Factual and Procedural Background

This opinion arises from FAO (OS) No. 310/2005. The appellant challenged an order of the learned Single Judge concerning a disputed measurement in a contractual/arbitration context. The appellant's counsel submitted that a request for joint measurement was made because the measurement produced by the opposite party was being questioned. The Single Judge did not grant the interim relief sought and made an observation about the contract clauses regarding finality of measurements recorded by the respondent's engineers. The appellate court reviewed the Single Judge's exercise of jurisdiction under Section 9 of the Arbitration and Conciliation Act, 1996, expunged a specific paragraph of the Single Judge's order, directed that the arbitrator decide the measurement issue in accordance with law, and dismissed the appeal.

Legal Issues Presented

  1. Whether the learned Single Judge erred in refusing to grant the appellant's request for joint measurement when the appellant had questioned the measurement filed by the opposite party.
  2. Whether and how the Court should exercise its discretionary power under Section 9 of the Arbitration and Conciliation Act, 1996, in the context of this dispute.
  3. Whether the Single Judge's observation that "the measurement recorded by the respondent's Engineers in absence of cooperation from the petitioner side will be final and binding between the parties" should remain part of the order or be expunged.

Arguments of the Parties

Appellant's Arguments

  • The appellant contended that the impugned order was legally erroneous because the learned Single Judge failed to appreciate that the request for joint measurement arose from the appellant's challenge to the measurement filed by the opposite party.

The opinion does not contain a detailed account of the opposite party's legal arguments.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court elaborated the following points in its analysis:

  • The discretion under Section 9 of the Arbitration and Conciliation Act, 1996, must be exercised sparingly and cautiously; courts should not routinely interfere at every stage of disputes subject to arbitration because the Act establishes an alternative dispute-resolution mechanism.
  • This caution does not remove the court's power to issue interim orders under Section 9 when appropriate; such powers remain available in suitable cases.
  • Applying these principles to the present matter, the appellate court found no reason to differ from the view taken by the learned Single Judge in refusing interim relief, except in respect of one specific observation made by the Single Judge concerning finality of measurements recorded by the respondent's engineers.
  • The court therefore expunged that particular paragraph (the paragraph stating that measurements by the respondent's engineers would be final and binding in the absence of cooperation by the petitioner) and directed that the arbitrator decide the dispute in accordance with law, without being influenced by the expunged observations of the Single Judge.

Holding and Implications

Final Ruling: The appeal is dismissed. (Appeal dismissed.)

Direct consequences for the parties:

  • The specific observation of the Single Judge — that "the measurement recorded by the respondent's Engineers in absence of cooperation from the petitioner side will be final and binding between the parties" — has been expunged from the Single Judge's order.
  • The arbitrator is directed to decide the measurement dispute in accordance with law and without being influenced by the expunged observations.

No broader precedent or new legal principle was articulated beyond the court's application of the established approach that Section 9 powers should be exercised sparingly; the decision confines itself to the disposition of this appeal and the expunction of the specified observation.

    Sanrachna (India) Inc. v. A.B. Hotels Ltd.

    FAO (OS) No. 310/2005:

    1. Mr. Sandeep Sethi, learned Counsel appearing for the appellant has contended that the impugned order is bad in law as the learned Single Judge has not appreciated that the request made for joint measurement was for the reason that the measurement filed by opposite party was questioned by the appellant.

    2. At the outset, we will make it very clear that the discretion under Section 9 of the Arbitration and Conciliation Act, 1996 has to be exercised sparingly and cautiously. It is not in all cases that a Court has to pass an order while exercising jurisdiction under Section 9 of the Arbitration and Conciliation Act. The insertion of Arbitration and Conciliation Act, 1996 and its objective is to create an alternative dispute redressal mechanism. Therefore, at every stage, the interference by Court is not required. However, we may hasten to add that it does not mean that the Court does not have power in appropriate cases to issue interim orders in terms of what is postulated under Section 9 of the said Act. However, in the present case, we do not see reason to take a different view than that taken by the learned Single Judge, except with one direction that the arbitrator will decide the matter in accordance with law, without being influenced by the observations of the learned Single Judge which are to the following effect:

    “Moreover under Clause 5.10.1 and 27 of the Contract between the parties the measurement recorded by the respondent's Engineers in absence of cooperation from the petitioner side will be final and binding between the parties.”

    3. The aforesaid paragraph quoted by the learned Single Judge while not granting any interim relief is expunged from the said order. The Arbitrator will decide the same in accordance with law.

    4. The appeal stands dismissed.

    Appeal dismissed.