AMICUS AI
Citation Codes
Neutral Citations
1963 INSC 252
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • The Arbitration Act, 1940
  • O. XLI, r. 27, Code of Civil Procedure
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
1963 INSC 252
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • The Arbitration Act, 1940
  • O. XLI, r. 27, Code of Civil Procedure
Smart Summary

Factual and Procedural Background

The Borough Municipality of Bhusawal filed two separate suits seeking refund of amounts it had paid, under protest, to the Bhusawal Electricity Company Ltd. as war-costs surcharge on electricity charges. The Municipality prevailed in the trial court and again on first appeal before the District Court. On second appeal, however, the Bombay High Court reversed those decrees—relying on additional documentary evidence admitted at that stage—and dismissed both suits. The Municipality obtained special leave to appeal to the Supreme Court, leading to the present judgment, which also governs Civil Appeal No. 48 of 1961.

Legal Issues Presented

  1. Whether the Municipality was entitled to a refund of the surcharge payments in view of a communication dated 22 May 1946, by which the Government of Bombay had decided—under the second proviso to Clause 5 of the Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944 (“Surcharge Order”)—that the Municipality must pay a 15 % surcharge to the Electricity Company.
  2. Whether the High Court, sitting in second appeal, was competent to admit additional evidence under Order XLI Rule 27 of the Code of Civil Procedure, 1908.
  3. Whether the second proviso to Clause 5 required that a dispute be referred to the Government by both parties, or whether a unilateral reference was sufficient.
  4. Whether the 22 May 1946 communication constituted a final and binding decision or was merely an opinion of the Government.

Arguments of the Parties

Appellant’s Arguments (Bhusawal Borough Municipality)

  • The High Court lacked power in second appeal to admit additional evidence; Order XLI Rule 27 is inapplicable at that stage and cannot be used to fill evidentiary lacunae.
  • No evidence showed that the dispute had been referred to the Government; the letter of 22 May 1946 was only an “opinion,” not a binding decision.
  • The second proviso to Clause 5 made the Government an arbitrator; therefore, under the Arbitration Act, 1940 a reference by both parties was necessary. (The Supreme Court declined to entertain this point because it had not been raised below.)

Respondent No. 1’s Position (Bhusawal Electricity Co. Ltd.)

  • The Government’s decision under the second proviso was final and binding, barring the Municipality’s claim for refund.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Supreme Court focused on the legal effect of the Government’s communication dated 22 May 1946:

  • The letter explicitly stated that “Government has fully considered your case … and has decided that you should pay the surcharge … at the rate of 15 %.” The Court saw no basis to treat this as a mere opinion; it amounted to a formal decision under the second proviso to Clause 5.
  • The proviso’s wording—“in the event of dispute by any party interested”—made clear that a unilateral reference sufficed; referral by both parties was not required.
  • Because the surcharge claim of the Electricity Company was founded directly on that Government decision, misconstruing the letter was an error of law. The High Court, therefore, acted within its jurisdiction in correcting that error in second appeal.
  • Given its conclusion on the binding nature of the Government’s decision, the Supreme Court found it unnecessary to rule on the propriety of admitting additional evidence, though it noted that no objection had been raised when the High Court did so.

Holding and Implications

The appeals were dismissed with costs.

Consequently, the Municipality must pay the 15 % surcharge as ordered by the Government of Bombay, and its suits for refund fail. The decision reinforces the finality accorded to Government determinations under the second proviso to Clause 5 of the 1944 Surcharge Order; however, the Court did not establish broader precedent beyond affirming the binding nature of such determinations on the parties.

To access the original judgment, please Sign In or Subscribe.

    Bhusawal Borough Municipality v. Amalgamated Electricity Co. Ltd., Bhusawal And Another

    http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4

    PETITIONER:

    BHUSAWAL BOROUGH MUNICIPALITY

    Vs.

    RESPONDENT:

    AMALGAMATED ELECTRICITY CO. LTD. &ANR.

    DATE OF JUDGMENT:

    10/12/1963

    BENCH:

    MUDHOLKAR, J.R.

    BENCH:

    MUDHOLKAR, J.R.

    SINHA, BHUVNESHWAR P.(CJ)

    DAYAL, RAGHUBAR

    AYYANGAR, N. RAJAGOPALA

    CITATION:

    1966 AIR 1652 1964 SCR (5) 905

    CITATOR INFO :

    F 1977 SC 27 (7)

    ACT:

    Bombay Electricity Supply (Licensed Undertakings was Cost. Order, 944, cl. 5-Scope of-Construction of document--If question of law.

    HEADNOTE:

    The Municipality filed two suits to claim refund of two sum of money paid by them to the respondent no. 1 under protest a, electricity charges. The defence of the respondent no. 1 was that the dispute between it and the municipality was decided by the Government of Bombay and that under the second proviso to cl. 5 of the Surcharge Order, 1944 the decision of the Government was final and binding both on the appellant and the respondent no. 1. The decision of the Government was communicates to the parties by the letter dated May 22, 1946. The appellant succeeded in both the suits in the trial court as well as the District

    906

    Court. In second appeal, the High Court dismissed the two units. Hence this appeal.

    Held: (i) The Municipality was not entitled to claim fund because the dispute between the parties had been decided by the Government under the second proviso to cl. 5 of the Surcharge order, 1944. The decision of the Government was final and binding on the parties.

    (ii) The communication dated May 22,1946 sent by the Govern- ment to both the parties was a final decision under the second proviso to cl. 5 of the Surcharge Order, 1944. There is no reason to think that the communication contains nothing but the opinion of the Government.

    (iii) The second proviso to cl. 5 of the Surcharge Order does not require that the dispute has to be referred by both the parties. Such a dispute can be referred by one of the parties as clear from the language of the proviso which says "in the event of dispute by any party interested" the decision of the provincial Government shall be final.

    (iv) The Trial Court and the District Court had wholly mis- construed the document dated May 22, 1946 which is not

    1

    merely of evidentiary value but is one upon which the claim of the respondent no. 1 for the surcharge is based. Misconstruction of such document would thus be an error of law and the High Court in second appeal would be entitled to correct it.

    JUDGMENT:

    CIVIL APPELLATE JURISDICTION: Civil Appeals Nos. 47 and 48 of 1961.

    Appeals by special leave from the judgment and decree dated August 5, 1957, of the Bombay High Court in Appeal No. 1085 of 1954 with second Appeal No. 1086 of 1954. G.S. Pathak and Naunit Lal, for the appellant.

    I. N. Shroff, for respondent no. 1 M.S.K. Sastri and R.H. Dhebar, for respondent No. 2. December 10, 1963. The Judgment of the Court was delivered by

    MUDHOLKAR J.-This judgment will also govern C.A. no. 48 of 1961. Both the appeals are by special leave from the judgment of the Bombay High Court in second appeal disposing of two appeals which arise out of two separate suits instituted by the appelant, the Borough Municipality of Bhusawal, against

    907

    the Bhusawal Electricity Co. Ltd., respondent No. 1 before us, to which suits the State of Bombay was later added as a defendant.

    In each of the two suits the appellant had claimed refund of two sums of money paid by them to the respondent No. 1 under protest as electricity charges to which the respondent No. 1 claimed to be entitled by virtue of an order made by the Government of Bombay under the Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944 (herein referred as Surcharge Order ). The appellant succeeded in both the suits in the trial court as well as the District Court. In second appeal, however, the High Court set aside the decrees passed by the trial court and dismissed the two suits. While doing so, the High Court admitted on record certain documents by way of additional evidence and the only contentions raised before us by Mr. G.S. Pathak for the appellant are firstly that the High Court is incompetent in second appeal to admit additional evidence on record in- asmuch as O. XLI, r. 27, Code of Civil Procedure is inapplicable to a second appeal. Secondly, the provisions of O. XLI, r. 27 cannot be used to fill up the lacuna in the evidence left by a party. We may incidentally mention that when the High Court, by its order dated April 30, 1958, decided to admit additional evidence on record, no objection was raised on behalf of the appellant before us. It seems to us to be wholly unnecessary to decide in this case whether the High Court has the power to admit additional evidence in second appeal and also whether even if it has that power it was right in admitting the evidence in the circumstances of this case. Basing itself on a particular interpretation of the agreements regarding payment of electric charges with respondent no. 1, the appellant claimed refund on the ground that it was not liable to pay the surcharge payable under the Surcharge Order, 1944 in respect of electrical energy consumed by it. The substantial defence of the respondent no. 1 was that the dispute between it and the municipality was

    908

    decided by the Government of Bombay and that under the

    2

    second proviso to cl. 5 of the Surcharge Order, 1944 the decision of the Government was final and binding both on the appellant and the respondent No. 1.The relevant provisions read thus:

    Clause 5: "Upon the rate of the War Costs

    Surcharge being fixed by the Provincial

    Government from time to time in accordance with this order, it shall not be lawful for the licensee or sanction-holder concerned to supply energy at other than charges surcharged at the rate for the time being so fixed:"

    * * * *

    Second proviso: "Provided further that no

    War Costs Surcharge shall be effective upon the charges for the supply of energy under any contract entrered into after the 1st May,

    1942, unless such contract provides for the same charges for energy as have been contained in similar previous contracts for similar

    supply by the licensee or sanction holder

    concerned (as to which in the event of dispute by any party interested, the decision of the Provincial Government shall be final) or

    unless and to such extent as such application may be expressly ordered by the Provincial Government."

    It is not disputed before us by Mr. Pathak that the decision of the Government upon the dispute is final and binding on the parties. But, according to him, it was not established by the evidence led in the trial Court that the dispute between the parties had at all been referred to the Government and that a certain communication sent by the Government to the parties, Ex. 68 dated May 22, 1946 relied upon by the respondent no. 1, contains nothing but the opinion of the Government. Mr. Pathak further urged that the proviso referred to by us purports to constitute the Govern-

    909

    ment into an arbitrator and, therefore, there had to be a reference to the arbitrator by both the parties to the dispute under the provisions of the Arbitration Act, 1940. This latter point, however, had not been taken in the courts below nor is it found in the statement of the case. We have, therefore, not permitted Mr. Pathak to rely upon it before us.

    The communication of May 22, 1946 relied upon by the first respondent runs thus:

    "No. 6404/36-E1(1). Public Works Department, Bombay Castel, 22nd May, 1946.

    From

    The Secretary to the Government of Bombay Public Works Department (Irrigation).

    TO

    The President, The Borough Municipality, Bhusawal.

    Subject: War Costs Surcharge. Dear sir,

    With reference to the correspondence ending with Government letter no. 6404/36, dated the 10th May, 1946 on the subject mentioned above, I am to inform you that Government has fully considered your case under the second proviso to clause 5 of the Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944, and has decided that you should pay the

    3

    surcharge to the Bhusawal Electricity Co. Ltd., at the rate of 15 % fixed in Government Order No. 6331/36 (IV) dated the 15th August, 1944, unless the Company raised its rate of supply of energy for street lighting to more than 4 annas per unit.

    Yours faithfully,

    Sd/ D.N. Daruwala.

    for Secretary to the Govt. of Bombay. Copy forwarded for information to: Public works Department, the Electrical Engineer to the

    910

    Government with reference to his No. LRM.57/ 5260, dated the 8th March, 1946. The Account- ant General, Bombay with reference to his No. O.A. 2888, dated the 2nd February 1946. Messrs The Bhusawat Electricity Co. Ltd., Bombay with reference to correspondence ending with Government letter No. 6404/36-El. (i) dated the 17th May 1946. CC to E.E. Bhusawal for information sent on 25th May 1946."

    It is obvious from this communication that both the parties, that is, the appellant as well as the respondent no. 1 had stated their respective cases before the Government. There was no occasion for them to do so unless they were both purporting to act under the second proviso to cl. 5 of the Order of 1944. After consideration of the cases of both the parties the Government has stated in the aforesaid communi- cation that it had decided that the municipality should pay to the Electricity Company surcharge at the rate of 15% fixed in a certain Government Order unless the Company raised its rate for the supply of energy for street lighting to more than four annas per unit. There is no reason to think that what is on the face of it a decision is nothing but an opinion because if there were anything in the correspondence to which a reference is made in that letter as well as in the endorsement at the bottom which went to show that the appellant did not purport to refer any dispute to the Government, it was for the appellant to produce that correspondence. Its omission to do so must be construed against it. Then Mr. Pathak said that under the Surcharge Order itself the dispute had to be referred by both the parties and not by only one of them. This contention is, however, untenable in view of the clear language of the proviso which says: "In the event of dispute by any party interested" the decision of the Provincial Government shall be final. There is, therefore, no substance in the contention. In our opinion the trial court and the District Court had wholly misconstrued this document which is not merely of evident-

    911

    iary value but is one upon which the claim of the respondent no. 1 for the surcharge is based. Misconstruction of such a document would thus be an error of law and the High Court in second appeal would be entitled to correct it. This is what in fact has been done.

    There is no substance in the appeals which are dismissed with costs.

    Appeals dismissed.