AMICUS AI
Citation Codes
Neutral Citations
1995 INSC 409
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 2 of the said Act
  • Explanation I(a) of Section 2(2) of the U.P Urban Buildings (Regulation of Letting, Rent and Eviction) Act, 1972
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
1995 INSC 409
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 2 of the said Act
  • Explanation I(a) of Section 2(2) of the U.P Urban Buildings (Regulation of Letting, Rent and Eviction) Act, 1972
Smart Summary

Factual and Procedural Background

The opinion arises out of an appeal in which leave was granted. Respondent 1 had already entered appearance, and service of notice of the appeal on Respondents 2 and 3 (described as formal parties) was dispensed with. The dispute before the Court concerned determining the relevant “date of construction” of a building under the U.P. Urban Buildings (Regulation of Letting, Rent and Eviction) Act, 1972. The High Court had decided the matter on the footing of an assessment effected in 1981; the Supreme Court found that certain aspects under the statutory explanation governing deemed completion did not appear to have been considered by the High Court.

Legal Issues Presented

  1. How should the “deemed date of completion/construction” be determined under Explanation I(a) to Section 2(2) of the U.P. Urban Buildings (Regulation of Letting, Rent and Eviction) Act, 1972, particularly where there is an earlier municipal assessment notice (dated 15-11-1977) and a later assessment (1981)?
  2. Whether the High Court erred by proceeding only on the basis of the 1981 assessment without considering whether an earlier municipal act (notice for assessment dated 15-11-1977) was the earliest relevant date under Explanation I(a).

Arguments of the Parties

Appellant's/Contending Party's Position

  • Under Explanation I(a) to Section 2(2) of the 1972 Act, deemed completion depends on the earliest relevant date among those specified (including reporting/recording by the local authority and the date when first assessment comes into effect, among others).
  • Since the Municipal Authority issued a notice for assessment on 15-11-1977, that date should be treated as the date on which the Municipal Authority had already taken note of the construction.
  • Because 15-11-1977 was asserted to be the earliest of the dates contemplated by Explanation I(a), it should be treated as the relevant deemed date of construction.
  • The High Court did not appear to have undertaken this inquiry and instead relied only on the 1981 assessment.

Respondent's Arguments

  • The respondent relied on the Supreme Court decision in Om Prakash Gupta v. Dig Vijendrapal Gupta, (1982) 2 SCC 61.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Om Prakash Gupta v. Dig Vijendrapal Gupta . (1982) 2 SCC 61 Relied upon by the respondent in relation to determining the relevant date for construction/assessment context. The Court held the decision was not applicable because, in that case, there was no question of the Municipal Authority having taken note of construction on an earlier date for the purpose of issuing a notice for assessment.

Court's Reasoning and Analysis

The Court considered that, to decide the “date of construction,” it was necessary to refer to Explanation I(a) of Section 2(2) of the U.P. Urban Buildings (Regulation of Letting, Rent and Eviction) Act, 1972. The Explanation provides that construction is deemed completed based on specified events/dates, including:

  • the date completion is reported to or otherwise recorded by the local authority having jurisdiction;
  • in case the building is subject to assessment, the date on which the first assessment comes into effect;
  • where the above dates differ, the earliest of those dates; and
  • in the absence of such report/record/assessment, the date of first actual occupation (excluding occupation merely for supervising construction or granting the building under construction).

Applying this framework, the Court observed that deemed completion, in terms of Explanation I(a), depends on identifying the earliest applicable date among those statutorily recognized. The contention before the Court was that a municipal notice for assessment dated 15-11-1977 indicated that the Municipal Authority had already taken note of the construction, and that this date was earlier than the assessment relied upon by the High Court.

The Court found that the High Court did not appear to have considered this aspect and instead proceeded solely on the basis of the assessment effected in 1981. As to the respondent’s reliance on Om Prakash Gupta v. Dig Vijendrapal Gupta (1982) 2 SCC 61, the Court distinguished it on the ground that, in that case, there was no issue of the municipal authority having taken note of construction on an earlier date through issuance of an assessment notice. Consequently, the precedent was held inapplicable to the issue raised.

Given the above, the Court set aside the High Court’s impugned decision and remitted the matter to the High Court for a fresh decision on merits, directing that the High Court determine which is the earliest deemed date of construction under Explanation I(a) to Section 2(2) for deciding the dispute.

Holding and Implications

IMPOUGNED HIGH COURT DECISION SET ASIDE; MATTER REMITTED; APPEAL DISPOSED OF.

  • The High Court’s decision was set aside and the case was remitted to the High Court for disposal on merits in light of the Supreme Court’s discussion, preferably within four months from receipt of the order.
  • The High Court was directed to determine the earliest deemed date of construction in terms of Explanation I(a) to Section 2(2) of the 1972 Act for purposes of deciding the dispute.
  • Until the High Court disposes of the matter, there would be a stay of eviction from the disputed premises.
  • The appeal was disposed of without any order as to costs. The opinion does not indicate that any new precedent was set; the direct effect was to require reconsideration by the High Court under the correct statutory framework and to maintain interim protection against eviction pending that decision.
To access the original judgment, please Sign In or Subscribe.

    Surendra Kumar Jain Alias Sunni v. Shanti Swaroop Jain And Others

    Order

    1. Leave granted.

    2. Respondent 1 has already entered appearance. Notice of the appeal need not be served on Respondents 2 and 3 who are formal parties and such notice on them is dispensed with.

    3. Heard learned counsel for the parties. It appears to us that for the purpose of deciding the date of construction it is necessary to refer to Explanation I(a) of Section 2(2) of the U.P Urban Buildings (Regulation of Letting, Rent and Eviction) Act, 1972. In the Explanation to the said section it has been indicated that the construction of a building shall be deemed to have been completed on the date on which completion thereof is reported or otherwise recorded by local authority having jurisdiction and in the case of building subject to assessment, the date on which the first assessment thereof comes into effect and where the said dates are different, the earliest of the said dates and in the absence of any such report record or assessment, the date on which it is actually occupied (not merely for the purpose of supervising the construction or granting the building under construction) for the first time.

    4. It, therefore, appears that in terms of Explanation I(a) the construction is deemed to have been completed on the date on which the completion thereof is reported to or otherwise recorded by the local authority having jurisdiction if such reporting or recording happens to be on the earliest point of time vis-à-vis various dates referred to hereinbefore. It is contended that in the instant case, the Municipal Authority having given notice for assessment on 15-11-1977, such date should be held to be the date when the Municipal Authority had already taken note of the construction of the building. Since that date is the earliest of the dates as referred to in Explanation I(a), that date becomes relevant for the purpose of considering deemed date of construction. It does not appear that such consideration has been made by the High Court in deciding the case. The High Court has proceeded on the footing only on the basis of the assessment effected in 1981. The learned counsel for the respondent has relied on a decision of this Court in Om Prakash Gupta v. Dig Vijendrapal Gupta (1982) 2 SCC 61. But it appears to us that in that case, there was no question of Municipal Authority having taken note of construction on an earlier date for the purpose of giving notice for assessment. Hence, that decision is not applicable for the purpose of deciding the issue raised in this case. We, therefore, set aside the impugned decision of the High Court and remit the case back to the High Court for disposal on merits in the light of above discussion preferably within a period of four months from the date of receipt of the order of this Court. The High Court will decide as to which is the earliest date of deemed construction in terms of date Explanation I(a) of sub-section (2) of Section 2 of the said Act for the purpose of deciding the dispute involved in the case. Until the matter is disposed of by the High Court, there will be stay of eviction from the disputed premises.

    5. The appeal is accordingly disposed of without any order as to costs.