Smart Summary

Court Opinion Summary — Manju Goel, J.

Factual and Procedural Background

This petition arises under Section 14 of the Arbitration Act, 1940 seeking a direction to file the original Award dated 1.12.1995 passed by the sole Arbitrator (respondent No. 2) and to permit objections under Sections 30 and 33 of the Act against that Award.

Respondent No. 1 (NDMC) had entrusted the work titled "Improvement of Piazza of Connaught Place from ‘A’ to ‘F’ Blocks" to the petitioner by a letter dated 28.7.1989 and under Agreement No. 8.PM (Cont. Place)/89-90. Disputes arising under the contract led the petitioner to request appointment of an arbitrator; when respondent No. 1 did not appoint one, the petitioner filed an application under Section 20 (Suit No. 2555A/1991). By order dated 6.1.1995 the Court appointed respondent No. 2 as sole Arbitrator.

The Arbitrator announced an Award on 1.12.1995 awarding Rs. 5,000/- against claimed amounts totaling Rs. 5,15,560/-. The petitioner objected to that Award before this Court under Section 14, asserting misconduct and insufficient reasoning by the Arbitrator and seeking setting aside of the Award.

The present opinion disposes of the objection petition (I.A. No. 4777/96) and addresses whether the Award should be set aside and remitted for fresh consideration.

Legal Issues Presented

  1. Whether the Arbitrator's Award is vitiated by misconduct for having ignored material documents placed before him.
  2. Whether the Award is vitiated by failure to give reasons, including how specific monetary figures (e.g., Rs. 1,000/- and Rs. 4,000/-) were arrived at and the absence of any reasoning for finding the claimant to be in breach.
  3. Whether the Arbitrator erred in declining to award interest where the petitioner sought pre-suit, pendente lite and future interest at 21% per annum compounded annually.
  4. Whether, as a consequence of the above defects, the Award should be set aside and the matter remitted to the Arbitrator for a fresh award.

Arguments of the Parties

Petitioner's (Claimant/Objector's) Arguments

  • The petitioner contended that certain claims were wrongly disallowed or inadequately awarded. For Claim No. 1 (site godown and related infrastructure) the petitioner argued that because NDMC admitted that a godown had been set up, the full claim ought to have been allowed rather than a token Rs. 1,000/-.
  • On Claim No. 2 (cost of barricading) the petitioner asserted that Annexure 2 had been submitted and was misread or overlooked by the Arbitrator.
  • For Claim No. 3 (cost of stone samples) the petitioner maintained that respondent No. 1 admitted supply of samples and that the Arbitrator failed to give reasons for the partial award; Annexure 3 (analysis of rates) was asserted to have been overlooked.
  • On Claims Nos. 4, 5 and 6 (loss of profit, non-utilisation of tools and plants, and engagement of staff), the petitioner argued these claims should not have been dealt with collectively, that the Arbitrator erred in finding the petitioner to be in breach, and that mobilisation was proved by Annexures C-5 to C-11. The petitioner also argued an engineer and chowkidar had to be engaged per Clause 36 of the Agreement and site security requirements.
  • The petitioner alleged the Arbitrator misconducted the proceedings by ignoring material documents (notably C-5, C-7, C-11 and others) and failed to provide reasons for key conclusions, including the finding of breach and the basis for reduced monetary awards.
  • Regarding Claim No. 8 (interest), the petitioner contended the Arbitrator erred in declining interest, claiming entitlement under the Interest Act and relevant judgments.

Respondent's (NDMC's) Arguments

  • NDMC supported the Award and submitted that there was no misconduct on the part of the Arbitrator and that the Award ought not to be set aside.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
K.P. Poulose v. State of Kerala, (1975) 2 SCC 236 : AIR 1975 SC 1259 That an Arbitrator may be found to have misconducted the proceedings where he ignores very material documents placed before him. The Court relied on this precedent to support the conclusion that the Arbitrator in the present case had misconducted the proceedings by ignoring material documents and therefore the Award could be set aside.
Sathyanarayana Brothers (P) Ltd. v. Tamil Nadu Water Supply & Drainage Board, 2004 (1) Arb.L.R (SC) 1 Expresses a similar principle that an Arbitrator's ignoring of material evidence may amount to misconduct of the proceedings. The Court noted that the opinion in Sathyanarayana Brothers (supra) was similar to K.P. Poulose and applied the same reasoning to conclude the Arbitrator had misconducted the proceedings in the present matter.

Court's Reasoning and Analysis

The Court undertook a focused examination of the Award and the objections raised by the petitioner. The reasoning can be broken down as follows:

  1. Requirement to Give Reasons:

    The Court emphasised that the Arbitrator was required to give reasons for his findings. It identified specific instances where reasoning was absent or inadequate: the Award granted Rs. 1,000/- on Claim No. 1 (claimed Rs. 12,700/-) without explaining how the Rs. 1,000/- figure was derived despite admitting a "symbolic godown"; and the Award granted Rs. 4,000/- on Claim No. 3 without stating the basis for that figure, although respondent had admitted receipt of some samples.

  2. Finding of Breach Without Explanation:

    A central defect was the Arbitrator's conclusion that the petitioner was in breach, a finding that led to refusal of Claims 4, 5 and 6 and costs (Claim 7). The Court observed there is "no discussion anywhere in the entire award" explaining how the contract was terminated or why the petitioner was held to be in breach. Because the petitioner’s major claims depended on alleging breach by the NDMC, the absence of reasons for the Arbitrator's contrary conclusion was critical.

  3. Ignoring Material Documents (Misconduct):

    The Court noted the petitioner had relied on documents such as C-5 (a letter complaining of delays by NDMC and asserting mobilisation of resources) and C-7 (a letter from NDMC admitting delay). The Arbitrator had not taken note of these and other documents. The Court treated the ignoring of such materials as misconduct in the arbitration proceedings.

  4. Precedent Support:

    The Court referred to K.P. Poulose and Sathyanarayana Brothers to show established authority that ignoring material documents may constitute misconduct justifying setting aside an award. The Court found the present facts analogous.

  5. Interest Claim:

    The Arbitrator's refusal to award interest was described as contrary to established legal principles on an Arbitrator's power to grant interest and a claimant's entitlement; the Court noted that the arbitrator's opinion that no interest was payable was "against the established legal principles."

  6. Resulting Conclusion:

    On the combined grounds of failure to give reasons for key findings, ignoring material documents (misconduct), and error on the question of interest, the Court concluded the Award is liable to be set aside and remitted for fresh consideration by the Arbitrator.

Holding and Implications

Holding: The objection petition (I.A. No. 4777/96) is allowed; the Arbitrator's Award dated 1.12.1995 is set aside and remanded to the Arbitrator, Shri S.R. Nigam, for passing a fresh award in the dispute.

Direct Consequences and Practical Implications:

  • The parties are directed to report to Shri S.R. Nigam on 1.8.2006 and to serve him with a copy of this judgment.
  • In the event Shri S.R. Nigam is not available, the petitioner may apply to the Court for appointment of a replacement Arbitrator.
  • The respondent (NDMC) is directed to bear the cost of the proceedings in the suit.
  • The Court's decision results in the Award being set aside and the dispute being reconsidered by the Arbitrator; the opinion does not purport to decide the substantive claims anew.
  • The opinion does not announce any new precedent; it applies existing authorities (as cited) to conclude that failure to give reasons and ignoring material documents justify setting aside an award.
Suit decreed and IA allowed.

    R.K Sharma & Co. v. Ndmc & Anr.

    Manju Goel, J.— This is a petition under Section 14 of the Arbitration Act, 1940 (hereinafter referred to as ‘the Act’) for a direction to file the original Award dated 1.12.1995 passed by the sole Arbitrator-respondent No. 2 and objections under Sections 30 and 33 of the Act against the Award. Respondent No. 1 entrusted the work titled ‘Improvement of Piazza of Connaught Place from ‘A’ to ‘F’ Blocks’ to the petitioner vide a letter dated 28.7.1989 and Agreement No. 8.PM (Cont. Place)/89-90. On account of the disputes arising in respect of the contract at work, the petitioner asked the Administrator of respondent No. 1 to appoint an Arbitrator and respondent No. 1 having failed to do so, the petitioner filed an application under Section 20 of the Act, being Suit No. 2555A/1991, which was allowed vide an order dated 6.1.1995 and respondent No. 1 appointed respondent No. 2 as the sole Arbitrator to adjudicate the claim of the petitioner. The Arbitrator thereafter announced the Award on 1.12.1995 for a sum of Rs. 5,000/- against the claim of Rs. 5,15,560/-. Since the Arbitrator was appointed pursuant to an order of this Court, an application under Section 14 is presented to this Court for a direction to the Arbitrator to file the Award.

    2. The Award deals with eight claims of the petitioner. Claim No. 1 was for a sum of Rs. 12,700/- for putting up infrastructure by way of a site godown and barricading, apart from deploying site Engineer, Chowkidars, etc. NDMC admitted that only a symbolic sort of a godown had been set up without any barricades. The Arbitrator awarded a sum of Rs. 1,000/- to the claimant towards the cost of the symbolic godown. Claim No. 2 was towards the cost of barricading, which was declined by the Arbitrator as no sufficient proof of the expense allegedly incurred towards the barricading was adduced before the Arbitrator. Claim No. 3 was for Rs. 13,095/- towards the cost of samples of Dholpur and Red Sand Stone which were to be laid. On account of termination of the work, the petitioner claimed, the samples went waste causing this damage. The Arbitrator found that no proof of the cost incurred for those stones had been furnished. Since the NDMC, i.e respondent No. 1, did not deny having received some samples, a sum of Rs. 4,000/- was allowed on this account. Claim Nos. 4, 5 and 6 were on account of loss of profit, non-utilisation of tools and plants and ungainful engagement of staff amounting to Rs. 3,08,913/-, Rs. 81,640/- and Rs. 73,612/- respectively. The Arbitrator observed that the total value of the work was Rs. 7.87 lacs and, therefore, a profit of over Rs. 3.00 lacs could not have been expected. Further, there was no evidence to show mobilisation of tools and plants, etc. Further, the Arbitrator found that since no work was done, there was no ground for claiming salary of an engineer. The claimant/petitioner himself was found to be in breach and, therefore, not entitled to any of the three claims. Thus, claim Nos. 4,5 and 6 were totally declined. Claim No. 7 was for a sum of Rs. 10,000/- towards the cost of the arbitration proceedings, which the Arbitrator declined on the ground that the claimant himself was in breach and, hence, not entitled to the cost of the arbitration. Claim No. 8 was for pre-suit, pendente lite and future interest @ 21% per annum compounded annually. The Arbitrator held that there was no provision in the agreement for payment of interest and no interest was payable. The Arbitrator, therefore, awarded a total sum of Rs. 5,000/- only.

    3. On the Arbitrator's Award on claim No. 1, the petitioner submits in his objection that since it was admitted by respondent No. 1 that the petitioner had set up a godown, the entire claim on this account should have been allowed. On the Arbitrator's Award on claim No. 2, the petitioner reiterates that the petitioner had submitted a document which was Annexure 2 which the Arbitrator misread. On the Arbitrator's Award on claim No. 3, it is contended that the Arbitrator failed to give any reasons for disallowing the claim despite the fact that respondent No. 1 had admitted the supply of samples. Further, it is contended that the petitioner had placed on record the analysis of rates in Annexure 3 which was overlooked by the Arbitrator. On the Arbitrator's Award on claim Nos. 4, 5 and 6, the objection is that the three claims could not have been dealt with together and that it was a mistake on the part of the Arbitrator in holding that it was the petitioner who was in breach. Further, the petitioner claims that Annexures C-5 to C-11 proved mobilisation of tools and plant. Further objection in this regard is that an engineer had to be engaged for a period of 15 months in anticipation of the work to commence and further Clause 36 of the Agreement required employment of an engineer at site. Similarly, employment of a Chowkidar at site was imperative for the security of the godown, tools and plant and, therefore, the Arbitrator misconducted himself by failing to award the amount claimed. Similarly, on the Arbitrator's Award on claim No. 8 it is contended that the Arbitrator misconducted himself by declining to grant interest which is available to the claimant under the Interest Act as well as under various judgments.

    4. In reply to the objections, the respondent/NDMC has supported the award and has alleged that there has been no misconduct on the part of the Arbitrator and the award cannot be set aside.

    5. At the time of hearing of arguments, the learned Counsel for the petitioner/objector has laid great stress on the failure of the Arbitrator to give reasons for the award and on the Arbitrator's failure to take note of certain documents. There is no dispute that the Arbitrator was required to give reasons. As mentioned earlier on claim No. 1 the Arbitrator awarded a sum of Rs. 1,000/- as against claim of Rs. 12,700/-. This claim was on account of infrastructure by way of a site godown and barricading the same besides deploying site engineer, Chowkidar, etc. Although no proof of the cost was placed on the record since the NDMC had admitted that some sort of symbolic godown was set up the sum of Rs. 1,000/- was awarded to the claimant. The Arbitrator has not given any reasons as to why the sum of Rs. 1,000/- could be arrived at. On claim No. 3 the Arbitrator has awarded a sum of Rs. 4,000/- towards the cost of samples of dholpur and red sand stone. This was also granted on admission of the respondent-NDMC that some samples had been received. How this figure of Rs. 4,000/- is arrived at is not mentioned by the Arbitrator. On Claims 4, 5 and 6 the Arbitrator awarded nothing. The reason for declining the three claims was mainly that it was the claimant, namely, the petitioner, who was in breach. There is no discussion anywhere in the entire award as to how the contract was terminated or withdrawn and who was in breach. For the same reason claim No. 7, i.e, cost of arbitration, has been declined. The claim for interest is declined on the ground that there was no contract for payment of interest.

    6. The most important aspect of the award is that the Arbitrator is heavily swayed by the opinion that it was the petitioner/claimant/objector who was in breach. The entire claim of the petitioner rested on his allegation of breach on the part of the respondent. Before the Arbitrator the claimant/petitioner submitted that the work was withdrawn on 27.11.1990 In paragraph 11 of the claim, the petitioner gave a narration of the negotiations and correspondence between the parties. In narrates that the NDMC has been changing the specifications from time-to-time and that by such changes the contract had virtually become a new contract. The petitioner charges the respondent with indecision on various aspects. The claim Nos. 3, 4 and 5 rested on the allegation of the petitioner that it was the NDMC who was in breach. The Arbitrator has not given any reasons for his conclusions that the petitioner was in breach. For this opinion of the Arbitrator the major part of the claim of the petitioner was declined. It is admitted position that the Arbitrator was required to give reasons for his award. The Arbitrator's award is, therefore, liable to be set aside on this ground alone.

    7. It is further alleged that the Arbitrator misconducted the proceedings by ignoring the documents. Particular reference is made to documents C-5 and C-11. C-5 is a letter complaining to the NDMC of the delays on the part of the NDMC which has been causing loss to the petitioner who has made all the arrangements at the site and had mobilized the resources in respect of staff, tools, plants and finances, etc. It is further pointed out that another document, C-7, a letter from NDMC, admits the delay on the part of the NDMC. The Arbitrator has not taken note of these two letters as well as of certain other letters. In fact, the Arbitrator has absolutely not taken any note of the documents filed by the claimant before him.

    8. The petitioner has referred to two judgments of the Supreme Court, namely, K.P Poulose v. State of Kerala, (1975) 2 SCC 236 : AIR 1975 SC 1259 and Sathyanarayana Brothers (P) Ltd. v. Tamil Nadu Water Supply & Drainage Board, 2004 (1) Arb.L.R (SC) 1. The Supreme Court held in the case of K.P Poulose (supra) that the Arbitrator had misconducted the proceedings by ignoring the two very material documents. Similar opinion was expressed in the case of Sathyanarayana Brothers (supra).

    9. In view of above findings, namely, that the Arbitrator had ignored material documents and thus had misconducted the proceedings, that the award does not give reasons for the findings, the award is liable to be set aside. It can be added that the Arbitrator's opinion that no interest is payable on the awarded amount is also against the established legal principles in respect of Arbitrator's power to grant interest and the claimant's entitlement for interest.

    10. Hence the objection petition (I.A No. 4777/96) is allowed and the Arbitrator's award is set aside and remanded back to the Arbitrator, namely, Shri S.R Nigam for passing a fresh award in the dispute. The parties shall report to Shri S.R Nigam on 1.8.2006 and serve a copy of this judgment on him. In case Shri S.R Nigam is not available for the arbitration, the petitioner shall be at liberty to apply to this Court for appointment of an Arbitrator in place of Shri S.R Nigam. The respondent shall bear the cost of the proceedings in this suit.

    Suit decreed and IA allowed.