By this Petition under Article 226 of the Constitution of India, the petitioner has prayed for directions to the Municipal Commissioner, Municipal Corporation of Greater Mumbai (hereinafter referred to as the “Municipal Commissioner”) to invoke the provisions of section 489 of the Mumbai Municipal Corporation Act, 1888, to carry out repairs of the petitioner's flat, being flat no. 1 on ground floor of the respondent no. 3 society in Borivli (West), Mumbai. There have been disputes between the petitioner and the respondent no. 3 which have culminated into orders dated 19.12.2007, 21.2.2008, 14.3.2008 and 26.3.2008 in Revision Application no. 73 of 2007.
2. The purport of these orders is that the petitioner is entitled to get the repairs carried out in his flat at the expense of the society and to recover the same from the respondent no. 3 society.
3. We are informed that during the pendency of the proceedings before the Co-operative Court, the petitioner was required to deposit the amount of maintenance charges otherwise payable to the respondent no. 3 society and, accordingly, the petitioner has deposited a sum of approx. Rs. 40,000/- and the amount is credited in the Reserve Bank of India in the account of Co-operative Court no. 3 in the case between the petitioner and the respondent no. 3 society.
4. Having heard the learned counsel for the parties, we are unable to accept the petitioner's contention that for the structural repairs to be carried out in the petitioner's flat, the Municipal Commissioner should be directed to spend from the public funds and, thereafter, to recover the same from the respondent no. 3 society. We do not find any such provision in section 489 or 499 of the Act which would justify this Court to direct the Municipal Commissioner to spend for repairs in a private flat from out of the public funds. At the highest, the petitioner is entitled to carry out the repairs in his flat and to recover the same from the respondent no. 3 society as per the decisions of the Co-operative Appellate Court. We, therefore, leave it open to the petitioner to approach the Cooperative Court which will permit the petitioner to withdraw the amount of approx. Rs. 40,000/- deposited during the pendency of the proceedings before the Co-operative Court. The petitioner will also be at liberty to carry out repairs in his flat and recover the amount from the respondent no. 3 society by taking out appropriate execution proceedings for execution of the orders of the Co-operative Appellate Court. If the petitioner moves the Co-operative Court with an application for withdrawal of the aforesaid amount, the Co-operative Court shall pass appropriate orders so as to enable the petitioner to withdraw the amount within one week from the date of filing of the application.
5. Writ Petition is, accordingly, disposed of with no order as to costs.