It is necessary to refer only to Exs. I-a, KK and II. Ex. I-a is a circular letter addressed by the acting Chief Engineer to all the Executive Engineers and Assistant Engineers working on the Mayavaram-Tranquebar Railway, on the 29th October 1926. The material portions of Ex. I-a are the following: “Apparently there is some doubt existing about the interpretation of this item which reads: ‘Increment for additional height or depth over 6 feet with the sub items (a), (b) etc………….The whole section should not be paid at the initial rate plus the increment for a bank 18 feet high. The printed specification of works, III Earthwork, para 19 is quite explicit on how payments should be made.” Pausing here for a moment, we must point out that this apparently had no reference to any particular contract but was a kind of instruction which the Chief Engineer thought fit to issue under paragraph 19 of S. 3 of Ex. IV before him. On the terms of that provision there is hardly any room for doubt. But it will be impossible to connect Ex. I-a with the suit contract, not only because no claim had been made under the suit contract at the date of Ex. I-a but also because the suit contract has not followed the language of Ex. IV in this respect. The next document Ex. KK is a letter, dated 22nd December 1926, sent by the Chief Engineer to the Executive Engineer of the Shoranur-Nilambur Railway. Referring to the question of payment for earth-work the Chief Engineer there says: “This was discussed with you on the 16th instant at Angadipuram. The interpretation to be given to the clause ‘These are through rates from ground to formation level’ is, the rates are through from ground to formation, i.e, on the various steps, 0 to 6, 6 to 9, 9 to 12 and so on. It would be absurd to claim that the first 6 feet in a bank 9 feet high cost any more to throw up than the 6 feet in a bank 6 feet high. In fact it would be the other way round, as there would be less dressing to do in proportion to the contents.” Here, we must repeat what we have said before, in dealing with Ex. I-a, that this is a kind of executive instruction issued to his own subordinates before any particular claim had been made so far as the plaint contract was concerned; and even before us, it was not insisted on as amounting to any decision within the meaning of Cl. 41.
On behalf of the appellant, reliance was chiefly placed upon Ex. II. There can be no doubt that Ex. II, was sent after the claim for payment under the suit contract had been put forward by the contractor. But it is important to examine its terms to see whether it can be regarded as a decision within the meaning of Cl. 41. It is admitted that neither Ex. I-a nor Ex. KK, had been communicated to the Contractor, though D. W. 1 says that, sometime or other, in the course of a conversation between them he might have informed the contractor about the views stated in this document. In the bill which the contractor submitted, the Executive Engineer seems to have allowed only a much smaller rate as now insisted on by the Company, and the Contractor therefore wrote to the Engineer to say that he is unable to see why his claim at the higher rate had not been admitted by the Company. (See paragraph 1 of Ex. D-1). We may, however, mention that in a letter dated 23rd November 1927 sent by the Assistant Engineer in charge of the Shoranur-Nilambur Railway to various Contractors including the Plaintiff, there is a statement that the calculations for payment for “lift” have been made in-accordance with the Engineer-in-Chief's instruction and his decision. The letter then goes on to say
“I have therefore to refer you to Cl. 41, of your agreement and to ask you to call at the office to sign the final measurements and bills in full acceptance to enable their being passed for payment.”
It does not however appear that any further light was thrown on this reference to Cl. 41, or to the Engineer's decision, so far as the information available to the Contractors went. Soon after the claim under Ex. D-1 was made, it would appear from the evidence of D. W. 1 that the Sub-office dealing with matters relating to the Shoranur-Nilambur Railway was closed and all matters relating thereto were dealt with by the Chief Engineer himself. So far as the record discloses, that appears to be the reason why Ex. D-1 was sent up to the Chief Engineer for disposal. There is nothing either in the documentary evidence or in the evidence of D. W. 1 to suggest that it was by reason of any request to him to decide a dispute between the parties in terms of Cl. 41, that the matter was sent up to the Engineer-in-Chief. All that we find from a note (Ex. D-2) on Ex. D-1, is that it was forwarded to the Engineer-in-Chief with the statement of remarks by the Assistant Engineer and by D. W. 1. What those remarks are we do not know as they have not been placed before the Court. It is admitted by D. W. 1 that when Ex. D-1, was received by the Chief Engineer, he discussed the contractor's claim with D. W. 1, that the contractor was not present at the discussion, that there was no other evidence before the Engineer-in-Chief except what was contained in Ex. D-1 itself and that the Engineer-in-Chief relied upon his knowledge of the works and the witness's knowledge. Under these circumstances, a communication was sent to the Contractor giving the answer of the Engineer in-Chief to the claim made in Ex. D-1. That is Ex. II. In respect of the claim now in question, it states, in paragraph 1, that “the measurements for lift recorded in the final measurements are in accordance with the agreement and specifications and as per my instructions on the subject and payment in the manner claimed by you is inadmissibile.” There is a note, marked Ex. II-a in the case, dated 14th February 1928, which purports to be a note by D. W. 1 sending up the draft of Ex. II, to the Chief Engineer for approval and signature. It is suggested on the plaintiff's side, that Ex. II, has really been prepared by D. W. 1 himself and sent on in the ordinary course with the signature of the Engineer-in-Chief like any other office communication. D. W. 1 would, however, state that he drafted Ex. II under instructions given to him orally by the Chief Engineer. It does not seem to us very material whether the draft was made in one way or the other. The real question for decision is whether in sending Ex. II, the Chief Engineer could be held to have acted with the consciousness that he was disposing of the matter under Cl. 41 of the agreement.
Our attention has been drawn to several cases dealing with the position of architects or Engineers whose decision is made final, in respect of contracts whose execution is put under their supervision. It is not necessary to refer to them in detail. There has no doubt been a consensus of opinion that they are, not “arbitrators” in the sense in which that term is used in the Arbitration Act, but all the cases recognise that, whether called arbitrators or quasi-arbitrators or by any other label, they are, when exercising that kind of power, discharging “judicial” functions, Decisions of the Privy Council and of the House of Lords particularly emphasise that Engineers placed in that situation especially when they happen to be the employees of one of the contracting parties, are in a very delicate and embarrassing situation, and while on the one hand it is true that the other party is bound by a contract into which he has entered with his eyes open knowing that finality is attached to the decision of an employee of the other side, that party is entitled to insist that that person should have acted judicially with a full realisation of the responsibilities of his position in dealing with a matter of that kind.
We are not now called upon to define the extent of formal procedure which should be adopted by a person exercising Such a power; but the procedure followed by him is at least important as indicating whether in the particular instance he intended to act only as a servant of one of the contracting parties or in the conscious exercise of the powers conferred on him by the special terms of the agreement. This aspect of the question is adverted to by their Lordships of the Privy Council in Bombay, Burmah Trading Corporation Limited v. Aga Mahomed Khaleel Shirazi (1) and by the House of Lords in Hickman & Co. v. Roberts (2) and Bristol Corporation v. John Aird and Co. (3). Two other cases referred to by the learned counsel for the appellant, namely, Stevenson v. Watson (4) and Chambers v. Goldthorpe, Restell v. Nye (5) are not much in point. They deal with the question how far an Engineer or architect acting under such circumstances can be held liable for negligence. It is one thing to say that he will not be liable for negligence but quite another thing to say whether he could be held to have acted judicially or not, in a particular matter. For instance, an award may be void owing to the fact that certain well-understood rules have not been complied with but, all the same, the arbitrator may not be liable in damages. We therefore think that these two cases really do not throw any light on the question for decision.
Taking it, then, that a Court, called upon to hold any expression of opinion by such an Engineer in such circumstances final and conclusive between the parties, must at least be satisfied that the person was conscious of the fact that he was called upon to exercise that power and was exercising that power with the sense of responsibility and judicial independence required for the purpose, we have given our best consideration to the circumstances here and we see no reason to differ from the lower Court in the view that it took as to Ex. II. The evidence does not show that the Chief Engineer was at all conscious of the fact that the contract in this case differed in very important particulars from the printed specification in the company's Standard Book (Ex. IV). Paragraph I of Ex. II, already quoted, only states that the measurements have been prepared in accordance with the Engineer's instructions on the subject and it is difficult to read it as importing a further decision that these instructions are right, in view of the terms of the particular contract. It is from this point of view that we attach particular significance to the fact that the contractor had not been heard at all before Ex. H was sent. It is one thing to say that he agreed to abide by the decision of a person who might have pre-formed views in the matter; but it is a different thing to say that these pre-formed views must bind him merely because they are reiterated in a subsequent letter before he has had any opportunity to persuade the Engineer in favour of his own contention. For these reasons we are unable to hold that Ex. II falls within the terms of Cl. 41 so as to preclude the Court from putting its own construction on the suit contract and giving to the contractor what he is undoubtedly entitled to under this head under the terms of his contract.
******
N. R. R.