Order
1. These appeals are directed against the judgment and order dated 8-5-2001 passed by the Division Bench of the Andhra Pradesh High Court.
2. We have heard the parties at length.
3. In view of the order that we propose to pass, it is not necessary to recite the entire facts leading to the filing of the present appeal. Suffice it to say that a contract was entered into between the appellant and the respondent regarding the construction of a laboratory, an officers' room and a classroom at the Indian Railway Institute, Secunderabad. The agreement was entered into on 31-1-1981. According to the agreement, the contract was to be completed within a period of 9 months i.e up to 27-10-1981. It is stated that on request made by the respondent contractor extension of time was granted under Clause 17(3) of the general conditions of the contract. Ultimately, the contract was completed on 31-8-1983.
4. A dispute arose between the parties and the respondent made various claims under 7 heads and demanded for arbitration. The arbitrator granted award under all 7 heads. The award was filed before the City Civil Court. The City Civil Court made the award a rule of the court in respect of Claims 2 to 6 but set aside the award regarding Items 1 and 7.
5. Aggrieved thereby, the respondent filed an appeal before the Division Bench of the High Court and by the impugned order the Division Bench maintained the order of the civil court with regard to Item 7. However, the Division Bench allowed the claim under Item 1. Hence, the present appeals.
6. The dispute now to be resolved is confined only to Item 1 of the claim. To answer this question, we may refer to Clause 17(3) of the contract. Clause 17(3) reads:
“17. (3) In the event of any failure or delay by the Railway to hand over to the contractor possession of the lands necessary for the execution of the works or to give the necessary notice to commence the works or to provide the necessary drawings or instructions or any other delay caused by the Railway due to any cause, whatsoever, the said failure or delay shall in no way effect or vitiate the contract or alter the character thereof or entitle the contractor to damages of compensation thereof but in any such case, the Railway may grant such extension or extensions of the completion date as may be considered reasonable.”
Clause 17(3) thus clearly shows that if there is delay by the Railways the term of the contract can be extended as has been done in the present case. However, the contractor shall not be entitled to damages or compensation.
7. A similar question raised before this Court was considered by a three-Judge Bench of this Court in Ch. Ramalinga Reddy v. Superintending Engineer (1999) 9 SCC 610. This Court held in that case that if the contract is extended under the terms of the contract, compensation cannot be awarded by the arbitrator. The aforesaid judgment has been followed in another decision of this Court in Northern Railway v. Sarvesh Chopra (2002) 4 SCC 45.
8. The learned counsel for the respondent referred to the judgment rendered by this Court in K.R Raveendranathan v. State of Kerala (1998) 9 SCC 410 (1). The said decision is not applicable in the facts of the present case.
9. For the reasons aforestated, the case in hand is squarely covered by the two decisions of this Court. In the result, the order of the High Court is not tenable in law and is accordingly set aside.
10. The appeals are allowed. No costs.