AMICUS AI
Citation Codes
Neutral Citations
2006 INSC 569
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 34(3) of the Arbitration and Conciliation Act, 1996
  • Rule 2 of Order 23 of the Code of Civil Procedure, 1908 (5 of 1908)
  • The Arbitration and Conciliation Act, 1996
  • Section 43 of the Arbitration and Conciliation Act, 1996
  • Section 34 of the Arbitration and Conciliation Act, 1996
  • Section 14 of the Limitation Act, 1963
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2006 INSC 569
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 34(3) of the Arbitration and Conciliation Act, 1996
  • Rule 2 of Order 23 of the Code of Civil Procedure, 1908 (5 of 1908)
  • The Arbitration and Conciliation Act, 1996
  • Section 43 of the Arbitration and Conciliation Act, 1996
  • Section 34 of the Arbitration and Conciliation Act, 1996
  • Section 14 of the Limitation Act, 1963
Smart Summary

Factual and Procedural Background

The respondent, an insured party, invoked Condition 7 of an insurance policy and initiated arbitration. Each side appointed an arbitrator, who in turn appointed a presiding arbitrator. On 10-10-2003 a majority award granted the respondent Rs 2,12,49,336 with 18% future interest, while a minority award fixed liability at Rs 1,23,08,104 with different interest and costs.

The appellant Insurance Company challenged both awards under Section 34 of the Arbitration and Conciliation Act, 1996:

  • It first filed a Section 34 petition in the Bombay High Court, which was dismissed for want of jurisdiction.
  • A fresh Section 34 petition, accompanied by an application under Section 14 of the Limitation Act, 1963 (seeking exclusion of time spent in the wrong forum), was filed before the District Court, Nagpur. The District Court rejected the Section 14 plea and dismissed the Section 34 petition.
  • The appellant’s writ petition against that dismissal was rejected by the Bombay High Court (Nagpur Bench) on 21-12-2005, relying on H.M.P. Engineers Ltd. v. Rallis India Ltd.
  • The present civil appeal challenges the High Court’s order.

Legal Issues Presented

  1. Whether Section 14 of the Limitation Act, 1963, which permits exclusion of time spent prosecuting a remedy in a court lacking jurisdiction, applies to an application under Section 34 of the Arbitration and Conciliation Act, 1996.
  2. Consequently, whether the appellant’s Section 34 petition before the District Court, Nagpur was filed within the permissible limitation period after applying Section 14.

Arguments of the Parties

Appellant (Insurance Company)

  • Relied on the Supreme Court decision in State of Goa v. Western Builders, (2006) 6 SCC 239, contending that Section 14 of the Limitation Act is applicable to proceedings under Section 34 of the Arbitration Act.
  • Asserted that the Bombay High Court’s reliance on H.M.P. Engineers Ltd. v. Rallis India Ltd. was incorrect in light of the later binding precedent of Western Builders.

Respondent (Insured)

  • Did not seriously oppose the applicability of Section 14 of the Limitation Act after the clarification in Western Builders.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
H.M.P. Engineers Ltd. v. Rallis India Ltd. (2003) 4 Mah LJ 931 Held that Section 14 of the Limitation Act is not applicable to Section 34 proceedings under the Arbitration Act. The Supreme Court held that reliance on this case by the High Court was erroneous in view of later binding precedent.
State of Goa v. Western Builders (2006) 6 SCC 239 Clarified that Section 14 of the Limitation Act applies to applications under Section 34 of the Arbitration Act. The Supreme Court followed this authority and applied Section 14, overruling the High Court’s contrary view.

Court's Reasoning and Analysis

The Court noted that Section 43 of the Arbitration and Conciliation Act, 1996 expressly makes the Limitation Act applicable to arbitration-related court proceedings. Referring to its own recent pronouncement in State of Goa v. Western Builders, the Court reiterated that:

  • There is no express exclusion of Section 14 within the Arbitration Act.
  • Section 14 must therefore be available to a party who, with due diligence and in good faith, prosecuted a remedy before a court that ultimately lacked jurisdiction.

Because the District Court and the High Court had refused to consider Section 14, their orders were legally unsustainable. The respondent’s counsel did not dispute this legal position, facilitating the Court’s conclusion.

Holding and Implications

HELD: The High Court’s judgment dated 21-12-2005 is set aside; the matter is remitted to the District Court, Nagpur.

Implications:

  • The District Court must now decide, on merits, the appellant’s objections under Section 34(3) of the Arbitration Act after applying Section 14 of the Limitation Act. It has been directed to dispose of the case within six months.
  • The appellant Insurance Company must, within one month, deposit Rs 1,70,65,170 (the amount awarded in the minority award) to the credit of Arbitration Petition No. 164 of 2005; the District Court shall invest the sum in a nationalised bank.
  • The respondent is granted liberty to apply for withdrawal of the deposited amount, which the District Court will consider on merits.
  • No finding has been rendered on the substantive objections to the arbitral awards; thus, no new precedent on those issues has been created. The decision primarily clarifies the procedural application of limitation law to arbitration matters.
To access the original judgment, please Sign In or Subscribe.

    United India Insurance Co. Ltd. v. J.A Infra Structure (P) Ltd. .

    Dr. Ar. Lakshmanan, J.— Leave granted.

    2. Heard learned counsel appearing on behalf of both sides.

    3. This appeal is directed against the final judgment and order dated 21-12-2005 passed by the High Court of Judicature at Bombay, Nagpur Bench in Writ Petition No. 5454 of 2005. The respondent is the insured. The respondent invoked arbitration as per Condition 7 of the Policy. The respondent appointed one Shri V.P Shah as arbitrator. The appellant Insurance Company appointed Shri A. Sankaran as arbitrator. Both the arbitrators appointed Shri B.R Mehta as presiding arbitrator. On 10-10-2003, the majority award was passed by the Presiding Arbitrator, Shri B.R Mehta and Co-Arbitrator, Shri V.P Shah awarding Rs 2,12,49,336.00 (Rupees two crores twelve lakhs forty-nine thousand three hundred thirty-six only) with future interest @ 18%. The minority award was passed by Co-Arbitrator, Shri A. Sankaran who awarded a sum of Rs 1,23,08,104 and interest of Rs 43,57,066 up to 10-10-2003 and cost of arbitration of Rs 4 lakhs and further interest on the aggregate of all these amounts @ 15% from the date of award till the date of payment of decree, whichever is earlier.

    4. Aggrieved by both the awards, the appellant filed arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996 (for short “the Act”) in the High Court of Judicature at Bombay. The petition was listed before a learned Single Judge of the High Court who after hearing the parties dismissed the petition for want of jurisdiction. The appellant Insurance Company thereafter filed a fresh petition under Section 34 of the Act before the District Court, Nagpur along with application under Section 14 of the Limitation Act on 17-1-2005. The District Court, Nagpur dismissed the application filed by the appellant Insurance Company under Section 14 of the Limitation Act and consequently, the application filed under Section 34 of the Act also stood dismissed. Aggrieved against the order passed by the District Court, the appellant again filed a writ petition before the High Court of Bombay at Nagpur Bench which was also dismissed on 21-12-2005. Aggrieved by the said judgment dated 21-12-2005, the appellant preferred the above appeal.

    5. The High Court by the impugned judgment dismissed Writ Petition No. 5454 of 2005 following the earlier judgment of the Bombay High Court in H.M.P Engineers Ltd. v. Rallis India Ltd. (2003) 4 Mah LJ 931 Learned counsel for the appellant submitted that in view of the recent judgment of this Court in State of Goa v. Western Builders JT (2006) 6 SC 125, (2006) 6 SCC 239, the view taken by the Bombay High Court in H.M.P Engineers Ltd. v. Rallis India Ltd. (2003) 4 Mah LJ 931 and followed by the High Court in the impugned judgment is not correct.

    6. This Court in the judgment in State of Goa v. Western Builders JT (2006) 6 SC 125, (2006) 6 SCC 239 was considering the question as to what extent Section 14 of the Limitation Act, 1963 which deals with exclusion of time spent in prosecuting the remedy before wrong forum is applicable to the Arbitration and Conciliation Act, 1996 or not. Section 14 of the Limitation Act reads thus:

    “14. Exclusion of time of proceeding bona fide in court without jurisdiction.—(1) In computing the period of limitation for any suit the time during which the plaintiff has been prosecuting with due diligence another civil proceeding, whether in a court of first instance or of appeal or revision, against the defendant shall be excluded, where the proceeding relates to the same matter in issue and is prosecuted in good faith in a court which, from defect of jurisdiction or other cause of a like nature, is unable to entertain it.
    (2) In computing the period of limitation for any application, the time during which the applicant has been prosecuting with due diligence another civil proceeding, whether in a court of first instance or of appeal or revision, against the same party for the same relief shall be excluded, where such proceeding is prosecuted in good faith in a court which, from defect of jurisdiction or other cause of a like nature, is unable to entertain it.
    (3) Notwithstanding anything contained in Rule 2 of Order 23 of the Code of Civil Procedure, 1908 (5 of 1908), the provisions of sub-section (1) shall apply in relation to a fresh suit instituted on permission granted by the court under Rule 1 of that Order, where such permission is granted on the ground that the first suit must fail by reason of a defect in the jurisdiction of the court or other cause of a like nature.”

    7. This Court also in para 13 (SCC para 14) of the said judgment has observed that Section 14 of the Limitation Act has been excluded by this special enactment i.e the Arbitration and Conciliation Act, 1996 and that Section 43 of the Arbitration and Conciliation Act, 1996 clearly says that the Limitation Act, 1963 shall apply to arbitration as it applies to the proceedings in the court. This Court has also followed few other judgments of this Court in support of the view taken by them. In the concluding portion this Court has observed that in the present context, there are no two opinions in the matter that the Arbitration and Conciliation Act, 1996 does not expressly exclude the applicability of Section 14 of the Limitation Act and that the prohibitory provision has to be construed strictly.

    8. In the result, this Court was of the opinion that the view taken by the Court below excluding the applicability of Section 14 in the said proceeding was not correct. This Court held that Section 14 of the Limitation Act, 1963 was applicable in the Arbitration and Conciliation Act, 1996 and accordingly this Court set aside the judgments and order and remanded the matters back to the District Court for deciding the application under Section 14 of the Limitation Act on merit. In view of the judgment in State of Goa v. Western Builders JT (2006) 6 SC 125, (2006) 6 SCC 239 the counsel for the respondent has not seriously opposed to the applicability of Section 14 of the Limitation Act which deals with exclusion of time spent in prosecuting the remedy before the wrong forum bona fide. Therefore, we set aside the order passed by the High Court and remit the matter back to the District Court, Nagpur to decide the objections raised by the appellant Insurance Company under Section 34(3) of the Arbitration and Conciliation Act, 1996 and decide the same on merit after affording opportunity to the respondent herein.

    9. Since the matter is pending for a very long time before one forum or the other, we direct the District Court, Nagpur to dispose of the matter within six months from today.

    10. We make it clear that we have not decided the objections and other issues raised on merits.

    11. The civil appeal stands disposed of accordingly with the above observation. However, pending disposal of the matter by the District Court, we direct the appellant Insurance Company to deposit the amount awarded by the Arbitrator Shri A. Sankaran to the credit of Arbitration Petition No. 164 of 2005 on the file of the District Court, Nagpur. The appellant Insurance Company shall now deposit Rs 1,70,65,170 (Rupees one crore seventy lakhs sixty-five thousand one hundred seventy only) to the credit of Arbitration Petition No. 164 of 2005 within one month from today. On such deposit, the District Court shall invest the same in a nationalised bank in a short-term deposit.

    12. We also reserve liberty to the respondent to move an application for withdrawal of the said amount before the said court and if such an application is filed, the District Court is directed to dispose of the same on merits and in accordance with law.

    Use AI to get other relevant cases.

    Comments

    United India Insurance Co. Ltd. v. J.A Infra Structure (P) Ltd. .
    (Aug 30, 2006)