  • The proviso to Section 41 and Section 3 of the Arbitration Act
  • Rule 7 of the Karnataka High Court Rules framed under the Arbitration Act, 1940
  • 1981 DSR (Document not specified as a legislative act, but rather a document used in the case)
  • Section 34 of the Civil Procedure Code
  • Sections 15, 16, 17, 30 and 33 of the Arbitration Act, 1940
  • The Arbitration Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Constitution Bench judgment of this Court in Irrigation Deptt., Govt. of Orissa v. G.C Roy (1992) 1 SCC 508
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • The proviso to Section 41 and Section 3 of the Arbitration Act
  • Rule 7 of the Karnataka High Court Rules framed under the Arbitration Act, 1940
  • 1981 DSR (Document not specified as a legislative act, but rather a document used in the case)
  • Section 34 of the Civil Procedure Code
  • Sections 15, 16, 17, 30 and 33 of the Arbitration Act, 1940
  • The Arbitration Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Constitution Bench judgment of this Court in Irrigation Deptt., Govt. of Orissa v. G.C Roy (1992) 1 SCC 508
Smart Summary

Factual and Procedural Background

National Buildings Construction Corporation Ltd. (“NBCC”), a public-sector undertaking, invited tenders on 12-01-1985 for construction of five 5000-MT food-storage godowns at Bhimavaram, Andhra Pradesh. The appellant-contractor submitted his bid; the work was accepted at 58.5% above the 1981 Delhi Schedule of Rates (DSR) and an agreement dated 26-06-1985 was executed. Disputes arose over payments, alleged delays, and deductions. Invoking Clause 25 of the contract, NBCC appointed a sole arbitrator (Shri N.S.L. Rao) on 15-12-1987.

On 17-08-1988 the arbitrator awarded various sums to the contractor but rejected some claims and denied interest. Both sides challenged the award before the VI Additional City Civil Judge, Bengaluru. By judgment dated 24-06-2000 the civil court largely affirmed the award, modified certain amounts (including Claim 3), and granted interest at 16.5% p.a.

NBCC’s appeal (MFA 4377/2000(AA)) and the contractor’s cross-objection were decided by the Karnataka High Court on 29-08-2002. The High Court:

  • Set aside the arbitrator’s award of Rs 8,16,412 towards 10% loss-of-profit on Claims 1(a)-(c) & 2(a), (c), (e), (f) & (g).
  • Altered certain components of Claim 3; reduced interest to 12% p.a.; upheld Rs 2,40,000 liquidated damages in favour of NBCC.

The contractor appealed to the Supreme Court, challenging the High Court’s power to interfere with the arbitrator’s fact-findings and its conclusions on DSR applicability, loss-of-profit and interest.

Legal Issues Presented

  1. Whether the High Court exceeded its limited jurisdiction under the Arbitration Act, 1940 by re-appreciating evidence and modifying the arbitrator’s award, particularly the 10% loss-of-profit component.
  2. Whether the 1981 Delhi Schedule of Rates and CPWD Manual bound NBCC, rendering its unilateral corrections in the Bill of Quantities unauthorised.
  3. Whether the award of interest at 16.5% p.a. by the civil court was sustainable, or required modification in light of precedents on pendente lite interest.

Arguments of the Parties

Appellant-Contractor

  • The High Court acted as an appellate court, re-appreciating facts that are within the arbitrator’s exclusive domain.
  • The contract explicitly incorporated 1981 DSR; NBCC’s alterations were unauthorised and ignored CPWD Manual procedures.
  • 10% profit/overheads was a reasonable technical allowance accepted by an expert arbitrator and should not have been disturbed.
  • Interest at 16.5% was justified because NBCC itself calculated delayed-payment interest at that rate in its own statement before the arbitrator.

Respondent-NBCC

  • The arbitrator committed legal misconduct by granting loss-of-profit without proof of actual loss or causal link to NBCC’s breach.
  • Corrections to the Bill of Quantities were made before execution of the contract; therefore the altered rates, not 1981 DSR, governed payment.
  • Interest awarded by the civil court was excessive; in absence of a contractual clause, interest should not exceed 6% p.a.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Deptt. of Irrigation v. Abhaduta Jena, (1988) 1 SCC 418 Limited arbitrator’s power to grant interest (overruled later). Referenced as the basis on which the arbitrator denied interest; later shown to be overruled by G.C. Roy.
State of Orissa v. Kalinga Construction Co., (1970) 2 SCC 861 Court’s power to set aside award for misconduct/error on face. Cited by High Court to justify interference with arbitrator’s findings.
K.P. Poulose v. State of Kerala, (1975) 2 SCC 236 Misconduct of arbitrator—non-consideration of vital documents. Relied on to test whether loss-of-profit award showed misconduct.
Sudarsan Trading Co. v. Govt. of Kerala, (1989) 2 SCC 38 Scope of court’s interference; interpretation confined to contract. Guided inquiry into whether arbitrator acted beyond contract.
FCI v. Joginderpal Mohinderpal, (1989) 2 SCC 347 Powers and limitations of arbitrator; misconduct standards. Supported High Court’s scrutiny of evidentiary basis.
Bijendra Nath Srivastava v. Mayank Srivastava, (1994) 6 SCC 117 Standards for setting aside an award. Added to list of authorities on interference grounds.
Port of Madras v. Engg. Constructions Corpn. Ltd., (1995) 5 SCC 531 Error apparent & misconduct justifying modification. Quoted by High Court in evaluating arbitrator’s reasoning.
Rajasthan State Mines & Minerals Ltd. v. Eastern Engg. Enterprises, (1999) 9 SCC 283 Court’s duty to maintain purity of arbitration standards. Reinforced High Court’s authority to correct legal errors.
Sikkim Subba Associates v. State of Sikkim, (2001) 5 SCC 629 Parameters for court’s intervention in arbitral awards. Applied while assessing misconduct in loss-of-profit award.
Irrigation Deptt. v. G.C. Roy, (1992) 1 SCC 508 (Const. Bench) Arbitrator’s power to award pendente lite interest when contract silent. Used by High Court to overrule arbitrator’s denial of interest and to settle rate at 12%.
Thawardas Pherumal v. Union of India, AIR 1955 SC 468 Earlier view on arbitrator’s incapacity to grant interest on unliquidated damages. Discussed in G.C. Roy extract to show legal evolution.

Court's Reasoning and Analysis

The Supreme Court examined whether the High Court’s interference constituted an impermissible re-appreciation of facts. It noted that the High Court identified misconduct in the arbitrator’s award: loss-of-profit was granted without any evidentiary finding of actual loss, causal breach or quantification methodology. Merely invoking delay was insufficient to justify 10% overheads.

On the applicability of 1981 DSR, the Court observed that the High Court scrutinised each item under Claim 3, comparing the original DSR rate, unauthorised corrections, and quantities executed. Where corrections had no evidentiary basis, the High Court restored 1981 DSR plus 58.5%; where the arbitrator misapplied DSR (e.g., ignoring deductions for brick class), the High Court reduced or disallowed the claim. This selective interference was characterised as correction of errors apparent on the face of the award, not a wholesale re-evaluation of evidence.

Regarding interest, the Supreme Court agreed that G.C. Roy authorises pendente lite interest where the agreement is silent, but also affirmed the High Court’s discretion to moderate the rate from 16.5% to 12% p.a., reflecting prevailing bank deposit rates in 1988 and balancing equities.

Finally, the Court held that all modifications by the High Court were grounded in recognised principles regulating arbitral misconduct and judicial oversight. No independent error of law or fact warranting Supreme Court intervention was demonstrated.

Holding and Implications

APPEALS DISMISSED. The Supreme Court upheld the Karnataka High Court’s judgment, including:

  • Deletion of Rs 8,16,412 awarded as 10% loss-of-profit.
  • Re-calculation of Claim 3 items, reducing the total to Rs 10,04,117.42 plus Rs 1,14,500.11.
  • Retention of Rs 2,40,000 liquidated damages payable by the contractor to NBCC.
  • Interest fixed at 12% p.a. from 28-12-1987 until payment, subject to adjustment of amounts already deposited.

Implications: the decision re-affirms the limited but real supervisory role of courts to correct arbitral awards for legal misconduct or errors apparent on the face, especially where awards grant damages without evidentiary basis. No new legal principle is announced, but the judgment consolidates existing precedents on judicial intervention and pendente lite interest under the Arbitration Act, 1940.

To access the original judgment, please Sign In or Subscribe.

    P. Radhakrishna Murthy v. National Buildings Construction Corporation Limited .

    The Judgment of the Court was delivered by

    V. Gopala Gowda, J.— The appellant contractor filed these civil appeals questioning the common judgment and order passed by the High Court of Karnataka dated 29-8-2002 in National Buildings Construction Corpn. Ltd. v. P. Radhakrishna Murthy wherein the appeal of National Buildings Construction Corporation Ltd. (hereinafter referred to as “NBCC”) was partly allowed and award passed by the arbitrator was modified in regard to Claims 1(a), (b), (c) and 2(a), (c), (e), (f) and (g). The High Court set aside the award of Rs 8,16,412 in regard to Claims 1(a), (b), (c) and 2(a), (c), (e), (f) and (g). Also, the rejection of claims under 1(d) and 1(e) is upheld and award of Rs 13,050 and 10,204 against Claims 2(c) and (d) are also upheld. The cross-objection filed by the contractor regarding grant of certain items of claims made by him is dismissed and consequently it is held that the contractor will be entitled to Rs 9,01,871.53 with interest at the rate of 12% per annum from 28-12-1987 till the date of deposit of payment by NBCC. Also, the amount paid by NBCC in pursuance of the interim order passed by the High Court will be adjusted to the amounts payable and if excess has been received by the contractor, then he shall repay the same within three months to NBCC. This order of the High Court is under challenge in these appeals urging various facts and legal contentions.

    2. For the purpose of appreciating the rival legal contentions urged on behalf of the parties the brief facts are stated hereunder: NBCC is a public sector company with its headquarters in New Delhi and is engaged in the business of (i) project management consultancy services for civil construction projects, (ii) civil infrastructure for power sector, and (iii) real estate development, etc. It has 10 regional/zonal offices across the country, with one such zonal/regional office at Bangalore, Karnataka. A notice was published in the newspapers by NBCC, Bangalore on 12-1-1985 with the purpose of inviting tenders for construction of five 5000 metric tonne food storage godowns comprising of Group I (civil and structural works) and Group II (internal and external electrification and sanitary work), structures at Bhimavaram, Phase II, West Godawari District, Andhra Pradesh. Pursuant to the said tender notice, the contractor submitted his tender for the said works and the offer of tender was accepted by NBCC.

    3. It is the case of the contractor that in terms of the tender notification, percentage of rate for tender works of Group I and item rate tenders for works of Group II referred to above were required to be submitted. The tender contained basic rate for work based on Central Public Works Department (CPWD) Delhi Schedule of Rates, 1981, which is called as “the 1981 DSR” for brevity.

    4. It is the case of the contractor that for any construction work, schedule of rates plays an important role in pre-construction stage like preparation of estimate. To meet this objective, CPWD is publishing DSR since 1931 on regular intervals based on the experiences and latest technologies which can be adopted in the construction sector. The DSR were revised many times in the subsequent years 1977, 1981, 1985, 1989, 1993, 1997, 2002, 2007 and 2010 based on the market rates of materials and labour prevailing during the period. The CPWD Manual is a reference document of CPWD and provides a basic framework for planning, designing and execution of construction works in CPWD. He further contends that the offer made by the contractor pursuant to the tender notice was accepted and works were awarded in his favour by NBCC on the basis of the 1981 DSR and the provisions of the CPWD Works Manual apply with all vigour to the case in hand. The contractor entered into a detailed agreement with NBCC on 26-6-1985 incorporating therein certain terms and conditions agreed upon by the parties. The following terms and conditions were agreed upon between the parties:

    (a) The rates of Group I works are governed by the 1981 DSR.
    (b) Tender was accepted at 58.5% above the 1981 DSR.
    (c) The appellant to be sanctioned an interest-free mobilisation advance of Rs 5 lakhs against bank guarantee, for which NBCC could avail 1% rebate.
    (d) Additional rebate of 0.1% could be availed by NBCC for prompt payment of bills submitted by the appellant.
    (e) Work to be completed within 10 months from the date of work order i.e 18-6-1985.

    Pursuant to the said agreement, the contractor commenced the work and completed the same.

    5. The NBCC had failed to pay the amounts due to him in terms of the agreement referred to above for all the works performed by him. In response to the various representations submitted by the contractor to NBCC, it had appointed Shri N.S.L Rao as sole arbitrator, in terms of Letter No. Engg. (CC/Gen/A/87-1363) dated 15-12-1987 to examine the claims made by the contractor by invoking Clause 25 of the agreement which empowered NBCC to appoint an arbitrator of their choice. The contractor had submitted the statement of claims on 25-1-1988 before the arbitrator claiming under various heads under Claim 1 and Claim 2 and Claims 3, 4, 5 and 6 and also prayed for interest at the rate of 24% from 28-12-1987 till the date of payment and further claimed a sum of Rs 32,500 towards the arbitration expenses.

    6. NBCC, in response to the said claims of the contractor filed its reply before the arbitrator on 22-2-1988. In the written statement filed by the NBCC before the arbitrator, it was stated for the first time that aforesaid works were undertaken by them on behalf of FCI as their agent and they were liable to pay liquidated damages to FCI on account of purported delay in completion of the works by the appellant, etc. NBCC has denied the liability to pay any amount claimed by the contractor before the arbitrator and further stated that the 1981 DSR does not govern the tender conditions of NBCC and therefore it is not liable to pay amounts to the contractor as per the said rates. The contractor filed his rejoinder statement on 25-3-1988 inter alia stating that the NBCC never disclosed that FCI was the real beneficiary and NBCC was merely acting as their agent and further stated that the disclosure made by NBCC as above came as a rude shock to the contractor.

    7. Through the relevant terms and conditions of the agreement entered into between NBCC and FCI, it has been agreed that the works shall have to follow the CPWD Manual as amended from time to time and NBCC shall be paid 9% of the construction cost as remuneration and it shall not be paid any other charges on whatever account, over and above the said remuneration. Further it was agreed that in the event of failure of execution of works in time, the liquidated damages at 1% of the contract value or part thereof subject to a maximum of 5% of the contract value or the actual amount recovered from the contractor by NBCC shall be payable to FCI. As per the aforesaid terms and conditions between NBCC and FCI, the respondent is an agent of FCI and is required to call for tenders and contract and perform in accordance with the provisions of the CPWD Manual and the 1981 DSR rates.

    8. The arbitrator, after offering opportunity to both the parties to present their respective cases in detail with all supporting documents passed an award on 17-8-1988 granting the relief in Claims 1 and 2, Items (a), (b) and (c) of Claim 1 and Items (a), (b), (e), (f) and (g) of Claim 2 which came to Rs 19,10,637.95.

    9. It is the case of the contractor that he suffered from loss of some additional amount which was spent by him on account of delay committed by NBCC in handing over sites for Godowns Nos. 10 and 11 as locations of some of the structures were changed after the work was awarded in favour of the contractor. NBCC had categorically admitted that it could not make timely payments of amounts due and that delayed payments were made. The arbitrator on the basis of submissions made by NBCC and admissions made by it, awarded a sum of Rs 8,16,412 representing 10% as normal provision for profit, etc. in respect of claims relating to Items (a), (b) and (c) of Claim 1 and Items (a), (b), (e), (f) and (g) of Claim 2. Against Item (c) of Claim 2 the arbitrator held that the claimant is also entitled to refund of Rs 13,050 deducted by NBCC from the contractors' bills for late recovery of mobilisation advance. As regards Item (d) of Claim 2, the respondents are not entitled to rebate at 2.35% on the claim of Rs 2,39,796.07. The arbitrator held that the said claim is not correct. The rebate offered by the claimant for prompt payment is 0.1% and as such he has held that claimant is entitled to refund of Rs 10,204 and accordingly awarded the said claim. The arbitrator, against Claims 1 and 2 under the aforesaid items, has awarded Rs 8,39,666 against his claim of Rs 26,93,000. Insofar as Claim 3 is concerned, by recording reasons he granted the same. As Claims 3(a) to (d) are concerned against the restricted claim of Rs 18,45,568.90, the arbitrator has awarded Rs 11,64,396.80 but he had omitted to add 58.5% over and above the 1981 DSR. Insofar as Claim 4 regarding non-reimbursement of losses due to floods is concerned, the said claim was rejected. The claim of interest at the rate of 24% per annum as Claim 5 was rejected by the arbitrator holding that the interest cannot be granted on the amounts claimed by the contractor on the basis of the judgment of this Court in Deptt. of Irrigation v. Abhaduta Jena (1988) 1 SCC 418, AIR 1988 SC 1520.

    10. As per the contractor, the award passed by the arbitrator is elaborate and takes into account numerous details and also that he had examined each of the claim put forward by the parties with reference to the record produced. The award of amount dated 17-8-1988 was granted to the contractor on the basis of cogent material placed on record and on admissions of NBCC. According to the contractor, not awarding all items under Claim 3 and rejection of Claims 4 and 5 is erroneous.

    11. Aggrieved by the award of the arbitrator, the appellant had filed petition under Sections 15, 16, 17, 30 and 33 of the Arbitration Act, 1940 before the VIth Additional City Civil Judge, Bangalore, Karnataka against NBCC to modify the award. The said petition was registered as Arbitration Case No. 16 of 1989 subsequently converted into Suit No. 5 of 2000 as provided under Rule 7 of the Karnataka High Court Rules framed under the Arbitration Act, 1940. In the proceedings, NBCC had also filed Arbitration Case No. 25 of 1988 seeking to set aside award passed by the arbitrator except to the extent of the sum of Rs 2,40,000 awarded in its favour towards liquidated damages. The said arbitration case was clubbed with Suit No. 5 of 2000. Both were disposed of by the learned City Civil Judge by a common judgment dated 24-6-2000 by elaborately dealing with all the issues and arrived at the conclusions in affirming the award of the arbitrator and modified the same to the required extent on the basis of evidence on record by recording his reasons. He also modified Claim 3 holding that the contractor is entitled for Rs 18,45,568 applying 58.5% over and above the rates quoted by the contractor. The learned Judge of the civil court has awarded interest at the rate of 16.5% from the date of reference till the realisation regarding Claim 5 after recording that the non-awarding of interest claimed by the contractor by the arbitrator is erroneous in law as the arbitrator has misread the law laid down by this Court insofar as non-awarding of interest by him is concerned. The said award was challenged by NBCC before the High Court by filing Miscellaneous First Appeal No. 4377 of 2000(AA). The contractor also preferred Cross-Objection No. 34 of 2001 aggrieved by the rejection of certain items. The appeal filed by NBCC was allowed to the extent as indicated above and the cross-objection filed by the contractor was dismissed by common judgment.

    12. These appeals were filed by the contractor urging the following grounds:

    12.1 That the High Court could not have appreciated evidence in order to arrive at a conclusion different from the one arrived at by the arbitrator. The appreciation of evidence by the arbitrator is never a matter which the court can question. In proceeding to set aside an award, the High Court cannot sit in appeal over the conclusions arrived at by the arbitrator and the learned City Civil Court. It is also not open to the High Court to sit as a court of appeal over the findings of the fora below, to find out as to how the findings were arrived at. The High Court while considering the legality of the award passed by the arbitrator which has been made the rule of the court, cannot examine the question as an appellate court.

    12.2 That though NBCC is liable to pay the Delhi Schedule of Rates of 1981 to the contractor, which governed the contract between the parties, the High Court had by a process of facile reasoning arrived at the conclusion that corrections in the 1981 DSR were made before contract documents were signed by the contractor. The High Court had totally ignored the provisions of the CPWD Manual and also the agreement executed by and between FCI and NBCC, which clearly stipulate the rates of work are governed by the 1981 DSR and that NBCC is entitled only for 9% remuneration of the construction cost.

    12.3 That NBCC having altered without authorisation the 1981 DSR on certain claims of the contractor is not entitled to rely upon the altered rates in respect of the amount payable to the appellant. Further, it is urged that the High Court in dealing with the issues involved had lost sight of the fact that irrespective of the fact that whether corrections were authorised or unauthorised in the agreement, the amounts were agreed to be paid to the appellant by NBCC in accordance with the 1981 DSR.

    12.4 That the High Court overlooked the fact that the arbitrator appointed in the matter was a retired Director General of Central Public Works Department (CPWD), Government of India and he was an expert, well versed in civil engineering and an award made by such a person should not therefore be interfered with. Being a highly skilled technical person, he has given reasons for awarding amounts under each of the claims. When the arbitrator came to the conclusion that granting 10% as normal provision for contractor's profit and overheads, the High Court could not have substituted the finding of the arbitrator by reappreciating the evidence and should not have held that the appellant is not entitled to 10% as that would not be within the jurisdiction of the High Court.

    12.5 That the law is well settled that an arbitrator is not required to give arithmetical calculation. If the reasons are adequate and clear, it is not essential for him to give a detailed reasoned decision indicating each minute step.

    12.6 That in the particular facts and circumstances of the case, it cannot be said that there is an error apparent on the face of award.

    12.7 That NBCC has filed a statement itself showing details of payment made to the appellant before the arbitrator. In the said statement at Column 8, NBCC had calculated interest @ 16.5% for delayed payments. The said statement was filed and marked as Annexure IV by the arbitrator. Therefore, NBCC cannot claim that rate of interest should not exceed 6%.

    12.8 That the High Court had failed to consider that the appellant was put to untold hardship, suffering and financial loss on account of persistent conduct of NBCC in not paying amount due to the appellant for past 27 years, despite the works having been completed as per schedule and in accordance with the agreed quality.

    13. Mr G.V.R Choudhury, the learned counsel for the appellant has contended that the judgment of the High Court is bad in law as the High Court could not have appreciated the evidence in order to arrive at a conclusion different from the one arrived at by the arbitrator. Therefore, setting aside the award of the arbitrator which is affirmed by the trial court for Rs 8,16,412 in regard to Claims 1(a), (b), (c) and 2(a), (c), (e), (f) and (g) are bad in law and the same is required to be interfered with by this Court in these appeals.

    14. In the light of the findings and reasons recorded by the High Court in the impugned judgment, we have examined the correctness of allowing the claim under the different items of Claims 1 and 2, which has been made the rule of the court by the civil court by recording valid reasons after referring to the various judgments of this Court regarding the power of the High Court to examine the misconduct of the arbitrator in passing of the award. The various judgments of this Court are referred to by the High Court viz. State of Orissa v. Kalinga Construction Co. (P) Ltd. (1970) 2 SCC 861, AIR 1971 SC 1646, K.P Poulose v. State of Kerala (1975) 2 SCC 236, AIR 1975 SC 1259, Sudarsan Trading Co. v. Govt. of Kerala (1989) 2 SCC 38, AIR 1989 SC 890, Food Corporation of India v. Joginderpal Mohinderpal (1989) 2 SCC 347, AIR 1989 SC 1263, Bijendra Nath Srivastava v. Mayank Srivastava (1994) 6 SCC 117 and Port of Madras v. Engg. Constructions Corpn. Ltd. (1995) 5 SCC 531, AIR 1995 SC 2423

    15. The High Court has rightly held that the arbitrator is not a conciliator and his duty is to decide the disputes submitted to him according to the legal rights of the parties and not according to what he may consider to be fair and reasonable. The High Court has further rightly made observation in the impugned judgment that an arbitrator cannot ignore law or misapply it, nor can he act arbitrarily, irrationally, capriciously or independent of the contract while passing the award. The courts of law have a duty and obligation to maintain purity of standards and preserve full faith and credit as well as to inspire confidence in the minds of litigants while adjudicating the claims of the parties by resorting to alternate dispute redressal method of arbitration under the provisions of the Arbitration Act.

    16. Further, the High Court with reference to Rajasthan State Mines & Minerals Ltd. v. Eastern Engg. Enterprises (1999) 9 SCC 283 and Sikkim Subba Associates v. State of Sikkim (2001) 5 SCC 629, clearly enunciated the aforesaid proposition of law for its interference with the erroneous findings of the arbitrator and the civil court in the award:

    16.1 The High Court with reference to the itemwise Claims 1(a), (b), (c) and 2(a), (b), (e), (f) and (g) examined the claims at threadbare in the backdrop of the legal position laid down by this Court in the cases referred to supra with a view to find out whether the award passed by the arbitrator in allowing certain claims was required to be interfered with on the ground that the arbitrator has committed misconduct in passing the award. The High Court has examined the correctness of the above claims awarded at Rs 8,16,412.00 as loss of profits at 10% of the contract value against Claims 1(a), (b), (c) and 2(a), (b), (e), (f) and (g) by assigning the reasons.

    16.2 In the impugned judgment, the reasons assigned by the arbitrator in allowing the said claims have been examined by the High Court with reference to the delay in handing over the sites of Godowns Nos. 10 and 11 to the contractor and locations of some structures which were changed after the work was awarded. The award of the above items of claims in favour of the contractor is found fault with by the High Court for the reason that the arbitrator neither examined any of the claims made by the contractor under Claims 1(a), (b), (c) and 2(a), (b), (e), (f) and (g) with reference to the evidence placed before the arbitrator nor has he recorded a finding as to whether the contractor in fact suffered losses as claimed by him in the aforesaid items of claims and as to whether NBCC was liable to pay to him. Therefore, it is a finding of fact recorded by the High Court on the relevant aspect holding that the arbitrator did not record reasons regarding the delay in handing over the location of the sites in favour of the contractor and rightly held that mere delay in handing over sites will not entitle the contractor to claim damages unless it is established that the same is the consequence of breach committed by the other party.

    16.3 Further, with regard to the finding recorded by the High Court as to whether the contractor had engaged skilled and unskilled labour and that they were idle, that the contractor had collected large quantity of material at original work site and had transported them to new site incurring a huge expenditure by him and that the contractor had borrowed amounts from banks and private financiers and had paid interest on such borrowed amount to them, that the contractor had engaged staff (establishment) and was spending Rs 22,566 per month for additional period of 18 months, that the contractor travelled to Delhi and other places incurring Rs 77,000 for obtaining release of bill amounts from NBCC, that the contractor had organised men, machinery and material for carrying work of the value of Rs 10 lakhs per month, that he suffered a loss of profit of 5% of the deficit turnover, that the contractor would have made a profit of Rs 9 lakhs to 10 lakhs and as the data furnished by NBCC showed that the net payment made to the contractor was Rs 89,80,540.91, the contractor should be awarded Rs 8,16,412 as 10% profits on the overheads, the High Court has rightly recorded a finding holding that the claim due to delaying the amount of 10% upon the overheads on the payment made by NBCC to the contractor is illogical.

    16.4 The said reasoning of the High Court on the above aspect of claims is perfectly legal and valid as it has assigned valid and cogent reasons in support of the said conclusions arrived at and rightly disallowed the claims.

    17. Further, the High Court has rightly held that the award of any sum in addition to the contract amount does not arise as has been awarded by the arbitrator and made the rule of the court, more particularly when the contractor did not claim 10% of loss of profits under specific claims. In that view of the matter, the claim of the contractor on the loss of profit of 10% of the total amount paid to him is rightly found fault with by the Court. The same is rightly set aside by the High Court by recording reasons stating that NBCC has claimed that the contractor has committed breach in performing his obligations by delaying the completion of the work awarded to him. The arbitrator has accepted the contention of NBCC that the work was delayed on account of the contractor and consequently awarded a sum of Rs 2,40,000 payable by the contractor to NBCC as damages on the ground that the owner of the godown (FCI) had recovered an amount of Rs 2,40,000 from NBCC on account of delay in completion of the work by the contractor. In that view of the matter, the High Court came to the correct conclusion and held that sustaining the award of amount of Rs 8,16,412 under the aforesaid items of 10% profit on the total amount made to the contractor would amount to upholding the decision of the arbitrator. This amounts to awarding damages in favour of the contractor against NBCC and the same cannot be found fault with by this Court.

    18. Another contention urged by the learned counsel on behalf of the appellant is that NBCC is liable to pay as per the 1981 DSR, which governed the contract between the parties and the High Court had by a process of facile reasoning arrived at the conclusion that corrections in the 1981 DSR were made before contract documents were signed by the contractor. It is also contended that the High Court had totally ignored the provisions of the CPWD Manual and also the agreement executed by and between FCI and NBCC, which clearly stipulate that the rates of work are governed by the 1981 DSR and that NBCC is entitled only for 9% remuneration. Much emphasis is placed upon the CPWD Manual regarding the procedure required to be followed. The relevant Clause 20.1.2 of the CPWD Manual clearly provides that:

    (1) The officer opening the tenders should encircle all corrections, cuttings, conditions, additions and overwritings and number them and attest them in red ink.
    (2) In case of number of corrections in the rate of any one item, either in words or in figures or in both, the number of corrections marked should indicate the correction serially, that is to say, in case of, say, three corrections in rates of any one item, each of these corrections should be allotted independent numbers serially and not one number to represent all the three corrections.
    (3) The number of corrections, cuttings, additions, conditions and overwritings must be clearly mentioned at the end of each relevant page of the schedule attached to the tender documents, and they should be properly attested with date. Any omission observed should also be brought out clearly on each relevant page of the schedule.

    It is contended that this has not been followed by NBCC and hence, the award passed by the arbitrator by not granting the rates on the basis of the 1981 DSR for various works is erroneous in law. On the other hand, the same was sought to be justified on behalf of NBCC. This aspect has been examined in reference to the reasoning given by the High Court in the impugned judgment.

    19. The High Court has referred to the items and description of work as per the 1981 DSR, the amounts actually paid, the quantity of work which is executed by the contractor and the amount of loss paid in terms of the 1981 DSR claim which is allowed by the arbitrator and accepted by the Court. These are carefully examined with reference to the agreement as the arbitrator has allowed Claims 3(a) to (d) and has awarded a sum of Rs 18,45,568.90 by assigning reasons and the correctness of which is examined by the High Court. The High Court examined the claims of four items referred to supra. The rates originally mentioned as per the 1981 DSR have been corrected by NBCC and the basis of the claims in the same is not mentioned and therefore, is not binding as the same is not in regard to the CPWD Manual as examined by the High Court with regard to the itemwise claim and the description in relation to the work. In this regard, the High Court with reference to the tabular statement made in the judgment, has elaborately referred to the same and examined the nature of the work executed by the contractor on the basis of contract entered into between the parties:

    19.1 The itemwise findings are recorded in the impugned judgment by the High Court on appreciation of both documents and oral evidence on record and it was held that neither is there any pleading nor any evidence on the part of NBCC before the arbitrator to demonstrate that the description of this item of work in the bill of quantities is different from the 1981 DSR Item Code No. 2.35

    19.2 It was further held that the contractor is entitled to 58.5% over basic schedule rates over and above the 1981 DSR and that the 1981 DSR rate is Rs 56.36 per square metre and also considered the scope of interference by the High Court in regard to award of the arbitrator which is limited and the Court is not sitting in appeal over the award of the arbitrator. Therefore, the Court declined to interfere on that aspect of the matter and found fault with only regarding the DSR rates.

    19.3 Regarding the DSR rates, it was found to be Rs 20 per square metre for an area which works out to Rs 6,35,512.27 as per the 1981 DSR rates and therefore the arbitrator has worked out the difference of Rs 36.36 for 17,223.24 sq m, plus Rs 3,70,604.85 as awarded by allowing the basic schedule rates over and above the 1981 DSR of the amount i.e 58.5% of Rs 6,33,512.57 and rightly held and awarded that the contractor is entitled for Rs 10,04,117.42. Accordingly, Claim 3(a) of the contractor was allowed.

    19.4 With regard to Claim 3(b) regarding the foundation and plinth, it has been contended that the rate as per the 1981 DSR is Rs 214.14 Also, the bill of quantities originally mentioned the rate as Rs 214.14 and the same has been corrected as Rs 150.69 without authorisation. The grant of said rates by the arbitrator was found fault with by the High Court holding that the arbitrator committed an error apparent on the face of the award by awarding the rates mentioned in the 1981 DSR for this item of work as Rs 214.14 by ignoring the deduction of Rs 63.45 provided in the 1981 DSR, where the brick class designation is at Rs 35. Therefore, the High Court found fault with the award of Rs 2,26,315.19 and the addition of 58.5% above the schedule rate was held to be not sustainable both on facts and in law and accordingly the same is set aside.

    19.5 In the impugned judgment, with regard to Item (c) of Claim 3, the High Court has examined the correctness of allowing the claim of the contractor and set aside the arbitrator's award of Rs 2,32,328.59 and the addition of 58.5% thereof.

    19.6 With regard to claim Item 3(d) it was held to be valid in law with reference to the 1981 DSR rates holding the original rate as Rs 438.81 which has been corrected as Rs 290. The said finding of fact, according to the High Court, is held even if it is erroneous, to be binding upon the parties for the reasons that the same is awarded under the 1981 DSR rates and hence, the award of the claims on the basis of the above rates is accepted by the arbitrator and is not open to question. Therefore, the High Court held that the contractor will be entitled to the difference at the rate of Rs 148.81, that is, the difference between Rs 438.81 and Rs 290 per square metre for 485.45 sq m which amounts to Rs 72,239.82 as has been accepted by the arbitrator. The arbitrator did not add 58.5% above the schedule rate to the amount and therefore the High Court held that the court below was justified in adding that percentage and rightly held that the contractor is entitled for Rs 1,14,500.11 under Claim 3(d).

    19.7 Further, the High Court has found fault with the award of the arbitrator in increasing the claims under Items 3(a) to (d) to Rs 18,45,568.90 and reduced the enhanced amount to Rs 10,04,117.42 plus Rs 1,14,500.11 which amounts to Rs 1,14,500.11 under Claims 3(a) and (d) and rejected the claims under Items 3(b) and (c). The challenge on the award of damages of Rs 2,40,000 against the contractor in favour of NBCC which is accepted by the trial court is rightly rejected by the High Court.

    20. The rate of interest at the rate of 16.5% on the amounts awarded by the civil court on the basis of the Constitution Bench judgment of this Court in Irrigation Deptt., Govt. of Orissa v. G.C Roy (1992) 1 SCC 508, after examining the power of the arbitrator under Section 34 CPC, with regard to award of interest, has rightly held that exercise of power by the arbitrator under Section 34 CPC in awarding the interest on the commercial rates in the absence of clause of agreement regarding non-payment of interest on the amounts due to the contractor is held to be legally valid. This Court in the above case has overruled its earlier decision in Deptt. of Irrigation v. Abhaduta Jena (1988) 1 SCC 418, AIR 1988 SC 1520 and enunciated the law regarding the award of interest on the claims awarded in favour of the contractor. It is worthwhile to refer to the relevant paragraphs of the above Constitution Bench decision, which read as hereunder: (G.C Roy case (1992) 1 SCC 508, 44 & 46)

    “43. The question still remains whether the arbitrator has the power to award interest pendente lite, and if so on what principle. We must reiterate that we are dealing with the situation where the agreement does not provide for grant of such interest nor does it prohibit such grant. In other words, we are dealing with a case where the agreement is silent as to award of interest. On a conspectus of aforementioned decisions, the following principles emerge:
    (i) A person deprived of the use of money to which he is legitimately entitled has a right to be compensated for the deprivation, call it by any name. It may be called interest, compensation or damages. This basic consideration is as valid for the period the dispute is pending before the arbitrator as it is for the period prior to the arbitrator entering upon the reference. This is the principle of Section 34 of the Civil Procedure Code and there is no reason or principle to hold otherwise in the case of arbitrator.
    (ii) An arbitrator is an alternative form (sic forum) for resolution of disputes arising between the parties. If so, he must have the power to decide all the disputes or differences arising between the parties. If the arbitrator has no power to award interest pendente lite, the party claiming it would have to approach the court for that purpose, even though he may have obtained satisfaction in respect of other claims from the arbitrator. This would lead to multiplicity of proceedings.
    (iii) An arbitrator is the creature of an agreement. It is open to the parties to confer upon him such powers and prescribe such procedure for him to follow, as they think fit, so long as they are not opposed to law. (The proviso to Section 41 and Section 3 of the Arbitration Act illustrate this point). All the same, the agreement must be in conformity with law. The arbitrator must also act and make his award in accordance with the general law of the land and the agreement.
    (iv) Over the years, the English and Indian courts have acted on the assumption that where the agreement does not prohibit and a party to the reference makes a claim for interest, the arbitrator must have the power to award interest pendente lite. Thawardas AIR 1955 SC 468 has not been followed in the later decisions of this Court. It has been explained and distinguished on the basis that in that case there was no claim for interest but only a claim for unliquidated damages. It has been said repeatedly that observations in the said judgment were not intended to lay down any such absolute or universal rule as they appear to, on first impression. Until Jena case (1988) 1 SCC 418, AIR 1988 SC 1520 almost all the courts in the country had upheld the power of the arbitrator to award interest pendente lite. Continuity and certainty is a highly desirable feature of law.
    (v) Interest pendente lite is not a matter of substantive law, like interest for the period anterior to reference (pre-reference period). For doing complete justice between the parties, such power has always been inferred.
    44. Having regard to the above consideration, we think that the following is the correct principle which should be followed in this behalf:
    Where the agreement between the parties does not prohibit grant of interest and where a party claims interest and that dispute (along with the claim for principal amount or independently) is referred to the arbitrator, he shall have the power to award interest pendente lite. This is for the reason that in such a case it must be presumed that interest was an implied term of the agreement between the parties and therefore when the parties refer all their disputes—or refer the dispute as to interest as such—to the arbitrator, he shall have the power to award interest. This does not mean that in every case the arbitrator should necessarily award interest pendente lite. It is a matter within his discretion to be exercised in the light of all the facts and circumstances of the case, keeping the ends of justice in view.
    46. In view of the above discussion we hold that in two appeals, namely, Civil Appeal No. 1403 of 1986 and Civil Appeal No. 2586 of 1985 the arbitrator acted with jurisdiction in awarding pendente lite interest and the High Court rightly upheld the award. In the result both the appeals fail and are, accordingly, dismissed but there will be no order as to costs. Even though we have held that the decision in Jena case (1988) 1 SCC 418, AIR 1988 SC 1520 does not lay down good law, we would like to direct that our decision shall only be prospective in operation, which means that this decision shall not entitle any party nor shall it empower any court to reopen proceedings which have already become final. In other words, the law declared herein shall apply only to pending proceedings.”
    (emphasis in original)

    21. The High Court has examined the rate of interest at 16.5% on the amount awarded in favour of the contractor by the civil court and has considered the contention urged on behalf of NBCC that the rate of interest awarded is excessive and also the contention that there is no contract of payment of interest on the same and alternatively contended that the interest rate should not normally exceed 6% per annum. These contentions have been seriously contested by the appellant's counsel contending that the award of interest between 15% to 18% per annum on the basis of bank lending rates should be allowed as NBCC itself has claimed interest at the rate of 18.5% per annum on the amount claimed from the contractor. Keeping the aforesaid aspect in mind and in the absence of contract with regard to the rate of interest to be awarded in favour of the contractor and having regard to the facts and circumstances of the case, the High Court has come to the right conclusion and awarded interest at the rate of 12% per annum on the amounts due to the contractor on the basis of the rate of interest paid by the banks to its customers on long-term deposits prevailing in 1988. The same cannot be found fault with by this Court for the reason that the High Court taking relevant aspects into consideration has rightly reduced the rate of interest to 12% per annum from 16.5% per annum after holding that exercise of discretionary power by the arbitrator under Section 34 CPC is a discretionary power and the same cannot be interfered with by the High Court.

    22. In our considered view the reasons recorded by the High Court on the contentious issues while examining the claims allowed by the arbitrator in the award with reasons which is affirmed by the civil court, wherein certain claims have been rightly disallowed, certain other claims accepted and yet some other claims modified by the High Court by adding certain amounts, are based on sound legal principles and after coming to the conclusion that the findings of the arbitrator and the court are erroneous and contrary to law. Therefore, the High Court has held that the impugned award passed by the arbitrator which was made the rule of the court by the civil court is erroneous in law and it amounts to misconduct. Accordingly, the High Court has rightly set aside certain claims of the contractor and affirmed the award and granted extra amount on certain claims. It has also interfered with the damages awarded in favour of NBCC and partly allowed the appeal of the respondent NBCC by allowing certain claims, setting aside certain other claims and also reducing the rate of interest at 12% from 16.5%.

    23. In our considered view, we do not find any good reason whatsoever to interfere with the same in exercise of this Court's jurisdiction in these appeals. Consequently, for the reasons stated above the appeals are dismissed, with no order as to costs.