Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • sec. 74 of the Contract Act in this connection. Sec. 7 of the Contract Act
  • sec. 74 of the Contract Act.10.
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • sec. 74 of the Contract Act in this connection. Sec. 7 of the Contract Act
  • sec. 74 of the Contract Act.10.
Smart Summary

Structured Summary of the Opinion — Modi, J.

Factual and Procedural Background

On 25 July 1949 the defendants, Badhava Singh and Suhava Singh, entered into a written agreement (Ex. P-1) to sell to the plaintiffs, Charan Singh and Chanan Singh, two squares of land (Nos. 1 and 7) measuring 50 bighas in Chak 53 G.V., Tehsil Anoopgarh, for Rs. 16,000. The vendees paid Rs. 200 as earnest money. Completion was to occur on or before 15 December 1949, the balance being payable by the vendees. The parties agreed to share registration, stamp and other necessary charges equally. The agreement stipulated mutual default consequences: if the vendors failed to complete, they would refund the earnest money and pay Rs. 4,000 as damages; if the vendees failed to complete, they would forfeit the earnest money and pay Rs. 2,000 as damages.

About ten days before the agreed completion date, on 5 December 1949, the defendants executed a sale-deed of the same land in favour of Sohan Singh and others. Upon learning of that sale, the plaintiffs sent a telegraphic protest and applied to the Registrar on 5 December 1949 to postpone registration; the Registrar refused and the document was registered. The plaintiffs instituted suit on 6 December 1949 claiming (a) return of the Rs. 2,000 earnest money and (b) Rs. 4,000 as contractual damages for breach. The trial court decreed Rs. 6,000 in favour of the plaintiffs.

The defendants admitted executing Ex. P-1 but resisted the suit on two principal grounds: (1) that the plaintiffs had breached by refusing to pay their half of the expenses and therefore the defendants were entitled to re-sell; and (2) that the Rs. 4,000 claimed as damages was in the nature of a penalty and therefore not recoverable. The trial court found that (i) the defendants breached, (ii) no permission was necessary to complete the sale, and (iii) the Rs. 4,000 was not excessive. The defendants appealed against that decree.

Legal Issues Presented

  1. Who was responsible for the breach of the contract for sale — the defendants (vendors) or the plaintiffs (vendees)?
  2. Whether the sum of Rs. 4,000 named in the agreement as damages for breach was a lawful, reasonable compensation under section 74 of the Indian Contract Act or an unlawful penalty (i.e., whether the plaintiffs could recover that amount).
  3. Whether the trial court erred procedurally in framing the issue on the question of damages and in placing the burden of proof on the defendants rather than on the plaintiffs.
  4. Whether the trial court's factual conclusion that the defendants re-sold the land for Rs. 22,000 (and therefore obtained an excess of Rs. 6,000 over the original price) was properly supported and should stand on appeal.

Arguments of the Parties

Defendants' (Appellants') Arguments

  • The plaintiffs breached the contract by refusing to pay their half of registration, stamp and incidental charges (despite repeated demands) and by declining to pay on 4 December 1949, rendering completion impossible.
  • Because the plaintiffs would not pay, and the defendants were in urgent need of money, the defendants were compelled to sell the land to Sohan Singh and others; therefore the defendants were not at fault.
  • The defendants sought to show that the plaintiffs expressly told the vendor they were unable and unwilling to buy, and that they had agreed to forego the claim for damages and accept forfeiture of earnest money only; that the plaintiffs agreed to attend on 5 December to execute documents but then refused; and that the resale was with the plaintiffs' knowledge or at their instance.
  • The Rs. 4,000 stipulated as damages was in the nature of a penalty and therefore the trial court erred in awarding it; the burden to prove actual damage rested on the plaintiffs (relying on Bhai Panna Singh v. Bhai Arjun Singh).
  • Procedurally, the trial court framed the issue imperfectly and placed the burden of proof on the defendants rather than on the plaintiffs, thereby prejudicing the defendants' opportunity to rebut the plaintiffs' evidence (specifically on the true consideration for the resale and the actual resale deed).

Plaintiffs' (Respondents') Arguments

  • The plaintiffs contended that the defendants re-sold the land before the agreed completion date and that the re-sale evidenced the defendants' breach of their contractual obligation to sell to the plaintiffs.
  • The plaintiffs relied on the telegram of protest and on their application to the Registrar (supported by the Registrar's evidence) to show they did not intend to abandon the contract and that they actively tried to prevent registration in favour of the third party.
  • The plaintiffs asserted entitlement to refund of the earnest money and to Rs. 4,000 damages as stipulated in the agreement for breach by the vendors, and led evidence to show the defendants obtained a larger price at re-sale (the trial court found Rs. 22,000) which justified the contractual damages awarded.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Bhai Panna Singh v. Bhai Arjun Singh (Privy Council) Interpreting sec. 74: plaintiff is not automatically entitled to the sum named; plaintiffs must prove the damages they have suffered; effect of sec. 74 disentitles recovery "simpliciter" of the fixed sum. The court relied on the Privy Council’s statement that the plaintiff must prove damages and treated that proposition as part of the analytical framework in interpreting sec. 74 for the present case, while applying it in light of other authorities.
Lachhman Das v. Bhoja Ram Where an identical sum is named payable by either party on breach, in absence of equitable grounds the stipulated sum should be decreed as damages. Used as an example where courts have enforced stipulated sums, forming part of the review of authorities on how sec. 74 has been applied.
Lekh Singh v. Dwarka Nath Where a fixed sum is mentioned as payable on breach, the court should award the stipulated sum unless there is evidence the amount is exorbitant or unconscionable. Adopted as authority that a contractual stipulation for damages may be enforceable, subject to a court’s inquiry into excessiveness or unconscionability.
Mahadeoprasad v. Siemens (Ameer Ali, J.) Held that the sum named in an agreement is some proof of damages and, absent other proof, might be sufficient; but the present court considered this view to go further than warranted. The court considered and criticized this approach as too expansive; it held that the plaintiff must show by tangible evidence (direct or circumstantial) that the sum was a genuine pre‑estimate and reasonable under sec. 74.
Michel Habib v. Sheikh Suleiman (Palestine) Agreed liquidated damages, to be enforceable, must be the result of a "genuine pre-estimate of damages"; sums fixed "in terrorem" or disproportionate to possible breaches are excluded. The court adopted the observation as a useful standard when assessing whether a stipulated sum under sec. 74 is a genuine pre‑estimate or merely penal/extravagant, and applied this standard in the case at hand.
Mool Chand Behari Lal v. S.D. Chand & Co. Where earnest money or deposit is to secure performance, the court must determine under sec. 74 what is "reasonable compensation"; the court may allow the named sum if not excessive, or reduce it to a reasonable figure but never exceed the named sum. Adopted for the proposition that the court has a duty under sec. 74 to determine reasonableness and may reduce an excessive stipulated sum; this principle guided the court's assessment of Rs. 4,000.

Court's Reasoning and Analysis

The court proceeded in two main stages: first the factual question of who breached; second the legal question whether the contractual Rs. 4,000 was recoverable under section 74 of the Contract Act and whether trial procedure was prejudicial to the defendants.

Factual determination of breach

  • The court reviewed the evidence and accepted the trial court's factual findings that the defendants re-sold the land about ten days before the completion date and that the plaintiffs did not abandon the contract.
  • The defendants' case (that plaintiffs refused to pay their share of expenses and had abandoned the contract) was rejected as inherently improbable and contradicted by the plaintiffs' telegram of protest and the plaintiffs' application to the Registrar made before registration.
  • Registrar Shri Baney Singh's evidence supported that the plaintiffs had actively sought postponement of registration. The sale to the third party occurred on 5 December, prior to the 15 December completion date, strengthening the conclusion that defendants breached.
  • Accordingly, the court concluded the defendants were responsible for the breach, not the plaintiffs.

Interpretation and application of section 74

  • The court surveyed prior authorities and distilled the legal effect of sec. 74 into a multi-point summary: (a) a plaintiff is not automatically entitled to the full sum named in the contract merely because it is mentioned; (b) the plaintiff is entitled to "reasonable compensation" not exceeding the contractual sum; (c) what is reasonable depends on circumstances; (d) Indian law removes the English distinction between "penalty" and "liquidated damages" but requires the court to ensure compensation is reasonable; (e) the plaintiff must prove damage but proof may be direct or circumstantial; (f) if the sum is a genuine pre-estimate, the court may award it in full, otherwise it may reduce it; (g) disproportionality and unfair allocation of burden are factors to consider.
  • The court rejected an overly permissive reading (attributed to Ameer Ali, J. in Mahadeoprasad) that would treat the contractual sum as sufficient proof of damage in the absence of other evidence without inquiry; instead the court insisted on tangible evidence (direct or circumstantial) that the sum is a genuine pre‑estimate.
  • The court accepted the Palestine decision (Michel Habib) as an illuminating standard: agreed damages must reflect a genuine pre-estimate and not be a sum fixed "in terrorem."

Application of law to the facts

  • Under Ex. P-1 the vendors (defendants) were to refund earnest and pay Rs. 4,000 if they broke the contract. The trial court found on the evidence that the defendants re-sold the land for Rs. 22,000, i.e., Rs. 6,000 more than the original Rs. 16,000 contract price.
  • The appellate court saw no reason to disturb the trial court’s finding on resale price because the defendants had not specifically challenged that finding in their grounds of appeal; they therefore were not in a position to dispute that conclusion on appeal.
  • Given the trial court's finding of Rs. 22,000 re-sale consideration, the court concluded the Rs. 4,000 stipulated damages were well covered by the Rs. 6,000 excess the defendants realized; the stipulated sum was not disproportionate or unconscionable in the local context (Ganganagar, where land values were high).
  • On procedural complaint that the burden was misallocated: the court acknowledged the trial court could have framed the issue more precisely and that, in principle, the burden should have been on the plaintiffs to prove damages. However, the defendants never objected to the issue and led the evidence they wished; they did not produce the further evidence they now claimed (e.g., second sale-deed or proof the re-sale was only for Rs. 16,000). The defendants had opportunity yet failed to lead such evidence; accordingly, the court found no miscarriage of justice requiring retrial.
  • The Registrar’s evidence that the second deed recorded an ostensible consideration of Rs. 16,000 did not end the inquiry because circumstantial evidence (including the defendants’ motive) could show the inducement was a larger price; the defendants' silence on appeal as to that factual finding was dispositive.

Holding and Implications

Final Ruling: The appeal is dismissed with costs. The decree of the trial court in favour of the plaintiffs for Rs. 6,000 (refund of earnest money Rs. 2,000 plus Rs. 4,000 damages) stands.

Implications:

  • The trial court's factual finding that the defendants breached the contract by re-selling prior to completion was affirmed.
  • The court applied section 74 of the Contract Act to hold that a contractual stipulation for damages does not confer an automatic entitlement to the full named sum; the plaintiff must prove reasonable compensation (by direct or circumstantial evidence), and the court will reduce any sum it finds to be in terrorem or unconscionable. In this case the stipulated Rs. 4,000 was held to be reasonable and properly recoverable.
  • Procedurally, a party who does not object to an issue as framed at trial and who fails to adduce available evidence cannot, on appeal, complain that the burden was misplaced so as to require a retrial of that issue.
  • No novel legal principle was announced beyond the court's synthesis and application of existing authorities on sec. 74: the decision affirms that stipulated damages will be enforceable only as reasonable compensation and that courts must inquire into genuineness and proportionality under the circumstances of each case.

This summary is prepared strictly from the content of the provided opinion and does not add facts or inferences not present in that text.

    Badhava Singh v. Charan Singh

    Modi, J.:— This is a first appeal by the defendants Badhava Singh and Suhava Singh in a suit for damages for breach of contract for sale of land.

    2. On 25th July, 1949, the defendants had entered into an agreement with the plaintiffs Charan Singh and Chanan Singh by which the former agreed to sell to the latter 2 squares of land Nos. 1 and 7, measuring 50 bighas in chak 53 G.V, Tehsil Anoopgarh for a sum of Rs. 16,000/- and the veendes Page: 175paid a sum of Rs. 200/- by way of earnest money on the same date. The sale was to be completed on or before the 15th of December, 1949, when the balance of the purchase money was to be paid by the vendees. It was also agreed between the part is that they would share the cost of registration, stamp paper and certain other necessary charges half and half A further stipulation was that if the defendant-vendors failed to complete the sale, they would be liable to refund the earnest money and in addition to pay a sum of Rs. 4000/- as damages for breach of contract, and it was similarly provided that if the vendees failed to complete the sale, they would be liable to forfeiture of this earnest money and to pay a further sum of Rs. 2000/- as damages for breach of contract. Some ten days before the final date for the completion of the sale, the defendants sold the land in question to Sohan Singh and others and executed a sale-deed in their favour on the 5th December, 1949. As the plaintiffs had come to know of the sale by the defendants in favour of the third party, they sent a telegraphic protest to the defendants and also made an application before the Registrar asking for postponement of the registration of the sale-deed on the very day, that is, 5th December, 1949, but the Registrar refused to the accede to the request of the vendees, and the document was registered. The plaintiffs, therefore, instituted the suit out of which the present appeal has arisen, on 6th December, 1949, claiming the refund of Rs. 2000/- in lieu of the earnest money and the stipulated sum of Rs. 4000/- as damages. The defendants admitted having executed the agreement Ex. P-1 dated 25th July, 1949, but resisted the suit on two grounds; firstly, that the contract for sale had been broken by the plaintiffs inasmuch as they had refused to pay half the share of the expenses which were required for the completion of the sale and for obtaining the permission of the authorities concerned to the sale which was rendered necessary on account of the circumstance that the defendants were Sikh Jats and the plaintiffs Seni Jats, and a sale from the one to the other required permission of competent authority before it could be validly effected. In the second place, the defendants contended that the damages asked for by the plaintiffs were in the nature of a penalty and, were, therefore, illegal. The trial court decreed the plaintiffs suit for a sum of Rs. 6000/-. Its findings are (1) that the defendants and not the plaintiffs were responsible for the breach of the contract for sale, (2) that no permission was necessary for the completion of the sale as non was required under any law and (3) that the sum of Rs. 4000/- named in Ex. P-1 as damages was in no way excessive and was in fact a reasonable compensation to which the plaintiffs were entitled in the circumstances of this case. In this connection, the trial court also came to the conclusion that the defendants had broken the contract as they had re-sold the land in dispute for Rs. 6000/- in excess of the price of Rs. 16,000/- stipulated between them and the plaintiffs the defendants have now come up in appeal.

    3. Learned counsel for the defendants did not contest before us the finding of the trial court that no permission was necessary for the completion of the sale. We shall, there fore, say nothing about this point. The points on which he attacked the decision of the court below are two in number. In the first place, he contended that the defendants were not responsible for the infringement of the contract and the plaintiffs were at fault in this regard. The case of the defendants originally was that the plaintiffs had refused to pay half of the expenses of registration, stamp paper and certain other incidental charge, and in spite of repeated demands, they finally declined to on the 4th December 1949. As the defendants were in urgent need of money, they were reduced to the necessity of selling the suit land to Sohan Singh and others, and, therefore they were not at all to blame in the matter. This case was sought to be proved by the evidence of D.W.S Pal Singh and Bhap Singh apart from the Statements of the defendants themselves at the trial. What the defendants actually sought to prove at the trial, however, was that when Badhava Singh want to the plaintiffs to obtain their half share of the expenses, the plaintiffs expressed their under utter inability to furnish the requisite money and stated that they would not purchase the land as they had no means to do so. Badhava Singh further said that owing to the helplessness of the plaintiffs, he had gone to the length of agreeing that he would fore go the damages which the plaintiffs would have to pay for breach of the contract and that he would be satisfied with the forfeiture of the earnest money only. This defendant would have us believe also that the plaintiffs had agreed to this and that they had consented to come to Raisinghnagar on the 5th December 1949, to execute the necessary document embodying the aforesaid terms and that the plaintiffs come to Raisinghnagar but refused to execute the deed and so the deal with Sohan Singh and others was effected. Not only this, the defendant further stated that the sale in favour of Sohan Singh and others was agreed to by the defendants at the instance of the plaintiffs. D.W.S Palsingh and Bhapsingh more or less support the story. We entirely concur in the finding of the court below that the version put forward the defendants at the trial is so absurd that it cannot be believed. The facts to which these witnesses have sworn during the course of the trial did not find any place in the written statement at all and are completely contrary to the course of normal human conduct. If the plaintiffs were unable to find the money for the completion of the sale, we are quite certain that they would not have dared to sent any protest whatsoever, much less by a telegram, to the defendants, or file an application before that Registrar praying for postponement of they registration. It is quite clear from the evidence of the Registrar Shri Baney Singh that the plaintiffs had submitted their application to him before the document had been registered we cannot also forget in this connection that the re-sale made by the Page: 176defendants was actually made 10 days before the date fixed between the parties for the completion of the contract. In face of these broad and incontrovertible facts, we do not feel the necessity of discussing the evidence of the plaintiffs at any length which has been led to show that although the plaintiffs asked the defendants for completion of the sale from time to time, the latter were putting it off and eventually made a re-sale in favour of Sohan Singh and others. We have, therefore, no hesitation in coming to the conclusion that the defendants were responsible for the breach of contract and not the plaintiffs.

    4. We are then left with the question whether the plaintiffs are entitled to the sum of Rs. 4000/- by way of damages, which was awarded to them by the trial court it was strenuously contended before us that the said sum was in the nature of the penalty and the lower court fell into serious error in awarding it to the plaintiffs. It was further argued that the trial court did not frame a proper issue on this point and wrongly put the burden thereof on the defendants instad of on the plaintiffs. Reliance was placed on Bhai Panna Singh v. Bhai Arjun Singh(1), a decision of their Lordships of the Privy Council. It was argued that the imperfect Wording and wrong allocation of the burden of proof of this issue misled the defendants and has resulted in grave injustice to them inasmuch as they have had no opportunity of rebutting the evidence led by the plaintiffs to show that the consideration for the re-sale Was not the ostensible one of Rs. 19,000/- but Rs. 6,000/- in excess there of that is, Rs. 22,000/-.

    5. We propose first to deal with the precise effect of sec. 74 of the Contract Act in this connection. Sec. 7 of the Contract Act in so for as it is material for our present purposes reads as fallows:—

    “When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, “the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named” or, as the case may be, the penalty stipulated for.”

    6. The first case to which we were referred for interpreting the aforesaid section was Lachhman Das v. Bhoja Ram (2). In that case the parties to the contract for sale of certain land had provided that in the even of a breach, thereof, an identical sum would be paid as damages by either party failing to perform his part of the contract. It was held that in the absence of any equitable ground, the stipulated sum should be decreed as damages. The same view was adopted in Lekh Singh v. Dwarka Nath (3), although in this case only the vendor was, under the agreement, fastened with liability to pay a sum of Rs. 2,000/- in the event of a breach on his part. It was held that where the parties have mentioned a fixed sum in case of breach, the court should award the stipulated sum as damages unless there is something to show that amount is exorbitant or unconscionable.

    7. Then came the decision of their Lord-ships of the Privy Council in Bhai Panna Singh v. Bhai Arjun Singh (1) There the vendors had agreed to sell a building to the vendees for Rs. 1,05,000/- and in the event of a breach the party responsible for the breach was to pay a sum of Rs. 10,000/- to the other party. The vendors eventually sold the property to another purchaser at Rs. 1,04,000/- as the original vendees had broken the contract. Their Lordship held as to the amount of damages that the effect of sec. 74 is to disentitle the plaintiffs to recover simpliciter the sum fixed in the contract whether penalty or liquidated damages. The plaintiffs must prove the damages they have suffered.” It was further held that the only evidence of loss was the loss of Rs. 1000/- suffered by the vendors on re-sale.

    8. We will next refer to Mahadeoprasad…Plaintiff; v. Siemens (India) Ltd.…Defendants. (4). In that case Ameer Ali, J. held that the sum named in the agreement was itself some proof of damages, and that in the absence of any other proof, that alone may be considered to be sufficient but if there is other evidence and the court comes to the conclusion that the sum named in the agreement was unreasonable, the plaintiff must prove his damages. With great respect, we must state that this view goes much further than we think, we ought to go. Suppose there is no evidence of damage caused to the plaintiff in a particular case. Suppose also that the sum named in the agreement has apparently been fixed in terrorem or does not place the burden of breach equitably or evenly on both sides to the contract. The question then arises whether in such circumstances the sum named in the agreement should be decreed under sec. 74 of the Contract Act? We think not. Besides we consider that it must be a fact to be determined in each case whether the sum named is a genuine pre-estimate or just a sum fixed in terrorem. There can be no doubt that in the former case the sum named in the agreement may be decreed as reasonable compensation under sec. 74 but that has got to be shown and we think that it is in that sense that the privy Council (in Panna Singh's case) said that the plaintiff must prove the damages suffered by him. Again, it appears to us that if the view propounded in the Culcutta case Mahadeoprasad…Plaintiff; v. Siemens (India) Ltd.…Defendants. (4) were to be adopted, then the plaintiff need not prove the damages at all and yet claim the entire amount named in the agreement as compensation on the ground that there is no other proof available on the record. But would that not be a negation of the principle embodied in sec. 74 and in the decision of their Lordships of the Privy Council in Panna Singh's case (1) Ameer Ali, J. concluded his discussion on this aspect on the matter by posing a question “Is not the estimate made by the parties with full consideration some evidence?” and answered it in the Page: 177affirmative. But that, in our opinion, begs the very question. We think there is no getting away from the fact that it must be shown by some tangible evidence, direct or circumstantial, that there was a pre-estimate and that it was made after “full consideration”, and that is what we think sec. 74 implies when it lays down that only reasonable compensation may be allowed subject to a further consideration that such compensation will not be in excess of the sum named by the parties themselves in their agreement.

    9. The next case to which we may refer is Michel Habib v. Sheikh Suleiman(5). That case came from Palestine. Their Lordships observed that the Code of Civil Procedure in Palestine did not know “penalties” as such but that when the difference between a ‘penalty’ and ‘liquidated damage’ was being introduced into the jurisprudence of Palestine, a plain and just meaning must be given to the Palestine Code. Their Lordships then proceeded to say that,

    “Agreed liquidated damages, if to be enforced, must be the result of a “genuine pre-estimate of damages” to use the illuminating phrase of Lord Dunadia They do not include a sum fixed in terrorem covering breaches of contract of many varying degrees of importance the possible damages from which bear no relation to the fixed sum, and which obviously have at no time been estimated by the contracting parties.”

    We would like to say that although the Indian Law obliterated the distinction between ‘a penalty’ and ‘liquidated damages’ as embodied in sec. 74, and allows only ‘reasonable compensation’, we think that the observations made by their Lordships in the Palestine case may well be borne in mind and applied as a standard for assessing reasonable compensation in cases falling under sec. 74 of the Contract Act.

    10. The last case to which we may refer is Mool Chand Behari Lal v. S.D Chand & Co. (6). It was held in that case that where some amount is paid by way of earnest money or kept in deposit for the due performance of any obligation under a contract, it is always for the court to determine under sec. 74, what amount would be “reasonable compensation” under the circumstances of a particular case. If the court considers that the sum named is not excessive or unreasonable, it shall allow it; but where it does not so consider it the court will reduce the stipulated amount to the figure it considers reasonable. In no case, however, the court will grant any compensation in excess of the figure named in the agreement.

    11. On a review of the authorities cited above, we are of opinion that the true effect of sec. 74 may be summarized somewhat as follows:—

    (1) Where as sum is named in the agreement as payable on breach thereof, the plaintiff cannot be entitled to the entire sum so named “simpliciter”, that is, merely because such a sum may be mentioned in the agreement to be so payable.

    (2) All that the plaintiff would be entitled to is a “reasonable compensation” subject to the amount named therein being the maximum.

    (3) What is “reasonable compensation” would depend upon and must be determined by the circumstances of each case.

    (4) The aforesaid result must hold good regardless of the consideration that the sum named in the agreement is what under the English law is termed as liquidated damages” or is in the nature of a “penalty”. The effect of the Indian law as embodied in sec. 74 is to do away with the distinction between “penalty” and unliquidated damages” under the English law which has been a prolific source of case law and which has sometimes given rise to not a little confusion.

    (5) It must be for the plaintiff to prove the damage suffered by him, but such proof may be direct or circumstantial, and need not possess the quality of arithmetical exactitude.

    (6) If the plaintiff succeeds in establishing that the sum named in the agreement is a genuine pre-estimate of damages, or would otherwise be a reasonable compensation for the breach, the court may grant the entire sum named in the breach as such compensation. If, on the other hand, the court comes to the conclusion that the amount so fixed was in terrorem or unconscionable and extravagant, it would be open to it to award such sum as may appear to be reasonable.

    (7) In deciding whether the amount fixed is a genuine pre-estimate or reasonable compensation or not, it would be a factor for consideration whether the sum named in the agreement is not disproportionate to the injury caused and whether the burden evenly and equitably fails on both parties to the contract.

    12. Now, applying the above principles to the case before us, we find that in the agreement entered into between the parties, it was stipulated that either party in the event of breach would be liable to pay a sum of Rs. 4000/- to the other by way of damages. In the case of a breach by the vendors, they were of course held liable to refund the earnest money and we see nothing unreasonable about this. We may further point out in this connection that although the defendants' case was that they had sold the land in question for Rs. 16,003/- to Sohansingh and others, that is for the same price as was settled at the original sale, the trial court came to the conclusion on the evidence before it that the defendants really sold the land for Rs. 22,000/- and not Rs. 16,000/- only. We see no sufficient reason to disagree from the conclusion arrived at by the trial court in this connection because if this was not a fact, we would have expected the defendants to challenge the conclusion of the trial court specifically and pointedly in the grounds of appeal before us, which they have not done at all. On the Page: 178hypothesis, therefore, that the re-sale took place for Rs. 22000/-, we have no hesitation in coming to the conclusion that the amount, which was the sum of Rs. 4000/- named in the agreement as damages for breach apart from the earnest money of Rs. 2,000/-, was perfectly justified and was indeed well-covered by the excess price to the tune of Rs. 6000/- received by the defendants at the re-sale. We any also add that in the event of breach, each party was fastened with the liability to pay an equal sum of Rs. 4,000/- according to the agreement Ex. P-1, and we do not think, in the circumstances of this case, that this sum was either extravagant or unconscionable or fixed in terrorem and was in any way disproportionate to the harm caused by the breach of the contract for sale of land in a place like Ganganagar where land values are notoriously high.

    13. The next question to which we may now briefly turn our attention is whether there was any serious errors to the procedure followed by the trial court in arriving at the conclusion to which it did. The issue framed by the trial court was in these terms;—

    The burden was obviously placed on the defendants which they accepted without any demur throughout the trial. The contention of learned counsel is that the burden of this issue should have been placed upon the plaintiffs. Now, in view of the terms of sec. 74 and the decision of their Lordships of the Privy Council in Panna Singh's case, we are of opinion that this issue might well have been framed in more precise language, and the burden of its proof should have been placed on the plaintiffs in the first instance. But the defendants did not object to the framing of the issue, and obviously led all the evidence which they wanted to lead relevant to this issue. We inquired from learned counsel for the defendants as to what further evidence he wished to lead in addition to that which was already led by him. All that learned counsel was able to tell us in reply was that he would endeavour to prove that the defendants had sold the land in dispute for Rs. 16,000/- and also to have the second sale-deed produced in evidence. Our answer is two-fold. In the first place, there was nothing which precluded the defendants from leading the evidence which they now want to lead on the issue as it was actually framed, and if they did not lead this evidence, they cannot now ask for an opportunity to lead it. In the second place, we are satisfied from the evidence of Shri Baney Singh, P.W 7 who was the Registrar that the second sale-deed was executed for an ostensible consideration of Rs. 16000/- only but this would not be the end of the matter because the defendants must have had some inducement for backing out of the first sale and that inducement was very probably a larger price at the re-sale. We have already pointed out above that the defendants for some reason or other which is best known to themselves did not choose to attack the finding of the court below on that point in their grounds of appeal in this Court and, therefore it is not really open to them to ask for opportunity to lead their evidence to dispute that point. We may also add that the issue as framed, in spite of all its imperfections, raised with sufficient clarity the points that the parties were required to prove, and there is no substance in the contention that the defendants were mis-led on account of the manner in which it was cast and were, therefore, precluded from leading the evidence which was relevant to it. Both parties had, in our opinion, a fair opportunity to produce evidence and if the defendants left, out such evidence which was available and material, we can not help thinking that they have to thank themselves. We are, therefore, decidedly of opinion that the prayer made on behalf of the defendants for re-trial of the issue as to the amount of damages is un-called for and would be wholly futile in the circumstances of this case.

    14. The result is that this appeal fails and is hereby dismissed with costs.