AMICUS AI
Citation Codes
Neutral Citations
2001 INSC 121
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 115 of the Code of Civil Procedure
  • Section 4, Sub-section (2), (3) and (4) of the Act
  • Schedule I of the Act
  • Section 25 of the Tamil Nadu Buildings (Lease and Rent Control) Act, 1960
  • Section 4 of the Tamil Nadu Buildings (Lease and Rent Control) Act, 1960
  • Schedule I in the Act
  • Section 2(2) of the Act
  • the 1983 Income Tax Act (not explicitly mentioned, but implied as a reference to a general legislative act)
  • Section 4 of the Act
  • Section 25 of the Act, Section 50 of the Karnataka Rent Control Act, 1961, Tamil Nadu Buildings (Lease and Rent Control) Act, 1960
  • Section 25(1) of the Revision Act
  • Schedule II of the Public Works Department Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2001 INSC 121
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 115 of the Code of Civil Procedure
  • Section 4, Sub-section (2), (3) and (4) of the Act
  • Schedule I of the Act
  • Section 25 of the Tamil Nadu Buildings (Lease and Rent Control) Act, 1960
  • Section 4 of the Tamil Nadu Buildings (Lease and Rent Control) Act, 1960
  • Schedule I in the Act
  • Section 2(2) of the Act
  • the 1983 Income Tax Act (not explicitly mentioned, but implied as a reference to a general legislative act)
  • Section 4 of the Act
  • Section 25 of the Act, Section 50 of the Karnataka Rent Control Act, 1961, Tamil Nadu Buildings (Lease and Rent Control) Act, 1960
  • Section 25(1) of the Revision Act
  • Schedule II of the Public Works Department Act
Smart Summary

Factual and Procedural Background

The landlords, Shri Govindas Purushothamdas and Shri Girdhari Govindas, applied under Section 4 of the Tamil Nadu Buildings (Lease and Rent Control) Act, 1960 for fixation of fair rent for non-residential premises occupied by the tenant, M/s Shaw Wallace & Co. Ltd. The dispute centred on whether an additional 1752 sq ft—described as “platform and henpen”—formed part of the building for rent-assessment purposes.

The Rent Controller and, on appeal, the Appellate Authority excluded this area, calculating fair rent on a plinth area of 4850 sq ft and fixing rent at Rs 22,403 per month. The landlords filed a revision under Section 25 of the Act. The Madras High Court included the disputed area, set aside the concurrent findings, and determined the fair rent at Rs 28,000 per month. The tenant appealed to the Supreme Court, challenging the High Court’s revisional order dated 24-12-1999 (CRP No. 2317 of 1996).

Legal Issues Presented

  1. Whether the High Court, in revision under Section 25 of the Act, was justified in disturbing concurrent findings of fact and including the “platform and henpen” within the plinth area for fixation of fair rent.
  2. Whether the definition of “building” and the statutory scheme of Section 4 required inclusion of appurtenant structures and land in calculating fair rent.

Arguments of the Parties

Appellant’s Arguments (Tenant)

  • The “henpen and platform” are not part of the building and cannot be utilised as such; their inclusion in the plinth area is erroneous.
  • The High Court exceeded its limited revisional jurisdiction by overturning concurrent factual findings of the Rent Controller and Appellate Authority.

Respondents’ Arguments (Landlords)

  • The High Court correctly interfered because the courts below overlooked the landlords’ pleading—and the tenant’s admission—that the total plinth area is 6602 sq ft.
  • Given this admitted fact, exclusion of 1752 sq ft was legally unsustainable.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
M.S. Zahed v. K. Raghavan, (1999) 1 SCC 439 Interpreting a pari materia provision (Section 50 of the Karnataka Rent Control Act), the Supreme Court held that a High Court in revision may interfere with findings of fact that are illegal or incorrect. Used to affirm that Section 25 confers wider revisional powers than CPC Section 115, thereby validating the Madras High Court’s interference with concurrent findings.

Court’s Reasoning and Analysis

1. Statutory interpretation of “building” and Section 4. Reading Section 2(2) (definition of “building”) with Section 4(4), the Court observed that the legislature intended the term “building” to encompass the structure, land appurtenant to it (up to the statutory limit), and other appurtenant structures or amenities. Consequently, even if the “platform and henpen” are not usable as enclosed space, they fall within the statutory definition when let with the main premises.

2. Rejection of the tenant’s contention. In light of the expansive definition and undisputed factual findings, the Court held that the appellant’s argument for exclusion of the 1752 sq ft could not be accepted.

3. Scope of revisional jurisdiction under Section 25. The Court compared Section 25 with Section 115 CPC, noting that it allows the High Court to correct errors regarding “regularity, correctness, legality or propriety.” Where lower courts ignore admitted facts or misconstrue statutory provisions, interference is permissible.

4. Application to the present case. The Rent Controller and Appellate Authority ignored the landlords’ pleading (admitted by the tenant) that the plinth area was 6602 sq ft and misapplied the Act. Therefore, the High Court’s modification of the fair rent was within its jurisdiction and legally proper.

Holding and Implications

Appeal Dismissed. The Supreme Court upheld the Madras High Court’s determination of fair rent at Rs 28,000 per month, confirmed inclusion of the disputed 1752 sq ft, and awarded costs of Rs 10,000 against the appellant. One month was granted to pay arrears in compliance with the High Court’s order.

Implications: The decision reiterates (a) the broad statutory definition of “building” for rent-control purposes, and (b) the High Court’s wide revisional powers under Section 25 to correct factual errors grounded in admissions or statutory misinterpretation. No new precedent is established, but the ruling clarifies application of existing principles under the Tamil Nadu Act.

To access the original judgment, please Sign In or Subscribe.

    Shaw Wallace & Co. Ltd. v. Govindas Purushothamdas And Another

    D.P Mohapatra, J.— Leave granted.

    2. Whether the revisional order dated 24-12-1999 passed by the High Court of Madras in CRP No. 2317 of 1996 suffers from any serious illegality which warrants interference by this Court is the question for determination in this case. M/s Shaw Wallace & Co. Ltd., the tenant in occupation of the premises, has filed this appeal assailing the aforementioned order of the High Court.

    3. The proceeding was initiated on the application filed by the landlords — Shri Govindas Purushothamdas and Shri Girdhari Govindas, respondents herein, for fixation of fair rent of the premises under Section 4 of the Tamil Nadu Buildings (Lease and Rent Control) Act, 1960 (hereinafter referred to as “the Act”). The controversy in the present proceeding relates to inclusion of the area of 1752 sq ft (approximately) described as “platform and henpen” as a part of the building. The Rent Controller and the Appellate Authority excluded the said area and assessed the fair rent on the basis of plinth area of 4850 sq ft. The fair rent was calculated as Rs 22,403 per month. In the revision petition filed by the landlord under Section 25 of the Act, the High Court set aside the order of the trial court as confirmed by the Appellate Authority and determined Rs 28,000 in place of Rs 22,403 per month as fair rent. The said order is under challenge in this appeal.

    4. The main thrust of the submissions made by Dr A.M Singhvi, learned Senior Counsel appearing for the appellant is that the High Court erred in including the “henpen and platform” within the plinth area of the building. According to the learned counsel, those structures cannot be said to be a part of the building and cannot be utilised as such. He further contended that the High Court should not have interfered with the concurrent findings of fact recorded by the trial court and the Appellate Authority that the area covered by the “henpen and platform” is not a part of the building.

    5. Per contra, Shri T.L.V Iyer, learned Senior Counsel appearing for the respondents contended that in this case the High Court was justified in interfering with the order of the trial court which was confirmed by the appellate court, since the courts below had overlooked the admission of the landlord in the pleadings that the plinth area of the structure in occupation of the tenant is 6602 sq ft (not 4850 sq ft).

    6. Before proceeding to consider the merits of the contentions raised by learned counsel for the parties, it will be convenient to notice some provisions of the Act which are relevant for the case. Section 2(2) of the Act, which defines “building” reads as follows:

    “2. (2) ‘building’ means any building or hut or part of a building or hut, let or to be let separately for residential or non-residential purposes and includes—
    (a) the garden, grounds and outhouses, if any, appurtenant to such building, hut or part of such building or hut and let or to be let along with such building or hut,
    (b) any furniture supplied by the landlord for use in such building or hut or part of a building or hut,
    but does not include a room in a hotel or boarding house;”

    Section 4, which deals with the fixation of fair rent reads:

    “4. Fixation of fair rent.—(1) The Controller shall on application made by the tenant or the landlord of a building and after holding such inquiry as he thinks fit, fix the fair rent for such building in accordance with the principles set out in the following sub-sections.
    (2) The fair rent for any residential building shall be nine per cent gross return per annum on the total cost of such building.
    (3) The fair rent for any non-residential building shall be twelve per cent gross return per annum on the total cost of such building.
    (4) The total cost referred to in sub-section (2) and sub-section (3) shall consist of the market value of the site in which the building is constructed, the cost of construction of the building and the cost of provision of any one or more of the amenities specified in Schedule I as on the date of application for fixation of fair rent:
    Provided that while calculating the market value of the site in which the building is constructed, the Controller shall take into account only that portion of the site on which the building is constructed and of a portion up to fifty per cent thereof of the vacant land, if any, appurtenant to such building, the excess portion of the vacant land, being treated as amenity:
    Provided further that the cost of provision of amenities specified in Schedule I shall not exceed—
    (i) in the case of any residential building, fifteen per cent; and
    (ii) in the case of any non-residential building, twenty-five per cent,
    of the cost of site in which the building is constructed, and the cost of construction of the building as determined under this section.
    (5)(a) The cost of construction of the building including cost of internal water supply, sanitary and electrical installations shall be determined with due regard to the rates adopted for the purpose of estimation by the Public Works Department of the Government for the area concerned. The Controller may, in appropriate cases, allow or disallow an amount not exceeding thirty per cent of the cost of construction having regard to the nature of construction of the building.
    (b) The Controller shall deduct from the cost of construction determined in the manner specified in clause (a), depreciation, calculated at the rates specified in Schedule II.”
    (emphasis supplied)

    7. The other statutory provision, which is relevant, is Section 25(1) which provides for a revision to the High Court. The provision is quoted hereunder:

    “25. Revision.—(1) The High Court may, on the application of any person aggrieved by an order of the Appellate Authority, call for and examine the record of the Appellate Authority, to satisfy itself as to the regularity of such proceeding or the correctness, legality or propriety of any decision or order passed therein and if, in any case, it appears to the High Court that any such decision or order should be modified, annulled, reversed or remitted for reconsideration, it may pass orders accordingly.”
    (emphasis supplied)

    8. Schedule I in the Act enumerates the amenities within the meaning of Section 4 of the Act.

    9. From a plain reading of the statutory provisions quoted above, it is clear that the expression “building” includes any building with the garden, grounds and outhouses appurtenant to such building, or part of such building let or to be let along with such building. In view of the expansive definition of the term, any structure which is part of the premises let out or to be let out comes within the purview of “building”. This position becomes further clear on reading sub-section (4) of Section 4 wherein it is provided that the total cost referred to in sub-section (2) and sub-section (3) shall consist of the market value of the site in which the building is constructed, the cost of construction of the building and the cost of provision of any one or more of the amenities specified in Schedule I as on the date of application for fixation of fair rent. In the first proviso to sub-section (4) it is laid down while calculating the market value of the site in which the building is constructed, the Controller shall take into account only that portion of the site on which the building is constructed and of a portion up to fifty per cent thereof the vacant land, if any, appurtenant to such building, the excess portion of the vacant land, being treated as amenity.

    10. Reading the two provisions together, it is clear to us that for the purpose of assessment of fair rent not only the area on which the building is constructed, but also the land appurtenant to it subject to the limit prescribed in the statute and other structures appurtenant to the main building and also the amenities described in Schedule I of the Act are all to be taken into account. Therefore, the contention raised by Dr Singhvi that the “platform and the henpen” are not to be included in calculating the area for the purpose of assessment of fair rent, since it cannot be used as a building, cannot be accepted having regard to the facts found in the case. The High Court, in our considered view, did not commit any illegality in including the said structures within the plinth area for the purpose of fixation of fair rent.

    11. Coming to the question of revisional jurisdiction of the High Court under Section 25 of the Act, the contention raised by Dr Singhvi is that the limited jurisdiction vested in the said section does not permit the High Court to disturb concurrent findings of fact recorded by the courts below.

    12. From the judgment/order of the High Court it is manifest that the High Court felt inclined to interfere with the orders passed by the courts below mainly for the reason that the courts below had ignored the specific averment made by the landlords in their pleadings that the total plinth area is 6602 sq ft which was admitted by the tenant to be true in para 12 of its counter-affidavit. The question, therefore, is whether the High Court not have the power to disturb the findings of fact concurrently recorded by the courts below in such circumstance.

    13. On a plain reading of Section 25 of the Act, it is clear that the revisional jurisdiction vested in the High Court under that section is wider than Section 115 of the Code of Civil Procedure. The High Court is entitled to satisfy itself as to the regularity of the proceeding, of the correctness, legality or propriety of any decision or order passed therein and if, on examination, it appears to the High Court that any such decision or order should be modified, annulled, reversed or remitted for reconsideration, it may pass such orders accordingly.

    14. In the case of M.S Zahed v. K. Raghavan (1999) 1 SCC 439 this Court, interpreting Section 50 of the Karnataka Rent Control Act, 1961 which is in pari materia to Section 25 of the Tamil Nadu Buildings (Lease and Rent Control) Act, 1960, held that it is within the scope of revisional jurisdiction of the High Court to interfere with the findings of fact, illegally or incorrectly arrived at.

    15. In the present case, the trial court and the appellate court had not only ignored the admission of the landlord in the pleadings but also misread and misconstrued the provisions of the Act. In the circumstances, the High Court cannot be faulted for having interfered with the judgments/orders of the courts below and modifying the fair rent as assessed therein. The contention raised by Dr Singhvi questioning the jurisdiction of the High Court has also to be negatived.

    16. In the result, the appeal being devoid of merit, is dismissed with costs. Hearing fee is assessed at Rs 10,000.

    17. On the prayer made by Dr A.M Singhvi, learned Senior Counsel, the appellant is granted one month's time to pay the arrears of rent due in compliance with the order passed by the High Court.

    Use AI to get other relevant cases.

    Comments

    Shaw Wallace & Co. Ltd. v. Govindas Purushothamdas And Another
    (Feb 27, 2001)