Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 39-A of the U.P Urban Planning and Development Act, 1973
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 39-A of the U.P Urban Planning and Development Act, 1973
Smart Summary

Factual and Procedural Background

The order arises out of continuous monitoring by the Court of various directions meant to protect the Taj Mahal and the surrounding Taj Trapezium Zone from industrial and vehicular pollution. Earlier orders required: (i) the Indian Oil Corporation to install a Hydro-cracking unit at its Mathura Refinery to reduce sulphur-dioxide emissions; (ii) the Gas Authority of India Ltd. (GAIL) to lay gas pipelines so that local industries could switch to cleaner fuel; (iii) the Uttar Pradesh State Electricity Board to provide uninterrupted power so that polluting diesel generators would not be used; and (iv) the Public Works Department of Uttar Pradesh to construct a 24-km Agra bypass. Affidavits and status reports were filed in compliance with specific orders dated 20-1-1995, 12-3-1996, 14-3-1996 and 15-3-1996, prompting the present directions and show-cause notices.

Legal Issues Presented

  1. Whether the Public Investment Board’s prolonged delay in approving the Hydro-cracking project warranted initiation of contempt proceedings against its Chairman.
  2. Whether Mathura Refinery should be subjected to a “pollution fine” for continued emission of approximately 500 kg of sulphur dioxide per hour, adversely affecting public health and the Taj Mahal.
  3. What further directions were necessary to ensure timely (a) Cabinet approval and construction of the Hydro-cracking unit, (b) completion of gas pipelines by GAIL, (c) provision of uninterrupted electricity by the Uttar Pradesh State Electricity Board, and (d) construction of the Agra bypass without unnecessary felling of trees.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
(1998) 8 SCC 711 (order dated 15-3-1996) Prior order directing the State of Uttar Pradesh regarding toll collection and urban amenities around the Taj Mahal. Referenced to explain why an affidavit from the State of Uttar Pradesh was filed concerning toll utilisation and city beautification.

Court's Reasoning and Analysis

1. The Court noted that despite earlier directions, even the preliminary “paper work” for the Hydro-cracking unit had not been finalised. The Public Investment Board had taken 14 months merely to grant clearance, which the Court regarded as a clear departure from its mandate of expeditious action.

2. Because of this delay, and given the refinery’s continued emission of hazardous sulphur-dioxide levels (accepted at about 500 kg per hour), the Court held that the Board’s Chairman had shown “scant respect” for its orders. It therefore issued a show-cause notice for contempt.

3. The Court simultaneously recognised that Cabinet Committee approval was still pending. It directed Mathura Refinery to forward the proposal within two weeks and requested the Cabinet Secretary to place it before the Cabinet Committee on Economic Affairs “as expeditiously as possible.” The refinery was ordered to file a fresh affidavit by 10-7-1996 giving progress details and explaining compliance with other National Environmental Engineering Research Institute (NEERI) recommendations.

4. Observing ongoing pollution, the Court considered imposition of a “heavy pollution fine” on Mathura Refinery and issued a separate show-cause notice on that question.

5. Turning to GAIL, the Court recorded progress on allocation of 0.60 MMSCMD of gas and on construction of two pipelines scheduled for completion by December 1996. It directed that pipeline routing must protect the Taj Mahal and local residents, allowed GAIL to seek NEERI’s technical advice, and required a time-frame affidavit for the city distribution network.

6. Regarding uninterrupted electricity supply, the Court took note of the Uttar Pradesh State Electricity Board’s short-, medium- and long-term projects costing approximately ₹190 crore. It ordered the Union of India to state, within two weeks, the funding sources and timeline for releasing the remaining ₹99.54 crore.

7. Concerning the 24-km Agra bypass, the Court accepted the State’s proposal to widen the existing road but refused permission to cut 263 trees for a one-metre kachcha extension. Only 80 trees could be felled if “absolutely necessary.” The Public Works Department was directed to complete the bypass by 30-12-1996 and to file quarterly progress reports.

Holding and Implications

Interim directions issued; show-cause notices for contempt and pollution fine; multiple compliance timelines set.

Immediate consequences include: (i) the Chairman of the Public Investment Board must explain why contempt proceedings should not be initiated; (ii) Mathura Refinery must justify avoidance of a pollution fine and update the Court on project progress and NEERI recommendations; (iii) GAIL, the Uttar Pradesh State Electricity Board, and the State PWD must meet strict deadlines on gas infrastructure, electricity supply, and bypass construction. No new legal precedent was set, but the order reinforces the Court’s continuing supervisory role in environmental protection around the Taj Mahal.

    M.C Mehta v. Union Of India And Others

    Order

    Item ‘A’

    1. Pursuant to this Court's order dated 14-3-1996 Mr C.P Jain, Chief Manager (Safety and Environment Protection), Indian Oil Corporation has filed an affidavit. In our order dated 14-3-1996 we noticed the statement of Mr C.P Jain to the effect that the Public Investment Board had given its clearance to the proposal for construction of Hydrocracking unit in Mathura Refinery on 14-3-1996.

    2. Mr Jain has in the affidavit under consideration stated that after the clearance from the Public Investment Board, the proposal shall have to be approved by the Cabinet Committee on Economic Affairs. It is stated that once the approval from the Administrative Ministry is received, the actual work of procurement of machinery and construction will start and the project is likely to be completed within a period of 42 months.

    3. We are constrained to say that despite continuous monitoring by this Court even the paper work has not as yet been completed.

    4. This Court on 20-1-1995 observed as under:

    “… Mr Mathur, in Para 7 of his affidavit has given details of the further procedure to be followed for the final completion of the project. According to the affidavit the Committee of the Public Investment Board has to sanction expenditure for the preparation of detail feasibility report. We are informed that the Secretary, Expenditure is the Chairman of the Public Investment Board. We request the Secretary, Public Investment Board to have this matter examined by the Board expeditiously keeping in view the importance of the project. We do not wish to fix any period within which the Board should finalise the matter but we trust and hope that the matter shall be finalised at an early stage.”

    5. It is obvious from the tenure of our order quoted above that this Court asked the Public Investment Board to grant its approval to the project expeditiously. Mathura Refinery is emitting more than 500 kg of sulphur dioxide per hour which is a health hazard for the human beings and also hazardous for the world heritage Taj Mahal. According to the Neeri Report, the emissions are 859 kg per hour, but according to Mr Jain, present in Court, the emissions as at present are 500 kg per hour.

    6. This Court directed the Public Investment Board to examine the matter expeditiously, which obviously did not mean a long period of 14 months. We are of the view that the Chairman of the Public Investment Board has shown scant respect to the orders of this Court. We issue show-cause notice to Mr N.K Singh, the Chairman of the Public Investment Board as to why contempt proceedings be not initiated against him.

    7. We are informed that the project has now been sent to the Cabinet Committee on Economic Affairs. The learned counsel appearing for Mathura Refinery states that the project shall be forwarded to the Cabinet Committee within two weeks from today. They may do so. We request Mr Surendra Singh, Cabinet Secretary to have this project placed before the Cabinet Committee on Economic Affairs as expeditiously as possible for clearance, after the same is received by the Committee. Mathura Refinery shall file a short affidavit before 10-7-1996 indicating the progress in this respect. The Refinery in the affidavit may also indicate as to whether other recommendations of the Neeri are being complied with, specially regarding the setting up of the Chemo-biochemical process.

    8. Since the work of controlling pollution—despite this Court's continuous efforts—is not being done according to the time schedule repeatedly set up by this Court and Refinery is polluting the ambience around Taj Mahal, we are of the view that pollution fine should be imposed on Mathura Refinery. We issue notice to Mathura Refinery to show cause as to why heavy pollution fine be not imposed on the Refinery.

    9. To come up on 10-7-1996.

    Gas Authority of India Ltd.

    10. Pursuant to this Court's order dated 14-3-1996 Mr P.C Gupta, General Manager (Civil), Gas Authority of India Ltd. has filed an affidavit dated 2-4-1996. It is stated in the affidavit that the Ministry of Petroleum and Natural Gas has already allocated 0.60 MMSCMD for distribution to the industrial units in Agra and Ferozabad. It is stated that as per the time schedule already filed in this Court, the two pipelines shall be completed by December 1996. It is further stated that the quantity of gas as mentioned above is only for the purposes of supplying the same to the industries located within the Taj Trapezium.

    11. We have no doubt that while laying down the supply line within the city of Agra, the safety of Taj and also the people living in the city of Agra shall have to be taken into consideration. We are told that expertise in this respect is available with GAIL. If necessary, the opinion of Neeri, which has been associated by this Court in Taj Trapezium matters, can also be obtained by GAIL.

    12. We have already heard the arguments regarding relocation of industries from the Taj Trapezium. Some of the industries which are not in a position to get gas connections or which are otherwise polluting may have to be relocated outside the Taj Trapezium. GAIL may also examine whether in the event of availability of more quantity of gas, the same can be supplied to the industries outside the Taj Trapezium which are located in the vicinity from where the gas pipe is passing.

    13. Mr Gupta has further stated that for the purposes of laying distribution network within the Taj Trapezium; GAIL is establishing a joint venture company. However, pending formation of the joint venture company, the required functions are being performed by GAIL. It is stated that GAIL had advertised comparative prices and heat equivalent of various fuels in the newspapers circulated in Agra and Ferozabad to enable the industries, who are prospective consumers of gas to evaluate the economics of conversion to gas. So far 214 parties from Agra and 364 parties from Ferozabad have responded. According to the affidavit these responses are being processed.

    14. Mr Reddy, on our asking, states that he would have the matter examined and file an affidavit in this Court within two weeks indicating the time-frame regarding the laying of distribution network within the Taj Trapezium. Mr Reddy further states that some land shall have to be required for the purposes of constructing city gas stations at Agra and Ferozabad. He states that the cooperation of the U.P Government is required for acquiring the land. We direct the Collector, Agra as well as the Collector, Ferozabad to render all assistance to GAIL in acquiring land for setting up the two stations for the public purposes.

    Item ‘G’

    15. Pursuant to this Court's order dated 15-3-1996 (1998) 8 SCC 711 Mr Rakesh Kumar Goel, Joint Secretary, Government of U.P, has filed an affidavit. Mr Satish Chandra, learned Senior Advocate appearing for U.P State, states that the toll at Taj Mahal, Agra is being collected by the Agra Development Authority in terms of Section 39-A of the U.P Urban Planning and Development Act, 1973. According to him the money collected is being spent on maintaining all the approach roads and other amenities provided by the authority to the tourists visiting the city of Agra. Mr Satish Chandra states that he would persuade his clients to engage a professional planner and sanitation expert to beautify and clean Agra City specially the area which is directly connected with the Taj Mahal.

    16. To come up on 8-5-1996.

    Regarding supply of continuous electricity to Agra City

    17. Mr B.B Singh and Mr Surendra Singh, Chief Engineers, U.P State Electricity Board have jointly filed affidavit dated 9-4-1996. It is stated in the affidavit that in order to ensure uninterrupted electricity supply in the Taj Trapezium, the Board has already planned the additional work required to be carried out for that purpose. The work has been divided into three categories, namely, short term, medium term and long term. It is stated in the affidavit that so far as the short term project is concerned, it shall be complete by August 1996 and the medium term, which is in two parts shall, be complete within 18 months i.e by June 1997.

    18. It is stated by Mr Jaitley, learned counsel appearing for the Board, that with the completion of the short term and the medium term projects, there shall be 30% improvement in the electricity supply, so far as Agra Town is concerned. After the completion of all the three projects, there shall be 100% uninterrupted supply to the Taj Trapezium. The total cost for all the three projects has been stated to be about Rs 190 crores.

    19. According to the affidavit, the Board has already started the short term and the medium term work with the Board's own funds amounting to Rs 90 crores. The learned counsel for the Union of India states that the copy of the affidavit has been received by him today. He would place the affidavit before the authorities concerned of the Government of India and file a short affidavit in this Court within two weeks from today. The affidavit shall indicate as to from what sources and within how much time the sum of Rs 99.54 crores needed to complete the electricity supply projects shall be made available to the U.P State Electricity Board.

    20. To come up on 8-5-1996.

    Agra Bypass

    21. Pursuant to this Court's order dated 12-3-1996 WP (C) No. 13381 of 1984 additional affidavit has been filed by Mr P.N Batham, Joint Secretary, U.P Shasan, Public Works Department, Lucknow. It is stated in the affidavit that the construction of 24 km proposed bypass shall continue. Mr Srivastava, learned counsel appearing for the State of U.P states that funds for the construction of this 24 km road are already available with the Department. 4.1 km road is under construction. The remaining 19.9 km is required to be widened to 3.7 m width. The present proposed road is less than 3 m and it is to be widened to the width of 3.7 m which is the minimum requirement for single-lane road. This may be done.

    22. The affidavit further states that another 1 m kachcha extension is necessary to provide clear sight of vision to drivers to prevent accidents. If that is done, then 263 trees are to be out. We are not inclined to permit the cutting of such a large number of trees and as such the extension of the kachcha road may be done only at those places where there are no trees.

    23. We make it clear that we do not permit the cutting of 263 trees as suggested in the affidavit. So far as cutting of 80 trees for widening the road by one metre is concerned, that may be done if it is absolutely necessary. Initially we were of the view that this stretch of road should be constructed within six months from the date of this Court's last order. Keeping in view the difficulties explained by Mr Srivastava, we direct the PWD of U.P to complete this 24 km bypass by 30-12-1996. A responsible officer of the Department shall file progress reports after every three months.