  • Companies Act. First respondent Kerala State Industrial Development Corporation
  • provisions of the Kerala Revenue Recovery Act.7.
  • provisions of the Kerala Revenue Recovery Act
  • Kerala Revenue Recovery Act. Since this Act
  • provisions of S. 14 of the Limitation Act.
  • ARTICLE 226 CONSTITUTION OF INDIA
  • S. 71 of the Kerala Revenue Recovery Act
  • REVENUE RECOVERY ACT
  • Kerala Revenue Recovery Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Companies Act. First respondent Kerala State Industrial Development Corporation
  • provisions of the Kerala Revenue Recovery Act.7.
  • provisions of the Kerala Revenue Recovery Act
  • Kerala Revenue Recovery Act. Since this Act
  • provisions of S. 14 of the Limitation Act.
  • ARTICLE 226 CONSTITUTION OF INDIA
  • S. 71 of the Kerala Revenue Recovery Act
  • REVENUE RECOVERY ACT
  • Kerala Revenue Recovery Act
Smart Summary

Factual and Procedural Background

The petitioner, a public limited company, entered into a contract with the first respondent, Kerala State Industrial Development Corporation Ltd. (KSIDC), a fully owned Government Company, for the erection of a Water Treatment Plant. The contract was formalized through a letter of indent and an agreement executed in early 1998, with an estimated work value of Rs. 1,36,20,295/- and a completion period of fifteen months. The petitioner alleged delays and incomplete drawings supplied by KSIDC, leading to cancellation of the contract by KSIDC's Chief Engineer in January 1999 at the petitioner's risk and cost.

The petitioner claimed damages amounting to Rs. 43 lakhs on six grounds and requested arbitration, which was rejected by KSIDC's Managing Director. The petitioner then filed an Original Petition treating the Managing Director's order as an arbitral award, which was dismissed due to absence of an arbitration clause. Subsequently, the petitioner instituted a suit for damages, which remains pending.

Meanwhile, KSIDC's Chief Engineer demanded Rs. 12,19,769/- from the petitioner for losses in rearranging the work and threatened to invoke the Kerala Revenue Recovery Act for recovery. The petitioner challenged this demand as illegal and arbitrary, arguing that no amount was adjudicated or settled in favor of KSIDC and that disputed damages cannot be recovered through revenue recovery proceedings without adjudication.

Legal Issues Presented

  1. Whether revenue recovery proceedings can be initiated by a Government Company to realize damages arising from an alleged breach of contract when such damages have not been quantified or adjudicated.
  2. Whether the Managing Director of KSIDC has the authority under the contract to determine damages without adjudication by an independent authority.
  3. Whether disputed amounts can be recovered under the Kerala Revenue Recovery Act without prior settlement or adjudication.
  4. The applicability and scope of the Kerala Revenue Recovery Act in recovering contractual dues claimed by a Government Company.
  5. The extent of judicial review available in contractual disputes involving Government Companies.

Arguments of the Parties

Petitioner's Arguments

  • The demand made by the Chief Engineer for recovery under the Kerala Revenue Recovery Act is illegal and unauthorized.
  • No amount is due to KSIDC; rather, KSIDC owes amounts to the petitioner, as claimed in a pending civil suit.
  • Damages cannot be realized through revenue recovery proceedings without prior adjudication or settlement.
  • The petitioner has not breached the contract; any breach is attributable to KSIDC.

Respondents' Arguments

  • The claim arises out of a contractual matter, and writ jurisdiction under Article 226 is not appropriate.
  • The contract empowers the Managing Director of KSIDC to determine the amount due, which can be recovered under the Kerala Revenue Recovery Act.
  • Notification under Section 71 of the Kerala Revenue Recovery Act authorizes KSIDC to recover dues like Government dues.
  • The Chief Engineer's demand is valid as per contract provisions and the Revenue Recovery Act.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Hansraj Gupta v. Dehra Dun Mussoorie Electric Tramway Co. Ltd. (AIR 1933 PC 63) Interpretation of the phrase "money due" as settled and fixed obligations. Supported the principle that only settled dues can be recovered under the Kerala Revenue Recovery Act.
State of Kerala v. Kalliyanikutty (1999 (2) KLT 146 (SC)) Kerala Revenue Recovery Act does not create new rights; only settled or adjudicated dues can be recovered. Emphasized that disputed or unadjudicated amounts cannot be recovered through revenue recovery proceedings.
Kerala State Electricity Board v. Kurien E. Kalathil ((2000) 6 SCC 293) Contractual disputes involving Government undertakings are not generally suitable for writ jurisdiction under Article 226. Reinforced the need for civil adjudication or arbitration for contractual disputes.
Tata Cellular v. Union Of India ((1994) 6 SCC 651) Judicial review applies to Government contracts only to prevent arbitrariness, bias, or mala fides. Confirmed that the court will not interfere in contractual terms unless there is patent illegality or arbitrariness.
Global Energy Ltd. v. Adani Exports Ltd. (2005 AIR SCW 2875) Terms of invitation to tender are not open to judicial scrutiny unless arbitrary or mala fide. Supported the principle that contractual terms must be respected unless clearly unreasonable.
Bihar State Mineral Development Corporation v. Encon Builders (I)(P) Ltd. ((2003) 7 SCC 418) Rejection of the principle that a party can judge its own cause (nemo sibi esse judex). Affirmed that adjudication of disputes must be by an independent authority, not by a party to the contract.
P.V Paily v. State of Kerala (2000 (3) KLT 343 : AIR 2000 Ker. 268) Same maxim of nemo judex applies in contractual adjudications. Supported the principle against self-adjudication by parties to a contract.
State Of Karnataka v. Shree Rameshwara Rice Mills, Thirthahalli ((1987) 2 SCC 160 : AIR 1987 SC 1359) Power to assess damages arises only if breach is admitted or undisputed; adjudication by one party is invalid if breach is disputed. Court held that adjudication on breach and damages by a party to the contract is not sustainable if breach is disputed.
K.A Ponnappan v. The D.F.O Chalakudy (1984 KLJ 853) Revenue Recovery Act proceedings can be initiated only after determination of the amount due. Held that enforcement under Revenue Recovery Act without determination of dues is impermissible.
Abraham Sebastian v. State Of Kerala (2002 (3) KLT 839) Disputed damages cannot be recovered through revenue recovery without prior adjudication. Supported the principle that breach must be admitted or adjudicated before recovery under Revenue Recovery Act.
Mohammed Kunhi v. K.S.E.B (2001 (3) KLT 733) Same principle regarding necessity of adjudication before revenue recovery. Reiterated the requirement of settled dues for Revenue Recovery Act proceedings.
V.P Kunhammed v. State of Kerala (1999 (3) KLT SN 49 Case No. 50 : 1999 (2) KLJ 678) Same principle regarding adjudication before recovery. Affirmed that disputed dues cannot be recovered without adjudication.
K.A Sobhanadas v. State of Kerala (1984 KLJ 684) Same principle regarding requirement of adjudicated dues for revenue recovery. Supported the principle that recovery under Revenue Recovery Act requires settled dues.

Court's Reasoning and Analysis

The court examined the nature of the claim and the provisions of the Kerala Revenue Recovery Act (KRRA), particularly Section 71, which authorizes government companies like KSIDC to recover dues as if they were government dues. However, the court emphasized that such recovery is permissible only for amounts that are "due," meaning fixed, settled, or adjudicated obligations. The court relied on authoritative precedents which establish that the KRRA does not create new rights but provides a mechanism for speedy recovery of legally established dues.

In this case, the petitioner disputed the amounts claimed by KSIDC, and the alleged damages had not been adjudicated or settled by an independent authority. The contract did not contain an arbitration clause, and the Managing Director's rejection of the claim was not an arbitral award. The Chief Engineer's demand for recovery under the KRRA was issued without proper adjudication and was therefore unauthorized.

The court further analyzed contractual provisions, including clauses relating to dispute resolution and jurisdiction, concluding that the civil courts retain jurisdiction over genuine disputes. The principle of nemo sibi esse judex (no one shall be a judge in their own cause) was applied to reject the idea that KSIDC could unilaterally adjudicate damages without independent determination.

Relying on precedents such as State of Karnataka v. Shree Rameshwara Rice Mills, the court held that assessment of damages by one party to the contract is impermissible if the breach is disputed. The court also referenced earlier decisions that revenue recovery proceedings require prior determination of the amount due.

Accordingly, the court set aside the Chief Engineer's demand and the threatened revenue recovery proceedings, without expressing any opinion on the merits of the underlying claim, and allowed the petitioner to pursue civil remedies.

Holding and Implications

The court held that revenue recovery proceedings under the Kerala Revenue Recovery Act cannot be initiated by a Government Company for recovering damages arising from an alleged breach of contract unless the damages are quantified, adjudicated, or settled.

The order set aside the demand made by KSIDC's Chief Engineer and restrained the use of revenue recovery proceedings in this matter. The petitioner is entitled to pursue the pending civil suit for damages. The decision clarifies that disputed contractual claims cannot be unilaterally recovered as government dues without proper adjudication.

No new legal precedent was created; the ruling reaffirms existing principles that the Kerala Revenue Recovery Act is a procedural mechanism for recovery of settled dues and does not authorize recovery of disputed or unadjudicated claims. The civil courts retain jurisdiction over contractual disputes involving Government Companies where breach and damages are contested.

    Shriram Engineering Construction Co. Ltd. v. K.S.I.D.C

    K.B Koshy, J.:— Can revenue recovery proceedings be taken by a Government Company for realising damages arising out of alleged breach of contract especially when damages are not quantified through adjudication is the main question to be decided in this Writ Petition. Petitioner is a public limited company registered under the Companies Act. First respondent Kerala State Industrial Development Corporation Ltd. (KSIDC) is a State Government undertaking and is a fully owned Government Company. The petitioner was issued with a letter of indent, Ext. P1 dated 21.2.1998, by the first respondent for erection of Water Treatment Plant with rapid and gravity filter pump house and value of the work was estimated at Rs. 1,36,20,295/-. Petitioner has deposited Rs. 2,00,000/- and the Indent Document was signed by both parties. Ext. P2 is the agreement executed. By Ext. P3 dated 8.3.1998, the site was handed over and the agreement was that project will be completed within fifteen months. According to the petitioner, only on 5.5.1998 drawings were made available by KSIDC and even those drawings were not complete. On 20.8.98, by Ext. P4, final drawings were supplied to the petitioner. Only on 22.12.1998, by Ext. P5, the respondent forwarded details of Footings to be provided for the stub columns supporting the Filter box, after closing of part of the work. Various correspondence took place between the parties. According to the petitioner, without fulfilling contractual obligations of me respondents, by Ext. P9 dated 13.1.1999, Chief Engineer of first respondent cancelled the contract at the risk and cost of the petitioner. Thereafter, by Ext. P10 dated 10.4.1999 addressed to Managing Director of respondent Corporation, the petitioner made claims for Rs. 43 lakhs and requested him for arbitration and settling the issue. The claims were made on six grounds namely:

    1. Return of Security deposit Rs. 2/- Lakhs with interest at 18%.

    2 Idle Labour charges Rs. One lakh with interest.

    3. Compensation due towards investment at idling machines (hold up of tools & Tackles Rs. 5/- lakhs with interest 18%.

    4 Compensation for building materials Rs. 5/- lakhs with interest at 18% p.a

    5. Damages and delay caused in releasing due payments Rs. 5/- lakhs.

    6. Consequential damages due to unlawful termination - loss of reputation, loss of business good will Rs. 25/- lakhs.

    2. Managing Director rejected the claims by order dated 7.6.1999 (Ext. P11). It is stated in Ext. P11 as follows:

    “Hence the claim petition dated Nil-3-99 of the claimant contractor is totally and summarily rejected outright.”

    3. Thereafter, the petitioner filed an Original Petition before this Court treating Ext. P11 order of the Managing Director as arbitral award. That was rejected accepting contentions of the respondents that there was no arbitration clause in the agreement and letter of the Managing Director cannot be treated as an arbitral award. Thereafter, the petitioner filed a suit as O.S No. 115 of 2006 before the Sub Court, Thiruvananthapuram, claiming damages from the K.S.I.D.C and the suit is pending. By Ext. P12 dated 22.7.1999 Chief Engineer of the first respondent (second respondent in this O.P) made a demand of Rs. 12,19,769/- as due from the petitioner for rearranging the work and also threatened that in the event of failure to pay the above sum, Revenue Recovery Act will be invoked for the recovery. Ext. P12 is reproduced as follows:

    “The above work which was awarded on contract to you as per agreement No. IGC/KTP/03 of KSIDC, was terminated as per ordersecondcited. Also, yourclaims were rejected vide letter third cited.

    As already informed and as per conditions of tender and agreement, the loss if any sustained by KSIDC in rearranging the work is to be realised from you.

    A statement showing the loss, provisionally assessed, in rearranging the work is enclosed herewith for reference. But you are informed that the final figures at the completion of work shall be assessed as cost of completion of the project and any further dues are required from you on this work shall be informed to you and the required amount on such circumstances shall be recovered from you.

    I request you to remit an amount of Rs. 12,19,769/- (Rupees Twelve lakhs nineteen thousand seven hundred and sixty nine only), within fifteen days on receipt of this letter. If you fail to adhere to this direction, we will be forced to proceed with R.R Act.”

    4. It is the case of the petitioner that the above demand made by the Chief Engineer is wholly illegal and arbitrary. The Chief Engineer is not authorized to make such a demand and threaten the petitioner to recover it under Revenue Recovery Act. When the petitioner's claim was rejected by the Managing Director, petitioner has already approached the civil court and the case is pending in the civil court. It is submitted mat without adjudication, the amount of damages even if payable cannot be determined for realising it from him through revenue recovery proceedings. According to the petitioner, Company did not commit any breach, but, breach is on the part of the KSIDG and hence respondent is liable to pay damages.

    5. Contention or the respondents is that even though respondent company is a public sector undertaking, claim is arising out of Ext. P2 contract, which is purely a contractual matter and a Writ Petition under Article 226 of the Constitution of India will not lie. Secondly it was contended that in Ext. P2 contract there is a provision for determination of the amount by the Managing Director of KSIDC. It is also submitted that notification was issued under S. 71 authorising KSIDC to realise the dues by taking steps under the provisions of the Kerala Revenue Recovery Act like Government dues and hence there is no infirmity in the decision. S. 71 of the Kerala Revenue Recovery Act provides as follows:

    “71. Power of Government to declare the Act applicable to any institution.— The Government may, by notification in the Gazette declare, if they are satisfied that it is necessary to do so in public interest, that the provisions of this Act shall be applicable to the recovery of ‘amounts due’ from any person or class of persons to any specified institution or any class or classes of institutions, and thereupon all the provisions of this Act shall be applicable to such recovery.”

    6. In exercise of the powers issued under notification, ‘amounts due’ to KSIDC also can be realised like dues to the Government by resorting to revenue recovery proceedings under the Act. But, it gives the right to KSIDC only to recover the ‘amount due’. The word ‘due’ as per Webster's Dictionary means ‘owing and demanding; payable’. According to Black's Law Dictionary, the word ‘due’ imports a fixed and settled obligation. After considering the decision of the Privy Council in Hansraj Gupta v. Dehra Dun Mussoorie Electric Tramway Co. Ltd. (AIR 1933 PC 63) interpreting the words ‘money due’, it was held by the Apex Court in State of Kerala v. Kalliyanikutty (1999 (2) KLT 146 (SC)) that only the settled and fixed dues can be recovered through the machinery under the Kerala Revenue Recovery Act and it does not create any new right. It only provides a process for speedy recovery of money due - that is settled dues which are either admittedly due or adjudicated and settled. Even time barred dues cannot be recovered. The Three Member Bench of the Apex Court in the above case held as follows:

    “The Kerala Revenue Recovery Act does not create any new right. It merely provides a process for speedy recovery of moneys due. Therefore, instead of filing a suit, (or an application or petition under any special Act), obtaining a decree and executing it, the bank or the financial institution can now recover the claim under the Kerala Revenue Recovery Act. Since this Act does not create any new right, the person claiming recovery cannot claim recovery of amounts which are not legally recoverable nor can a defence of limitation available to a debtor in a suit or other legal proceeding be taken away under the provisions of the Kerala Revenue Recovery Act.”

    7. Here, the contention of the petitioner is that no amount is due to the KSIDC from the petitioner. In fact, amounts are due from the KSIDC and a bona fide suit is instituted before the civil court for that. Before settling the question whether ‘any amount is due’ revenue recovery proceedings cannot be taken.

    8. In this connection, we also refer to Clause 3 of the preliminary agreement which is as follows:

    “3. If the contractor does not come forward to execute the original agreement after the said work is awarded and selection notice issued in his favour or commits breach of any of the conditions of the contract as stipulated in clause 14 of the Notice inviting Tenders as quoted above within the period stipulated, KSIDC may rearrange the works otherwise or get it done otherwise at the risk and cost of the contractor and the loss so sustained by KSIDC can be realised from the contractor under the Revenue Recovery Act as if arrears of land revenue as assessed, quantified and fixed by an adjudicating authority consisting of KSIDC or any other officer or officers authorised by KSIDC taking into consideration the prevailing rates and after giving due notice to the contractor. The decision taken by such authorised officer or officers shall be final and conclusive and shall be binding on the contractor.”

    9. This clause is admittedly not applicable as agreement was executed and there is no breach of any of the conditions of the contract as stipulated in Clause 14 of the Notice inviting tenders. In Clause 31 of Ext. P2 general contract it is stated as follows:

    “31. SETTLEMENT OF DISPUTES

    All disputes and difference of any kind whatever arising out of or in connection with the contract or the carrying out of the works (whether during the progress of the work or after their completion and whether before or after the determination, abandonment or breach of the contract) shall be settled by The Managing Director KSIDC who shall state his decision in writing. Such decision may be in the form of a final certificate or otherwise. The decision of the Managing Director KSIDC shall be final and binding on the contractor.”

    10. In Clause 34 it is stated as follows:

    “34. JURISDICTION

    The Courts at Trivandrum alone shall have jurisdiction in respect of any matter arising out or in connection with this contract.”

    11. In Clause 18 of the Notice inviting tenders for work which finally resulted in the contract it is stated as follows:

    “18. Arbitration shall not be a means for settling of disputes. All disputes unless settled by mutual negotiation, will be referred to the Civil courts with jurisdiction at Trivandrum.”

    12. With regard to the contention that a writ will not lie, it is an accepted proposition of law that generally in contractual matters writ will not be issued merely because one party is a Government undertaking. Apex Court in Kerala State Electricity Board v. Kurien E. Kalathil ((2000) 6 SCC 293) held as follows:

    “The contract between the parties in the realm of private law. It is not a statutory contract. The disputes relating to interpretation of the terms and conditions of such a contract could not have been agitated in a petition under Art. 226 of the Constitution of India. That is a matter for adjudication by a civil court or in arbitration if provided for in the contract. Whether any amount is due and if so, how much and refusal of the appellant to pay it is justified or not, are not the matters which could have been agitated and decided in a Writ Petition. The contractor should have relegated to other remedies.”

    13. It has been repeatedly held by the Apex Court that no Government company is obliged to make a contract, but, once it makes a contract, it should be fair and reasonable and it should not be arbitrary. If there is patent illegality or wednesbury arbitrariness, the courts have jurisdiction to interfere in the same in a writ proceedings. In Tata Cellular v. Union Of India. ((1994) 6 SCC 651) it was held by the Apex Court that the principles of judicial review would apply to the exercise of contractual powers by Government bodies in order to prevent arbitrariness or favouritism. However, there are inherent limitations in exercise of that power of judicial review. Only if there is patent illegality, irrationality, namely, Wednesbury unreasonableness or procedural impropriety court can interfere in contractual matters. Apex Court further held that the Government must have freedom of contract. In other words, a fair play is a necessary concomitant whether it is functioning in an administrative sphere or quasi-administrative sphere. However, the decision must not only be tested by the application of Wednesbury principles of reasonableness, but, must be free from arbitrariness not affected by bias or actuated by mala fides. It is settled law that terms of the invitation to tender are not open to judicial scrutiny. Court also cannot whittle down the terms of contract unless the same is wholly arbitrary, discriminatory or actuated by mala fides as held by the Apex Court in Global Energy Ltd. v. Adani Exports Ltd. (2005 AIR SCW 2875). Here, admittedly, petitioner is not asking for judicial review of terms of the contract. Petitioner is not attacking any of the terms of the contract. Petitioner is only stating mat no amounts are due to KSIDC. It has not committed breach and breach, if any, is committed by KSIDC. It has already filed a suit for recovering the damages. KSIDC initiated revenue recovery proceedings stating that ‘amounts are due’. It is even without an adjudication by the Managing Director of KSIDC. Disputed amounts not settled or adjudicated cannot be recovered by the proceedings under Revenue Recovery Act. Ext. P2 is not a statutory contract. Respondents can realise disputed amount only by adjudication and in the absence of clause for arbitration the only remedy available is to file a suit or file a counter claim in the pending suit. In this case, the Managing Director did not decide the question of damages payable from KSIDC as mentioned under Clause 34 after notice and adjudication. Ext. P12 is a decision from Chief Engineer. Clause 34 cannot be treated as an arbitration clause. When petitioner's claim for damages to the tune of Rs. 43 lakhs was rejected under Clause 34, petitioner, treating it as arbitration award, filed petition to set aside the award and KSIDC itself contended that Clause 34 cannot be equated to arbitration and Ext. P11 decision of Managing Director is not amounting to arbitration award. Here, breach of contract is not admitted and petitioner contended that termination of contract by KSIDC is illegal and suit for recovering damages is pending.

    14. The maxim nemo sibi esse judex vel suis jus dicere debet, i.e no man, can, judge his own cause is accepted by Indian Courts in various decisions. See for example paragraph 17 of the decision in Bihar State Mineral Development Corporation v. Encon Builders (I)(P) Ltd. ((2003) 7 SCC 418) and the decision in P.V Paily v. State of Kerala (2000 (3) KLT 343 : AIR 2000 Ker. 268). We also agree with the contention that settled dues to the notified Government company can be realised through revenue recovery proceedings as if it is a Government due and the dues should be an agreed or adjudicated amount. Dues cannot be demanded and recovered by revenue recovery proceedings according to whims and fancies of the parties. In this case, already a claim was made by the petitioner. On its rejection by the Managing Director, the matter is pending in the civil court and claim by the KSIDC is not adjudicated. When the legality of termination itself is a question pending adjudication in a civil court, the Chief Engineer cannot make a demand and threaten the petitioner with revenue recovery proceedings. Now, we will consider the contention of the respondents based upon Clause 34 of Ext. P2 contract that Managing Director of KSIDC, one of the contesting parties, can determine the amount without adjudication by a third party even when breach of contract is not admitted. In this case, Ext. P12 order is not an adjudicated order of the Managing Director as envisaged in Clause 18 of the Notice inviting tenders for work (supra). Even going by the contractual terms which were relied on by the respondents, there is no power for the Chief Engineer to determine the amount and demand and recover it from the petitioner. Here, so far the Managing Director has not decided the amount as mentioned in the clause relied on by the respondents. Further, clauses 18 and 34 (supra) would show that civil court's jurisdiction, if the amount really and genuinely disputed, is not ousted, but is genuinely contested by the parties.

    15. A similar clause like Clause 31 was interpreted by the Apex Court in State Of Karnataka v. Shree Rameshwara Rice Mills, Thirthahalli, Thirthahalli ((1987) 2 SCC 160 : AIR 1987 SC 1359) wherein it was held as follows:

    “On a plain reading of the words it is clear that the right of the second party to assess damages would arise only if the breach of conditions is admitted or if no issue is made of it. If it was the intention of the parties that the officer acting on behalf of the State was also entitled to adjudicate upon a dispute regarding the breach of conditions the wording of clause 12 would have been entirely different. It cannot also be argued that a right to adjudicate upon an issue relating to a breach of conditions of the contract would flow from or is inhered in the right conferred to assess the damages arising from a breach of conditions. The power to assess damages, as pointed out by the Full Bench, is a subsidiary and consequential power and not the primary power. Even assuming for argument's sake that the terms of clause 12 afford scope for being construed as empowering the officer of the State to decide upon the question of breach as well as assess the quantum of damages, we do not think that adjudication by the Officer regarding the breach of the contract can be sustained under law because a party to the agreement cannot be an arbiter in his own cause. Interests of justice and equity require that where a party to a contract disputes the committing of any breach of conditions the adjudication should be by an independent person or body and not by the other party to the contract. The position will, however, be different where there is no dispute or there is consensus between the contracting parties regarding the breach of conditions. In such a case the Officer of the State, even though a party to the contract will be well within his rights, in assessing the damages occasioned by the breach in view of the specific terms of clause 12”.

    16. A Division Bench of this court earlier, two decades ago, in K.A Ponnappan v. The D.F.O Chalakudy (1984 KLJ 853) held that proceedings under the Revenue Recovery Act can be initiated only after determination of the amount even if it is a Government due. The Division Bench held as follows:

    “In case the contract conceives of determination otherwise than through a civil suit such as arbitration, that may be the mode of determination. Normally the civil court will have to determine whether any damages is due and if so what the quantum is. Only on such determination of the amount it could be said to be due and then the Revenue Recovery Act can be put into action. Enforcement by resort to the Revenue Recovery Act when there is no amount due is not permissible. Amount would not be due merely because of breach. Breach gives rise to a right to sue. When that right is exercised and as a consequence it is found on adjudication that amount is due, that would be recoverable. This aspect the learned single Judge has not considered though it is seen urged before him and it is seen raised under ground No. 2. In these circumstances we think the demand under Revenue Recovery Act cannot succeed. The proceedings for recovery will stand quashed.”

    17. When breach is not admitted, before determining the amount by suit or arbitration by independent authority, revenue recovery cannot be initiated for recovering disputed damages as settled by this court in various decisions. (See Abraham Sebastian v. State Of Kerala (2002 (3) KLT 839) (judgment delivered for Division Bench by Justice B.N Srikrishna (as he then was), Mohammed Kunhi v. K.S.E.B (2001 (3) KLT 733), V.P Kunhammed v. State of Kerala (1999 (3) KLT SN 49 Case No. 50 : 1999 (2) KLJ 678) and K.A Sobhanadas v. State of Kerala (1984 KLJ 684).

    18. In the above circumstances, we set aside Ext. P12 issued by the Chief Engineer without prejudice to the rights of the parties elsewhere. We are not expressing any opinion regarding merits of the claim put forward by the KSIDC. If the first respondent wants to file a separate suit or counter claim in the suit filed by the petitioner, since there was stay in this case and was pending for some time, the time taken during the pendency of this proceedings shall be excluded considering the provisions of S. 14 of the Limitation Act. The Original Petition is allowed to the above extent.

    Use AI to get other relevant cases.

    Comments

    Shriram Engineering Construction Co. Ltd. v. K.S.I.D.C
    (Jan 22, 2007)