AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Smart Summary

Factual and Procedural Background

The plaintiffs (appellants) sought an injunction to restrain Defendants 1 and 2—recorded owners of land comprising Survey Nos. 32 (part) and 33 (part), equal to CTS Nos. 74, 75, 84, 84(1 to 7), 95, 95(1 to 4) in Village Kurar, Malad, Bombay—covering 8006.04 m² from interfering with their possession. Defendants 3 and 4 claimed an interest through a partnership with Defendants 1 and 2. Interim relief was initially granted by the City Civil Court, but on appeal a learned Single Judge of the Bombay High Court required the plaintiffs to file a fresh suit in the High Court, leading to Suit No. 1811 of 1980 on the High Court’s Original Side.

A new interim injunction was granted but subsequently vacated at the instance of the respondents; the Division Bench upheld that vacation. Parallelly, in a writ petition questioning the grant of Floor Space Index (FSI) for the entire 17,000 m² plot—including the disputed 8006.04 m²—an interim order against using the FSI was first obtained and later vacated. Both matters reached the Supreme Court by special leave, resulting in the present consolidated appeals.

Legal Issues Presented

  1. Whether the plaintiffs established a prima facie case of lawful possession justifying an interim injunction restraining the respondents from interfering with that possession.
  2. Whether the respondents should be restrained from utilising the FSI for the whole 17,000 m² plot pending final adjudication, given the plaintiffs’ claim to approximately 8006 m².
  3. Where the balance of convenience lay in granting or refusing interim relief.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court noted that both sides were effectively litigating through proxies: the plaintiffs had granted an irrevocable power of attorney to third parties, while Defendants 1 and 2 had transferred their interest in the land to Defendants 3 and 4 via a partnership arrangement. Nevertheless, the central inquiry on an application for interim relief remained whether the plaintiffs had ever been in lawful possession and, if so, whether dispossession had occurred.

Without delving into detailed evidence—so as not to prejudice the forthcoming trial—the Court was satisfied that the plaintiffs demonstrated sufficient prima facie possession to warrant protection. It emphasised two practical considerations:

  • If the respondents proceeded to exploit the FSI over the entire parcel, irreversible construction could occur, undermining a fair adjudication of title.
  • Granting the injunction would cause limited inconvenience to the respondents, who still held approximately 9,000 m² on which they could continue construction activities.

Balancing these factors, the Court concluded that refusal of interim relief would risk irreparable harm to the plaintiffs and impede an impartial final determination.

Holding and Implications

Appeals ALLOWED; prior orders vacating interim injunctions are set aside. The respondents are restrained from (a) interfering with the plaintiffs’ possession of the disputed land and (b) using the FSI on the premise that they control the entire 17,000 m² parcel.

Implications: The decision reinstates interim protection for the plaintiffs and preserves the status quo until trial and writ proceedings are concluded. The Supreme Court directed the High Court to expedite those matters. No new legal precedent was announced; the ruling is confined to interlocutory relief based on the specific facts.

    Gangubai Bablya Chaudhary And Others v. Sitaram Bhalchandra Sukhtankar And Others

    Desai, J.— Appellants filed a suit for injunction restraining Defendants 1 and 2 who were the recorded owners of the land bearing Survey Nos. 32 (part) and 33 (part) equal to CTS Nos. 74, 75, 84, 84(1 to 7), 95, 95(1 to 4) of village Kurar, Malad, Bombay admeasuring 8006.04 sq metres. Defendants 3 and 4 claimed to have entered into partnership with Defendants 1 and 2. In this suit a notice of motion was taken out for interim injunction restraining the respondents for interfering in any manner with the possession of the plaintiffs during the pendency of the suit. Interim injunction appears to have been granted. In an appeal, a learned Single Judge of the Bombay High Court directed the plaintiffs to file a separate suit in the High Court for declaration of the title and for injunction, whereupon the suit filed by the plaintiffs in the City civil court was withdrawn and suit bearing No. 1811 of 1980 was filed on the original side of the Bombay High Court. A notice of motion was taken out for interim injunction which was granted by learned Single Judge of the High Court, with a reservation for reconsideration of the order on the happening of certain events set out in the order. It appears that the respondents moved the High Court for vacating the order and the interim injunction was vacated. After an unsuccessful appeal to the Division Bench, this appeal by special leave is filed.

    2. In a writ petition filed by the petitioners questioning the validity of the order granting the use of FSI for the whole land including the land on which the plaintiffs claimed title, an interim injunction was obtained restraining the use of the FSI by the respondents. Subsequently, this interim order was vacated. After an unsuccessful appeal, the present appeal has been filed by special leave.

    3. Mr V.S Desai addressed at some length for the appellant and Mr Tarkunde for the respondents.

    4. This court is called upon to examine the proceeding at the stage when it is necessary to find out whether plaintiffs have a prima facie case to enable them to obtain an interim injunction restraining the respondents from interfering with their possession as also restraining the respondents from using the FSI for the whole of the land? The whole plot is around 17,000 sq metres. Plaintiffs claimed title to and possession of an area admeasuring 8006.04 sq metres. The use of the FSI is granted to the respondents on the footing that they are entitled to put up construction over the entire area admeasuring 17,000 sq metres. It is also necessary to examine where the balance of convenience lies.

    5. It is unfortunate that this is more or less a fight by proxy. Plaintiffs have executed an irrevocable power of attorney in favour of Shri Velji Ramlal Shah & Shri Gashi Ramlal Shah. Similarly Respondents 1 and 2 who were the original Defendants 1 and 2 had entered into a partnership with Defendants 3 and 4 contributing the land involved in the dispute as their capital and Defendants 3 and 4 bringing in cash contribution and this partnership is dissolved whereby Respondents 1 and 2 have taken the cash and the land involved in the dispute has gone to Defendants 3 and 4. We do not propose to express any opinion on the nature of this transaction. Fact remains that this is a fight by proxy.

    6. When an interim injunction is sought, the court may have to examine whether the party seeking the assistance of the court was at any time in lawful possession of the property and if it is so established one would prima facie ask the other side contesting the suit to show how the plaintiffs were dispossessed? We pin-pointed this question and heard the submission. We refrain from discussing the evidence and recording our conclusions because evidence is still to be led and the contentions and disputes have to be examined in depth and any expression of opinion by this court may prejudice one or the other party in having a fair trial and uninhibited decision. Having given the matter our anxious consideration, we are satisfied that this is not a case in which interim injunction could be refused. Similarly we are of the opinion that if respondents are allowed to put up construction by the use of the FSI for the whole of the land including the land involved in dispute, the situation may become irreversible by the time the dispute is decided and would preclude fair and just decision of the matter. If on the contrary injunction is granted as prayed for the respondents are not likely to be inconvenienced because they are in possession of about 9000 sq metres of land on which they can put up construction.

    7. We accordingly allow both the appeals, set aside the decision of the learned Single Judge vacating the injunction in both the matters as well as the decision of the Appellate Bench and order that the respondents are restrained from interfering with the possession of the plaintiffs-appellants of the suit land. The respondents are further restrained from using the F.S.I on the footing that they are in possession of the whole of the land.

    8. In view of the fact that we grant interim relief, we direct that the hearing of the suit and the writ petition from which these appeals arise be expedited and we hope and trust that the High Court would give top priority to the same consistent with its calendar.

    9. In the circumstances of the case, there will be no order as to costs.

    Use AI to get other relevant cases.

    Comments

    Gangubai Bablya Chaudhary And Others v. Sitaram Bhalchandra Sukhtankar And Others
    (May 13, 1983)