  • Section 47 of the Code of Civil Procedure
  • Section 115 of the Code of Civil Procedure, 1908
  • Article 226 of the Constitution of India
  • Section 34 of the Arbitration and Conciliation Act, 1996
  • The Arbitration Act, 1940
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 47 of the Code of Civil Procedure
  • Section 115 of the Code of Civil Procedure, 1908
  • Article 226 of the Constitution of India
  • Section 34 of the Arbitration and Conciliation Act, 1996
  • The Arbitration Act, 1940
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Smart Summary

Factual and Procedural Background

The appellant’s tender for construction of an indoor stadium at Gulbarga University was accepted and a contract dated 21-5-1993 was executed for an estimated cost of Rs 91,88,909. After completion of the work, disputes arose and, pursuant to clause 30 of the contract, the Superintending Engineer, PWD, Gulbarga Circle, acted as arbitrator. An award dated 30-7-1999 was rendered, but no copy was initially supplied to the appellant, prompting a writ petition under Article 226 that resulted in delivery of a certified copy.

The appellant sought execution of the award before the Principal Civil Judge (Senior Division), Gulbarga. Gulbarga University objected under Section 47 CPC, but the executing court rejected the objection on 19-10-2000. The University filed Civil Revision Petition No. 3719 of 2000 under Section 115 CPC before the Karnataka High Court, contending that clause 30 was not an arbitration agreement. The High Court accepted that contention and set aside the execution proceedings. The present appeal challenges that High Court decision.

Legal Issues Presented

  1. Whether clause 30 of the contract constitutes a valid “arbitration agreement” within the meaning of the Arbitration Act, 1940.
  2. If clause 30 is a valid arbitration agreement, whether the award rendered by the Superintending Engineer is executable.

Arguments of the Parties

Appellant’s Arguments

  • Clause 30 satisfies all criteria of an arbitration agreement; therefore, the High Court erred in holding otherwise.
  • The Superintending Engineer is an independent person and functioned as arbitrator after giving both sides an opportunity to present claims and counter-claims.
  • Principles of natural justice are implicitly complied with; specific recital of hearing or evidence is unnecessary.

Respondent’s Arguments

  • Relied on Bharat Bhushan Bansal v. U.P. Small Industries Corpn. Ltd. (1999) 2 SCC 166 to assert that clause 30 is merely a decision-making clause, not an arbitration agreement.
  • Contended that disputes were never properly referred to arbitration and that the University lacked adequate opportunity to lead evidence.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Bihar State Mineral Development Corpn. v. Encon Builders (I) (P) Ltd., (2003) 7 SCC 418 Enumerated essential elements of an arbitration agreement: (i) existing or future disputes, (ii) intent to submit to private tribunal, (iii) agreement in writing to be bound, (iv) consensus ad idem. Court applied these elements to clause 30 and held that each requirement is satisfied.
Bharat Bhushan Bansal v. U.P. Small Industries Corpn. Ltd., (1999) 2 SCC 166 Held that clauses 23 and 24 in that contract did not amount to an arbitration agreement because they lacked intention to arbitrate and procedural safeguards. Distinguished on facts; unlike the clauses in that case, clause 30 names a specific independent decision-maker (Superintending Engineer) and therefore qualifies as an arbitration clause.

Court's Reasoning and Analysis

1. The Court examined clause 30 and found that it vests the Superintending Engineer with authority to decide “any dispute” arising out of the contract and makes his decision “final, conclusive and binding,” thereby reflecting the parties’ intention to submit disputes to a private tribunal.

2. Applying the four-part test from Bihar State Mineral Development Corpn., the Court held that: (a) present or future disputes are contemplated, (b) the Superintending Engineer is the chosen private tribunal, (c) the parties agreed in writing that his decision is binding, and (d) the parties were ad idem.

3. The Court rejected the respondent’s reliance on Bharat Bhushan Bansal, noting that clauses in that case did not designate a specific arbitrator or require adjudication, whereas clause 30 expressly does.

4. The Superintending Engineer is not an officer of the University and had no operative role in supervising the project; his independence supports the existence of an arbitration agreement.

5. The Court noted that both parties actively participated in the arbitral proceedings, filed claims and counter-claims, produced documents, and were offered an opportunity to be heard. The respondent raised no objections during or immediately after the proceedings and only challenged jurisdiction during execution, undermining its present stance.

6. Because clause 30 is a valid arbitration agreement and the award has not been set aside under Section 34 of the 1996 Act or otherwise, the executing court correctly proceeded with execution.

Holding and Implications

Appeal Allowed; High Court order set aside.

The executing court is directed to continue execution of the arbitral award. The decision reaffirms that contractual clauses conferring binding decisional authority on an independent person can constitute valid arbitration agreements if the parties intended private adjudication. No broader precedent is established beyond confirming this interpretive approach.

To access the original judgment, please Sign In or Subscribe.

    Mallikarjun v. Gulbarga University .

    Order

    1. In response to the notification issued by Gulbarga University inviting tenders for construction of an indoor stadium, the appellant herein submitted his tender. His tender was accepted and on 21-5-1993, an agreement was executed between the appellant and the respondent University in connection with the work to be carried out by the appellant. The estimated cost of construction for the work order issued to the appellant was for Rs 91,88,909. It is not disputed that in pursuance of the work order, the appellant completed the construction. Certain disputes arose in relation whereto the appellant herein invoked the arbitration clause. It is not in dispute that the Superintending Engineer, PWD, Gulbarga Circle, Gulbarga, ex officio, was named to decide such disputes. Before the arbitrator, the parties filed their claims and counter-claims. The University also filed certain counter-claims. After hearing the parties, the Superintending Engineer, Gulbarga Circle, Gulbarga, who acted as an arbitrator, gave the award. However, no copy of the award was furnished to the appellant as a result of which the appellant filed a petition under Article 226 of the Constitution of India for issue of a writ of mandamus directing the arbitrator to deliver a certified copy of the award given by him. In compliance with the directions of the High Court, the arbitrator sent a certified copy of the award dated 30-7-1999. After the receipt of the certified copy of the award, the appellant put the award for execution before the Principal Civil Judge (Senior Division), Gulbarga. Gulbarga University filed an objection in the execution petition filed by the appellant purported to be under Section 47 of the Code of Civil Procedure. However, the executing court rejected the said objection on 19-10-2000. Aggrieved, Gulbarga University filed Civil Revision Petition No. 3719 of 2000 under Section 115 of the Code of Civil Procedure, 1908 before the High Court of Karnataka.

    2. In the said civil revision petition a plea was raised that the purported agreement on the basis whereof the dispute between the parties was referred to the Superintending Engineer, Gulbarga Circle, Gulbarga, was not an arbitration agreement and consequently, the award made by him is not one made in terms of the provisions of the Arbitration Act, 1940. The High Court accepted the plea taken by the University. Consequently, the execution proceedings were set aside and the civil revision petition was allowed. It is against the said judgment of the High Court, the appellant is in appeal before us.

    3. Shri Bhaskar P. Gupta, the learned Senior Counsel appearing for the appellant, submitted that clause 30 of the contract agreement constitutes an arbitration agreement as the same fulfils all the criteria laid down therefor and, thus, the High Court must be held to have erred in passing the impugned judgment.

    4. Learned counsel appearing on behalf of the respondent on the other hand support the judgment of the High Court.

    5. Clause 30 of the agreement, which reads as under:

    “The decision of the Superintending Engineer of Gulbarga Circle for the time being shall be final, conclusive and binding on all parties to the contract upon all questions relating to the meaning of the specifications, designs, drawings and instructions hereinbefore mentioned and as to the quality of workmanship or material used on the work, or as to any other question, claim, right, matter, or thing whatsoever, in any way arising out of, or relating to the contract designs, drawings, specifications, estimates, instructions, orders or those conditions, or otherwise concerning the works or the execution or failure to execute the same, whether arising during the progress of the work, or after the completion or abandonment thereof in case of dispute arising between the contractor and Gulbarga University.”
    (emphasis supplied)

    6. A plain reading of the aforementioned clause would show that in case of dispute between the contractor and Gulbarga University, the decision of the Superintending Engineer of Gulbarga Circle, Gulbarga, shall be final and binding on all parties to the contract, such dispute may embrace within its fold all questions relating to the matters specified therein as also any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract. Such dispute may also relate to designs, drawings, specifications, estimates, instructions, orders or those conditions or otherwise concerning the works or the execution or failure to execute the same. Such disputes may be referred to for decision of the Superintending Engineer; whether arising during the progress of the work or after the completion thereof.

    7. There cannot, thus, be any doubt whatsoever that clause 30 aforementioned fulfils all the criteria of a valid arbitration agreement. It is further not in dispute that the Superintending Engineer, Gulbarga Circle, Gulbarga is an independent person.

    8. In Bihar State Mineral Development Corpn. v. Encon Builders (I) (P) Ltd. (2003) 7 SCC 418 this Court laid down the essential elements of the arbitration agreement, which are as follows:

    (i) There must be a present or a future difference in connection with some contemplated affair;
    (ii) there must be the intention of the parties to settle such difference by a private tribunal;
    (iii) the parties must agree in writing to be bound by the decision of such tribunal; and
    (iv) the parties must be ad idem.

    9. The principles laid down in the aforementioned decision are not in question. We, therefore, are required to construe clause 30 of the said agreement.

    10. Applying the aforesaid principle to the present case, clause 30 requires the Superintending Engineer, Gulbarga Circle, Gulbarga, to give his decision on any dispute that may arise out of the contract. Further, we also find that the agreement postulates present or future differences in connection with some contemplated affairs inasmuch as there also was an agreement between the parties to settle such difference by a private tribunal, namely, the Superintending Engineer, Gulbarga Circle, Gulbarga. It was also agreed between the parties that they would be bound by the decision of the Tribunal. The parties were also ad idem.

    11. In the aforesaid view of the matter, it must be held that the agreement did contain an arbitration clause.

    12. The learned counsel appearing for the respondent, relying on or on the basis of the decision of this Court in Bharat Bhushan Bansal v. U.P Small Industries Corpn. Ltd. (1999) 2 SCC 166 argued that in the said case it was held by this Court that it does not constitute an arbitration clause. In Bharat Bhushan Bansal case (1999) 2 SCC 166 clauses 23 and 24 read as follows:

    “23. Except where otherwise specified in the contract, the decision of the Executive Engineer shall be final, conclusive and binding on both the parties to the contract on all questions relating to the meaning, the specification, design, drawings and instructions hereinbefore mentioned, and as to the quality of workmanship or materials used on the work or as to any other question whatsoever in any way arising out of or relating to the designs, drawings, specifications, estimates, instructions, orders or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work, or after the completion thereof or abandonment of the contract by the contractor shall be final and conclusive and binding on the contractor.
    24. Except as provided in clause 23 hereof, the decision of the Managing Director of UPSIC shall be final, conclusive and binding on both the parties to the contact upon all questions relating to any claim, right, matter or thing in any way arising out of or relating to the contract or these conditions or concerning abandonment of the contract by the contractor and in respect of all other matters arising out of this contract and not specifically mentioned herein.”

    13. It was difficult for the Court to spell out any intention of the parties to appoint the Managing Director as an arbitrator having regard to the contents of the said two clauses. We may refer to the observations of this Court therein made in this regard, which are as under:

    “Therefore, in respect of certain claims, the decision of the Executive Engineer is final and binding on both the parties to the contract. While in respect of the remaining matters, the decision of the Managing Director of the respondent is final, conclusive and binding on both the parties to the contract. Clause 24 does not mention that any dispute can be referred to the arbitration of the Managing Director. Clause 24 also does not spell out any duty on the part of the Managing Director to record evidence or to hear both parties before deciding the questions before him. From the wording of clause 24, it is difficult to spell out any intention of the parties to leave any disputes to the adjudication of the Managing Director of the respondent as an arbitrator.”

    14. Para 5 of Bharat Bhushan Bansal case (1999) 2 SCC 166 reads thus:

    “5. In the present case, reading clauses 23 and 24 together, it is quite clear that in respect of questions arising from or relating to any claim or right, matter or thing in any way connected with the contract, while the decision of the Executive Engineer is made final and binding in respect of certain types of claims or questions, the decision of the Managing Director is made final and binding in respect of the remaining claims. Both the Executive Engineer as well as the Managing Director are expected to determine the question or claim on the basis of their own investigations and material. Neither of the clauses contemplates a full-fledged arbitration covered by the Arbitration Act.”

    15. A bare comparison of clause 30 of the contract agreement involved in the present matter and clauses 23 and 24 involved in Bharat Bhushan Bansal case (1999) 2 SCC 166 would show that they are not identical. Whereas clause 30 of the agreement in question provides for resolution of the dispute arising out of the contract by persons named therein; in terms of clause 24, there was no question of decision by a named person in the dispute raised by the parties to the agreement. The matters which are specified under clauses 23 and 24 in Bharat Bhushan Bansal case (1999) 2 SCC 166 were necessarily not required to arise out of the contract, but merely claims arising during performance of the contract. Clause 30 of the agreement in the present case did provide for resolution of the dispute arising out of the contract by the Superintending Engineer, Gulbarga Circle, Gulbarga. For that reason, the case relied upon by the learned counsel for the respondent is distinguishable.

    16. Once clause 30 is constituted to be a valid arbitration agreement, it would necessarily follow that the decision of the arbitrator named therein would be rendered only upon allowing the parties to adduce evidence in support of their respective claims and counter-claims as also upon hearing the parties to the dispute. For the purpose of constituting the valid arbitration agreement, it is not necessary that the conditions as regards adduction of evidence by the parties or giving an opportunity of hearing to them must specifically be mentioned therein. Such conditions, it is trite, are implicit in the decision-making process in the arbitration proceedings. Compliance with the principles of natural justice inheres in an arbitration process. They, irrespective of the fact as to whether recorded specifically in the arbitration agreement or not are required to be followed. Once the principles of natural justice are not complied with, the award made by the arbitrator would be rendered invalid. We, therefore, are of the opinion that the arbitration clause does not necessitate spelling out of a duty on the part of the arbitrator to hear both parties before deciding the question before him. The expression “decision” subsumes adjudication of the dispute. Here in the instant case, it will bear repetition to state, that the disputes between the parties arose out of a contract and in relation to matters specified therein and, thus, were required to be decided and such decisions are not only final and binding on the parties, but they are conclusive which clearly spells out the finality of such decisions as also their binding nature.

    17. A clause which is inserted in a contract agreement for the purpose of prevention of dispute will not be an arbitration agreement. Such a provision has been made in the agreement itself by conferring power upon the Engineer-in-Charge to take a decision thereupon in relation to the matters envisaged under clauses 31 and 32 of the said agreement. Clauses 31 and 32 of the said agreement provide for a decision of the Engineer-in-Charge in relation to the matters specified therein. The jurisdiction of the Engineer-in-Charge in relation to such matters are limited and they cannot be equated with an arbitration agreement. Despite such clauses meant for prevention of dispute arising out of a contract, significantly, clause 30 has been inserted in the contract agreement by the parties.

    18. The very fact that clause 30 has been inserted by the parties despite the clauses for prevention of dispute is itself a pointer to the fact that the parties to the contract were ad idem that the dispute and differences arising out of or under the contract should be determined by a domestic tribunal chosen by them.

    19. The said clause being a part of the contract agreement, it is beyond any cavil that the parties were ad idem in relation thereto.

    20. The Superintending Engineer, Gulbarga Circle, Gulbarga, is an officer of the Public Works Department in the Government of Karnataka. He is not an officer of the University. He did not have any authority or jurisdiction under the agreement or otherwise either to supervise the construction works or issue any direction(s) upon the contractor in relation to the contract job. He might be an ex officio member of the Building Committee, but thereby or by reason thereof, he could not have been given nor in fact had been given an authority to supervise the contract job or for that matter issue any direction upon the contractor as regards performance of the contract.

    21. In that view of the matter also clause 30 of the contract agreement should be construed to be an arbitration agreement.

    22. The submission of the learned counsel for the respondent that the dispute was not referred to the arbitrator is not correct. Whatever be the understanding of the Vice-Chancellor of the respondent University; before the arbitrator the parties proceeded on the basis that a reference of the disputes had been made to him in terms of clause 30 of the contract, which was construed to be an arbitration agreement. Further, from the award dated 30-7-1999, it would appear that the arbitrator entered into the reference in view of the reference made by the Registrar of Gulbarga University on the claims and disputes arising out of the contract of “construction of indoor stadium at university campus”, which has arisen between the parties hereto.

    23. The learned counsel for the respondent then urged that his client has not been given sufficient opportunity to lead evidence. The contention cannot be accepted for more than one reason. The matter was heard by the arbitrator. Both the parties were represented by their agents and authorised representatives. It will bear repetition to state that claims and counter-claims were filed by the parties and they filed documents in support of their respective claims.

    24. The learned arbitrator in his award recorded that the parties were given full opportunity to present their case and have their say on each of their claims and contentions in the meeting held in his office on 5-3-1999. The arbitrator in his award further stated that as the parties based their cases only on the documents and did not pray for adduction of oral evidence and in that view of the matter, in our opinion the award cannot be faulted. Furthermore, concededly during the arbitration proceedings and immediately thereafter, no objection was taken by the respondent to the effect that clause 30 does not constitute an arbitration agreement or the Superintending Engineer, Gulbarga Circle, Gulbarga, was not an arbitrator. If the contention of the respondent is to be accepted, there was no occasion for it to submit its counter-claim. It should have filed a suit. With its eyes wide open it submitted itself to the jurisdiction of the arbitrator, filed documents in support of its defence to the claims raised by the appellant as also its own counter-claims and took part in the proceedings. Even when an award was made and the appellant herein filed a writ petition for direction upon the arbitrator to issue a certified copy of the award, it was not contended that the said writ petition was not maintainable as the Superintending Engineer, Gulbarga Circle, Gulbarga, did not act as an arbitrator. When a writ was issued by the High Court of Karnataka to the arbitrator, directing him to furnish a certified copy of his award, the respondent herein must be held to have accepted the same as it did not carry the matter further.

    25. It took the said objection only in its purported objection filed in the execution proceedings under Section 47 of the Code of Civil Procedure. If its contention was that the award made by the Superintending Engineer, Gulbarga Circle, Gulbarga, was without any authority or beyond his jurisdiction, it could have furthermore filed an appropriate application in terms of Section 34 of the Arbitration and Conciliation Act, 1996.

    26. For the aforesaid reason, the appeal deserves to be allowed. The order under challenge is set aside. We direct the executing court to proceed with the execution of the award. There shall be no order as to costs.