Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • section 100 C.P.C
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • section 100 C.P.C
Smart Summary

Factual and Procedural Background

This appeal arises from a suit filed by the plaintiff-respondent (the Government of Rajasthan) against the defendants-appellants, who are the legal representatives of the late Fauj Raj, proprietor of "Faujraj & Company." The plaintiff alleged breach of contract for the supply of ration commodities to the Central Jail, Jodhpur, during the period from August 1, 1955 to June 30, 1956. The contract was based on a tender accepted by the Government, followed by an agreement (Ex. 5). Fauj Raj initially supplied the commodities but later failed to supply from March 25, 1956, citing illness. Consequently, the Jail Authorities purchased commodities from the market at higher prices, incurring a loss of Rs. 4984.11, for which recovery was sought.

The suit was instituted on May 11, 1961 before the Civil Judge, Jodhpur. The defendants contested the suit, notably arguing that no completed contract existed as the agreement was not finalized and that Fauj Raj could terminate the contract at any time. The trial court partly decreed the suit for Rs. 4685.33, limiting the decree to assets left by Fauj Raj. The defendants appealed, and the District Judge, Jodhpur, confirmed the trial court's decree on March 28, 1969. The defendants then filed the present appeal under Section 100 of the Code of Civil Procedure.

Legal Issues Presented

  1. Whether the agreement (Ex. 5) constituted a binding and completed contract or merely a continuing/standing offer that required specific orders to create a binding contract.
  2. Whether the defendants (legal representatives of late Fauj Raj) are liable for breach of contract and consequent loss due to non-supply of ration commodities without specific orders placed by the Jail Authorities.

Arguments of the Parties

Appellants' Arguments

  • The agreement (Ex. 5) did not amount to a completed contract; it was a continuing offer requiring specific orders for quantities to be placed by the Jail Authorities to create binding contracts.
  • Clause 2 of the agreement and condition No. 2 of the tender implied that supply obligations arose only upon the placing of specific orders, without which no breach could be established.
  • Therefore, defendants cannot be held liable for breach of contract for failure to supply goods when no specific orders were given.

Respondent's Arguments

  • The agreement (Ex. 5) was a completed and binding contract upon acceptance of the tender by the Government.
  • Late Fauj Raj committed breach of the contract by failing to supply the contracted commodities as per the terms, thus liable for the loss suffered.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Percival Ltd. v. London County Council Asylums and Mental Deficiency Committee Standing offer converted into a series of contracts by subsequent orders; orders prevent revocation of the offer for those quantities. Supported the view that the agreement was a standing offer requiring specific orders to create binding contracts.
Union of India v. M. Thathaish Acceptance of tender may amount to contract depending on terms; continuing offers require specific orders for binding contracts. Reinforced the principle that the tender acceptance alone may not create a binding contract without specific orders.
Chaturbhuj Vithaldas v. Moreswar Parashram Letters setting terms for business create continuing arrangement; contract arises only on placement and acceptance of orders. Supported the idea that no contract exists until specific orders are placed and accepted.
Rose and Frank Co. v. J.R Crompton & Bros. Ltd. Continuing arrangements and the nature of contracts arising from orders under such arrangements. Referenced in support of the requirement of specific orders to form binding contracts.
Secretary of State v. Madho Ram Tender as an offer to supply goods subject to acceptance by order; offer can be revoked before acceptance by order. Used to illustrate that the tender was a continuing offer, not a binding contract until orders were placed.
Bengal Coal Company v. Homee Nadial & Co. Supply contracts based on tenders are continuing offers; each order given is an acceptance creating separate contracts. Supported the conclusion that the agreement was a standing offer revocable till acceptance by order.
Kundanlal v. The Secretary of the State for India in Council Tender creates series of continuing offers; binding contract arises only after orders placed and accepted. Applied to affirm that no binding contract existed without specific orders.
Jigna Devi v. State of Rajasthan (D.B. Civil Regular First Appeal No. 54 of 1954) Acceptance of tender does not always produce binding contract; depends on language and terms of tender and acceptance. Distinguished by the court as not supporting the plaintiff-respondent's claim in this case.

Court's Reasoning and Analysis

The court carefully analyzed the terms of the tender (Ex. 2) and the agreement (Ex. 5), focusing particularly on Clause 2 of the agreement, which required the agent to deliver commodities "in accordance with the requirements of Central Jail at the godown, Jodhpur." The court examined authoritative legal principles on tenders and contracts, referencing Halsbury's Laws of England and various precedents which distinguish between binding contracts and continuing or standing offers.

The court noted that an invitation to tender generally constitutes an offer to receive offers, and that acceptance of such tenders results in binding contracts only when specific orders are placed and accepted. The cited cases established that a mere acceptance of a tender does not necessarily create a binding contract unless the terms specify fixed quantities or obligations to purchase all required goods.

Applying this to the facts, the court found that the agreement in question was a continuing offer rather than a completed contract. The Jail Authorities were at liberty to place orders which, upon acceptance, would create binding contracts. Since no specific orders were placed for the period after March 25, 1956, and the agent had not supplied the commodities, no breach of contract occurred for that period. Hence, the plaintiff was not entitled to recover the loss incurred due to market purchases without prior orders.

The court also distinguished the precedent relied upon by the lower courts (Jigna Devi v. State of Rajasthan), finding it inapplicable to the facts here because that case involved a firm contract obliging purchase of the entire allotment, unlike the present case.

Holding and Implications

The appeal is partly allowed. The court modified the decree of the trial and first appellate courts by reducing the decretal amount from Rs. 4685.33 to Rs. 924.18. The suit is dismissed for Rs. 4060.51 (the balance amount), and the decree for Rs. 924.18 is maintained with interest at 6% per annum. Costs are to be borne according to success and failure in this Court.

The direct effect of this decision is to limit the liability of the defendants to the loss attributable to the period when specific orders were placed and supply was due (up to March 1956). No new precedent is established beyond the application of existing principles distinguishing standing offers from binding contracts in tender cases.

    Mrs. Chand Kunwar v. State Of Rajasthan

    S.K Mal Lodha, J.:— This appeal under section 100 C.P.C is by defendants against the appellate judgment and decree dated March 28, 1969, of the learned District Judge, Jodhpur by which he confirmed the decree for Rs. 4685.33 with proportionate costs passed by the Civil Judge, Jodhpur on April 15, 1966 in a suit for recovery of Rs. 4984.69 on account of loss suffered by the plaintiff-respondent as there was a breach of contract.

    2. A few facts giving rise to this appeal may briefly be recounted here. The defendants-appellants are the legal representative of late Fauj Raj, who according to the plaintiff-respondent, worked under the name and style ‘Faujraj & Company’ for the supply of Ration Commodities. The Authority of the Central Jail, Jodhpur invited tenders for the supply of ration commodities for the period commencing from July 1, 1955 to June 30, 1956. The conditions of the contract are contained in Ex. 2. Material conditions for the disposal of the appeal are as under:

    Late Faujraj proprietor of Fauj Raj & Company gave a tender on April 30, 1955. His tender was accepted by the Government of Rajasthan. A contract for the supply of ration commodities mentioned in memorandum No. D-4233/- F. 16(143) Home. II/55 dated July 29, 1955 was sanctioned in his favour for the Page: 67period from August 1, 1955 to June 30, 1956. The sanction was conveyed to late Faujraj by the Superintendent, Central Jail on August 2, 1955. An agreement (Ex. 5) in pursuance of the sanction was executed. The security amount was not deposited by Faujraj. He, however, supplied the ration commodities regularly to the Jail Authorities for some time, but later on he could not arrange for regular supply. On March 25, 1956 he refused to supply the commodities and intimated to the jail authority vide letter dated June 27, 1956 that he was cmfined to bed and, therefore, was unable to make the necessary arrangement for supply of the contracted articles. As Faujraj failed to supply the contracted commodities, the Jail Authorities purchased them from the market at a higher price upto June 30, 1956. The plaintiff respondent has stated that on account of the purchase of the contracted articles from the market, the Government had suffered a loss of Rs. 4984-11 because of the breach of contract committed by Faujraj. The State, therefore, instituted a suit for the recovery of Rs. 4984.11 in the court of Civil Judge, Jodhpur on May 11, 1961 against the defendants appellants being the legal representative of Faujraj. The suit was resisted by the defendants. One of the important pleas taken by them was that even if the case of the plaintiff is taken to be proved, the agreement (Ex. 5) was not completed and, therefore, the defendants are not liable for breach and Faujraj was at liberty to put an end to this contract at any time. The trial court framed five issues inclusive of the relief. After trial, the learned Civil Judge, by his judgment dated April 15, 1956, partly decreed the suit for Rs. 4685.33 and the bar of the decree was limited to the extent of the assets left by Faujraj and received by the defendants and not satisfactorily accounted for. The suit for the amount of Rs. 299.36 was dismissed with costs and future and pendentelite interest was allowed at the rate of 6% p.m on the decretal amount.

    3. Being dissatisfied, the defendants went in appeal and the learned District Judge, by his judgment, dated March 28, 1969, confirmed the judgment and decree passed by the learned Civil Judge on April 15, 1966. Aggrieved, the defendants have come up in appeal to this Court.

    4. I have heard Mr. Rajendra Mehta, learned counsel for the appellants and the learned Additional Government Advocate on behalf of the respondent.

    5. Mr. Rajendra Mehta, appearing for the appellants has not raised any controversy in regard to the sum of Rs. 924.3 as mentioned in Ex. 126. This amount pertained to the loss suffered by the respondents for non-supply of contracted commodities upto March, 1956. The controversy in this appeal, therefore, remains confined to the balance of the decretal amount.

    6. The only argument raised by Mr. Rajendra Mehta is that by means of the agreement (Ex. 5), no completed contract come into existence and as there was no completed contract, the defendants cannot be held to liable for its breach. On the basis of condition No. 2, reproduced from Ex. 2 and Clause 2 of the agreement (Ex. 5), it was strenuously contended that the ‘Agent’ (Late Faujraj) was bound to deliver the contracted commodities in accordance with the requirements of Central Jail at the godown, Jodhpur. This, according to the learned counsel pre-supposed a specific order relating to specific quantity of the conttacted commodities and if the Agent had failed to supply the goods on placing of the order of their supply then there would have been a breach of contract. In other words, according to the learned counsel the binding contract could only come into existence after the placing of the order by the Jail Authorities with regard to specified quantity of the contracted commodities. Learned Additional Government Advocate controverted this position and submitted that Ex. 5 was a completed contract and as Late Faujraj committed breach of the conditions thereof, he was liable to make good the loss suffered by the plaintiff.

    7. I have given my most anxious and thoughtful consideration to the rival contentions raised on behalf of the learned counsel for the parties and I am of opinion that there is considerable force in what the learned counsel for the appellant has contended.

    8. It was contended before the learned District Judge whether upon the true construction of Ex. 2 and agreement Ex. 5, it could be held that there was a contract part on the of late Faujraj to supply certain commodities to the Central Jail, the learned District Judge opined that the agreement (Ex. 5) did not give an option to the Jail Authorities to give or not to give the tenderer any order at all for supply of specified goods, After considering the relevant case-law, he reached the conclusion that the parties had entered into a binding contract which became irrevocable after the tender was accepted by the Government and it was not merely a revocable continuing offer which was to be accepted from time to time by giving orders. It will be useful here to quote clause 2 of the agreement (Ex. 5) which is as under:

    “The agent agrees to deliver the said commodities in accordance with; the requirements of Central Jail at the godowns Jodhpur.”

    9. The question, that, therefore, arises is whether having regard to condition No. 2 in Ex. 2 and clause 2 in the Agreement (Ex. 5), a binding contract came into existence or it was merely a standing offer.

    10. Para 230 of the Halsbury's Law of England Fourth Edition, Vol. 9, deals with ‘Tenderers’. The learned Author has stated in para 230 that an advertisement that goods or services are to be bought or sold by tender is not, prima facie; an offer to sell to the person making the highest tender and normally, the actual tender will amount to an offer. It follows that in the usual case, acceptance of such a tender concludes a binding contract. He has stated as under:

    “In one instance, however, such an acceptance does not usually have this effect. Ordinarily, a tender for the supply of such goods as may be required, no quantity, being specified, is not an offer whish may be accepted generally so as to form a binding contract, but is a continuing offer, which is accepted from time to time whenever an order is given for any of the goods specified in the tender. An acceptance of such a tender merely amounts to an intimation that the offer will be considered to remain open during the period specified, and that it will be accepted from time to time by orders for specific quantities, and does not bind either party unless and until such orders are given. Nevertheless, a tender may be so worded as to impose an obligation on the person who accepts it to order all the goods that he requires for a particular business or purpose during the period specified from the person whose tender has been accepted provided it is sufficiently specified what the terms of the contract are.”

    Cheshire and Fiffot on Law of Contract, under the topic ‘Acceptance in the case of tenders’ have mentioned as follows: There is no doubt, of course, that the tender is an offer. The question, however, is whether its “acceptance” by the corporation is an acceptance in the legal sense so as to produce a binding contract. This can be answered only by examining the language of the original invitation to tender. There are at least two possible cases. First, the corporation may have stated that it will definitely require a specified quantity of goods, no more and no less, as, for instance, where it advertises for 1,000 tons of coal to be supplied during the period January 1st to December 31st. Mere the “acceptance” of the tender is an acceptance in the legal sense, and it creates an obligation. The trader is bound to deliver, the corporation is bound to accept, 1,000 tons and fact that delivery is to be by instalments as and when demanded does not disturb the existence of the obligation. Secondly, if the corporation advertises that it may require articles of a specified description upto a maximum Page: 69amount, as, for instance, where it invites tenders for the supply during the coming year of coal not exceeding 1,000 tons altogether, deliveries to be made if and when demanded, the effect of the so-called “acceptance” of the tender is very different. The ‘tender’ has made what is called a standing offer. Until revocation he stands ready and willing to deliver coal upto 1,000 tons at the agreed price when the corporation from time to time demands a precise quantity. The “acceptance” of the tender, however, does not convert the offer into a binding contract, for a contract of sale implies that the buyer has agreed to accept the goods. In the present case, the corporation has not agreed to take 1,000 tons, or indeed any quantity of coal. It has merely stated that it may require supplies upto a maximum limit. In this latter case, the standing offer may be revoked at any time provided that it has not been accepted in the legal sense and acceptance in the legal sense is complete as soon as a requisition for a definite quantity of goods is made. Each requisition by the offeree is an individual act of acceptance which creates a separate contract. If the corporation in the case given telephones for twenty five tons of coal, there is an acceptance of the offer and both parties are bound to that extent and to that extent only the one to deliver, the other to accept twenty five tons. If, however, the tradesman revokes his offer, he cannot be made liable for further deliveries, although he is bound by requisition already made.” The nature of ‘standing offer’ was considered in Percival Ltd. v. London County Council Asylums and Mental Deficiency Committee (1). In that case the plaintiffs advertised for tenders for the supply of stores. The defendant made a tender to the effect that he undertook to supply the company for twelve months with such quantities of special articles as the company may order from time to time. The Company, by a letter accepted the tender and subsequently gave various orders which were executed by the defendant. Ultimately the Company gave an order for goods within the schedule, which the defendant refused to supply. The Company succeeded in an action for breach of contract. The tender was a standing offer, to be converted into a series of contracts by the subsequent acts of the company and that an order prevented protento the possibility of revocation, and the defendant, though he might regain his liberty of action for the future, was meanwhile bound to supply the goods actually ordered. Reference of the aforesaid paras in Law of the Contract by Cheshire and Fiffot has been made by their Lordships in Union of India v. M. Thathaish (2). It will be useful here to refer to Chaturbhuj Vithaldas v. Moreswar Parashram (3). In that case, certain letters were analysed. After analysing these letters, their Lordships opined that no binding engagement can be spelt out of them except that the company undertook to sell to the canteen contractors only through the Canteen Stores and not direct and undertook to pay a commission on all sales. It was held that this constituted a continuing arrangement under which Canteen Stores, i.e, the Government would be entitled to the commissions on all orders placed and accepted in accordance with the arrangement. The letters merely set out the terms on which the parties were ready to do business with each other if and when orders were placed and executed. As soon as an order was placed and accepted a contract arose. It is true that this contract would be governed by the terms set out in Page: 70the letters but until an order was placed and accepted there was no contract. Also, each separate order and acceptance constituted a different and distinct contract. In this connection, reliance was placed by their Lordships of the Supreme Court on Rose and Frank Co. v. J.R Crompton & Bros. Ltd. (4). Chaturbhuj's case (3) was referred to in Union of India's case (2). From Chaturbhuj's case (3), their Lordships in Union of India's case (2), excerpted the following:

    “But except for this the letters merely set out the terms on which the parties were ready to do business with each other if and when orders were placed and executed. As soon as an order was placed and accepted a contract arose. It is true, this contract would be governed by the term set out in the letters but until an order was placed and accepted there was no contract.” It was held in that case that on the basis of the note, the acceptance of respondent's tender by the Deputy General Manager may even amount to a contract in the strict sense of the term. It was observed:

    “……………We do not consider it in that sense in view of the provisions of paras 8, 9 of the tender requiring a deposit of security and the placing of the formal order.”

    In Secretary of State v. Madho Ram (5), one M signed a tender for the supply of petroleum oil to the military authorities in the Lahore Division for the period of one year. The tender was in the following terms: “I, hereby agree that on acceptance of this tender or so much thereof as relates to the supply petroleum oil, I shall in accordance with such acceptance supply and deliver at my own expense so much oil petroleum as the offer I.G supplies concerned, may require subject to the condition set forth in the tender and in schedule annexed thereto.” The schedule to the tender set out the respective prices to be charged on the estimated requirements. The price to be charged was fixed in the schedule at Rs. 3,12.0 per gallon and the estimated requirement stated to be 200 gallons. In a footnote to the schedule appeared the words “and as required after completion of these quantities.” M. claimed the exclusive right of supplying to the military authorities of Lahore all supplies of petrol ordered for the military department and sued the military department for damage for having purchased petroleum from persons other than himself. In those facts, it was held that the tender was merely an offer to supply goods at certain price for the fixed period and so long as the offer remained open M was bound to supply the goods at the price when called upon to do so upto at least the estimated quantity and M could at any time withdraw his offer upon proper notice to the military authorities and upon such withdrawal his liability to supply the goods not already ordered would have terminated. It was further held that the military authorities were free to accept the offer or not as they would think fit and they could buy the goods from any other source without any reference to M. In that case, reliance was placed on M. Percival Ltd.'s case (1). In the Bengal Coal Company v. Homee Nadial & Co. (6), “A agreed in writing to supply coal to B at certain prices and upto a stated quantity, or in any quantity, which may be required for a period of twelve months, is not a contract unless B binds himself to take some certain quantity, but a mere continuing offer which may be accepted by B from time to time by ordering goods upon the terms of the offer. In such a case, each order given by B is an acceptance of the offer and A can withdraw the offer, or, to use the phraseology of the Act revoke the proposal, at any time before its acceptance by an order from B. Such a transaction may be reduced to a statement by the intending vendor in this form ‘If you will send me orders for coal, I shall supply it to you for a period of twelve months at a particular rate.’ This is merely a proposal from A to B If in reply to such a proposal, B says to A ‘I agree’, it does not constitute an acceptance of the proposal. An acceptance can take place only by B sending an order to A” The Bengal Coal's case (6) was relied on in Kundanlal v. The Secretary of the State for the India in Council (7). In that case, the Commissariat Department invited tenders for the supply of such gram as it might require for a period of twelve months. The defendant sent in a tender to supply the gram for that period at a certain fixed price in such quantities as the Department might order from time to time. By one of the terms of the tender the plaintiff was bound to give fifteen day's notice if more than 1,000 maunds of gram was required at a time. The plaintiff accepted the tender and on September 12, gave a notice to the defendant (which was not despatched from plaintiff's office until the 14th that he would require delivery of 1,4000 maunds on or before the 28th September. The plaintiff having failed Page: 71to deliver the gram (although several extensions were allowed to him), the plaintiff rescinded the contract and brought an action for damages for nondelivery against the defendant. It was, inter alia, held that the tender made by the defendant and accepted by the plaintiff was not a contract by itself, but, created a series of continuing offers on the part of the defendant which plaintiff was at liberty to convert into contract by giving orders in accordance with the terms of the tender.

    11. In this case, it is clear from Ex. 2 that the person in whose favour the contract as sanctioned, would be required to send the contracted commodities to the Jail Godown within a week without recovering the additional charges. Clause 2 of the agreement (Ex. 5) lays down that the X Agent would be required to deliver the contracted commodities in accordance with the requirements of Central Jail at Godown, Jodhpur. Clause 2 of the agreement (Ex. 5) does not constitute the contract by itself, but it merely created a series of continuing offers on the part of the Agent, which the plaintiff (Jail Authorities) were at liberty to convert them into contract by giving orders in accordance with the terms of the tender. As the agreement (Ex. 5) is not a binding contract, the failure to supply the goods without placing any specific order in regard to them does not give rise to a breach of contract so as to entitle the plaintiff respondent to recover the loss from the defendants. This view of mine stands supported by Percival Ltd.'s case (1), Bangal Coal Company's case (6), Kundanlal's case (7) and Secretary of State's case (5). The learned District Judge has made reference to the decision rendered in Jigna Devi v. the State of Rajasthan (D.B Civil Regular First Appeal No. 54 of 1954, decided on April 10, 1958), in which Percival Ltd.'s case (1) and Bengal Coal Company's case (6) have been referred. It was observed by the Division Bench in Jigna Devi's case (supra) as follows:

    “It is true that the acceptance of a tender does not in every case produce a binding contract. Whether or not it does so depends upon the language of the original invitation to tender, of the tender which is offered and of the acceptance or other formal document if any executed between the parties. It is quite common for large bodies that require supplies over a year to ask for tenders and to obtain them. It sometimes happens that the effect of the form of the tender with an acceptance is to make a firm contract by which the purchasing body undertakes to buy all the specified material from the conrtractor. On the other hand, these tenders are very often in a form under which the purchasing body is not bound to give the tenderer any order at all, in other words, the contractor offers to supply goods at a price, and if the purchasing body chooses to give him an order for goods during the stipulated time, then he is under an obligation to supply the goods in accordance with the order; but apart from that no body is bound. Only an offer comes into being which the tenderer is free to revoke at any time before the next order is placed. Once an order is placed the tenderer is bound to supply the goods under that particular order. He is still free to revoke the offer for purposes of future orders. There is also an intermediate contract that can be made in which although the parties are not bound to any specified quantity, yet they bind themselves to buy and to pay for all the goods that are in fact needed by them. In such a case there is a binding contract which will be broken if the purchasing body in fact does need some of the articles which are subject of the tender and does not take them from the tenderer.”

    I have carefully read the above judgment and am clearly of the opinion that it is of no avail to the plaintiff-respondent. In that case in clause 2 of the notice inviting tenders, it was specified that the licensee shall supply raw opium according to the allotment made by the Kotah State except the Sambhar Shamlat area and to no other person or persons in the State. Clause 7 of the agreement reads as under:

    “If the licensee fails to supply the required quantity of opium from time to time within the time required the cash security deposited by him shall be liable to forfeiture.” Clauses 8, inter alia, provided for the grant of necessary permits to the licensee for the import of the opium. The learned Judges, after taking into consideration clauses 1 to 14, reached the conclusion that “On a careful consideration of the language of the notice inviting tenders and of the agreement dated 1.4.49 we are of opinion that the Jodhpur Government entered into a firm contract with the plaintiff under which it bound itself to purchase the entire quantity of opium allotted to it by the Kotah State.” The words “according to allotment made by the Kotah State” are said to have meant the whole of the allotment made by the Kotah State.

    12. The learned District Judge misdirected himself when he construed the agreement (Ex. 5) as a binding contract. Having regard to the language used in condition No. 2 of Ex. 2 and clause 2 of the agreement (Ex. 5). I am of opinion that the contract was merely a continuing offer and no binding contract came into existence. It was merely a standing offer and it was only after the orders were placed for specified quantity that the appellant was bound to supply the contracted commodities to the Jail Authorities. It was only after the acceptance of the order that a completed binding contract could have come into existence.

    13. In view of the conclusion to which I have arrived at hereinabove, I am unable to agree with the finding recorded by the learned District Judge that the parties entered into the binding contract which became irrevocable after the tender was accepted by the Government and the plaintiff-respondent is not entitled to recover the loss from the defendants on account of the breach of contract.

    14. For the reasons mentioned above, I am constrained to allow this appeal in part.

    15. The result is that the appeal is partly allowed and the decree of the trial court as confirmed by the first appellate court is modified and the decretal amount is reduced from Rs. 4685.33 to Rs. 924.18 In other words, the suit of the plaintiff respondent is dismissed for Rs. 4060.51 (Rs. 299.36 + Rs. 3761.15) and decree for Rs. 924.18 only is maintained. The plaintiff will be antitled to interest pendente lite and future @ 6% per annum on the decretal amount of Rs. 924.18 The parties will be entitled to receive and pay costs through according to their success and failure in this Court.