Factual and Procedural Background

The petitioners sought writ directions from the High Court of Madhya Pradesh, Jabalpur, compelling the respondents to issue them tender forms for works on a National Highway project. They asserted compliance with “Condition 2” of the tender notice, which specifies prior completion of certain large-scale highway/runway works.

A learned Single Judge, and subsequently a Division Bench on 14 August 1996 in LPA No. 138 of 1996, dismissed the petitions. During the pendency of the writ proceedings, an interim order had allowed the petitioners to submit tender forms, but the final judgment rejected their claims. The petitioners then filed the present special leave petitions before the Supreme Court challenging the High Court’s dismissal.

Legal Issues Presented

  1. Whether the petitioners satisfied “Condition 2” of the tender, which requires satisfactory completion of at least two runway/National Highway works of specified monetary value within the previous five years.
  2. Consequently, whether the High Court erred in law in refusing to direct the respondents to issue and consider the petitioners’ tender forms, thereby allegedly infringing their right to compete for government contracts.

Arguments of the Parties

Petitioners' Arguments

  • They possess past experience in National Highway works and had secured two contracts valued at approximately 42 % of Rs 4 crore and Rs 6 crore respectively, which meets the monetary threshold under Condition 2.
  • Certificates from competent engineers (Executive Engineer and Superintending Engineer) attest to satisfactory performance.
  • A “major part” of both projects has been executed within the contractual period; therefore, full completion should not be a prerequisite for receiving tender documents.
  • Denial of tender forms violates their fundamental right to compete for public contracts.
  • Reliance on New Horizons Ltd. v. Union of India (1995) 1 SCC 478, urging that prior experience should be assessed after submission of tenders, not before issuance of tender documents.

Respondents' Arguments

The opinion does not contain a detailed account of the respondents' legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
New Horizons Ltd. v. Union of India (1995) 1 SCC 478 Prior experience is to be evaluated after tender submission, not as a pre-condition for obtaining tender forms. The Court distinguished this case, holding that New Horizons dealt with evaluation criteria after a valid tender is submitted, whereas the present tender expressly makes completion of specified works a preliminary eligibility condition.

Court's Reasoning and Analysis

Examining the language of Condition 2, the Court emphasised the term “satisfactorily completed” as a mandatory pre-condition. The requirement is that, on the date of applying for a tender form, the bidder must have already completed at least two runway/National Highway projects (preferably rigid pavement) of Rs 400 lakhs each, or one project of Rs 600 lakhs, within the preceding five years, and possess specified equipment and turnover.

The petitioners conceded that the referenced contracts were still in progress, albeit “substantially” performed. The Court held that partial completion does not satisfy the express language of the tender. Therefore, the High Court’s refusal to compel issuance of tender forms was legally sound.

The reliance on New Horizons was rejected because that judgment concerned post-submission evaluation of prior experience, not pre-eligibility where completion is explicitly stipulated.

Holding and Implications

DISMISSED

The special leave petitions were dismissed, leaving the High Court’s decision intact. The immediate consequence is that the petitioners remain ineligible to receive or have their tenders considered for the present contract. The order reinforces that government purchasers may impose—and strictly enforce—objective, pre-tender eligibility criteria. No new legal doctrine was formulated beyond affirming adherence to explicit tender conditions.

To access the original judgment, please Sign In or Subscribe.

    Shapers Construction (P) Ltd. And Another v. Airport Authority Of India And Another

    Order

    1. The petitioners have filed these special leave petitions against the order of the Division Bench of the High Court of M.P at Jabalpur made on 14-8-1996 in LPA No. 138 of 1996. The learned Single Judge as well as the Division Bench dismissed the writ petitions in which the petitioners had sought direction to the respondents to give the tender form on the ground that they had satisfied condition 2 of the tender conditions. Pursuant to the interim order passed by the High Court, the petitioners submitted their tender forms. But, at the final hearing, the writ petitions came to be dismissed. Thus, these special leave petitions.

    2. It is contended for the petitioners that they have past experience in execution of the national highway. They have two contracts of more than required amount specified in the tender conditions, 42% of Rs 4 crores and Rs 6 crores respectively. The certificates issued by the competent engineers, namely Executive Engineer and the Superintending Engineer would show that the petitioners have been satisfactorily performing their duties in execution of the work. The petitioners, after securing the contracts, have executed major part of the work within the scheduled time granted under the contracts. Therefore, the failure to give tender form at the inception and consideration thereof after the interim direction is violative of their fundamental right to compete in the tender for the further contract. The question is whether the view taken by the High Court is wrong in law? Tender condition 2 envisages as under:

    “The tenderer who wish to apply shall have satisfactorily completed at least two runway/National highway, preferably rigid pavement works involving considerable earth filling each of value Rs 400 lakhs or one work of Rs 600 lakhs during the last five years and have annual turnover of Rs 500 lakhs in each (1992-93, 1993-94 & 1994-95) and should possess computerised hot mix plant and concrete batching plant for executing asphaltic and rigid pavement works.”

    3. A reading of this condition would clearly indicate that the tenderers who wish to apply shall have satisfactorily completed at least two runway/National highway, preferably rigid pavement works involving considerable earth filling, each valuing Rs 400 lakhs and one work of Rs 600 lakhs during the last five years and have annual turnover of Rs 500 lakhs in each of the last three years (1992-93, 1993-94 and 1994-95). He should possess computerised hot mix plant and concrete batching plant for executing asphaltic and rigid pavement works.

    4. It is true, as contended by the petitioners, that the tender condition would indicate that they had completed at least two runway/National highway, preferably rigid pavement works. He contends that the completion of the work is different from tendering the contracts for execution of the work. They had two contracts as envisaged thereunder; though they had not totally completed the same, major part of the work had been completed. Therefore, they have fulfilled the conditions prescribed thereunder. The petitioners, thereby, could not be denied of their right to compete in, apply for and be considered for assignment of the work under the tenders now in dispute. We find no force in the contention.

    5. The condition envisages that he shall have satisfactorily completed. The word ‘completed’ would indicate that as on the date of application for the tenders, he should have completed at least two runway/National highway works, preferably rigid pavement works involving considerable earth filling. In other words, the completion of the work of at least two runway/National highway is a precondition. On their own admission, they had not completed, though the major part of the work as professed by them is completed. Under these circumstances, the view taken by the High Court cannot be said to be unwarranted.

    6. The learned counsel placed strong reliance on the judgment of this Court in New Horizons Ltd. v. Union of India (1995) 1 SCC 478, in particular, paras 21 and 22 in support thereof. This case relates to previous experience and the question therein was whether the previous experience would be considered after submitting the tenders or before submitting the tenders? This Court had held that the question would arise only after the submission of the tender. In support of consideration of the tender thereof, the previous experience would play an important role for awarding the contract. In that case, this Court considered and held that at the inception, the tender forms cannot be refused on the ground that he had not proved the previous experience. That question has no relevance to the facts in these petitions. Under these circumstances, as stated earlier, the completion of the work of at least two runway/National highway works is a precondition for submitting the application. On their own admission, since the petitioners had not completed the works in hand, we cannot find any illegality in respondents not giving the tender forms nor in non-consideration of their cases pursuant to the interim direction given by the High Court.

    7. The petitions are accordingly dismissed.

    Use AI to get other relevant cases.

    Comments

    Shapers Construction (P) Ltd. And Another v. Airport Authority Of India And Another
    (Sep 17, 1996)