Smart Summary

Factual and Procedural Background

This appeal arises from a suit for damages resulting from the defendants' non-acceptance of goods agreed to be sold by the plaintiffs. The plaintiffs and defendants, merchants dealing in yarn and cloth, entered into a contract on 20th August 1918 for the sale of 50 bales of double deer yarn at a specified price per bundle. The plaintiffs procured the yarn from the Pedlad factory and notified defendants of the availability of the goods in September and October 1918. The defendants accepted delivery of only 10 bales in early October but refused to accept the remaining 40 bales, offering no response to the plaintiffs' notices. The plaintiffs alleged breach of contract and sold the unaccepted goods at defendants' risk, subsequently filing suit for damages. The Subordinate Judge dismissed the suit, leading to this appeal.

Legal Issues Presented

  1. Whether the defendants' refusal to accept the remaining 40 bales constituted a breach of contract.
  2. Whether the plaintiffs proved that the 40 bales tendered conformed to the contract specifications.
  3. Whether the defendants' conduct amounted to a waiver of conditions precedent entitling plaintiffs to damages despite any alleged defects in the goods.
  4. The applicability and interpretation of the precedent Braithwaite v. Foreign Hardwood Co. in relation to repudiation and waiver of conditions precedent.

Arguments of the Parties

Plaintiffs' Arguments

  • The goods tendered complied with the contract terms, supported by evidence that the Pedlad factory produces only one kind of orange-dyed yarn marked as count 20 and weighing 10 lbs per bundle.
  • Counts ranging from 20 to 25 are commercially regarded as equivalent.
  • The contract should be interpreted as referring to yarn commercially known under the description rather than exact technical specifications.
  • The defendants' silence and refusal to accept the goods amounted to a repudiation of the contract, waiving conditions precedent.
  • Reliance on Braithwaite v. Foreign Hardwood Co. to establish that defendants cannot escape liability by later claiming goods were not as contracted if they initially repudiated the contract.

Defendants' Arguments

  • The 10 bales accepted were defective as the packets did not weigh 10 lbs and the yarn was of 24 count rather than 20 count as agreed.
  • The defendants reported these defects and claimed the contract was cancelled by mutual consent.
  • Contended that Braithwaite v. Foreign Hardwood Co. was not applicable because it involved an express repudiation, whereas their repudiation was implied by silence.
  • Asserted that the case was disapproved by the House of Lords.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Braithwaite v. Foreign Hardwood Co. Establishes that a party who repudiates a contract cannot later rely on non-performance of conditions precedent to avoid liability; repudiation waives conditions precedent. The court applied this principle to hold that defendants’ silence and refusal to accept goods amounted to repudiation and waiver of conditions precedent, entitling plaintiffs to damages.
Taylor v. Oakes Roncoroni & Co. Distinguishes express and implied repudiation; discusses the effect of repudiation on contract obligations. The court found the present case analogous to this precedent, affirming that implied repudiation by silence stands on the same footing as express repudiation.
British & Beningtons Ltd. v. North Western Cachar Tea Co. Clarifies the interpretation of readiness and willingness to perform, and the effect of repudiation on conditions precedent. The court relied on this case to support the view that plaintiffs were ready and willing to perform and that defendants’ repudiation waived any conditions precedent.
De Medina v. Norman Defines readiness and willingness to perform contractual obligations as including capacity to perform. Cited to reinforce the principle that plaintiffs’ offer to perform was sufficient to meet contract conditions.
Jones v. Barkley Establishes that a party must show readiness but if the other party prevents performance, further effort is unnecessary. Used to support the proposition that plaintiffs’ readiness was established despite defendants’ refusal to accept goods.
Cort v. Ambergate etc. Ry. Co. Supports the principle of readiness to perform even if actual performance is not immediate or complete. Referenced to uphold the plaintiffs' position regarding readiness to perform their contractual obligations.
Ridgway v. The Hungerfood Market Company Discusses liability in contracts involving specific goods and the effect of tendering goods not conforming to contract. Referred to in the context of interpreting repudiation and tender of goods under contract law.
Boston Deep Sea Fishing and Ice Company v. Ansell Relates to master and servant law principles applied analogously to contracts for sale of goods. Used to discuss the legal principles around tender and acceptance of goods.

Court's Reasoning and Analysis

The court examined the factual matrix, noting the defendants accepted 10 bales but refused to accept the remaining 40 bales without inspection or communication. The defendants alleged defects in the accepted bales and claimed contract cancellation, but the court found no credible evidence of mutual cancellation. Expert evidence showed variation in yarn count, but the court held that testing a small sample was insufficient to establish that the entire 40 bales did not conform to the contract.

The court emphasized that no time was fixed for delivery, so plaintiffs were required to perform within a reasonable time, which they did by notifying defendants of availability and tendering the goods. The defendants’ silence and refusal to accept the goods were treated as an implied repudiation of the contract, effectively waiving conditions precedent.

In analyzing precedent, the court relied heavily on Braithwaite v. Foreign Hardwood Co., interpreting it to mean that a party repudiating a contract cannot later avoid liability by claiming non-conformity of goods. The court rejected the defendants' distinction between express and implied repudiation, holding both to be legally equivalent in effect.

The court also addressed the plaintiffs’ contention regarding commercial equivalence of yarn counts but found the pleadings and evidence insufficient to support this argument. However, since the defendants repudiated the contract by refusing to accept the goods, plaintiffs were entitled to damages regardless of the exact conformity of the 40 bales.

The court calculated damages based on the difference between contract price and market price at the dates of breach, less advances paid, with interest and costs awarded accordingly.

Holding and Implications

The appeal was allowed and the plaintiffs were entitled to a decree for damages in respect of the 40 bales not accepted by the defendants.

The court held that the defendants’ refusal to accept the goods without inspection or communication amounted to a repudiation of the contract, waiving any conditions precedent on the part of the plaintiffs. Consequently, the plaintiffs were entitled to damages calculated as the difference between contract and market prices on the dates of breach, less advances paid, with interest and costs.

No new precedent was set; the decision affirmed the application of established principles regarding repudiation, waiver of conditions precedent, and the effect of non-acceptance of goods in contract law.

    N.M. Rayulu Aiyar, Nagasami Aiyar & Co. v. Thirukonda M. Kuppu Aiyar And Sons

    Ramesam, J. — This appeal arises, out of a suit for damages, for non-acceptance of goods, agreed to be sold to defendants by plaintiffs. The Subordinate Judge dismissed the suit. The plaintiffs appeal.

    The plaintiffs and defendants are merchants of Madura dealing in yarn and cloth. On 20th August, 1918, Ex. A, was executed for the purchase of 50 bales (each of 20 bundles) of “double deer yarn (Palukka)” at Rs. 21-0-0 per bundle, the defendants being represented by Broker K.M Nagasami Aiyar. Ex. I is the corresponding entry in defendants' Chitta, of the same date. Rs. 100 was paid, as earnest money and Rs. 25 was to be paid, as advance for each bale. Ex. B is the letter of plaintiffs, dated 24th August, 1918, acknowledging the receipt of Rs. 1,250, as advances and promising to intimate the arrival of the bales from Bombay, It shows that the bales contracted for, were out of the bales ordered for, by the plaintiffs' Bombay firm, from the dyeing factory at Pedlad.

    The plaintiffs got Pedlad yarn from Bombay in September 1918. On the 23rd September, by Ex. C, plaintiffs gave intimation to defendants, that they had 20 bales ready for delivery, out of those contracted for, in August. Answer 2 to the interrogatories, served on the plaintiffs shows that 50 bales arrived in Bombay, on 14th August and they arrived in Madras in September, 30 bales on 18th and 20 bales on 22nd September. The defendants waited for some time and took delivery of 5 of the bales on the 5th October, and another 5 of the bales on 14th October. The plaintiffs gave notice, by Ex. D, dated 21st October, 1918, that the remaining 30 bales (according to the contract, Ex. A) were ready for delivery. The defendants did nothing. By Ex. E, dated 7th January, 1919, the plaintiffs gave notice, that if the balance of 40 bales were not received, they would be sold at defendants' risk. There was no reply from the defendants. The plaintiffs, alleging that the goods have been sold on 9th March, 1919, and after a further notice dated 27th March, 1919 (Ex. F), filed the present suit, on August 6th.

    Prom the above history of the case, it is clear the defendants' attitude was one of silence. The reason for this was obviously the continuously falling market, which was conceded and assumed by both parties, in the argument before us. The defendants must be regarded, as having broken the contract, without giving any reason for the breach.

    In the written statement, their plea is that, after the goods were accepted on 5th October, 1918 and 14th October, 1918, some of the said bales were opened and it was found that “packets are not those of 10 lbs. weight, which the parties agreed to supply to the defendants. Nor is the yarn of 20 counts. They are of the 8½ lbs. weight”: …………….”that matter was reported by the defendants to the plaintiffs, on 17th October, 1918 and the contract was cancelled,” These sentences, I have quoted, practically constitute the whole defence. It is clear from this, that, so far as the balance of 10 bales offered by Ex. C and not accepted and the 30 bales offered by Ex. D, there is no other defence, except the cancellation of the contract. But, at the time of the first hearing, the defendants raised only the third issue, viz., whether the goods tendered were not of the description in the agreement, dated 4th August, 1918, and no issue was raised about cancellation of the contract by mutual contract.

    To prove their plea on the 3rd issue, the defendants produced one of the bundles, out of the bales supplied to them and this was tested by an expert to whom it was sent by the Court. He examined 12 skeins (1 skein—120 yards; 1 hank=7 skeins=840 yards, A bundle contains 10 packets. A packect weighs 1 lb. The number of hanks in a packet determines the count. If there are 20 hanks in a packet, so that the weight of a hank is 1 ft by 20 and the weight of a skein is 1000 grains by 20, or 50 grains, the count of the yarn is 20. If the skein weighs less, the count is higher). The expert found in the present case that the average of the weight of the skeins examined by him is 40.8 grains and the count is therefore 24.4, When we remember that a bale consists of 20 bundles, or 200 packets or (according to the average of the expert) 4880 hanks, or 34,160 skeins, it is difficult to regard an examination of 12 skeins, as a test of 34,160 skeins. If a bale is of the right kind of yarn of No. 20-count, it ought to contain 4,000 hanks or 28,000 skeins. Even if one may assume that the bale out of which the 12 skeins, examined by the expert, is all of yarn, of an average 24.4 count, it is difficult to assume that the other nine bales, contained yarn of the same average count. Even the 12 skeins, examined by the expert show considerable variety, ranging from 23.2 to 25.5

    We are not dealing with the 10 bales, accepted and paid for by the defendants. We are informed as to those, a separate suit has been filed by the defendants for breach of warranty.

    But, as to the other 40 bales, the Subordinate Judge, having regard to the fact that the 10 bales actually delivered did not contain yarn of No. 20 count and seeing that plaintiffs have not produced samples of packets from the 40 bales, held that the plaintiffs have not proved that the 40 bales answered to the description in the contract and found the issue against plaintiffs. He also held that there is no proof that the goods were from Petlad factory. As to this, it is enough to observe that no such plea was raised in the written statement, even as to the 10 bales delivered and the only complaint made related to the count and weight.

    On these facts, the plaintiffs' vakil first contended that the goods tendered, in pursuance of Ex. C, complied with the terms of the contract. He relied on the evidence of P. W. 2, and D. Ws. 2 and 3 and sought to draw the following inferences:—That the Pedlad factory was only turning out one kind of orange-dyed yarn, marked count 20, a bundle of which is marked as weighing 10 lbs. That, as a matter of fact, its count is not exactly 20, but over it. That, for all practical purposes, counts from 20 to 25 are regarded as the same, by the people who deal in them. That, the subject of the contract before us, is really not yarn of exactly 20 counts, or bundles of 10 lbs,; but, what the Pedlad factory was turning out, with labels of 20 counts and 10 lbs. I have a strong suspicion that this contention of the appellants is probably true; but unfortunately, the pleadings have not been framed on such a basis. As soon as the defendants pleaded that the goods delivered on 5th and 14th October, did not answer to the description in the contract, the plaint must have been suitably amended, or the issues should have been made to cover, what the plaintiffs now suggest. This was not done. Another difficulty is that the evidence is far too meagre, to justify by findings, in favour of the appellants. The point raised by them requires that more persons engaged in the trade should be examined to prove the trade usage. Incidentally, I am also constrained to observe that evidence is not recorded, so as to make the evidence intelligible. For instance, I would refer, to P. W. 2. “His master sells count No. 20. The packet goes by the name of 10 lbs. packet. There is no other goods of that denomination.” Now, seeing that a packet of count 20 must weigh 10 lbs., the words ‘goes by the name of are meaningless. Nor can there be other goods of that denomination. What was meant was: ‘A yarn marked “count 20”, whether it is really that counter not, is the only thing available in the market and there is no other; if we find it actually to be count 24.4, this does not matter. This is all that is known as count 20 and 10 lbs. weight.’ The meaning is not brought out in the deposition. Similar sentences in the evidence of D. W. 1 and D. W. 3 are similarly recorded. But, as I said, on the pleadings and the meagre evidence, it is not possible to record the finding, the appellants require. One can only hope that he will gain by this experience in the other case.

    The next question is whether the defendants, by their breach, in not taking delivery of the other 10 bales (relating to Ex. C) after accepting the first ten bales and not caring to respond to the offer in Ex. D, have committed such a breach of the contract, as to amount a waiver of all conditions precedent, binding on the plaintiffs, The appellants rely on Braithwaite v. Foreign Hardwood Co.. In that case, there was a repudiation by the defendants, on October, 5, long before the goods arrived. The Bill of Lading arrived on October, 30, and the plaintiffs not accepting the repudiation by the defendants (dated 5th October,) tendered two Bills of Lading to the defendants, who refused to accept it, or pay for the rosewood comprised in it. The goods arrived on November, 9, and were sold by the plaintiffs, as against the defendants. Collins M. R. said, with reference to the second repudiation at p. 551;

    “In my opinion, that act of the defendants amounted, in fact, to a waiver by them of the performance by the plaintiffs of the conditions precedent, which would otherwise have been necessary, to the enforcement by him of the contract, which I am assuming he had elected to keep alive against the defendants, not-withstanding their prior repudiation, and it is not competent for the defendants now to hark back and say that the plaintiff was not ready and willing to perform the conditions precedent, devolving upon him, and that if they had known the facts, they might have rejected the instalment, when tendered to them. The defendants are not in a position, by reason of their after acquired knowledge, to set up a defence, which they previously elected not to make. We must, in such a case, look to see, whether at the time of each alleged breach, each side was ready and willing to perform the conditions of the contract, which it lay upon them to perform, and there was clearly a breach by the defendants, for they had by their own act absolved the plaintiff from the performance of the conditions of the contract.”

    Mathew L. J., said at p. 554:

    “But they repudiated the whole contract and by so doing clearly absolved the plaintiffs from the performance of conditions precedent, which in the ordinary course he would have been obliged to perform.”

    Cozenz Hardy L, J. agreed. Mr. Ananthakrishna Iyer, who appeared for the defendants, contended that Braithwaite v. Foreign Hardwood Co. cannot apply for two reasons: (1) in that case, there was an express repudiation on 5th October, and at or about October. 30th; the anticipating breach of 5th October, is the crux of that case; (2) the case was also disapproved by the House of Lords. As to the first point, the distinction sought somewhat resembles the distinction sought to be made out in Taylor v. Oakes, Roncoroni & Co.. Bankes L. J. says at p. 271:

    “But Mr. Merriman seeks to distinguish this case, by endeavouring to convince us that a distinction must be drawn, where the repudiation consists of a curt and impolite disclaimer of the existence of a contract and a very polite statement that, under circumstances, over which the buyer has no control, he is not liable to take the goods.”

    Mr. Anantakrishna Aiyar's distinction is not between ‘Impolite’ and ‘polite’ repudiation, but between “express” and “implied” repudiation. The implied repudiation by silence resembles a ‘polite’ repudiation. But it stands on the same footing, as an express repudiation. The second point raised by him requires more careful consideration. It is clear that, according to Collins, M. R., the contract was kept alive up to October 30th, by the plaintiff's non-acceptance of the earlier repudiation and the waiver of the conditions precedent is the result of the later act. Mathews, L.J seems to be of the same opinion, though his view is not very explicit. In Taylor v. Oakes, Roncoroni & Co., Greer, J., seems to have felt some difficulty, as to the application of Braithwaite v. Foreign Hardwood Co.(2). His view seems to be that, if specific goods were actually tendered, on the second occasion, and were not substantially of the kind contracted for, the defendants in Braithwaite v. Foreign Hardwood Co., would not have been liable. For this view, he relies on Ridgway v. The Hungerfood Market Company(3), and Boston Deep Sea Fishing and Ice Company v. Ansell(4), which are oases of master and servant and thinks that the principle applies equally to a contract, for the sale of goods. He gets over the difficulty, by explaining that, in Braithwaite v. Foreign Hardwood Co., the second offer by plaintiff was not an actual tender of the goods, but a mere offer to tender them and therefore the offer is not an actual breach of contract. One may observe here that the second offer is of the actual Bills of Lading, relating to certain specific goods on the ‘Spheroid’ and the goods were not only ascertained, but were afterwards identified and their nature known. I confess that the difficulties in understanding Braithwaite v. Foreign Hardwood Co., are not solved by Greer, J's explanation of it. On appeal, Scrutton. L. J., and Atkin, L. J., refused to be drawn by Greer, J., into a discussion of Braithwaite v. Foreign Hardwood Co.. They were of opinion that, on the facts of the case before them, the point did not arise, in that case, by letters which passed between the parties in December, the defendants stopped delivery of the balance of the goods and refused to accept, them. There was neither tender of specific goods, nor tender of a Bill of Lading, relating to actual specific goods, the nature of which was afterwards known. Such a repudiation was held to be ‘anticipatory’. Bankes L.J said:

    “it seems to me, after the decision in Braithwaite v. Foreign Hardwood, Co. which binds this Court, that where there has been a repudiation by way of anticipatory breach &c.”

    His view seems to be that the second repudiation in Braithwaite v. Foreign Hardwood Co. is also an anticipatory breach and he agreed with Greer, J's view—a point into which, the other Lord Justices refused to be drawn. According to them, on the facts, it was a clearer case than Braithwaite v. Foreign Hardwood Co. and that was enough. In my opinion, the present case is a afortiori case and the difficulties in understanding Braithwaite v. Foreign Hardwood Co. need not affect it. It is, in my opinion, on all fours with the facts of Taylor v. Oakes Roncoroni & Co.

    The next case I need discuss is British and Beningtons Ltd., v. North Western Cachar Tea & Co.. Only Lord Atkinson and Lord Sumner delivered judgments. Lords Buckmaster and Carson agreed with Lord Sumner. Lord Wrenbury merely concurred. On the disposal of the case before them, there was no difference of opinion. It was only about the proper interpretation of Braithwaite v. Foreign Hardwood Co., that Lord Sumner thought some criticism had to be made. Lord Atkinson, after pointing out that ‘readiness and willingness includes the capacity to perform (citing Lord Abinger in De Medina v. Norman, proceeds to cite Lord Mansfield in Jones v. Barkley(5) and Lord Campbell in Cort v. Ambergate etc., Ry. Co.(6), for the position that the condition of “readiness and willingness” is satisfied by the offer of the plaintiffs to perform. The latter case is of a case of ‘railway chairs’, which were not actually made, but which presumably could be made at short notice. He then refers to Braithwaite v. Foreign Hardwood Co. and quotes Collins, M.R's., opinion with approval. Lord Mansfield's sentence in the case of Jones v. Barkley, was then quoted: “The party must show he was ready; but, if the other stops him on the ground of an intention not to perform his part, it is not necessary for the first to go further.” Lord Sumner, after remarking at p. 70 that the decision in Braithwaite v. Foreign Hardwood Co., is not quite easy to understand and that his recollection of it is not as clear as Scrutton L.J's (both appeared in the case), says at p. 71:

    “Furthermore, it does not anywhere appear, that, even if the first cargo might rightly have been rejected, the seller could not have found another exactly conforming with the contract, which he might have duly tendered and so have put himself right”.

    This sentence shows that, far from disagreeing with Braithwaite v. Foreign Hardwood Co., Lord Sumner applies its principle and does not go in favour of the defendants, even as far as Greer J. in the Law Times case, The only reservation he makes is:

    “If the sellers had become wholly and finally disabled from performing essential terms of the contract altogether”

    at the time of breach, such a fact is open to the defendant in defending a suit for damages, though he did not state it, at the time of the repudiation and this is all that he could have meant, when earlier he said:

    “if he had repudiated, giving no reason at all, I suppose all reasons and defences in the action, partial or complete, would be open to him.”

    He then adds:

    “What he says is, of course, very material upon the question, whether he means to repudiate at all, and, if so, how far, and how much, and on the question in what respects he waives the performance of conditions still performable in future or dispenses the opposite party from performing his own obligations any further.” (page 72).

    In my opinion. Lord Sumnor has not dissented from Braithwaite v. Foreign Hardwood Co. and the last case is good law. The present case is a clearer case. There is no evidence to show the nature of the goods in the 10 bales (offered by Ex. C, but not received by the defendants) and in the 30 bales (offered by Ex. D). I cannot assume, in favour of the defendants, that the yarn in these bales is of 24 count only. The only reason for such an assumption is that no other yarn (orange dyed at Pedlad) exists—an assumption, I refused to make at an earlier stage of the case, in favour of the appellant. I must assume that pedlad factory can supply all counts of yarn (orange dyed) and it does not follow from the fact that the 10 bales accepted on 5th and 14th October, are of 24 count that the other bales which have never been identified since, could be only of 24 count and 30 bales offered by Ex. D would also turn out to be of 24 count. It follows that plaintiffs were always not only willing to perform the contract, but, if at anytime, the goods they delivered turned out, not to be of the correct kind, could have set it right. All conditions were waived by the defendants, by their repudiation. In this case, there is no evidence to support any suggestion that the plaintiff was totally unable and disabled to perform the contract altogether.

    It follows that plaintiffs are entitled to a decree for damages, in respect of the 40 bales.

    On the terms of Ex. B, the dates of breach were 23rd September, 1918 (for the 10 bales) and 21st October, 1918, (for the 30 bales) and it is not open to the plaintiffs to argue that the breach was at a later date. On the 23rd, the price was Rs. 19, per bundle. We have nothing to do with the results of the re-sale in March. It follows that plaintiffs are entitled to a decree for 200×2, plus 600×5-14-0, i.e, 3,925 minus Rs. 1,000 (given as advance) i.e, 2935—with subsequent interest at 6 per cent up to this date and 6 per cent on the aggregate amount, from this date to the date of payment, getting and paying proportionate costs throughout.

    Reilly, J.—It is admitted that the contract with which we are concerned in this case was made on 20th August, 1918 and was to the effect that plaintiffs should supply to defendants at Madura 50 bales of 20 count yarn from the Pedlad factory, each bale to contain 20 bundles and each bundle to weigh 10 lbs, and that defendants should take delivery of the bales on payment, at the rate of Rs. 21 a bundle, that is, Rs. 420 a bundle. Defendants pleaded that one of the terms of the contract was that the 50 bales should be delivered, within a month from the date of the contract. An issue was framed on that plea but was not pressed by defendants at the trial. The Subordinate Judge's finding in effect was that no time was fixed, for the performance of the contract by plaintiffs. It was, therefore, plaintiffs' duty to supply the 50 bales, within a reasonable time. There is undisputed evidence that by their notice, Ex. C, plaintiffs informed defendants on 23rd September, 1918, that 20 bales were ready for delivery at Madura and by Ex. D, on 21st October, 1918, that the remaining 30 bales were ready for delivery there. Defendants took delivery of 5 bales, out of the first lot of 20 bales, on 5th October, 1918, and of 5 other bales, out of the same lot of 20, on 14th October, 1918. Defendants did not take delivery of the remaining 10 bales of the first lot of 20 bales, or of the second lot of 30 bales: they did not even inspect these 40 unaccepted bales, nor did they send to plaintiffs, any written communication about them.

    2. There is evidence that out of the 10 bales of which defendants took delivery, some of the yarn was not of the contract description. D. W. 2, a weaver, has given evidence that he bought 10 bundles of this yarn from defendants and found it to be 24 count yarn, not 20 count. D. W. 3, another weaver, says that he bought 10 or 20 bundles of the yarn and found it to be 24 count yarn. There is also expert evidence that a bundle from one of the 10 bales, accepted by defendants, was found to contain yarn of 24 counts or 26 counts, according as the dye was taken into consideration or not, and that the bundle weighed only 8½ lbs, instead of 10 lbs. D. W. 1, the manager of defendants' firm, says that he complained on 17th October, 1918, to Rayulu, the senior partner of plaintiffs' firm (who died before the trial), that the yarn in the 10 bales accepted, was not of the contract description and cancelled the order for the remaining 40 bales, to which cancellation Rayulu agreed. The Subordinate Judge says in his judgment that there is good ground for believing that D. W. 1 complained to Rayulu about the yarn, but that he does not believe that the contract was cancelled by consent, as alleged by D. W. 1. It has been argued here for plaintiffs, that D. W. 1's evidence that be complained to Rayulu about the yarn should not be believed at all, as no question about this was put, at the trial, to plaintiff's two gumastahs, P. Ws. 1 and 2, who are said by D. W. 1, to have been present at his conversation with Rayulu. Mr. Ananthakrishna Aiyar for defendants has said nothing about this part of the case, and I think that D. W. 1's evidence that he complained about the yarn to Rayulu may be disregarded.

    3. It appears that there was another suit between the parties, in respect of the 10 bales accepted by defendants. In this suit, plaintiffs claim damages for breach of contract, in respect of the remaining 40 bales. It is contended for defendants that no damages are due from them, as the 40 bales were not of the contract description and in effect, therefore, it was plaintiffs, who were guilty to breach of contract, in respect of these bales. It is admitted that defendants never even inspected the 40 bales, and the evidence, offered in support of this contention, is that which I have mentioned to the effect that some of the yarn and one of the bundles in the 10 bales, which they accepted, were not of the contract description. I agree with my learned brother that from the evidence that a comparatively small part of the 10 bales, accepted by defendants, was not of the contract description, we cannot infer anything regarding the other 10 bales of the first lot of 20, or regarding the 30 bales of the second lot. It is true that in the course of arguments here and also before the Subordinate Judge, a contention has been put forward for plaintiffs that the subject of the contract was, not bales of yarn, literally of the contract description, but bales of yarn commercially known under that description, but actually varying from it. The evidence to which plaintiff's vakil points to support this contention is clearly insufficient, and there is no mention of such a contention in the pleadings. I think this contention must be regarded, as a false motive in argument, for which plaintiffs cannot be penalised. On the evidence, we do not know whether the 40 bales in question were of the contract description or not. All we know is that plaintiffs tendered them, in performance of their part of the contract and that defendants failed to accept them and even to inspect them and merely ignored the tenders.

    4. But, even if we assume for the sake of argument, that the 40 bales in question were not of the contract description, the defendants' position is not really improved. As no time had been fixed, for the delivery of the bales by plaintiffs, if defendants had inspected these 40 bales, and had them found that they were not of the contract description, plaintiffs would have had time to supply other bales, in place of those rejected and on the evidence, there is no reason to suppose that they would have found it impossible, or even difficult to do so.

    5. It is clear that defendants, by their conduct, refused to accept the 40 bales, tendered by plaintiffs, without even troubling to inspect them, or to ascertain whether they were or were not of the contract description. Defendants were, therefore, guilty of breach of contract, for which plaintiffs are entitled to damages. In the circumstances, I do not think it is necessary for plaintiffs to call in aid the decision in Braithwaite v. Foreign Hardwood Co., But I may add that in my opinion the weight of the decision in Braithwaite v. Foreign Hardwood Co., as an exposition of law, has not been affected, by either of the later cases mentioned before us. As I understand it, the principle of Braithwaite v. Foreign Hardwood Co. is that, if A contracts to buy goods of a certain description from B and refuses for other reasons to accept goods tendered by B, as in performance of the contract, he cannot escape liability to pay damages, by proving afterwards that the goods tendered were not of the contract description. It is true that Lord Sumner in British & Beningtons Ltd., v. North Western Cachar Tea Co., and others, and Greer, J., in Taylor v. Oakes Roncoroni & Co.,, interpreted the decision in Braithwaite v. Foreign Hardwood Co. more, narrowly; but their remarks, though to be treated, of course, with the greatest respect, were obiter dicat. On the other hand. Lord Atkinson in British & Beningtons Ltd., v. North Western Cachar Tea Co., and others interpreted Braithwaite v. Foreign Hardwood Co. in effect as I have stated it. But in the present case, as it has not been proved that the 40 bales in question were not of the contract description, and as, even if they were not of that description, plaintiffs had still time to supply others in their stead, the exact interpretation of Braithwaite v. Foreign Hardwood Co. does not appear to me of immediate importance to us.

    6. The damages to which plaintiffs are entitled are the difference between the contract price of the 40 bales and the market price on the dates of the breach, less Rs. 1,000, paid by defendants in advance, for those bales. According to Ex. B, defendants were to take delivery, on the day on which they received intimation of the arrival of the bales and in the plaint the dates of breach, in respect of the two lots of bales have been given as 23rd September, 1918 and 21st October, 1918. Although plaintiffs allowed defendants some time for the removal of the bales and might reasonably do so and although defendants were very dilatory in taking delivery of those bales, which they accepted, I do not think plaintiffs, can now contend that the breach in each case should be assumed to have occurred, at some later date and so increase the amount of damages due to them. I agree that the damages to which they are entitled are the difference between the contract price for 10 bales and the market price for 10 bales, on 23rd September, 1918, plus the difference between the contract price for 30 bales and the market price for 30 bales, on 23rd October, 1918, minus the Rs. 1,000, paid in advance. On principle, I should prefer not to allow interest on the amount so calculated, before the date of the suit; but I do not wish to differ from my learned brother, on that comparatively minor point. I agree that the parties should pay and receive proportionate costs, in both Courts.

    C. K.Decree varied..