AMICUS AI
Citation Codes
Neutral Citations
2005 INSC 322
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • the Electricity (Supply) Act, 1948 and the rules framed thereunder
  • Article 226 of the Constitution
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2005 INSC 322
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • the Electricity (Supply) Act, 1948 and the rules framed thereunder
  • Article 226 of the Constitution
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Smart Summary

Factual and Procedural Background

The judgment decides three consolidated civil appeals arising from separate writ petitions filed in the High Court of Orissa under Article 226 of the Constitution. In each writ petition, relatives of persons who died by electrocution sought compensation from the State-owned electricity utility (GRIDCO or its predecessors):

  • Civil Appeal No. 1726 of 1999 (OJC No. 13281 of 1997) – A live, illegally hooked, un-insulated wire lay on the ground after detaching from a private lift-irrigation (LI) point. A bullock was electrocuted; three villagers who tried to rescue each other also died. The police and GRIDCO officials recorded that the wire had been unlawfully drawn by third parties without GRIDCO’s knowledge. The High Court nonetheless awarded Rs 2,70,000.
  • Civil Appeal No. 4552 of 2005 @ SLP (C) No. 9788 of 1998 (OJC No. 6290 of 1994) – During a heavy storm on 10-5-1984 an LT conductor snapped. Before the utility learnt of the break, the deceased came into contact with it the next morning and died. A prior money suit (No. 199/1987) had been dismissed in 1992. Ten years after the accident, the claimant filed a writ petition which the High Court allowed, granting Rs 40,000.
  • Civil Appeal No. 4560 of 2005 @ SLP (C) No. 5591 of 1999 (OJC No. 4247 of 1997) – On 28-5-1992 a wire allegedly snapped and fell on the respondent’s husband while he was returning from a polling station, leading to his death. GRIDCO denied that any wire had fallen and contended that the writ petition raised disputed facts unsuitable for writ jurisdiction. The High Court nevertheless ordered payment of Rs 1,50,000.

The Supreme Court had earlier decided a batch of ten similar appeals in Chairman, GRIDCO v. Sukamani Das (1999) 7 SCC 298, holding that compensation claims involving disputed negligence should ordinarily proceed in civil suits, not writ petitions. The three present appeals, delayed earlier because service had not been completed, were heard and decided in light of that precedent.

Legal Issues Presented

  1. Whether the High Court, in exercise of its jurisdiction under Article 226, could award compensation for electrocution deaths when the electricity board specifically denied negligence and raised disputed questions of fact.
  2. Whether prior dismissal of a civil suit and long delay barred the subsequent writ petition seeking identical relief.

Arguments of the Parties

Appellants’ Arguments (Electricity Board / GRIDCO)

  • The deaths were not caused by any negligence on their part but by (a) illegal hooking by third parties, (b) acts of God such as storm and rain, or (c) negligence of the victims themselves.
  • Maintenance checks had been performed; the snapping of conductors occurred despite reasonable care.
  • Article 226 is not an appropriate forum to try tort claims involving disputed facts; claimants must prove negligence in a civil court.
  • In one case, a civil suit on the same cause of action had already been dismissed; the writ petition filed a decade later was barred by delay and principles analogous to res judicata.
  • They relied on Chairman, GRIDCO v. Sukamani Das (1999) 7 SCC 298 and W.B. SEB v. Sachin Banerjee (1999) 9 SCC 21.

Respondents’ Arguments (Claimants)

  • Snapping of a live wire and consequent electrocution is sufficient to fasten strict liability on the supplier of electricity.
  • They relied on the later decision in M.P. Electricity Board v. Shail Kumari (2002) 2 SCC 162, where the Board was held liable after a live wire fell on a rain-soaked public road.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Chairman, GRIDCO v. Sukamani Das (1999) 7 SCC 298 Writ jurisdiction should not be invoked to decide tort claims with disputed facts; negligence must first be proved by claimant. Treated as directly governing. Court applied it to hold that the High Court erred in awarding compensation without a trial.
W.B. SEB v. Sachin Banerjee (1999) 9 SCC 21 No negligence where electrocution results from illegal hooking by third parties. Cited to reinforce that utilities cannot automatically be held liable when illegal hooking is proved.
M.P. Electricity Board v. Shail Kumari (2002) 2 SCC 162 Electricity Board can be liable for snapped live wire; strict liability affirmed where negligence found by trial court. Distinguished. Supreme Court noted that in Shail Kumari negligence was factually established in a civil suit, unlike the present writ petitions.
H.S.E.B v. Ram Nath (2004) 5 SCC 793 Writ petition may succeed where the utility does not dispute material facts about negligence. Distinguished on ground that, unlike Ram Nath, GRIDCO had specifically denied negligence in the present cases.

Court's Reasoning and Analysis

The Supreme Court reiterated the principle laid down in Sukamani Das that compensation claims founded on tortious negligence, where liability is disputed, require a full evidentiary trial in a civil court. The Court’s analytical steps were:

  1. Existence of disputed facts. GRIDCO had categorically denied negligence, asserting illegal hooking, act of God, or other intervening causes. The High Court recorded no finding of negligence.
  2. Inappropriateness of writ jurisdiction. Determining negligence needs oral and documentary evidence, cross-examination, and possibly expert testimony—procedures unavailable in a summary writ proceeding.
  3. Precedential constraint. The earlier binding decision in Sukamani Das squarely covered the present factual matrix; the High Court had failed to follow it.
  4. Distinction of contrary authorities. The later decision in Shail Kumari was inapplicable because negligence there had been found in a civil suit; likewise Ram Nath involved undisputed facts.
  5. Delay and prior litigation. In Civil Appeal No. 4552 of 2005, the writ petition was filed ten years after the accident and after dismissal of a prior suit, rendering the writ doubly untenable.
  6. Equitable consideration. Although the High Court lacked jurisdiction to award compensation, amounts already disbursed need not be recovered given the passage of time.

Holding and Implications

Holding: The Supreme Court ALLOWED the appeals and SET ASIDE the judgments of the High Court awarding compensation. The civil appeals were disposed of with no order as to costs; monies already paid to the respondents are not to be recovered.

Implications: The decision re-affirms that tortious claims against electricity boards involving contested negligence cannot ordinarily be resolved through writ petitions. Claimants must resort to properly constituted civil suits where factual disputes can be tried. The judgment does not create new precedent but strengthens adherence to the earlier ruling in Sukamani Das.

To access the original judgment, please Sign In or Subscribe.

    Sdo, Grid Corporation Of Orissa Ltd. And Others v. Timudu Oram .

    Ashok Bhan, J.— Leave granted in Special Leave Petitions (C) Nos. 5591 of 1999 and 9788 of 1998.

    2. In this batch of three appeals the question which arises for determination is as to whether the High Court was justified in exercising its power under Article 226 of the Constitution and awarding compensation to the respondent-writ petitioners even though the appellants — who were the respondent in the writ petition — had denied the liability on the ground that the deaths had not occurred as a result of their negligence but because of the negligence of the respondent themselves or of an act of God or because of an act of some other persons. These appeals were ordered to be listed along with the case of Chairman, Grid Corpn. of Orissa Ltd. (GRIDCO) v. Sukamani Das (1999) 7 SCC 298 but were delinked as the service had not been completed on the respondent. The Bench disposed of the batch of 10 appeals and these appeals were ordered to be heard after service is complete.

    3. The facts of Civil Appeal No. 1726 of 1999 arising against the order passed by the High Court of Orissa in writ petition bearing OJC No. 13281 of 1997 are:

    One Themba Bhim, a co-villager of the deceased had taken power supply to his LI point. Some other villagers of Village Khuntagaon viz. Ralbindra Oram, Fatha Oram, Gobardhan Kisan and Etwa Oram had illegally taken power supply without the knowledge of GRIDCO Authorities by use of a hook from the LI point to their houses by means of an uninsulated GI wire. On 22-8-1997 the unauthorised GI wire, through which the line was illegally taken, got disconnected and fell on the ground. At that time the father of the respondent Japana Oram was coming that way with his bullock. The bullock came in contact with the live GI wire and as a result thereof got electrocuted. On finding this Japana Oram tried to rescue the bullock and got electrocuted. His wife came to his rescue and hearing her cries her daughter Sabi Oram, while trying to detach her parents was also electrocuted. The incident was reported to the local police by the villagers of Khuntagaon on 23-8-1997 wherein the fact of illegal hooking and death due to electrocution was admitted. The local police enquired into the matter and reported the cause and manner of death as stated above. On 23-8-1997 the Junior Engineer of GRIDCO sent a telegram to the Chief Electrical Inspector, Government of Orissa, for necessary action at his end. The SDO, Electrical Sub-Division, Ujalapur on 24-8-1997 also submitted a report in which the cause of death was mentioned to be due to illegal electric connection taken through hook. On 16-9-1997 the respondent herein filed a writ petition in the High Court of Orissa at Cuttack being OJC No. 13281 of 1997 claiming compensation for the death of the deceased. Counter-affidavit was filed by the appellants herein. In the counter-affidavit it was contended that deaths that had occurred were due to the negligence of the deceased themselves and the electric live wire belonging to and maintained by GRIDCO had not snapped and, therefore, the appellants were not liable to pay any compensation. By the impugned judgment the High Court disposed of the writ petition with a direction to the appellants to pay a sum of Rs 2,70,000 by way of compensation to the respondent herein.

    4. In Civil Appeal No. 4552 of 2005 [@ SLP (C) No. 9788 of 1998] arising from OJC No. 6290 of 1994, on the night of 10-5-1984, due to heavy storm and rain, one LT conductor snapped. This happened despite the fact that the appellants had taken adequate steps to maintain the supply line properly. Before the storm and rain on the night of 10-5-1984 the supply line was checked by the Junior Engineer and the lineman in the regular course of checking. However, before information about the snapping of the line was received by the appellants, the deceased while moving in the morning came in contact with the snapped electric line and became unconscious. He was taken to the hospital where he was declared dead. The respondent had filed a suit in the Court of Subordinate Judge, Jajpur against the appellants claiming compensation for the death of the deceased being Money Suit No. 199 of 1987. The said suit was dismissed by the Subordinate Judge, Jajpur vide order dated 16-5-1992. Thereafter, after a delay of 10 years, in the year 1994 the present writ petition was filed in the High Court. The High Court ignoring the fact that the suit filed on the same cause of action had already been dismissed, awarded compensation of Rs 40,000 to the respondent. According to the appellants, the death occurred not because of their fault but due to the act of God.

    5. In Civil Appeal No. 4560 of 2005 [@ SLP (C) No. 5591 of 1999] arising from OJC No. 4247 of 1997, the respondent filed a writ petition in the High Court of Orissa at Cuttack inter alia on the allegations that on 28-5-1992 at about 12.00 noon while her husband was returning from the polling station, a live electric wire suddenly snapped and fell on him as a result of which he received severe electrical burn injuries and lost his senses. Some local people took him to S.D Hospital, Jajpur but on the way he breathed his last. The respondent alleged that the accident had occurred due to the negligence of the appellants and claimed compensation for the death of the deceased. In the counter-affidavit filed by the appellants, it was inter alia submitted that generation and distribution of energy are regulated through statutory provisions, namely, the Electricity (Supply) Act, 1948 and the rules framed thereunder. The family of the deceased did not lodge a complaint/FIR in the police station. According to the appellants the husband of the respondent may have died due to electric shock but it was not due to the fall of the electric wire. The allegation made in the writ petition that death occurred due to negligence of the appellants was denied. It was stated that there was no negligence on the part of the appellants. It was also submitted that the writ petition involved disputed questions of fact which could not be decided in exercise of writ jurisdiction under Article 226 of the Constitution. The High Court allowed the writ petition and commanded the appellants to pay a sum of Rs 1,50,000 towards compensation to the respondent.

    6. In Chairman, Grid Corpn. of Orissa Ltd. (GRIDCO) (1999) 7 SCC 298 with which case these appeals were listed for hearing but could not be heard for want of service, this Court took the view that the High Court committed an error in entertaining the writ petitions under Article 226 of the Constitution and were not fit cases for exercising the jurisdiction under Article 226 of the Constitution. It was held that actions in tort and negligence were required to be established initially by the claimants. The mere fact that the wire of electric transmission line belonging to the appellants had snapped and the deceased had come into contact with it and died by itself was not sufficient for awarding compensation. The Court was required to examine as to whether the wire had snapped as a result of any negligence on the part of the appellants, as a result of which the deceased had come in contact with the wire. In view of the defence raised and the denial by the appellants in each of the cases, the appellants deserved an opportunity to prove that proper care and precautions were taken in maintaining the transmission line and yet the wires had snapped because of the circumstances beyond their control or unauthorised intervention of third parties. Such disputed questions of fact could not be decided in exercise of jurisdiction under Article 226 of the Constitution. That the High Court could not come to the conclusion that the defence raised by the appellants had been raised only for the sake of it and there was no substance in it. In para 6 it was observed thus:

    “6. In our opinion, the High Court committed an error in entertaining the writ petitions even though they were not fit cases for exercising power under Article 226 of the Constitution. The High Court went wrong in proceeding on the basis that as the deaths had taken place because of electrocution as a result of the deceased coming into contact with snapped live wires of the electric transmission lines of the appellants, that ‘admittedly/prima facie amounted to negligence on the part of the appellants’. The High Court failed to appreciate that all these cases were actions in tort and negligence was required to be established firstly by the claimants. The mere fact that the wire of the electric transmission line belonging to Appellant 1 had snapped and the deceased had come in contact with it and had died was not by itself sufficient for awarding compensation. It also required to be examined whether the wire had snapped as a result of any negligence of the appellants and under which circumstances the deceased had come in contact with the wire. In view of the specific defences raised by the appellants in each of these cases they deserved an opportunity to prove that proper care and precautions were taken in maintaining the transmission lines and yet the wires had snapped because of circumstances beyond their control or unauthorised intervention of third parties or that the deceased had not died in the manner stated by the petitioners. These questions could not have been decided properly on the basis of affidavits only. It is the settled legal position that where disputed questions of facts are involved a petition under Article 226 of the Constitution is not a proper remedy. The High Court has not and could not have held that the disputes in these cases were raised for the sake of raising them and that there was no substance therein. The High Court should have directed the writ petitioners to approach the civil court as it was done in OJC No. 5229 of 1995.”

    7. Similar view was taken by this Court in W.B SEB v. Sachin Banerjee (1999) 9 SCC 21. In the said case it was observed as under:

    “The only grievance of the petitioners relates to an observation in the impugned judgment that two victims had died because of the negligence of the petitioner State Electricity Board. Looking to the fact that the two victims were electrocuted because of an illegal hooking for the purpose of theft of electricity, the petitioners cannot be held guilty of negligence although they may have stated that there is a need for conducting dehooking raids more frequently.”

    8. As against this counsel for the respondent cited a later judgment of this Court in M.P Electricity Board v. Shail Kumari (2002) 2 SCC 162 wherein this Court has taken the view that the Electricity Board could be fastened with the liability in a case in which the live wire snapped and fell on the public road which was partially inundated with rainwater. The observation made by this Court in the aforesaid case would not be applicable to the facts of the present case as in the said case a suit had been filed in which a finding of negligence was recorded by the trial court against the Board. The trial court after coming to the conclusion that the respondents were entitled to a compensation of Rs 4.34 lakhs non-suited the respondents solely on the premise that the claimants had failed to prove their liability for such compensation. The High Court in the said case had recorded a finding:

    “Therefore, the defences put up by MPEB are absolutely without any basis and do not reflect the real position at the spot, rather attempt has been made to conceal the real position in order to avoid responsibility and liability for payment of compensation.”

    On these facts, this Court came to the conclusion that the claimants were entitled to the compensation. Counsel for the appellants also cited a judgment in H.S.E.B v. Ram Nath (2004) 5 SCC 793 in which a similar view was taken. In the said case it was observed by the Bench that where disputed questions of fact were involved writ petition would not be the proper remedy but since there was no denial in the written statement that wires were loose and drooping and the claimant had asked the Board to tighten the wires, the Board was held liable to pay the compensation. This finding was recorded because the supplier of electricity did not controvert the facts alleged by the respondent writ petitioner. Disputed questions of facts were not involved and as a result of which the finding recorded by the High Court was upheld.

    9. In the present case, the appellants had disputed the negligence attributed to it and no finding has been recorded by the High Court that GRIDCO was in any way negligent in the performance of its duty. The present case is squarely covered by the decision of this Court in Chairman, Grid Corpn. of Orissa Ltd. (GRIDCO) (1999) 7 SCC 298. The High Court has also erred in awarding compensation in Civil Appeal No. 4552 of 2005 [@ SLP (C) No. 9788 of 1998]. The subsequent suit or writ petition would not be maintainable in view of the dismissal of the suit. The writ petition was filed after a lapse of 10 years. No reasons have been given for such an inordinate delay. The High Court erred in entertaining the writ petition after a lapse of 10 years. In such a case, awarding of compensation in exercise of its jurisdiction under Article 226 of the Constitution cannot be justified.

    10. As the High Court had exercised its power under Article 226 of the Constitution without properly appreciating the nature of its jurisdiction, the impugned judgments deserve to be set aside. However, in view of the long lapse of time the appellants will not recover the amounts already paid to the respondents. The civil appeals are disposed of accordingly. No costs.