Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Neutral Citations
2001 INSC 120
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 14, Section 16, Section 30 of the Arbitration Act
  • Section 16 of the Arbitration Act
  • Arbitration Act, Section 16
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 39 of the Arbitration Act
  • Sections 30 and 16 of the Arbitration Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2001 INSC 120
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 14, Section 16, Section 30 of the Arbitration Act
  • Section 16 of the Arbitration Act
  • Arbitration Act, Section 16
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 39 of the Arbitration Act
  • Sections 30 and 16 of the Arbitration Act
Smart Summary

Factual and Procedural Background

The dispute arises out of a contract for the north excavation work of the approach channel of the Srisailam Project, Andhra Pradesh. The contract contained an arbitration clause. Six claim items were placed before a panel of arbitrators. The panel:

  • Rejected Claim Items 1, 2 and 3.
  • Allowed Claim Item 4 in part.
  • Allowed interest at 12% p.a. on the amount awarded (Claim Item 5).
  • Directed each party to bear its own costs (Claim Item 6).

The claimants (contractors) objected to the rejection of Items 1–3 and sought remission under Section 16 of the Arbitration Act, 1940. They also moved under Section 14 to make the allowed part of the award a rule of court. The State of Andhra Pradesh filed a petition under Section 30 to set aside the part of the award that favoured the contractor.

The Vth Additional Judge, City Civil Court, Hyderabad:

  • Made the award on Claim Item 4 a rule of court.
  • Set aside the award on Claim Items 1, 2, 3 and 5 and remitted them to the arbitrators for reconsideration.

The State appealed under Section 39 of the Act. The Andhra Pradesh High Court:

  • Set aside the remission in respect of Claim Item 1.
  • Upheld remission for Claim Items 2 and 3 but appointed a retired Chief Justice as arbitrator for those items and the related interest claim.

The present Supreme Court appeal, filed by the claimants, concerns only Claim Item 1.

Legal Issues Presented

  1. Whether the civil court was justified, under Section 16 of the Arbitration Act, in remitting Claim Item 1 (extra payment for additional hard-rock excavation) to the arbitrators for fresh determination.
  2. Whether, under the terms of the contract or applicable government orders, the contractor was entitled to a higher rate for excavation quantities exceeding the agreed limits.

Arguments of the Parties

Appellant (Claimants/Contractors)

  • The High Court erred in relying on clause 59 of the contract and letters dated 15-7-1980 and 19-5-1983 to deny a higher rate for excess excavation.
  • Government Order (GOMs) No. 2289 dated 12-6-1968 permits deviation only up to 25%; beyond that the contractor is entitled to separate rates, as recognised in S. Harcharan Singh v. Union of India.
  • Recommendations of the Executive Engineer implied acceptance of higher rates; the arbitrators failed to consider this, amounting to an error on the face of the award.
  • Clause 63 of the contract, dealing with “supplemental items”, entitled the contractor to enhanced payment for the additional excavation.

Respondent (State of Andhra Pradesh)

  • Court interference with a reasoned award is permissible only for patent errors; none exist here.
  • The contractor never invoked clause 63 before the arbitrators or lower courts; the argument is belated.
  • Clause 63 applies only to supplemental items, not to excess quantities of the same item already covered by the contract; payment has already been made under clause 25.
  • Letters granting extension of time (15-7-1980 and 19-5-1983) expressly disclaimed liability for extra payments, a position supported by Ch. Ramalinga Reddy v. Superintending Engineer.
  • The civil court gave no reasons for remission, exceeding the limited scope of Sections 30 and 16; the High Court correctly rectified this.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
S. Harcharan Singh v. Union of India (1990) 4 SCC 647 Where contractual deviation exceeds the permissible limit, higher rates may be payable if the contract or competent authority so provides. Distinguished. Court held no analogous clause (like 12-A) or authoritative correspondence existed in the present contract; precedent therefore inapplicable.
Ch. Ramalinga Reddy v. Superintending Engineer (1999) 9 SCC 610 Extension-of-time letters that deny extra payment bar subsequent claims for escalation or higher rates. Relied upon to support the State’s contention that letters dated 15-7-1980 and 19-5-1983 foreclosed the contractor’s claim for enhanced rates.
National Fertilizers v. Puran Chand Nangia (2000) 8 SCC 343 Court’s power to interfere with a non-speaking award is limited; contractual interpretation should balance parties’ rights. Cited but found not determinative. Court noted that, unlike in that case, the present contract lacked any clause or assent justifying escalated rates.

Court's Reasoning and Analysis

The Supreme Court first outlined the limited circumstances under Section 16 in which a court may remit an award—namely where an arbitrator omits to decide a referred issue or commits an error apparent on the face of the award. It emphasised that documents not incorporated into the award cannot be considered for finding such errors.

Applying these principles, the Court found:

  • The civil court provided no reasoned basis for holding that the arbitrators left Claim Item 1 undetermined; hence its order of remission exceeded the scope of Section 16.
  • Clause 63 of the contract relates to “supplemental items” introduced during execution; the excavation of additional hard rock was not a supplemental item but merely an increased quantity of an existing work item. Therefore clause 63 did not entitle the contractor to higher rates.
  • There was no contractual provision similar to clause 12-A in Harcharan Singh, nor any letter from a competent authority agreeing to escalated rates. Recommendations of the Executive Engineer lacked contractual force.
  • Letters granting extension of time explicitly denied entitlement to additional compensation, reinforcing the conclusion that the contractor was limited to payments already made under clause 25.

Consequently, no error apparent existed in the arbitrators’ rejection of Claim Item 1, and the High Court correctly overturned the civil court’s remission order.

Holding and Implications

Appeal Dismissed. The Supreme Court affirmed the High Court’s decision refusing to remit Claim Item 1 back to arbitration. No order as to costs.

Implications: The ruling reiterates the narrow grounds on which courts may interfere with arbitral awards, underscores the need for explicit contractual or authoritative basis before awarding higher rates for excess work, and signals that unilateral recommendations or vague claims will not suffice to override the terms of a construction contract.

To access the original judgment, please Sign In or Subscribe.

    Ramachandra Reddy & Co. v. State Of A.P And Others

    G.B Pattanaik, J.— The claimants are the appellants against the judgment of the Andhra Pradesh High Court, arising out of an arbitration proceeding. The north excavation work of approach channel of Srisailam Project had been awarded to the claimants for different amounts indicated in the contract. The contract itself contained an arbitration clause. Dispute being raised on different items of claim, those disputes had been referred to a panel of arbitrators and the panel of arbitrators, ultimately passed an award whereunder Claim Items 1, 2 and 3 stood rejected. So far as Claim Item 4 is concerned, the same was allowed in part. Claim Item 5 was claim of interest and the arbitrators allowed the interest @ 12 per cent per annum over the amount awarded. Claim Item 6 was the claim of cost and the arbitrators directed that each party will bear its own costs. Against the award of the arbitrators, rejecting Claim Items 1, 2 and 3, the claimants filed an objection in the civil court and sought for remittance under Section 16 on the ground that the arbitrators have left undetermined the claims of the claimants on Items 1, 2 and 3 on an erroneous view of the relevant clauses of the agreement. The claimants also filed an application under Section 14 to make the award in relation to claim allowed by the arbitrators as a rule of court. The State of Andhra Pradesh also filed a petition under Section 30 of the Arbitration Act to set aside that part of the award which allowed the claim of the contractor to the extent of Rs 57,000. All these applications which were registered as OS No. 1094 of 1986, OPs Nos. and 424 of 1987 were disposed of by a common judgment of the learned Vth Additional Judge, City Civil Court, Hyderabad. The said learned Judge made the award in relation to Claim Item 4 a rule of court. But he set aside the award in relation to Claim Items 1, 2, 3 and 5 and remitted the same for reconsideration to the panel of arbitrators. Against the aforesaid judgment of the Additional Judge, City Civil Court, remitting the disputes/claims in relation to Claim Items 1, 2, 3 and 5 to the panel of arbitrators, the State of Andhra Pradesh preferred appeals under Section 39 of the Arbitration Act. The High Court by the impugned judgment set aside the order of the Additional Judge, so far as it relates to remitting Claim Item 1 to the panel of arbitrators for reconsideration. So far as Claim Items 2 and 3 are concerned, the High Court upheld the direction of the Additional Judge, but, appointed a retired Chief Justice of the Court as arbitrator to arbitrate Claim Items 2 and 3 and a part of Claim Item 5 relating to interest. In this appeal filed by the claimants, we are concerned only with Claim Item 1. The legality of the award in relation to Claim Items 2 and 3 are the subject-matter of an appeal, which is pending in this Court.

    2. Claim Item 1 relates to increase in quantity of hard rock abnormally and on this head, the claimants had claimed Rs 93,76,990. The claimants' statement that was filed before the arbitrator, makes out a vague claim on this score without indicating the basis for the claim in question. In respect of the aforesaid quantity of extra excavation on hard rock, the State of Andhra Pradesh had made the payment in terms of clause 25 of Schedule C of Section 2 of the agreement as per its letter dated 21-10-1981. Notwithstanding the said payment, the claimants had made the extra claim on the ground that the quantity of excavation of hard rock being abnormally high and much beyond the anticipated quantity indicated in the agreement and even much in excess of the so-called 25 per cent of the work as per GOMs No. 2289 dated 12-6-1968, the claimants are entitled to a separate rate for such extra excavation and the arbitrators failed to exercise their jurisdiction in not granting the claim and, on the other hand, rejecting the same. The High Court in the impugned judgment however, referring to clause 59 of the agreement, which deals with delay and extension of time and in view of the letters of the Superintending Engineer dated 15-7-1980 and 19-5-1983, came to hold that the claimant contractor will not be entitled to be paid at any higher rate for such additional excavation work and accordingly set aside the order of the learned trial Judge, remitting Claim Item 1 for being redisposed of by the arbitrator.

    3. Mr P.P Rao, the learned Senior Counsel appearing for the appellant, contended that the High Court committed serious error in referring to clause 59 as well as to the letter dated 15-7-1980 and 19-5-1983, in coming to the conclusion that the claimant contractor will not be entitled to be paid at any higher rate for the extra amount of excavation made by him. Mr Rao further submitted that under GOMs No. 2289 dated 12-6-1968, a deviation limit up to a maximum of 25 per cent being permissible, for any work in excess of that limit, the contractor is entitled to claim a higher rate and that being the position, the arbitrators had committed an error apparent on the face of the award in refusing the claim and the High Court committed an error in setting aside the order of remittance passed by the Additional Judge. In support of this contention, reliance was placed on the judgment of this Court in the case of S. Harcharan Singh v. Union of India (1990) 4 SCC 647. Mr Rao also further urged that in view of the recommendations of the Executive Engineer, notwithstanding the continued objection of the claimant, expressing inability to continue with the abnormal increase in the hard rock excavation, it must be held that the payment at a higher rate for the additional or excess quantity of excavation was implied and failure on the part of the arbitrator to consider the same constitutes an error on the face of the award and as such the learned Additional Judge was justified in remitting the matter for reconsideration of the arbitrator. Mr Rao lastly submitted that for this excess of excavation work, the contractor was entitled to be paid in accordance with clause 63 of the agreement, which has not been noticed by the arbitrator and, adjudged from that standpoint, the High Court also committed an error in setting aside the order of remittance made by the learned Additional Judge.

    4. Ms K. Amareswari, appearing for the respondent State of Andhra Pradesh, on the other hand contended that the power of interference of the court under Sections 30 and 33 as well as under Section 16 is of a limited nature and the court would be justified in interfering with the reasoned award of an arbitrator, if the award contains any apparent error on the same. If the impugned award is examined from the aforesaid standpoint, the conclusion is irresistible that it did not contain any error and, therefore, the interference of the court was not warranted. Ms Amareswari further contended that the claimants nowhere in the claim petition had made out a case that for the additional quantity of excavation work, they are entitled to the rate as per clause 63 of the agreement which was urged for the first time in this Court and, therefore, the said contention should not be allowed to be raised. Ms Amareswari further urged that clause 63 will have no application for the extra item of excavation made by the contractors since that clause applies to any supplemental items, which are found essential, incidental and inevitable during the execution of the work and by no stretch of imagination, the additional excavation which is the subject-matter of claim in Claim Item 1 can be held to be a supplemental item. Ms Amareswari further submitted that for this additional quantity of excavation the claimant having been paid for in accordance with clause 25 of the agreement, the further claim of the contractor is not arbitrable at all and, the High Court therefore was fully justified in setting aside the order of remittance made by the Additional Judge. Ms Amareswari further contended that the claim for payment of higher rate for the work done beyond the agreement is not at all sustainable in view of the positive letter of the authorities dated 15-7-1980 and 19-5-1983, while allowing extension of time for completion of the work, as has been held by this Court in the case of Ch. Ramalinga Reddy v. Superintending Engineer (1999) 9 SCC 610 and, therefore, the High Court was fully justified in interfering with the directions of the Subordinate Judge in remitting the said Claim Item 1 for fresh arbitration. Ms Amareswari lastly submitted that a bare scrutiny of the order of the Vth Additional Judge, City Civil Court, Hyderabad, remitting Claim Items 1, 2 and 3 for reconsideration would indicate that no reasons had been given for such remittance and, on the face of it, the said judgment of the civil court tantamounts to gross error of jurisdiction in interfering with an award and transgressing the scope and limitation provided under Sections 30 and 16 and, therefore, the High Court was justified in correcting the said error in appeal.

    5. Under the Arbitration Act, Section 16 is the provision under which the court may remit the award for reconsideration of an arbitrator and necessity for remitting the award arises when there are omissions and defects in the award, which cannot be modified or corrected. Remission of an award is in the discretion of the court and the powers of the court are circumscribed by the provisions of Section 16 itself. Ordinarily, therefore, a court may be justified in remitting the matter if the arbitrator leaves any of the matters undetermined or a part of the matter which had not been referred to and answered and that part cannot be separated from the remaining part, without affecting the decision on the matter, which was referred to arbitration or the award is so indefinite as to be incapable of execution or that the award is erroneous on the face of it. Discretion having been conferred on the court to remit an award, the said discretion has to be judicially exercised and an appellate court would not be justified in interfering with the exercise of discretion unless the discretion has been misused. What is an error apparent on the face of an award which requires to be corrected, has always been a subject-matter of discussion. An error of law on the face of the award would mean that one can find in the award or a document actually incorporated thereto stating the reasons for a judgment some legal propositions which are the basis of the award and which can be said to be erroneous. Documents not incorporated directly or indirectly into the award cannot be looked into for the purpose of finding out any alleged error. The courts are not to investigate beyond the award of the arbitrators and the documents actually incorporated therein and, therefore, when there would be no patent error on the face of the award, it would not be open for the court to go into the proceedings of the award. If the application for remittance filed by the claimants invoking jurisdiction of the court under Section 16 is examined from the aforesaid standpoint and if the order of the learned civil court, remitting Claim Item 1 is tested in the light of the discussions made above, the conclusion is irresistible that no case for remittance had been made out and the learned trial Judge exercised his discretion on the grounds which do not come within the four corners of the provisions of Section 16 of the Arbitration Act. In fact no reasons had been ascribed for interference with the award, rejecting Claim Item 1 and for remittance of the same. The High Court being the court of appeal, was therefore, fully justified in exercise of its appellate power in correcting the error made by the Civil Judge in remitting Claim Item 1.

    6. Let us now examine the contentions of Mr P.P Rao, the learned Senior Counsel appearing for the appellant. The learned counsel's contention in fact centres round the question as to whether for the additional quantity of excavation work, the contractor would be entitled to at a higher rate in accordance with clause 63 of the agreement. Ms Amareswari, appearing for the State, was fully justified in her submissions that this contention had never been raised either before the arbitrator or before the Subordinate Judge or even before the High Court. In fact, the claim petition filed before the arbitrator is rather cryptic and absolutely vague, not indicating on what basis the additional claim was made, though the foundation for the claim was there, namely there had been an increased amount of excavation work beyond the agreement. It is in this connection Mr Rao had relied upon the two decisions of this Court in the case of S. Harcharan Singh v. Union of India (1990) 4 SCC 647 and National Fertilizers v. Puran Chand Nangia (2000) 8 SCC 343. But before examining the said contention, it would be appropriate for us to extract clause 63, which was the sheet anchor of the argument of Mr Rao. Clause 63 reads as under:

    “63. Payment for additions and deductions for omissions.—(A) The contractor is bound to execute all supplemental items that are found essential, incidental and inevitable during the execution of the work, at the rates to be worked out as detailed below:
    (a) For all items of work in excess of the quantities shown in Schedule A of the tender the rates payable for such items shall be either the tender rates or the standard schedule of rates for the items plus or minus the overall tender percentage accepted by the competent authority, whichever is less.
    (b) For items directly deducible from similar items in the agreement, the rates shall be derived by adding to or subtracting from the agreement rate of such similar items, the cost of difference in quantity of material or labour between the new items and similar items in the agreement, worked out with reference to the schedule of rates adopted in the sanctioned estimate plus or minus the overall tender percentage.
    (c) For new items which do not correspond to any items in the agreement, the rates shall be standard schedule rate plus or minus the overall tender percentage.
    The term ‘standard schedule of rates’ used in the above sub-clauses (a), (b) and (c) means the schedule of rates on which the sanctioned estimate was prepared.
    (d) In the event of the Executive Engineer and the contractor failing to agree on a rate for such additional work, the Executive Engineer may, at his option, either:
    (i) employ other parties to carry out the additional work in the same manner as provided for under clause 48, or
    (ii) the contractor shall execute the work upon written orders from the Executive Engineer and the cost of labour and materials plus 10 per cent thereon shall be allowed therefor, provided that the vouchers for the labour and materials employed shall have been delivered to the Executive Engineer or his representative within seven days after such work shall have been completed. If the Executive Engineer considers that payment for such work on the basis of the vouchers presented is unduly high, he shall make payment in accordance with such valuation as he considers fair and reasonable and his decision to the matter shall be final, if the amount involved in additional payment is Rs 1000 or less, for each occasion on which such additional works shall have been authorised. If such amount exceeds Rs 1000, the contractor shall have the right to submit the matter to arbitration under the provisions of arbitration clause 73.
    (e) If, in the opinion of the Executive Engineer, a rate for the additional work is not capable of being properly arrived at prior to execution of work, or if the work is not capable of being properly measured, then the cost and payment thereof shall be dealt with as provided for in the preceding sub-clause (d)(ii).”

    7. In the case of S. Harcharan Singh v. Union of India (1990) 4 SCC 647, on which Mr Rao had strongly relied, this Court had quoted clause 12 of the agreement in para 8 of the judgment and referring to the standard form of contract of the Central Public Works Department, specifically permitting for a limit of variation called “deviation limit” up to a maximum of 20 per cent, it was held that the contractor has to carry out the work at the rate stipulated in the contract up to such limit but for work in excess of that limit he has to be paid at the rates to be determined in accordance with clause 12-A, under which the Engineer-in-charge can revise the rates, having regard to the prevailing market rates. The Court also referred to the letters of the Executive Engineers, the Superintending Engineer and the Additional Chief Engineer recommending that the additional work may be confined to 20 per cent and for the extra quantity of additional work, he may be paid remuneration at the increased rate taking into account the increased cost of the execution of work on account of the peculiar nature of the work. We fail to understand how the aforesaid decision will be of any assistance to the claimant in the present case, where there is no clause like clause 12-A nor is there any letter from the competent authority agreeing to payment at a higher rate for the additional work beyond the limit of 25 per cent as provided under GOMs No. 2289 dated 12-6-1968. An arbitrator being a creature of the agreement, unless the agreement either specifically or inferentially provides for a higher rate to be awarded for any additional or excess work done by the contractor, it would not be permissible for the arbitrator to award for the so-called additional work at a higher rate. In the case in hand, not only is there no letter from the competent authority, namely, the Superintending Engineer that the contractor would be paid at any higher rate for the additional excavation of rock, though the Executive Engineer had indicated that he has recommended to the Superintending Engineer. But such recommendation of the Executive Engineer, who was not competent to decide the question of awarding a higher rate for the excess quantity of excavation will not clothe (sic confer) any jurisdiction on the arbitrator to award the contractor at a higher rate nor would it entitle the contractor to get a higher rate for the claim in question on the basis of agreement. Now coming to the very clause, upon which Mr Rao relied, we find that the said clause relates to supplemental items, which have been found essential, incidental and inevitable during the execution of the work. The excavation of hard rock cannot be held to be a supplemental item and, on the other hand, it is an item of work tendered and accepted, and as such clause 63 will have no application to Claim Item 1. Mr Rao had also relied upon the decision of this Court in National Fertilizers v. Puran Chand Nangia (2000) 8 SCC 343 wherein this Court had held that an interpretation of a particular clause of the agreement must be such, so as to balance the rights of both the parties and when a variation clause permits the employer to make variation in the work up to a specified limit, beyond the said limit the claimant could be paid at a higher rate. The Court in the aforesaid case was examining the principle of integrity of the contract and refused to interfere with the award merely because the arbitrator had granted an escalation. In the aforesaid case, the Court was examining whether it would be permissible for interfering with an award which was a non-speaking one merely because the arbitrator had awarded the claim at an escalated rate for the excess quantity of work and since the award itself was a non-speaking award, the Court held that it is not permissible to probe into the mental process of the arbitrator and then interfere with the same. Then again the question of granting a higher rate for any extra quantity of work executed by the contractor would at all arise only when the contract provides for such escalated rate either expressly or by implication as in the case of S. Harcharan Singh (1990) 4 SCC 647 where the competent authority had agreed for the same by correspondence. But in the case in hand, when there is no such acceptance by the competent authority, and there is no provision in the contract, permitting such escalated rate for the additional quantity of excavation made and in view of our rejecting the contention raised on the basis of clause 63, the conclusion is irresistible that the contractor will not be entitled to a higher rate for the additional excavation work and as such the High Court was fully justified in setting aside the direction of the trial Judge, remitting Claim Item 1 for reconsideration and we see no infirmity with the said direction of the High Court to be interfered with. We also find sufficient force in the submission of Ms Amareswari, relying upon the letters of the competent authority, specifically intimating that the grant of extension of time will not in any way make the contractor eligible for any extra claim due to escalation in rates of labour and materials or due to any other reasons under any circumstances and the decision of this Court in Ramalinga Reddy (1999) 9 SCC 610 supports the aforesaid contention. In the aforesaid premises, we do not find any merit in this appeal, requiring our interference with the impugned judgment of the High Court. The appeal fails and is dismissed but in the circumstances there will be no order as to costs.

    Use AI to get other relevant cases.

    Comments

    Ramachandra Reddy & Co. v. State Of A.P And Others
    (Feb 27, 2001)