AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Sections 3, 5, 11 and 12 read with Sections 8 and 9 of the Indian Arbitration Act
  • The Arbitration Act, 1940
  • Section of the Arbitration Act, 1940 (not specified)
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Sections 3, 5, 11 and 12 read with Sections 8 and 9 of the Indian Arbitration Act
  • The Arbitration Act, 1940
  • Section of the Arbitration Act, 1940 (not specified)
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Smart Summary

Factual and Procedural Background

The appellant, a Class I contractor, entered into an agreement dated 11 December 1986 with the Andhra Pradesh Industrial Infrastructure Corporation Ltd. (“the Corporation”) for constructing a main sewer line. After completion of the work, disputes arose regarding payment and other matters. Relying on what he believed to be Clause 73 of the “standard specifications” incorporated in a copy of the agreement supplied to him, the appellant sought arbitration. The named arbitrator did not act on the request.

Consequently, the appellant filed O.P. No. 132 of 1989 before the 5th Additional Judge, City Civil Court, Hyderabad, seeking removal of the named arbitrator and appointment of a new sole arbitrator. The trial court granted the application and appointed a retired District Judge as arbitrator.

The respondents challenged that order in Civil Revision No. 2269 of 1991 before the Andhra Pradesh High Court, which reversed the trial court on 13 February 1992, holding that the original, signed contract contained no arbitration clause. The appellant then filed Special Leave Petition No. 7575 of 1992 before the Supreme Court, leading to the present appeal.

Legal Issues Presented

  1. Whether an arbitration clause could be inferred or incorporated by reference when the original, signed contract contained no such clause.
  2. Whether the trial court was correct in appointing a sole arbitrator under Sections 3, 5, 8, 9, 11, and 12 of the Arbitration Act, 1940.
  3. Whether a copy of the contract, forwarded after execution and containing an arbitration clause, could bind the parties despite the absence of such a clause in the executed original.

Arguments of the Parties

Appellant's Arguments

  • The copy of the agreement (Ex. A-3) supplied by the Corporation, bearing its seal and signature, contained Clause 3 incorporating the standard specifications that provide for arbitration.
  • Because government and public-sector construction contracts generally include arbitration provisions, the omission in the original agreement should be treated as inadvertent.
  • The Corporation’s refusal to refer the dispute to arbitration and the inaction of the named arbitrator warranted judicial intervention to appoint a new arbitrator.

Respondents' Arguments

  • The original agreement (Ex. B-1), signed by both parties, deliberately omitted any arbitration clause pursuant to a 9 April 1984 policy decision of the Corporation to delete such clauses from its contracts.
  • The arbitration clause in the forwarded copy was included by mistake and was brought to the appellant’s notice before litigation commenced.
  • Since the contract lacked an arbitration clause, the trial court had no jurisdiction to appoint an arbitrator.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Jugal Kishore Rameshwardas v. Mrs Goolbai Hormusji (1955) 2 SCR 857 A written arbitration agreement need not be signed by both parties, provided the terms are reduced to writing and agreed upon. Reiterated to show that writing is essential, but the Court emphasised that here the signed writing contained no arbitration clause.
Union of India v. A.L. Rallia Ram (1964) 3 SCR 164 Contractual terms may be gathered from multiple documents/correspondence. Cited to underscore that multiple documents can form a contract, yet the Court found no evidence of mutual intent to arbitrate outside the signed agreement.
Rukmanibai Gupta v. Collector, Jabalpur (1980) 4 SCC 556 Arbitration clause need not follow any particular form; intention to arbitrate is decisive. Used to test whether intention to arbitrate could be inferred; Court held that such intention was absent.
Heyman v. Darwins Ltd. 1942 AC 356 Distinguishes arbitration agreements from other contractual clauses; arbitration clauses are specifically enforceable. Referenced to highlight the special status of arbitration clauses and the need for clear assent.
North Western Rubber Co. and Huttenbach & Co., Re (1908) 2 KB 907, overruled on other points in Produce Brokers Co. v. Olympia Oil & Cake Co. (1916) 1 AC 314 Arbitration clauses concern the mode of determining rights, not the rights themselves. Cited in passing while discussing the nature of arbitration agreements; no direct effect on the outcome.

Court's Reasoning and Analysis

The Supreme Court reiterated that, under the Arbitration Act, an enforceable arbitration agreement must be in writing and mutually assented to. Both the trial court and the High Court had found that the original contract signed on 11 December 1986 contained no arbitration clause.

The appellant relied on a later-forwarded copy containing Clause 3, arguing that it incorporated the standard specifications with an arbitration provision. However, the Court noted:

  • The Corporation had adopted a policy on 9 April 1984 to delete arbitration clauses from its contracts, explaining the omission in the signed agreement.
  • The respondents had promptly informed the appellant that inclusion of the clause in the copy was a mistake.
  • No evidence showed that the parties mutually intended to add an arbitration clause after execution or that the forwarded copy superseded the original contract.

Applying the principles from the cited precedents, the Court held that incorporation of an arbitration clause by reference requires clear and specific intent. Such intent was absent; therefore, no arbitration agreement existed. The trial court’s appointment of an arbitrator was thus without jurisdiction. The High Court’s reversal was correct, and no ground for Supreme Court interference existed.

Holding and Implications

Appeal Dismissed.

The Supreme Court affirmed the High Court’s decision, ruling that the contract between the parties contained no arbitration clause and that the trial court’s appointment of an arbitrator was erroneous. The immediate consequence is that the parties must resolve their dispute through ordinary civil proceedings, as no arbitral forum is available. The decision reinforces the requirement of clear, written mutual assent for arbitration and clarifies that an inadvertently inserted clause in an unsigned copy cannot create an enforceable arbitration agreement.

To access the original judgment, please Sign In or Subscribe.

    M. Dayanand Reddy v. A.P Industrial Infrastructure Corporation Limited And Others

    G.N Ray, J.— Leave granted.

    2. Pursuant to the notice issued on the Special Leave Petition No. 7575 of 1992, the respondents have appeared and have filed counter-affidavits and the appellant has also filed affidavit of rejoinder. The special leave petition out of which this appeal arises is directed against order dated February 13, 1992 passed by the Andhra Pradesh High Court in Civil Revision No. 2269 of 1991. The said civil revision was filed by the respondents against order dated May 10, 1991 by which the learned 5th Additional Judge, City Civil Court of Hyderabad allowed the application filed under Sections 3, 5, 11 and 12 read with Sections 8 and 9 of the Indian Arbitration Act for removal of the named arbitrator in the agreement dated December 11, 1986 and to appoint the sole arbitrator in his place.

    3. The learned Judge, City Civil Court, inter alia came to the finding that it was a fit case where the sole arbitrator should be appointed for adjudicating the disputes and differences between the parties arising out of the agreement in question and the learned Judge appointed a retired District Judge as the sole arbitrator for adjudicating the disputes and differences arising out of the arbitration agreement for entering upon the reference and sign and pass the award according to law.

    4. The case of the appellant in short is that the appellant is a Class I Contractor. He entered into an agreement with respondent 1, A.P Industrial Infrastructure Corporation Ltd., for the construction of main sewer line from Point (H) near C.C Building IDA Nacharam to the disposal units of Nallacheru (near Uppal) on December 11, 1986. Pursuant to such agreement, the appellant completed the work in question. Since certain disputes and differences had arisen between the appellant and the said Corporation during the execution and completion of the contract, the appellant by notice dated June 27, 1988 requested the Chairman of the Corporation to refer the dispute for arbitration as per Clause 73 of the preliminary specifications of A.P standard specifications, hereinafter referred to as the standard specifications. As the first respondent refused to settle the claims, the appellant sent a claim petition dated October 3, 1988 to the named arbitrator which was received by the said named arbitrator on October 5, 1988. As the appellant did not receive any communication from the named arbitrator, he sent a reminder under registered post on November 28, 1988 to the named arbitrator. The named arbitrator, however, did not enter upon the reference within a period of one month and also did not pass any award within a period of four months as contemplated in the Indian Arbitration Act. The appellant also contended in the said application for appointment of arbitrator in place of the named arbitrator that the Chairman of the Corporation, namely, the first respondent had sent an undated letter signed on November 8, 1988 informing the appellant that para 3 of the article of the agreement since referred to by the appellant was erroneous and while making copies of the arbitration agreement entered into between the parties, wrong sheets were enclosed but in the original agreement, since signed between the parties, there was no arbitration clause for the work in question. The appellant, however, gave a further notice dated January 5, 1989 through his learned advocate calling upon the said respondent to concur for the appointment of anyone of the three persons named in the said notice to act as an arbitrator to adjudicate the disputes and differences arising between the parties. On receiving such notice, the first respondent by his letter dated January 18, 1989 informed the learned advocate of the appellant that as there was no arbitration clause in the agreement entered into between the parties, the question of entertaining the request to appoint arbitrator did not arise. In view of such failure on the part of the respondent to refer the dispute to the arbitration in terms of the said agreement between the parties, the appellant made a prayer for removing the named arbitrator in respect of the works in question and to appoint anyone of the three persons named in the application as sole arbitrator to adjudicate the disputes and differences. On such application made by the applicant in the court of the 5th Additional Judge, City Civil Court, Hyderabad, the proceeding being O.P No. 132 of 1989 arose.

    5. Respondent 1 opposed the said application and filed counter to the said application inter alia contending therein that the appellant entered into the agreement dated December 11, 1986 with the A.P Industrial Infrastructure Corporation for the said work and the time stipulated for the construction of the work was six months from the date of handing over of the site. The appellant, however, completed only a part of the work although the site was handed over to him. But before the completion of the entire work, the accounts were settled between the parties and the final bill was also paid to the appellant and the balance of work was got completed through other agencies. It was further contended that the original agreement signed between the parties did not provide for any arbitration clause and such fact was made known to the appellant. In view of the aforesaid position, the question of referring the matter to the arbitration or to the named arbitrator or to any other arbitrator did not arise.

    6. The learned Judge inter alia came to the finding that the original agreement dated December 11, 1986 executed between the parties in relation to the contract work did not contain any arbitration clause and the articles of the agreement only provided for various terms and conditions of the work and such agreement containing the aforesaid terms was also signed by both the parties. The learned Judge, however, held that conspicuously the agreement was silent about the mode of settlement of the disputes, if any, arising between the parties in respect of the work. Generally, every agreement of civil contract between the Government and the contractors or between the local bodies and the contractors contains an arbitration clause for settling the disputes between the parties. In the copy of the agreement which was supplied to the appellant since marked as Ex. A-3, the clauses appearing in the agreement were similarly entered without variation. In the copy of the agreement since furnished to the applicant, there was a clause being Clause 3 which provided for reference to arbitration in accordance with the standard specifications. It was further held by the learned Judge that the copy since supplied to the applicant had the stamp of respondent 2 and the covering letter under which the copy of the agreement was forwarded to the applicant also bore the seal and signature of the second respondent. Since the said copy of the agreement had not been fabricated by the applicant, the respondents were bound by the said clause 3 as referred to in the copy of the agreement. As, despite such agreement, the respondents failed and neglected to refer the matter for arbitration, the learned Judge was of the view that the application should be allowed. The learned Judge, therefore, appointed Shri J. Venugopal Rao, a retired District Judge, as the sole arbitrator for adjudicating all the disputes and differences between the parties and for entering upon the reference and thereafter sign and pass the award in accordance with law.

    7. The respondents being aggrieved by the aforesaid order of the learned Civil Additional Judge, moved the Andhra Pradesh High Court for revision. The learned Judge inter alia came to the finding that the original agreement Ex. B-1 since signed by the parties did not contain any arbitration clause at all. A copy of the agreement (Ex. A-3) was, however, forwarded to the applicant eleven days after the original agreement and the clause relating to arbitration as contained in Ex. A-3 was absent in the original agreement. The learned Judge was of the view that only the terms contained in original agreement since signed by the parties and not the terms contained in the copy forwarded to the applicant were binding between the parties. The learned Judge was also of the view that as in the original agreement, (Ex. B-1) signed by both the parties, there was no arbitration clause at all, it was not necessary to look into the other material or to consider other circumstances for the purpose of finding that the parties had also agreed for arbitration. The contention on behalf of the applicant that in the absence of any specific clause for reference of disputes to arbitration in the original agreement (Ex. B-1) the existence of such a clause should be assumed because the Government contractors are governed by the standard specifications, was not accepted by the High Court. In that view of the matter, the revision application was allowed by the High Court inter alia holding that the impugned order appointing an arbitrator was erroneous and not sustainable in law. As aforesaid, such order of the Andhra Pradesh High Court is impugned in the instant appeal.

    8. Under the Arbitration Act, 1940, only an arbitration agreement in writing is recognised by the Act. It has been held by this Court in Jugal Kishore Rameshwardas v. Mrs Goolbai Hormusji (1955) 2 SCR 857, AIR 1955 SC 812 that it is not necessary that the contract between the parties should be signed by both the parties. But it is necessary that the terms should be reduced in writing and the agreement between the parties on such written terms is established. It has also been held by this Court in Union of India v. A.L Rallia Ram (1964) 3 SCR 164, AIR 1963 SC 1685 that it is not necessary that all the terms of the agreement should be contained in one document. Such terms may be ascertained from the correspondence consisting of number of letters. In Rukmanibai Gupta (Smt) v. Collector, Jabalpur (1980) 4 SCC 556, AIR 1981 SC 479 this Court has laid down that an arbitration clause is not required to be stated in any particular form. If the intention of the parties to refer the dispute to arbitration can be clearly ascertained from the terms of the agreement, it is immaterial whether or not the expression arbitration or ‘arbitrator’ or ‘arbitrators’ has been used in the agreement. It is also not necessary that agreement to arbitration should appear in the document containing the other terms of agreement between the parties. Law is well settled that arbitration clause may be incorporated by reference to a specific document which is in existence and whose terms are easily ascertainable. It is to be noted, however, that the question whether or not the arbitration clause contained in another document is incorporated in the contract, is always a question of construction. It should also be noted that the arbitration clause is quite distinct from the other clauses of the contract. Other clauses of agreement impose obligation which the parties undertake towards each other. But arbitration clause does not impose on any of the parties any obligation in favour of the other party. Such arbitration agreement embodies an agreement between the parties that in case of a dispute, such dispute shall be settled by arbitrator, or umpire of their own constitution or by an arbitrator to be appointed by the Court in an appropriate case. It is pertinent to mention that there is a material difference in an arbitration agreement inasmuch as in an ordinary contract the obligation of the parties to each other cannot, in general, be specifically enforced and breach of such terms of contract results only in damages. The arbitration clause however can be specifically enforced by the machinery of the Arbitration Act. The appropriate remedy for breach of an agreement to arbitrate is enforcement of the agreement to arbitrate and not to damages arising out of such breach. Moreover, there is a further significant difference between an ordinary agreement and an arbitration agreement. In an arbitration agreement, the courts have discretionary power of dispensation of a valid arbitration agreement but the courts have no such power of dispensation of other terms of contract entered between the parties. This very distinctive feature of an agreement for arbitration has been highlighted in the decision in Heyman v. Darwins Ltd. 1942 AC 356, (1942) 1 All ER 337 It has been held in North Western Rubber Company and Huttenbach & Co., Re (1908) 2 KB 907 (overruled in Produce Brokers Co. v. Olympia Oil and Cake Co. (1916) 1 AC 314 (HL) on other points), that an arbitration agreement in no way classifies the right of the parties under the contract but it relates wholly to the mode of determining the rights. In the backdrop of such position in law relating to an agreement for arbitration, it is to be decided whether the existence of an agreement to refer the dispute to arbitration can be clearly ascertained in the facts and circumstances of the case. This, in turn, depends on the interaction of the parties to be gathered from the relevant documents and surrounding circumstances. In the instant case, it is the specific finding of the learned Judge of the City Civil Court, Hyderabad and also the Andhra Pradesh High Court that in the original agreement signed by the parties, there is no clause for referring the disputes to arbitration. The agreement between the parties in this case has been reduced in writing and has been signed by both the parties. It is therefore not necessary to make any effort for the purpose of finding out as to what were the terms agreed between the parties. The learned Judge, City Civil Court, allowed the application for appointment to arbitrator simply on the ground that a copy of the agreement was forwarded to the appellant with the seal and signature of a competent officer of the Corporation, namely, respondent 2 and in such copy, which was not fabricated by the applicant there was a reference for arbitration as contained in the standard specifications. The learned Judge, City Civil Court, also proceeded on the footing that usually in the agreements relating to the nature of the contract, a provision for arbitration is made. As in the original agreement signed between the parties there was no such provision and the agreement was silent on the question as to what would happen if the disputes would arise between the parties, it should be presumed that the parties had really intended to refer the dispute to arbitration in accordance with the standard specifications and in the copy of the agreement which was forwarded to the applicant the provision for arbitration was included. The High Court however, was not inclined to accept this view of the learned Judge of the City Civil Court. The High Court was of the view that it was the signed agreement between the parties which was binding on the parties and only such written terms in the original agreement signed by the parties should be taken into consideration and not the terms contained in the copy of the agreement which was forwarded to the applicant after some time.

    9. It has been indicated hereinbefore that the case of respondent is that through mistake the clause containing the arbitration agreement was not scored out in the copy of the agreement since forwarded to the applicant. The attention of the appellant was drawn to such mistake by the respondents before initiation of the proceedings before the City Civil Court. It also appears that on April 9, 1984, which is long before the agreement dated December 11, 1986, respondent 1, Corporation, came to the decision that arbitration was not really necessary as the aggrieved party to the agreement could always seek redress in a court of law. It was, therefore, decided that the arbitration clause in the standard specifications should be deleted altogether and the agreement was to be finalised in respect of engineering work without any provision for arbitration. It was also indicated that the instruction for deleting the arbitration clause should be followed with immediate effect. If in spite of such policy decision, the original agreement entered between the parties had contained the arbitration clause there is no manner of doubt that the parties to the agreement would have been bound by such arbitration agreement. Admittedly, in the instant case, in the original agreement signed between the parties, there is no clause for arbitration and the reason for absence of arbitration clause can be well explained by the aforesaid policy decision of the Corporation. An arbitration clause may be incorporated by reference to a specific document but the intention to refer to arbitration by such incorporation must be clear and specific. In the instant case, the original agreement signed between the parties does not contain any clause for arbitration. It is not the case of the applicant that the applicant had no occasion to know the terms of the agreement since signed by the parties and there was any clear representation that the copy of agreement was to be followed by the parties and terms contained in the copy were to be treated as the terms of agreement between the parties. Hence, it cannot be held that after the signed agreement the parties had clearly intended to include arbitration clause in the standard specifications. In the absence of clear intention of both the parties, agreement for arbitration cannot and should not be inferred more so when the specific case of the respondents is that by mistake the clause relating to arbitration crept in the copy of agreement. In our view, the High Court was justified in holding that in the facts of the case, only the original agreement, and not the copy, was binding between the parties. Hence, no reference to arbitration could be made. In the aforesaid circumstances, no interference is called for in the instant appeal and the appeal, therefore, fails and is dismissed, without, however, any order as to costs.

    Use AI to get other relevant cases.

    Comments

    M. Dayanand Reddy v. A.P Industrial Infrastructure Corporation Limited And Others
    (Mar 24, 1993)