations of fraud were neither specifically pleaded nor substantiated with particulars as required under Order 6 Rule 4 CPC. The court emphasized that fraud must be of an egregious nature to vitiate the underlying transaction and that mere assertions without clear and explicit pleading are insufficient.

On the contention of special equities or irretrievable injury, the court held that the matters raised by respondent No.1, such as delays caused by the appellant and payment disputes, are subject matters for the arbitrator and do not constitute exceptional circumstances warranting an injunction against invocation of the bank guarantees.

The court also addressed the maintainability of a single application for interim relief concerning two separate arbitration agreements. It held that since the causes of action arise from distinct awards and transactions, the respondent No.1 could not join the claims in one application under Order 2 Rule 3 CPC. Consequently, the application under Section 9 of the Act was not maintainable.

Holding and Implications

The court allowed the appeal and set aside the judgment of the Single Judge dated 15.9.2014 which had granted injunction restraining the invocation of the bank guarantees.

As a result, the injunction restraining the appellant from invoking the bank guarantees is vacated, and the appellant is entitled to invoke the bank guarantees in accordance with their terms. The court disposed of any pending applications and left the parties to bear their own costs.

No broader precedent was created beyond reaffirming the established principles governing invocation of unconditional bank guarantees and the strict requirements for pleading and proving fraud or special equities to restrain such invocation.

    Himachal Pradesh State Electricity Board Ltd. v. M/S. Ahluwalia Contracts (India) Ltd. And Another S

    IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA.

    Arb. Appeal No. 8 of 2014 .

    Judgment reserved on: 28.7.2015

    Date of Decision : August 05, . 20P15. Himachal Pradesh State Electricity Board Ltd. H …Appellant Versus

    f

    M/s Ahluwalia Contracts (India) Ltd. and ano o ther …Respondents Coram t

    The Hon'ble Mr. Justice M u ansoror Ahmad Mir, Chief Justice. The Hon'ble Mr. Just o ice Tarlok Singh Chauhan, Judge. Whether approved for reporting ? Yes For the Appe lla C nt : Mr. J.S. Bhogal, Senior Advocate, with Mr. Satish Sharma, Advocate. For the h respondents : Mr. S.K. Maniktala & Ms. Shweta Joolka, Advocates, for respondent No.1. i g Mr. Sanjay Dalmia, Advocate, for respondent No.2.

    H

    Tarlok Singh Chauhan, Judge

    This appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (for short 'Act') is directed against the judgment passed by learned Single Judge of this Court on 15.9.2014 whereby he allowed the application filed by respondent No.1 under Section 9 of the Act and restrained the appellant from invoking the bank guarantee(s) furnished by respondent No.1.

    The facts in brief may be noticed.

    2. The respondent No.1 had entered into two contracts with ______________________

    1 Whether reporters of Local Papers may be allowed to see the Judgment ?

    1

    2

    the appellant for the Design Engineering, Manufacturing, Testing of Equipment, Erection, Commissioning alongwith other allied works suc . h as Earthmat and Civil Works on turn key basis of 132/33KV, . 1x P 25/31.5 MVA Sub-station at Maliana near Shimla and separate formal agreements were executed between the parties p H ursuant to two separate letters of award, both dated 18.01.20 f 11. While one award letter related to the supply portion of t the wo o rks, the other related to the erection, commissioning and civil works.

    3. At the time o u f starrt of the works, the appellant had advanced certain amo o unts to respondent No.1 and for securing such amounts, respo C ndent No.1 had given unconditional bank guarantee(s) issued by res pondent No.2 bank in favour of the appellant. In addition, respond h ent No.1 had also furnished the bank guarantee(s) as Pe g rformance Guarantee(s) for the contract. The Performance i Guarantee(s) were for the amounts of `72,09,680/- and ` 28,08,180/-

    H

    respectively for the works of supply and erection. The guarantees furnished to secure the advance given to respondent No.1 were for the amounts of `42,24,297/- and ` 21,99,556/- respectively for the works of supply and erection. Thus, the total amount of the bank guarantees

    issued by respondent No.2 and furnished by respondent No.1 to the

    appellant came to `1,64,41,713/-.

    4. The respondent No.1 moved an application under Section 9 of the Act in which it sought the following substantive reliefs:

    "(a) Pass an order staying operation of the letter dated 04.07.2014 bearing No. SE(D)ES/SSD-273/Maliana/2014-2168, of respondent No.1, levying liquidated damages on the petitioner and further restraining respondent No.1 and its agents,

    3

    employees, servants etc. from giving any effect thereto; and/or taking any coercive action on the basis thereof;

    (b) pass an order restraining respondent No.1 by itself or through .its employees, agents, servants etc. from invoking t P he Bank Guarantees furnished by respondent No.2 Bank on b . ehalf of the petitioner, and as more specifically detailed i H n para 6 & 7 above, and further restraining respondent No.2 Bank from encashing the said Bank Guarantees furnished by r espondent No.2 to

    respondent No.1 on behalf of the petiti f oner;

    ( c) pass ad-interim ex-parte orders in terms of prayers (a) and (b)

    above, and confirm the sa t me aftoer notice to the respondent s."

    5. The learned Single r Judge allowed the application by granting the reliefs (b) and u (c) supra and directed the respondents to keep alive the bank gu o arantees by way of its renewal till the completion of the arbitral proceedings or the issue of revocation thereof is decided by the A Ch rbitra tor/Court. 6. It is contended by the appellant that the learned Single

    iJug dge has not taken into consideration that there was no exceptional H

    case for grant of injunction made out by respondent No.1. Further, there was no legal ground for restraining the appellant from invoking the bank guarantees especially when admittedly substantial amounts were found due from the respondent No.1 even by the learned Single Judge towards the appellant. It is also contended that a single

    application for interim relief in respect of two separate arbitration

    agreements was not maintainable and, therefore, objections ought to

    have been dismissed on this short score alone.

    7. On the other hand, learned counsel for the respondents have supported the order passed by the learned Single Judge. We have heard learned counsel for the parties and have gone through the records of the case carefully and meticulously.

    4

    8. The instant dispute relates to the release of the bank guarantees. The nature and purpose of the bank guarantees has bee . n succinctly discussed by the Hon'ble Supreme Court in th . e P case of

    Hindustan Construction Co. Ltd. vs. State of Bi H har and others (1999) 8 SCC 436, the relevant observation f s a re reproduced as under:- o

    " 8. Now, a Bank Guar r antee t is the common mode, of securing payment of money in commercial dealings as the beneficiary, under the Guarantee, is entitled to realise th u e whole of the amount under that Guarantee in terms thereof irrespective of any pending dispute between the person on whose behalf the G o uarantee was given and the beneficiary. In contracts awarded to private individuals by the Government, which involve huge expenditure, as, C for example, construction contracts, Bank Guarantees are usually r equired to be furnished in favour of the Government to secure payments h made to the contractor as "Advance" from time to time during the course of the contract as also to secure performance of the work entrusted under the g

    contract. Such Guarantees are encashable in terms thereof on the lapse of i

    the contractor either in the performance of the work or in paying back to the "Government Advance", the Guarantee is invoked and the amount is H

    recovered from the Bank. It is for this reason that the Courts are reluctant in granting an injunction against the invocation of Bank Guarantee, except in the case of fraud, which should be an established fraud, or where irretrievable injury was likely to be caused to the Guarantor. This was the principle laid down by this Court in various decisions. In U.P. Cooperative Federation Ltd. v. Singh Consultants & Engineers Pvt. Ltd., [1988] 1 SCC

    174, the law laid down in Bolivinter Oil SA v. Chase Manhattan Bank,

    [1984] 1 All E.R. 351 was approved and it was held that an unconditional

    Bank Guarantee could be invoked in terms thereof by the person in whose

    favour the Bank Guarantee was given and the Courts would not grant any

    injunction restraining the invocation except in the case of fraud or

    irretrievable injury. In Svenska Handelsbanken v. Indian Charge Chrome,

    [1994] 1 SCC 502; Larsen & Toubro Ltd. v. Maharashtra State Electricity

    Board, [1995] 6 SCC 68; Hindustan Steel Works Construction Ltd. v. G.S.

    Atwal & Co. (Engineers) (P) Ltd., [1995] 6 SCC 76; National Thermal

    Power Corporation Ltd. v. Flowmeore (P) Ltd., [1995] 4 SCC 515; State of

    Maharashtra v. National Construction Co., [1996] 1 SCC 735; Hindustan

    Steel Works Construction Ltd. v. Tarapore & Co., [1996] 5 SCC 34 as also

    5

    in U.P State Sugar Corporation v. Sumac International Ltd. ., [1997] 1 SCC 568, the same principle has been laid down and reiterated. .

    9. What is important, therefore, is that the Bank Guarantee should be in unequivocal terms, unconditional and recite that the amo . untP would be paid without demur or objection and irrespective of a H ny dispute that might have cropped up or might have been pending betw een the beneficiary under the Bank Guarantee or the person on whos f e behalf the Guarantee was furnished. The terms of the Bank Guarantee are, therefore, extremely material. Since the Bank Guarantee represents an independent contract

    between the Bank and the beneficiary, o both the parties would be bound by

    the terms thereof. The invo r catio t n, t herefore, will have to be in accordance with the terms of the Bank Guarantee; or else, the invocation itself would be bad."

    9. Law relati o ng tou invocation of Bank Guarantee is by now well settled by c C atena of decisions of the Hon'ble Supreme Court. The Bank Guaran tee which provides that they are payable by the guarantor on dem h and is considered to be an unconditional Bank Guarantee. So,

    iwhg en in the course of commercial transaction/dealings, an unconditional Bank Guarantee is given or accepted, the beneficiary is

    H

    entitled to realise such a Bank Guarantee in terms thereof irrespective of any pending disputes. 10. The Courts have carved out only two exceptions. A fraud in connection with such a bank guarantee would vitiate the very

    foundation of such a bank guarantee. Hence if there is such a fraud of

    which the beneficiary seeks to take advantage, he can be restrained

    from doing so. The second exception relates to cases where allowing

    the encashment of an unconditional bank guarantee would result in

    irretrievable harm or injustice to one of the parties concerned. Since in

    most cases payment of money under such a bank guarantee would

    adversely affect the bank and its customer at whose instance the

    6

    guarantee is given, the harm or injustice contemplated under this head must be of such an exceptional and irretrievable nature as wou . ld override the terms of the guarantee and the adverse effect o . f P such an injunction on commercial dealings in the country. The two grounds are not necessarily connected, though both may coexist in H some cases.

    11. In the case of U.P.Cooper o ative f Federation Ltd. vs. Singh Consultants and Engineers t (P) Ltd. (1988) 1 SCC 174, which was the case of works contract where the performance guarantee given under the contract was rsought to be invoked, the Hon'ble

    Supreme Court, after referri u ng extensively to English and Indian cases

    on the subjec C t, said o that the guarantee must be honoured in accordance with its terms. The bank which gives the guarantee is not concern h ed in the least with the relations between the supplier and the cu g stomer; nor with the question whether the supplier has performed i his contractual obligation or not, nor with the question whether the

    H

    supplier is in default or not. The bank must pay according to the tenor of its guarantee on demand without proof or condition. There are only two exceptions to this rule. The first exception is a case when there is a clear fraud of which the bank has notice. The fraud must be of an

    egregious nature such as to vitiate the entire underlying transaction.

    Explaining the kind of fraud that may absolve a bank from honouring its

    guarantee, the Hon'ble Supreme Court in the above case quoted with

    approval the observations of Sir John Donaldson, M.R. in Bolivinter Oil

    SA v. Chase Manhattan Bank NA (1984) [1] AER 351 at 352):

    "The wholly exceptional case where an injunction may be granted is where it is proved that the bank knows that any demand for payment already made or which may thereafter be made will clearly be

    7

    fraudulent. But the evidence must be clear both as to the fact of fraud and as to the bank's knowledge. It would certainly not normally be sufficient that this rests on the uncorroborated statement of th.e customer, for irreparable damage can be done to a ban . k's P credit in the relatively brief time which must elapse between the granting of such an injunction and an application by the ba nk H to have it charged". The Hon'ble Supreme Court set aside an injunction granted by the High Court to restrain the realisation of th e o bank

    fguarantee.

    12. In case of U.P.State Sugar Corporation vs. Sumac International Ltd. (1997) 1 SCC r 56t8, the Hon'ble Supreme Court in para 12 observed as under: u

    "The law re o lating to invocation of such bank guarantees is by now well settled. When in the course of commercial dealings an u nc C onditional bank guarantee is given or accepted, the beneficiary is entitled to realise such a bank guarantee in terms thereof irrespective h of any pending disputes. The bank giving such a guarantee is bound to honour it as per its terms irrespective of any dispute raised by its

    ig

    customer. The very purpose of giving such a bank guarantee would otherwise be defeated. The Courts should, therefore, be slow in granting an injunction to restrain the realisation of such a bank

    H

    guarantee." 13. It is equally well settled in law that Bank Guarantee is an independent contract between the bank and the beneficiary thereof. The bank is always obliged to honour its guarantee as long as it is

    unconditional and irrevocable one. The dispute between the

    beneficiary and the party at whose instance, the bank has given

    guarantee is immaterial and of no consequence.

    14. In case of BSES Limited vs. Fenner India Ltd. (2006) 2 SCC 726, the Hon'ble Supreme Court in para 10 observed as under:-

    "10. There are, however, two exceptions to this Rule. The first is when there is a clear fraud of which the Bank has notice and a fraud of the beneficiary from which it seeks to benefit. The fraud must be of

    8

    an egregious nature as to vitiate the entire underlying transaction. The second exception to the general rule of nonintervention is when there are special equities in favour of injunction, such as whe.n irretrievable injury or irretrievable injustice would occur if P such an injunction were not granted. The general rule and its exc . eptions has been reiterated in so many judgments of this court, that in U.P.Sugar Corpn. vs. Sumac International Ltd. (1997) 1 SC H C 568 (hereinafter U.P.State Sugar Corpn) this Court, correct f ly d eclare that the law was settled."

    15. In Himadri Chemicals t In duostries Ltd vs. Coal Tar Refining Co. (2007) 8 SCC r 110, the Hon'ble Supreme Court summarized the principles f u or grant or refusal to grant of injunction to restrain enforcement of a bank guarantee or a letter of credit, in para 14, which reads C as undoer:-

    h "(i) While dealing with an application for injunction in the course of commercial dealings, and when an unconditional Bank Guarantee or Letter of Credit is given or accepted, the g

    Beneficiary is entitled to realize such a Bank Guarantee or a i

    Letter of Credit in terms thereof irrespective of any pending disputes relating to the terms of the contract. H

    (ii) The Bank giving such guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. (iii) The Courts should be slow in granting an order of injunction to restrain the realization of a Bank Guarantee or a Letter of Credit.

    (iv) Since a Bank Guarantee or a Letter of Credit is an independent and a separate contract and is absolute in nature, the existence of any dispute between the parties to the contract is not a ground for issuing an order of injunction to restrain enforcement of Bank Guarantees or Letters of Credit.

    (v) Fraud of an egregious nature which would vitiate the very foundation of such a Bank Guarantee or Letter of Credit and the beneficiary seeks to take advantage of the situation.

    (vi) Allowing encashment of an unconditional Bank Guarantee or a Letter of Credit would result in irretrievable harm or injustice to one of the parties concerned." Keeping these principles in mind, we shall now proceed to apply the same to the present case.

    9

    16. It is evident from the perusal of the impugned judgment that the only reason that weighed with the learned Single Judge . in granting the injunction is that after coming to the conclusio . n P that the respondent No.1 owes a considerable amount to the appellant, it proceeded to hold that no prejudice was likely to b H e caused to the appellant because the performance guarantee a f nd bank guarantee in lieu of mobilization advance would re t ma in o in its custody and would be kept alive by the contractor. It w r as further observed that since the Arbitrator had already been u appointed, the parties could approach the Arbitrator for settleme o nt of the issue qua encashment of the bank guarantees duri C ng the course of arbitral proceedings. 17. . Now, in case the aforesaid reasons as set out in the impugn h ed judgments are tested in light of the principles as have been la g id down by the Hon'ble Supreme Court in the aforesaid decisions, i then it can conveniently be held that none of the aforesaid principles

    H

    have in fact been taken into consideration while passing the impugned judgment. 18. Learned counsel for the respondents would however vehemently argue that the learned Single Judge did not commit any

    error in granting the injunction, as the appellant's had played fraud.

    19. Fraud is defined in Section 17 of the Indian Contract Act in the following terms:

    "Fraud defined.- Fraud means and includes any of the following acts committed by a party to a contract, or with his connivance, or by his agent, with intent to deceive another party thereto or his agent, or to induce him to enter into the contract:-

    (1) the suggestion, as a fact, of that which is not true, by one who does not believe it to be true;

    10

    (2) the active concealment of a fact by one having knowledge or belief of the fact;

    (3) a promise made without any intention of performing it; .

    (4) any other act fitted to deceive; P

    (5) any such act or omission as the law specifically de . clares to be fraudulent.

    Explanation.- Mere silence as to facts like f ly to a H ffect the willingness of a person to enter into a contract is not fraud, unless the circumstances of the case are such o that, regard being had to them, it is the duty of the person keeping silence to speak, or unless his silence, is, in itself, equivalen t t to speech."

    20. The contract of guara r ntee is defined under Section 126 of the Indian Contract Act in th u e following terms:

    "126. 'Con o tract of guarantee', 'surety', 'principal debtor' and 'cre C ditor'- A 'contract of guarantee' is a contract to perform the p romise, or discharge the liability, of a third person in case of his default. The person who gives the guarantee is called the 'surety'; the h person in respect of whose default the guarantee is given is called g

    the 'principal debtor' and the person to whom the guarantee is given i

    is called the 'creditor'. A guarantee may be either oral or written." H

    21. Bank Guarantee constitutes an agreement between the Banker and the Principal, albeit, at the instance of the promisor. When a contract of guarantee is sought to be invoked, it is primarily for the bank to plead a case of fraud and not for a promisor to set up a case of breach of contract.

    22. The expression 'fraud' has been lucidly dealt with and explained in the case of Meghmala and others vs. G. Narasimha Reddy and others (2010) 8 SCC 383 and the Courts have been advised to take the element of fraud seriously and it has held that any act which is tainted by fraud should not be condoned and sustained and it was observed as under:

    11

    Fraud/Misrepresentation: -

    28. It is settled proposition of law that where an applicant gets a . n order/office by making misrepresentation or playing fraud upon the competent Authority, such order cannot be sustained in . theP eyes of law. "Fraud avoids all judicial acts ecclesiastical or temporal." (Vide S.P. Chengalvaraya Naidu (dead) by L.Rs. Vs. J H agannath (dead) by L.Rs. & Ors. AIR 1994 SC 853). In Lazaru f s E state Ltd. Vs. Besalay 1956 All. E.R. 349), the Court observed without equivocation that "no judgment of a Court, no order of a Minister can be allowed to stand if

    it has been obtained by fraud t , for fra o ud unravels everything." 29. In Andhra Pradesh State Financial Corporation Vs. M/s. GAR Re-Rolling Mills & u Anr. A r IR 1994 SC 2151; and State of Maharashtra & Ors. Vs. Prabhu (1994) 2 SCC 481. this Court observed that a writ Court, while o exercising its equitable jurisdiction, should not act as to prevent perpetration of a legal fraud as the courts are obliged to do ju sti C ce by promotion of good faith. "Equity is, also, known to prevent the law from the crafty evasions and sub-letties invented to evade h law." g

    30. In Smt. Shrisht Dhawan Vs. M/s. Shaw Brothers. (1992) 1 i

    SCC 534, it has been held as under: (SCC p. 553, para 20) H

    "20.Fraud and collusion vitiate even the most solemn proceedings in any civilised system of jurisprudence. It is a concept descriptive of human conduct." 31. In United India Insurance Co. Ltd. Vs. Rajendra Singh & Ors. AIR 2000 SC 1165, this Court observed that "Fraud and justice never dwell together" (fraus et jus nunquam cohabitant) and it is a pristine

    maxim which has never lost its temper over all these centuries.

    32. The ratio laid down by this Court in various cases is that dishonesty should not be permitted to bear the fruit and benefit to the persons who played fraud or made misrepresentation and in such circumstances the Court should not perpetuate the fraud. (See District Collector & Chairman, Vizianagaram Social Welfare Residential School Society, Vizianagaram & Anr. Vs. M. Tripura Sundari Devi (1990) 3 SCC 655; Union of India & Ors. Vs. M. Bhaskaran (1995) Suppl. 4 SCC 100; Vice Chairman, Kendriya Vidyalaya Sangathan & Anr. Vs. Girdharilal Yadav (2004) 6 SCC 325; State of Maharashtra v. Ravi Prakash Babulalsing Parmar (2007) 1 SCC 80; Himadri Chemicals Industries Ltd. Vs. Coal Tar

    12

    Refining Company AIR 2007 SC 2798; and Mohammed Ibrahim & Ors. Vs. State of Bihar & Anr. (2009) 8 SCC 751). .

    33. Fraud is an intrinsic, collateral act, and fraud of a . n egregious nature would vitiate the most solemn proceedings of courts Pof justice. Fraud is an act of deliberate deception with a design to secure

    something, which is otherwise not due. The H expression "fraud"

    involves two elements, deceit and injury to the person deceived. It is

    a cheating intended to get an adva o ntage. f [Vide Vimla (Dr.) v. Delhi Administration AIR 1963 SC 15 72, Indian Bank v. Satyam Fibres (India) Pvt. Ltd. . (1996) 5 SCC t 550, State of A.P. v. T. Suryachandra Rao (2005) 6 SCC 149, r K.D. Sharma v. SAIL (2008) 12 SCC 481 and Central Bank of India v. Madhulika Guruprasad Dahir (2008) 13 SCC 170.]

    34. An o act ofu fraud on court is always viewed seriously. A collusion or conspiracy with a view to deprive the rights of the others in re C lation to a property would render the transaction void ab initio. Fraud and deception are synonymous. Although in a given case a h deception may not amount to fraud, fraud is anathema to all equitable principles and any affair tainted with fraud cannot be perpetuated or g

    saved by the application of any equitable doctrine including res i

    judicata. Fraud is proved when it is shown that a false representation has been made (i) knowingly, or (ii) without belief in its truth, or (iii)

    H

    recklessly, careless whether it be true or false. Suppression of a material document would also amount to a fraud on the court. (Vide S.P. Changalvaraya Naidu (supra); Gowrishankar & Anr. Vs. Joshi Amba Shankar Family Trust & Ors. AIR 1996 SC 2202; Ram Chandra Singh Vs. Savitri Devi & Ors. (2003) 8 SCC 319; Roshan Deen Vs. Preeti Lal AIR 2002 SC 33; Ram Preeti Yadav Vs. U.P.

    Board of High School & Intermediate Education AIR 2003 SC 4628;

    and Ashok Leyland Ltd. Vs. State of Tamil Nadu & Anr. AIR 2004 SC

    2836).

    35. In kinch Vs. Walcott (1929) AC 482, it has been held that:

    "....mere constructive fraud is not, at all events after long delay, sufficient but such a judgment will not be set aside upon mere proof that the judgment was obtained y perjury." Thus, detection/discovery of constructive fraud at a much belated stage may not be sufficient to set aside the judgment procured by perjury.

    13

    36. From the above, it is evident that even in judicial proceedings, once a fraud is proved, all advantages gained by playing fraud can be taken away. In such an eventuality th.e questions of non-executing of the statutory remedies or statu P tory bars like doctrine of res judicata are not attracted. Suppres . sion of any material fact/document amounts to a fraud on th H e court. Every court has an inherent power to recall its own order obtained by fraud as the order so obtained is non est". f

    23. The respondent No.1 in order o to establish its plea of fraud has claimed that the exercise of t pow ers by the appellant are of fraudulent nature and the th u reaten r ing action of levying compensation is a fraud being played by the appellant. The respondent No.1 has repeatedly averred tha o t the threatened imposition/recovery of damages

    amounts to gro C ss misrepresentation, suppression and distortion of materia h l facts, which clearly amounts to fraud being perpetrated by the appellant, giving rise to special equities in its favour. But how and in

    iwhg at manner the fraud has been committed is neither forthcoming nor H

    spelled out. 24. Rule 4 of Order 6 CPC reads thus: "4. Particulars to be given where necessary.- In all cases in which the party pleading relies on any misrepresentation, fraud, breach of trust, willful default, or undue influence, and in all other cases in which particulars may be necessary beyond such as are exemplified in the forms aforesaid,

    particulars (with date and items if necessary) shall be stated in the

    pleading."

    It is thus clear from the aforesaid provisions that the

    allegations in regard to fraud must be specifically and explicitly pleaded

    so as to enable the opposite party to reply thereto effectively.

    25. That apart, the fraud in terms of the judgments of the Hon'ble Supreme Court (supra) must be of an egregious nature as to vitiate the entire underlying transaction. Having failed to raise the plea

    14

    of fraud as envisaged under the law, we find no force in this plea . of respondent No.1.

    26. Learned counsel for respondent No. 1 would t . he P n argue that there were special equities in favour of grant of an injunction or else irretrievable injury or irretrievable injustice f w ou H ld be caused to respondent No.1.

    27. Undoubtedly, there is anoth er o exception where the Court can grant injunction, which r rela t tes to cases where allowing encashment of an uncond u itional bank guarantee would result in irretrievable harm or in o justice to one of the parties concerned. Since in most cases the C payment of money under such a bank guarantee would adversely affect the bank and its customer at whose instance the guarant h ee is given, the harm or injustice contemplated under this head m g ust be of such an exceptional and irretrievable nature as would i override the terms of the guarantee and adverse effect of such an

    H

    injunction on commercial dealings in the country. 28. The respondent No. 1 has claimed that there were number of hindrances created by the appellant, which resulted in the delay of the execution of the project, such as site not being cleared and

    earmarked. The control room area where the existing material store

    was located was not vacated and therefore, the civil work for control

    room construction could not be done. The continuous stacking of

    materials/poles/ transformers/isolators in the area was always a

    hindrance and respondent No.1 had to demobilize on several

    occasions with notice to the appellant. The retaining wall design was

    submitted by respondent No. 1 to the appellant on 9.5.2011. However,

    15

    the matter remained unresolved till as late as December, 2011. Similarly the appellant took as long as five months (19.3.2011 . to 23.8.2011) to finalise the bench levels and as a result thereo . f t P he work could not be executed during the period.

    29. It is further contended that though f the c H ontract specified that the time was the essence of the contr o act but the conduct, attitude and approach of the appellant in t th e matter of discharge of its reciprocal obligations left no room for any doubt that it was not ready with all that was required o u f it urnder the contract and get the work executed within the sti o pulated contract period. It is also contended that there were hug C e quantity variations and in terms of the contract stipulation, r espondent No.1 was entitled to be paid for such deviatio h ns/variations, but the same was not paid. 30 g . We have considered these submissions of the learned i counsel for respondent No.1 and are of the considered opinion that all

    H

    the aforesaid contentions are matters which are required to be determined by the Arbitrator in the proceedings which are already pending before it and the same do not create any special equities in favour of respondent No. 1 entitling it to the grant of injunction.

    31. As cautioned by the Hon'ble Supreme Court, the dispute between the beneficiary and the party at whose instance the bank has given guarantee, is an independent contract between the bank and the beneficiary thereof and the beneficiary is entitled to realise such a bank guarantee irrespective of any pending disputes relating to the terms of the contract. The bank giving such guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer.

    16

    32. The respondent No.1 has failed to show any special equities in its favour whereby it could be proved that irretrievab P le inju . ry or irretrievable injustice would be caused to it in case the in . junction is not granted. As already observed earlier, these are the dispute, which

    are yet to be established and determined and th e m H atter is already

    pending adjudication before the Arbitrator. f

    33. That apart, it would be see n t o hat even as per the case of respondent No.1, there are two s r epa t rate letters of awards made in its favour vide letter dated 18 u .1.2011, while one award relating to the supply portion of t o he works, the other relating to erection, commissioning C and civil works. If that be so, then the appellant is right in contending that a single application for interim relief for two separate arbitrati h on ag reements was not maintainable. 34 g . The respondent No. 1 has sought to justify the i maintainability of the objections by invoking the provisions of Order 2

    H

    Rule 3 CPC which reads as under: "3. Joinder of causes of action.- (1) Save as otherwise provided, a plaintiff may unite in the same suit several causes of action against the same defendant, or the same defendants jointly; and any plaintiffs having causes of action in which they are jointly interested

    against the same defendant or the same defendant jointly may unite

    such causes of action in the same suit.

    (2) Where causes of action are united, the jurisdiction of the Court as regards the suit shall depend on the amount or value of the aggregate subject matters at the date of instituting the suit."

    35. We are at a lose to understand as to how the aforesaid provisions would be applicable to the facts of the instant case, more particularly, when it is not disputed even by respondent No.1 that two separate and distinct awards had been made in its favour. The mere

    17

    fact that the parties are common to both the awards, would not entitle respondent No.1 in uniting the claim in one application as the cause . of action in both the claims is separate and distinct. Violation or . br P each of one award would not essentially mean the breach o H r violation of the other. Moreover, the right to relief does not arise f out of the same act or transaction but arises out of two separate and distinct awards. Therefore, the respondent No.1 cannot b o e permitted to unite in one

    application several causes of r acti t on by taking protection of the provisions of Rule 3 of Orde u r 2 CPC and consequently the application preferred by responde o nt No.1 under Section 9 of the Act itself was not maintainable.

    36. I n v C iew of the aforesaid discussion, we find merit in this appeal h and the same is accordingly allowed, consequently the ju g dgment passed by learned Single Judge on 15.9.2014 is set-aside. i Pending application(s), if any, stands disposed of. Parties are left to

    H

    bear their own costs. ( Mansoor Ahmad Mir) Chief Justice August 05, 2015 (Tarlok Singh Chauhan),

    (GR) Judge.

    Use AI to get other relevant cases.

    Comments

    Himachal Pradesh Sta... v. M/S. Ahluwalia Contr...
    (Aug 5, 2015)