AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Order 6 Rule 17 of the Code of Civil Procedure
  • RTI Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Order 6 Rule 17 of the Code of Civil Procedure
  • RTI Act
Smart Summary

Factual and Procedural Background

The respondents-plaintiffs are members of the appellant cooperative housing society (“the Society”). In November 2006 the Society entered into a development agreement with Respondent 4, M/s Universal Builders, for redevelopment of the Society’s property comprising CTS Nos. 978 and 979. The plaintiffs unsuccessfully challenged the redevelopment before the Cooperative Court and the Cooperative Appellate Court. They then filed Suit No. — /2010 in the City Civil Court, Mumbai, seeking various remedies concerning amalgamation of the two plots, demolition of existing/partially constructed buildings, restraint on use of balance TDR/FSI, and safeguarding of proceeds from sale of FSI/TDR.

The plaintiffs’ notice of motion for interim relief was dismissed on 4-1-2011. An Appeal from Order before the Bombay High Court also failed. The plaintiffs thereafter sought to amend the plaint by chamber summons to add a declaration that a conveyance deed dated 8-2-1989 was illegal and forged. On 3-12-2011 the City Civil Court dismissed the chamber summons, holding that the plaintiffs knew of the deed, lacked due diligence, and that the amendment was unnecessary.

In writ petition No. 130 of 2012 under Article 227, the Bombay High Court on 14-2-2012 set aside the trial court’s order and permitted the amendment. The Society obtained special leave, and the present Supreme Court appeal is against the High Court’s order.

Legal Issues Presented

  1. Whether the plaintiffs should be permitted to amend the plaint in 2011-2012 to challenge the conveyance deed of 8-2-1989, in light of Order VI Rule 17 CPC and the requirements of due diligence and limitation.
  2. Whether the Bombay High Court erred in overturning the City Civil Court’s refusal to allow the amendment.

Arguments of the Parties

Appellant (Society)

  • The plaintiffs were fully aware of the 1989 conveyance deed; Respondent 1 had been an office-bearer authorised to complete the transaction.
  • The amendment application was belated and an afterthought intended to overcome limitation.
  • The plaintiffs failed to satisfy the “due diligence” requirement under the proviso to Order VI Rule 17 CPC.
  • Allowing the amendment would prejudice the defendants and expand the scope of the suit beyond its original frame.

Respondents (Plaintiffs)

  • They allegedly learnt of the 1989 conveyance deed only on 2-3-2009 through documents obtained under the Right to Information Act.
  • The deed was executed after the death of one of the supposed executants, indicating forgery.
  • The omission to seek declaratory relief earlier was due to oversight and should be rectified to enable complete adjudication.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Supreme Court reviewed the pleadings and the proposed amendment. It found the plaintiffs’ assertion of ignorance of the 1989 conveyance deed “prima facie … not correct” because:

  • Respondent 1 had been an office-bearer of the Society and was specifically authorised by resolution to complete the 1989 transaction.
  • The plaintiffs admitted knowledge of the deed by 2009 but did not seek relevant relief when filing the suit in October 2010.

The Court held that the High Court applied only the general principles of amendment without considering these undisputed facts or the statutory bar created by the proviso to Order VI Rule 17, which requires the party to show that despite due diligence the matter could not have been raised earlier. The plaintiffs failed to demonstrate due diligence; the amendment was therefore both belated and an afterthought aimed at avoiding limitation. Consequently, the High Court’s order permitting amendment was legally unsustainable.

Holding and Implications

Appeal Allowed – High Court order setting aside dismissed; trial court order refusing amendment restored.

Direct Effect: The plaint will remain unamended; the suit proceeds on its original pleadings. The plaintiffs cannot now challenge the 1989 conveyance deed within this suit.

Broader Implication: The judgment reinforces strict application of the “due diligence” proviso to Order VI Rule 17 CPC and signals that belated amendments designed to overcome limitation hurdles are unlikely to be entertained.

To access the original judgment, please Sign In or Subscribe.

    Mashyak Grihnirman Sahakari Sanstha Maryadit v. Usman Habib Dhuka And Others

    M.Y Eqbal, J.— Leave granted. This appeal is directed against the order dated 14-2-2012 of the High Court of Judicature of Bombay passed in Usman Habib Dhuka v. Mashayak Grihnirman Sahakari Santha Maryadit WP No. 130 of 2012 whereby the order dated 3-12-2011 passed by the learned Judge of the City Civil Court, Dindoshi, Goregaon, Mumbai was set aside and the plaintiffs (Respondents 1 to 3 herein) were permitted to amend the plaint.

    2. The facts of the case are that the plaintiffs are allegedly the members of the appellant, a cooperative housing society (Defendant 1 in the suit) (in short “the Society”) which had entered into a development agreement in the month of November 2006 with Respondent 4, M/s Universal Builders (in short “the developer”) in respect of the development of the Society's property. The plaintiffs challenged the redevelopment in the Cooperative Court at Mumbai but failed. The Cooperative Appellate Court also refused to grant any relief to them. They thereafter filed a suit in the City Civil Court at Mumbai inter alia challenging amalgamation of plots bearing CTS Nos. 978 and 979 (both owned by the appellant Society), praying for directions to Municipal Corporation of Greater Mumbai as regards demolition of fully/partially constructed buildings of appellant Society on the amalgamated plot, seeking injunction restraining the Society and the developer from utilising the entire available balance TDR/FSI of the plot and praying for directions that the entire amount received/receivable by the Society by selling its balance FSI/TDR be kept in a fixed deposit to be utilised for reconstruction of the existing buildings, etc. The plaintiffs also took out notice of motion in the suit for getting interim relief seeking that the Society and the developer be restrained from carrying out any construction over the plot.

    3. The Civil Judge vide order dated 4-1-2011 rejected the notice of motion holding that the plaintiffs were aware of all the facts but they did not raise any objection on dispute; they allowed the Society and the developer to enter into agreement to obtain the amalgamation order, IOD and CC and to raise construction; and when the substantial construction had been raised the plaintiffs were seeking relief of restraining the Society and the developer from raising further construction. It was further held by the City Civil Court that the plaintiffs never raised any objection or protested against the conveyance deed dated 8-2-1989.

    4. The matter was carried in appeal before the High Court by filing appeal from order (AO), but no relief was granted by the High Court and the plaintiffs sought adjournment to seek amendment in the suit. Thereafter, the plaintiffs took out chamber summons for amending the plaint thereby seeking to incorporate the relief of declaration of conveyance deed dated 8-2-1989 as illegal, mala fide and bad in law stating that due to oversight and bona fide mistake the relief could not be sought earlier and to add certain other facts which were allegedly not incorporated in the plaint. The said application was opposed by the opposite parties on several grounds including that Order 2 Rule 2 leave was not obtained and that the decision not to challenge the conveyance at the time of filing suit was in order to get out of the clutches of limitation.

    5. The chamber summons was dismissed by the learned Judge of the City Civil Court vide order dated 3-12-2011 holding:

    “18. Thus, on going through record, prima facie it appears that the proposed amendment in the schedule of chamber summons was within the knowledge of the plaintiffs at the time of filing of the suit. However, at the time of filing the suit, they have failed to challenge execution of conveyance deed dated 8-2-1989 as mala fide and bad in law. On the contrary it has come on record that they do not want to challenge the same as the same was obtained by fraud or misrepresentation. Moreover, the plaintiffs are not party to execution of said conveyance deed nor legal heirs of deceased, Jamal Gani. So also the plaintiffs have not made the six executants of the said conveyance deed a party to the chamber summons nor sought any relief against them. It also appears from record that the plaintiffs in their chamber summons stated that due to oversight and in spite of ‘due diligence’ they could not bring the said facts on record at the time of filing of suit. But the said statement appears to be contrary to their pleading in the plaint as well as in AO. Therefore, cannot be accepted.
    20. … In the present case, I have already held that the plaintiffs were within the knowledge of proposed amendment at the time of filing of the suit. But they have failed to incorporate the same in the suit. So also the plaintiffs failed to show that in spite of the ‘due diligence’ they could not … relief against them. It also appears from record that the plaintiffs in their chamber summons stated that due to oversight and in spite of ‘due diligence’ they could not incorporate said facts in the plaint. On the contrary record shows that they have omitted to incorporate the same in the plaint. The plaintiffs also failed to show that the proposed amendment is necessary for the purpose of determining the real controversy and dispute between the parties. Therefore, observations made in the above authorities are not helpful to the plaintiffs in support of their submission.
    26. In the present case also deed of conveyance was executed in the year 1989 and prior to 1988 Plaintiff 1 was a member of the Society and also was Chairman of the Society from 1997-2002 and he was aware about execution of said conveyance deed since 1989. So also he was aware about the said facts prior to filing of the suit. In spite of the same he has failed to seek declaration….
    27. Thus, considering the facts and circumstances of the case, it appears from record that the facts mentioned in the schedule of chamber summons which the plaintiffs want to incorporate in the plaint as well as prayer clause were of the year 1989 and the plaintiffs were within knowledge of the same prior to filing of the suit. However, the plaintiffs have failed to bring the said facts before the court. So also the plaintiffs have only challenged amalgamation of Plots Nos. 978 and 979 in the suit. So also the plaintiffs were not a party to the conveyance deed nor legal heirs of deceased Jamal Gani. The plaintiffs also failed to show that the proposed amendment is necessary for determining the real question in controversy between the parties. So also the plaintiffs failed to show that in spite of ‘due diligence’ they could not bring the same on record, therefore, they are not entitled for the same. Hence they are not entitled to amend the plaint as prayed….
    … Chamber Summons No. 322 of 2011 is hereby dismissed with cost.”

    6. Aggrieved by the abovequoted order, the plaintiffs filed a writ petition under Article 227 of the Constitution of India before the High Court. The High Court vide order dated 14-2-2012 WP No. 130 of 2012 set aside the order dated 3-12-2011 of the City Civil Court permitting the plaintiffs to amend the plaint observing:

    “3. The basis upon which the opposition is considered and the order is made is not in accordance with law. A party must be entitled to aver whatever the party requires. The averments in the plaint would not show whether the case is truthful or false. That would be agitated on merits. That has been agitated upon in the interim application as also in the appeal from order.
    4. It may be clarified that amendments allowed can be defended by the defendants in a separate written statement if an earlier written statement is filed. Consequently, the impugned order disallowing the amendments sought by the plaintiff and dismissing the chamber summons with costs is required to be revised….”

    Hence, Defendant 1 Society (the appellant herein) has filed this appeal by special leave.

    7. We have heard the learned counsel appearing for both sides and have minutely gone through the pleadings of the parties and the amendment petition. From a perusal of the amendment petition, it reveals that the main ground for seeking relief is that Respondents 1 to 3-plaintiffs were allegedly not aware of the conveyance deed dated 8-2-1989. For better appreciation, Para 32(b) of the amendment petition is reproduced hereinbelow:

    “The plaintiffs say that all documents were applied under RTI and some of the same were received by the plaintiffs on 2-3-2009. The plaintiffs further say that prior thereto the plaintiffs were unaware of any such conveyance dated 8-2-1989. The plaintiffs further say that for the first time after going through the certified copies received under the RTI Act the plaintiffs came to know about such manipulation and forgery in the registered conveyance dated 8-2-1989. The plaintiffs further say that the signatures of the deceased Jamal Gani Khorajia have been got forged and documents executed and registered and a signature got manipulated through some fake persons, who must have impersonated deceased Mr Jamal Gani Khorajia. The plaintiffs say that it is the matter of common sense that when Jamal Gani Khorajia had expired on 14-8-1984 then how could he execute the said conveyance dated 8-2-1989 after 5 years from the date of his death.”

    Prima facie the aforesaid statement made in the amendment petition is not correct.

    8. Indisputably, Respondent 1-plaintiff was the office-bearer of the Society at the relevant time and by resolution taken by the Society Respondent 1 was authorised to complete the transaction. Hence, it is incorrect to allege that Respondent 1-plaintiff was not aware about the transaction of 1989. Moreover, before the institution of the suit in the year 2010, the plaintiffs allegedly came to know about the conveyance deed dated 8-2-1989, sometime in the year 2009, but relief was not sought for in the plaint which was filed much later i.e 14-10-2010. The High Court has not considered these undisputed facts and passed the impugned order on the general principles of amendment as contained in Order 6 Rule 17 of the Code of Civil Procedure. Hence we do not find any ground for allowing the amendment sought for by the plaintiffs which was not only a belated one but was clearly an afterthought for the obvious purpose to avert the inevitable consequence. The High Court has committed serious error of law in setting aside the order passed by the trial court whereby the amendment sought for was dismissed. The impugned order WP No. 130 of 2012 of the High Court cannot be sustained in law.

    9. For the aforesaid reasons, the appeal is allowed, the impugned order WP No. 130 of 2012 passed by the High Court is set aside and the order passed by the trial court is restored. No order as to costs.

    Use AI to get other relevant cases.

    Comments

    Mashyak Grihnirman Sahakari Sanstha Maryadit v. Usman Habib Dhuka And Others
    (Apr 18, 2013)