Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
Smart Summary

Case Summary — Appeal against refusal to stay suit under Section 34 of the Arbitration Act

Factual and Procedural Background

The plaintiff, Jawahar Mal and Sons, filed a suit for recovery of Rs. 68,349/5/3 against the Punjab State for damages for breach of a contract for erecting a high-level bridge over the Rangeelpur Naddi. The State sought a stay of the suit under the provisions of Section 34 of the Arbitration Act, asserting that an arbitration clause in the agreement required disputes to be decided by arbitration.

The trial Court (Senior Sub-Judge, Simla) framed four issues: (1) validity of the agreement to refer disputes to arbitration; (2) competence of Shri Walaya Ram to enter into the agreement on behalf of the plaintiff firm; (3) whether the Superintending Engineer, Ambala Circle, had debarred himself from acting as arbitrator by his conduct; and (4) relief.

The trial Court held that clause 25-A (the arbitration clause) had not been scored out before tender submission and remained binding; that Walaya Ram had authority to bind the firm; but that the Superintending Engineer (Shri Bikramjeet) had already expressed his opinion in a report to the Government and therefore should not act as arbitrator. The State appealed the trial Court's refusal to stay the suit to the present Court.

Legal Issues Presented

  1. Whether there is any valid agreement between the parties to refer the disputes arising between them to arbitration (i.e., validity and effect of clause 25-A).
  2. Whether Shri Walaya Ram was competent to enter into the said agreement on behalf of the plaintiff firm.
  3. Whether the Superintending Engineer, by his conduct (report to the Government and prior expressions of view), had debarred himself from acting as arbitrator.
  4. Relief (i.e., whether the suit should be stayed under Section 34 or proceed in Court).

Arguments of the Parties

Appellant (Punjab State) — submissions recorded in the opinion

  • The State relied on the arbitration clause (clause 25-A) in the agreement and urged that disputes should be referred to the arbitrator and proceedings stayed under Section 34 of the Arbitration Act.
  • The Deputy Advocate-General referred to authority (Keating on Building Contracts) emphasizing that architects/engineers appointed as arbitrators are commonly employed by one party and that prior expression of opinion by an architect/engineer is not necessarily disqualifying.
  • By implication (from the State's appeal), the State contested the trial Court's exercise of discretion in refusing the stay.

Respondent (Jawahar Mal & Sons) — submissions recorded in the opinion

  • The plaintiff contended that clause 25-A had been scored out after the tender was accepted and that the arbitrator (the Superintending Engineer) was likely biased because he had already examined the evidence and made a report to the Government adverse to the plaintiff.
  • It was argued (by Mr. Faqir Chand Mital for the plaintiff) that the Engineer had in effect already decided the dispute (by his report) and it would be improper to refer the matter to him for arbitration because he could not form an independent view or change his position.
  • The plaintiff also raised ancillary factual disputes (whether certain clauses were scored out) such that the Court was better placed than an arbitrator to decide those preliminary matters.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Union of India v. M/s. Narayan Cold Storage Ltd., AIR 1958 Punj 24 That an order to stay proceedings will not be granted if there is good ground for apprehension that the arbitrator will not act fairly; appellate court will not interfere with trial Court's discretion unless it is arbitrary. The trial Court's refusal to stay was supported by this decision; the present Court regarded it as fortifying the view that refusal of stay was properly exercised in the circumstances.
Bristol Corporation v. John Aird & Co., 1913 A.C. 241 House of Lords authority emphasizing that where an arbitrator would be judge and witness or where there is reasonable prospect of bias, the Court may refuse to refer the dispute to arbitration; also stresses judicial discretion but with bias in favour of maintaining special bargains. The Court relied on Lord Atkinson and Lord Moulton's observations to uphold the trial Court's discretion in refusing to stay since the Superintending Engineer had already made a report and there was probable inability to act impartially.
Ives & Barker v. Willans, (1894) 2 Ch. 478 Where engineers/architects are named arbitrators in building contracts, long experience justifies trusting them; contractors understand whom they deal with and accept that arbitrator's role. Cited to contrast earlier English cases which favored sanctity of arbitration clauses; Court noted that such cases emphasize the special nature of building contracts but that later House of Lords decisions qualify that position.
Jackson v. Barry Railway Co., (1893) 1 Ch. 238 Prior statements by an engineer are not necessarily disqualifying; repetition of the same view after commencement of arbitration does not disqualify unless it shows the arbitrator has closed his mind to change. The opinion used this authority to explain the boundary between mere prior expression of view and disqualification; but concluded that in the present case the engineer's prior report to Government made it improper to refer the dispute to him.
Hickman & Co. v. Roberts, 1913 A.C. 229 Principles from the House of Lords that must be followed when considering a stay of action despite an arbitration clause (i.e., judicial discretion and circumstances permitting refusal to stay). The Court stated that the principles laid down in Hickman must be followed and applied those standards to the facts (noting the complete production of plaintiff's evidence before the engineer and the nature of the claim).
Walmsley v. White, (1892) 67 L.T. 433; Joplin v. Postlethwaite, (1889) 61 L.T. 629 Authorities cited by Lord Moulton as examples that these matters are within judicial discretion; courts should consider all circumstances with a bias toward maintaining contractual bargains but vigilantly ensure substantial justice. Used to show the surrounding English authority recognizing judicial discretion; the Court relied on the dictum that appellate interference is not lightly given on questions of judicial discretion.
McKenzies, Ltd. v. Sulleman & Co., AIR 1933 Sind 75 Followed earlier English cases emphasizing sanctity of arbitration agreement but discussed without deep elaboration in the opinion. Mentioned as part of the body of English case law considered; the Court noted limited discussion in that decision but placed weight on subsequent House of Lords authorities.
Dwarkadas Co. v. Keshardeo Bubua, ILR (1948) 1 Cal 190 Principle that sanctity of arbitration agreement is subject to the Court's discretion; an agreement is enforceable only if the Court, considering all circumstances, decides to enforce it; release from bargain may be allowed if arbitrator has made up his mind or probable bias exists. The Court relied on this Calcutta decision to support the view that later authorities emphasize the Court's discretion and that a party may be released from an arbitration bargain where the arbitrator has effectively prejudged the matter.
Punjab State v. Lakshmi Narain Gupta, F.A.F.O. No. 146 of 1955 (decided 15-5-1957, Punj) Recent Punjab decision where a clause referring disputes to the Superintending Engineer was considered and the Court declined to stay a suit when the Engineer had expressed clear opinions adverse to the contractor. The present Court treated that decision as analogous and supportive of refusing a stay where the Superintending Engineer had already indicated his views in inspection notes and directions.

Court's Reasoning and Analysis

The Court proceeded by examining: (a) the factual findings of the trial Court on the framed issues; (b) the body of English and Indian authorities concerning arbitration clauses in building contracts and the disqualification or bias of engineers/architects named as arbitrators; and (c) the particular facts and documents in this case.

Key factual findings by the trial Court (accepted by this Court) were:

  • Clause 25-A (the arbitration clause) was intact when the plaintiff submitted the tender and, if scored out later, that scoring out occurred after acceptance; therefore the clause was binding.
  • Shri Walaya Ram had authority to bind the plaintiff-firm in matters including arbitration.
  • Shri Bikramjeet, the Superintending Engineer, had required production of evidence from the plaintiff, examined account-books and other materials, and had made recommendations in a report to the Government which were unfavourable to the plaintiff; that report was not produced by the plaintiff in evidence, suggesting it was adverse.

On legal principles the Court reviewed:

  • The older English line of cases (e.g., Ives & Barker) that emphasized the sanctity of arbitration clauses in building contracts and that prior expressions of opinion by an engineer do not, by themselves, disqualify him.
  • The later House of Lords authorities (notably Bristol Corporation v. John Aird and Hickman & Co. v. Roberts) which placed greater stress on the Court's discretion and held that where there is a reasonable prospect that the named arbitrator will not decide fairly (or is placed in a position where he would be judge and witness), the Court may refuse to refer the dispute to arbitration.
  • Indian decisions (including Dwarkadas Co. v. Keshardeo Bubua and the Punjab decisions cited) which recognized that sanctity of arbitration agreements is subject to the Court's discretion and that a party may be released from an arbitration bargain if the selected arbitrator has clearly prejudged matters or there is a probability of bias.

Applying those principles to the facts, the Court reasoned as follows:

  1. Although clause 25-A was binding, the core question was whether the Superintending Engineer could act impartially as arbitrator having already examined plaintiff's evidence and made a report to the Government that appeared to be adverse to the plaintiff.
  2. The Court accepted the plaintiff's contention that the Engineer had effectively formed and communicated an opinion on the merits in the Government report, leaving little or nothing for further determination; this created a legitimate apprehension that he could not form an independent view or change his opinion.
  3. English authorities recognize that mere prior views are not always disqualifying, but where an arbitrator has placed himself in a position which makes it improper, fitting or decorous for him to act (e.g., where he is both judge and witness or has made a final report), the Court may refuse to stay proceedings. The Court found the present facts analogous to such circumstances.
  4. Additional considerations militated against a stay: the trial Court had made observations on whether other clauses (12, 13 and 25) were scored out along with 25-A, but the issue concerning those clauses had not been fully tried and the trial Court was better placed to decide factual questions of whether they were scored out; also the suit's factual and legal complications were such that a Court was more appropriate to decide them.
  5. Given the trial Court's exercise of discretion after considering all circumstances, and in light of authorities recognizing limited circumstances in which a Court should refuse to enforce an arbitration bargain, the appellate Court concluded it should not interfere with the trial Court's discretionary refusal to stay the action.

Holding and Implications

Holding: The appeal is dismissed. The appellate Court refused to interfere with the trial Court's order declining to stay the suit under Section 34 of the Arbitration Act.

Implications and direct effects:

  • The suit will proceed in the trial Court; the parties were directed to appear before the Court below on 24-11-1958 for further proceedings.
  • The parties were directed to bear their own costs in this Court.
  • The Court clarified that while arbitration clauses (especially in building contracts) are to be respected, the sanctity of such clauses is subject to the Court's discretion; where an arbitrator has, by conduct or report, created a reasonable apprehension of inability to act fairly, the Court may refuse to stay proceedings and itself decide the dispute.
  • No novel legal rule was laid down: the decision applies existing House of Lords and Indian precedents to hold that the trial Court properly exercised its discretion in the particular factual circumstances; the opinion emphasizes that this is not an occasion to lightly upset an exercise of judicial discretion by the trial Court.

This summary is based exclusively on the content of the provided opinion.

    The State Of Punjab, v. Jawahar Mal & Sons,

    1. This is an appeal against an order of the Senior Sub-Judge, Simla, refusing to stay a suit under the provisions of Section 34 of the Indian Arbitration Act.

    2. The suit was filed by Jawahar Mal and Sons for recovery of Rs. 68,349/5/3 against the Punjab State for damages for breach of a contract which had been entered into for erection of a high level bridge over the Rangeelpur Naddi. The State moved the Court under the provisions of Section 34 of the Arbitration Act for stay of proceedings on the ground that there was an arbitration clause in the agreement and that the disputes between the parties had to be decided by arbitration. Various pleas were raised on which the following issues were framed :

    1. Whether there is any valid agreement between the parties to refer the disputes arising between them to arbitration?

    2. Whether Shri Walaya Ram was competent to enter into the said agreement on behalf of the plaintiff firm?

    3. Has the Superintending Engineer, Ambala Circle, debarred himself from acting as an arbitrator by his conduct?

    4. Relief.

    It has been held by the Court on issue No. 1 that clause 25-A which related to the arbitration agreement had not been scored out as alleged by the plaintiff but was intact when the plaintiff submitted the tender and had been scored out after the tender had been accepted and was, therefore, binding on the parties. On issue No. 2 it was found that Walaya Ram had the authority to enter into an agreement relating to arbitration on behalf of the plaintiff-firm. On issue No. 3, however, the Court considered that the disputes had to be decided by Shri Bikramjeet, the Superintending Engineer, who had already ex-pressed his opinion on the merits of the case in a report submitted to the Government.

    In these circumstances, the Court considered that the plaintiff could have a legitimate impression that Shri Bikramjeet might not be able to form an independent view of the controversy between the parties. Following the observations made in Union of India v. M/s. Narayan Cold Storage Ltd., Amrit-sar, AIR 1958 Punj 24 and Bristol Corporation v. John Aird and Co., 1913 A.C. 241, the learned Judge decided that the dispute between the parties should not be referred to the arbitrator but should be decid-ed by the Court itself. The State is dissatisfied with the order and has come up to this Court in appeal.

    3. The Deputy Advocate-General has invited my attention to the statement contained in the Law and Practice of Building Contracts by Keating at pages 188 and 189 which is as follows :

    "Parties to an arbitration are normally entitled to an unbiased arbitrator with no interest in the result of the proceedings. Where the architect of a contract is appointed arbitrator for that contract he is interested to the extent that he is employed and paid by one of the parties to the dispute, and is probably further interested in that in his capacity as agent for the employer he may have given orders relating to the matter in dispute, or have already expressed a strong view on the subject, and may even be judge, so to speak, in his own quarrel'.

    Such interests have been held not to be sufficient in themselves to disqualify the architect from acting as arbitrator. It has been held that the contractor must show, if not that the architect is biased, that at least there is a probability that he would be biased. The basis of these decisions was that 'the court. ..ought to hold that nothing known at the lime of the contract, nothing fairly to be expected from the position of the engineer when he becomes arbitrator, can be alleged as a ground why it should not keep the parties to their bargain."

    It is contended that in such contracts the engineer for the architect is the proper person who should decide the disputes arising between the contracting parties even if he is the employee of one of the parties. In Ives and Barker v. Willans, (1894) 2 Ch. 478, in which also the question was whether an ac-tion should be stayed or not in view of an arbitration clause by which the dispute was to be referred to the engineer, Lindley, L.J., considered that such contracts were of a special nature and it had been ascertained by long experience that engineers of the highest character might be trusted, and, when a contractor entered into such a stringent provision, he knew the man he had to deal with.

    It was further laid down that in order to make out that such an arbitrator was not a proper person to decide the dispute, the sub-contractors must prove a great deal more than that the engineers had formed an opinion already on the subject of the dispute; they must attack the character of the engineers to such an extend, and in such a manner, as to show that the engineers would probably be guilty of some misconduct in the matter of arbitration and that they would not act fairly. Lopes, L.J., dealing with the attacks which had been made against the engineers as arbitrators in that case, observed that the parties knew perfectly well, when they consented to those engineers acting as arbitrators, that difficulties of the nature suggested might arise; they perfectly well knew that these engineers were the persons who were to determine the quality and character of the materials in question; they knew that these engineers had to do that as well as to act as arbitrators.

    Knowing that, they agreed that they would accept the arbitrators and they could not turn round and say that, because their judgment was erroneous, therefore, they were not bound to accept it. They agreed to be bound by the judgment of the arbitrators, however erroneous it might be, provided it was honest, provided it was not tainted with fraud or with misconduct. Mr. Kaushal points out that the mere fact that an opinion has been expressed by the engineer would not be sufficient to debar him from acting as an arbitrator. In Jackson v. Barry Rly. Co., (1893) 1 Ch. 238, there was an arbitration clause by which disputes had to be referred to the company's engineer. A dispute arose whether the contract required the interior of a certain embankment to be made of stone, or whether rocky marl was allowable, so that, if the contractor by the direction of the engineer used stone, he would be entitled to be paid for it as an extra. A correspondence took place between the contractor and the engineer, in which the engineer stated his view to be that the contract bound the contractor to use stone and that it was not extra. The company then referred the dispute to the arbitration of the engineer. After this reference and on the day for which the first appointment had been made the engineer wrote to the contractor a letter in which he repeated his former view.

    An action was brought to restrain the company from proceeding with the arbitration by the engineer. Kekewich, J., held that the correspondence showed that the engineer had finally made up his mind on the point and was, therefore, disqualified to act as an arbitrator, and granted an injunction. The Court of Appeal, however, held that considering the position or the engineer who, as engineer of the company, must necessarily have already expressed an opinion on the point in dispute, his writing after the commencement of the arbitration a letter repeating the same opinion would not disqualify him from acting as arbitrator unless, on the fair construction of the letter, it appeared that he had made up his mind so as not to be open to change it upon argument. It may be mentioned that A. L. Smith, L.J., expressed a dissenting opinion, and the following observations made by him at page 250 are noteworthy :

    "It appears also to me that when a dispute arose and Mr. Barry became the arbitrator, no matter how difficult it might be for him to lay aside his preconceived opinions, expressed as they properly may have been by him as engineer to the contractor, he was in duty bound as far as possible to do so and to keep an open mind as to the matters upon which he was called upon to adjudicate, and if it be shewn that he has failed in this duty, then, in my judgment, to use the words of Sir George Jessel, he is not fit or competent to adjudicate upon the case."

    Lindley, L. J., however, considered that unless an inference could be drawn from the evidence that the engineer had precluded himself by the letter from keeping his mind open and from deciding according to the evidence and according to the advice which might be given him, he should not be stopped from carrying on the arbitration, particularly because under the 19th section of the Arbitration Act, 1889, there was a method by which the contractor could, if he felt aggrieved, obtain the opinion of the Court upon the true construction of the contract. Bowen, L.J., considered that the contractor was catching at a straw and was endeavoring on the ground that the engineer had revealed a view which everyone was aware he entertained, to escape from an onerous arbitration clause which the contractor accepted as part of the consideration for his bargain. These cases were followed by Aston, A.J. C., in McKenzies, Ltd. v. Sulleman and Co., AIR 1933 Sind 75, but there is hardly any discussion o£ the principles which could be applicable in such cases,

    4. The law on the subject has been fully laid by the House of Lords in 1913 AC 241. The contractor had executed works under a contract containing a provision for the reference of disputes to the engineer of other party to the contract. Upon final settlement of account there arose a bona fide dispute of a substantial character between the contractor and the engineer involving a probable conflict of evidence between them. An application for stay of the action had been made but the Master had refused to stay the same. Scrutton, J., sitting in Chambers and the Court of Appeal had also affirmed his order. When the matter came before the House. Lord Atkinson made the following observations at pages 247-248 :

    "But though the contractor is bound by that con-tract, still he has a right to demand that, notwithstanding those pre-formed views of the engineer that gentleman shall listen to argument and determine the matter submitted to him as fairly as he can as an honest man; and if it be shewn in fact that there is any reasonable prospect that he will be so biased as to be likely not to decide fairly upon those matters, then the contractor is allowed to escape from his bargain and to have the matters in dispute tried by one of the ordinary tribunals of the land. But I think he has more than that right. If, without any fault of his own, the engineer has put himself in such a position that it is not fitting or decorous or proper that he should act as arbitrator in any one or more of those disputes, the contractor has the right to appeal to a Court of law and "they are entitled to say, in answer to an application to the Court to exercise the discretion which the 4th section of the arbitration act vests in them, 'We are not satisfied that there is not some reason for not submitting this question to the arbitrator.' "

    In that particular case Lord Atkinson applying the above principles considered that on two most important matters, namely, the filling and the excavation between the monoliths, Mr. Squire, who was the en-gineer, would necessarily be at once in the position of a Judge and a witness. His Lordship could not imagine any position more unpleasant, any position more undesirable. It was held that the discretion refusing to stay the action had been properly exercised.

    Lord Moulton, while laying down that the Court must consider all the circumstances of the case with a strong bias in favour of maintaining the special bargain between the parties, observed, however, that at the same time the Court had to see with vigilance that it was not driving either of the parties to a tribunal where he would not get substantial justice. Lord Moulton appears to have rested his decision largely on the discretion which had been exercised by the Courts below. At pages 259 to 260 are certain observations made by him which are particularly noteworthy in such cases and which read as follows :

    "But in this case the way in which the disputes arose and what has happened in connection with them make me feel that a Court may well take the view that there is good reason why this matter should not be referred to arbitration as provided by the contract. I agree with the cases like Walmsley v. White, (1892) 67 L.T. 433 and Joplin v. Postlethwaite, (1889) 61 LT 629 which lay down that this is a matter of a judicial discretion for the Court.

    I find in this case that the Court of Appeal after a very long hearing has unanimously come to the conclusion that there are reasons why this claim should not be referred to arbitration, and the able arguments which your Lordships have heard have not convinced me mat the Court of Appeal was wrong in corning to that conclusion; and therefore, without differing from the Court of Appeal in this but mainly from a feeling that "on a question of judicial discretion one ought not lightly to allow an appeal from a Court which has not proceeded on wrong judicial lines", I have come to the conclusion that the appellants have not made out their case, and I concur in the motion which is about to be put to your Lordships."

    As stated by Russell on Arbitration at page 11 it may be presumed that the Court will not lightly interfere with an appointment deliberately agreed upon by the parties, and the provision common in building contracts, by which certain possible disputes? between building contractor and building owner are: determined by the architect or engineer, will still be enforceable.

    5. But while considering the question of stay of an action owing to the existence of an arbitration clause, the principles that have been laid down by the House of Lords in Hickman and Co. v. Roberts 1913 AC 229, must be followed. In the present case it is common ground that the entire evidence which the plaintiff-firm had to produce has been produced with regard to their claim before the engineer. It would be proper at this stage to notice the actual nature of the claim and the allegations on which it is founded. The contract is alleged to be for construction of a high level bridge on the basis of plans, lay-outs and alignments which had been prepared on behalf of the defendant.

    The plaintiff's case is that the preparatory work had started and a good deal of money was expended on labour, purchase of materials etc. According to the terms of the contract it had been agreed that the defendant shall provide a certified and signed copy of the layouts, alignments, plans etc. and that demarcation of the site had also to be made. The plaintiff requested the defendant for demarcation as also for the layouts, plans etc. which were necessary for the execution of the work, but the defendant inordinately and without justification delayed in furnishing the plaintiff with the necessary demarcation and the details. Later on, the defendant shifted the previous layouts, designs and plans and suggested another site without any other change to which also the plaintiff agreed as he had invested lot of money on labour, purchase of materials etc. The plaintiff started the work of digging of the wells, manufacture of steel well curbs, bending, threading and cutting of steel bars etc. etc. and purchased Materials of the value of Rs. 36,000/- odd for the execution o£ the work. The plaintiff had spent Rs. 78,000/- odd in all on the preparatory work when the defendant, through its officers desired to substitute an absolutely new contract in place of the one originally tendered for. This, according to the plaintiff, the defendant was not entitled to do. The plaintiff claims the damages sustained by him for the aforesaid reasons.

    6. Shri Bikramjeet who appeared as a witness on behalf of the Punjab State admitted that he did write to the plaintiff to produce all evidence relating to the case before him and that account-books and other evidence were produced. After examining that evidence he did make certain recommendations to the Government relating to the matter. According to the learned trial Judge, it is evident that the report was not favourable to the plaintiff. If it had been favourable, the firm might nave compromised the matter outside the Court. It appears from the circumstances of the present case that the report could not have been favourable to the plaintiff as in spite of an effort having been made for its production by the plaintiff it was never produced.

    With this background it is not difficult to see the force in the argument of Mr. Faqir Chand Mital who appears on behalf of the plaintiff-firm that the Superintending Engineer has already made up his mind and that there is nothing left further for his decision and, in fact, he has already given a decision, and the award which he will now give, if the matter is referred to him, will simply embody the decision expressed in his report. It is contended that the po-sition may have been different if the Engineer had formed a certain opinion with regard to the works or materials as had been done in some of the English cases. That may not have presented any hurdle in the way of his acting fairly and without bias, but in the present case it will be very difficult, according to Mr. Mital, to accept that on the same evidence the Engineer will change his opinion and give a different award.

    In any case, it is suggested that the Engineer is likely to be biased and it will not be possible for him to decide fairly upon the matters which arise for decision in the present case and which are of a very different nature from those which arose in the earlier English cases, namely, (1894) 2 Oh. 478 and (1893) I Ch. 238. There may or may not he much substance in the contention that Shri Bikramjeet, the Superintending Engineer, would, in any way, be biased, but it seems to me that it will not be right to put him in such a position that it would not be fitting or decorous or proper for him to act as an arbitrator in the words of Lord Atkinson.

    There is bound to be a good deal of embarrassment for the Engineer, if he wishes to change his report now as he has already made a final report to the Government. I consider, therefore, that iri the present case the discretion which has been exercised by the Court below, should not be interfered with as it has been properly exercised after a due consideration of all the circumstances. Lord Moulton in Bristol Corporation case 1913 AC 241 laid a good deal of stress, as has been stated before, on this aspect of the matter, and to use his Lordship's words

    "on a question of judicial discretion one ought not lightly to allow an appeal from a Court which has not proceeded on wrong judicial lines"
    . I am also fortified in the view which I am taking in this case by certain recent decisions of this Court.

    In AIR 1958 Punj 24, Tek Chand J. considered that any order to stay legal proceedings in a Court of law would not be granted if it could be shown that there was good ground for apprehending that the arbitrator was not likely to act fairly in the matter for that it was for some reason improper that he should arbitrate on the dispute. On the question of discretion also it has been observed by him that where the same has been exercised by the trial Court in a manner which cannot be considered to be arbitrary, the appellate Court will not interfere. In F. A. F. O. No. 146 of 1955, Punjab State v. Lakshmi Na-rain Gupta, decided by G. L. Chopra J., on 15-5-1957 (Punj), there was a similar clause of reference to the arbitration of the Superintending Engineer.

    The Court below had declined to stay the suit. The Superintending Engineer had visited the works and had pointed out a number of defects and issued directions to be complied with by the contractor. He had made certain observations in his inspection-note relating to the quality of the mud plaster and the founding of the corners which were adverse to the contractor. The learned Judge considered that the inspection-note left no doubt that the Superintending Engineer had already expressed his opinion in clear terms in respect of the main terms between the parties.

    The principles of law laid down by Lord Atkinson in 1913 A.C. 241 were applied. In Dwarkadas, Co. v. Keshardeo Bubua, ILR (1948 1 Cal 190, Das, J. as he then was, has examined a similar point at length and has laid down that the principle of sanctity of an arbitration agreement is subject to the discretion of the Court, for there must be read in every such agreement an implied term or condition that it will be enforceable only if the Court, having due regard to all the surrounding circumstances, thinks fit, in its discretion to enforce. A party to an arbitration agreement may be released from his bargain if he can show that the selected arbitrator has not kept an open mind but has made up his mind against the party by any act or conduct which is more than a passing expression of opinion or there is a probability that he would in fact be biased or that there is sufficient reason to suspect that he will act unfairly or that he has been guilty of continued unreasonable conduct. After considering the English case law it was observed as follows at page 206 :

    "The point to be noted is that while the decisions of the Court of appeal relating to arbitration clauses in building-contracts gave forceful and emphatic expression to the principle of sanctity of contract the later decisions of the House of Lords in similar, cases laid more emphasis on the discretion of the Court.

    In those decisions of the House of Lords I can clearly discern a change of the angle of vision and a new attitude and outlook towards the question. The two House of Lords cases I have mentioned which

    " placed greater emphasis on the discretion of the Court appear to me to show that the Court was receding from the extreme position taken up by the Court of appeal in respect of arbitration clauses in building contracts."

    Even if some difficulty was created by the nature of observations contained in the earlier English decisions in the matter of deciding whether stay should be granted or refused in such cases, the position now is clear in view of the observations and the principles contained in the Calcutta case.

    7. Moreover, there are other considerations also which impel me to hold that this is not a fit case in which the suit ought to be stayed under Section 34 of the Arbitration Act. One of the matters in controversy between the parties is whether clauses 12 (relating to "alterations in specifications and designs"), 13 (relating to "no compensation for alteration in, or restriction of, work to be carried out") and 25 (relating to "claims for payment of an extraordinary nature to be referred to Government for decision") were scored out along with clause 25-A, which re-lated to arbitration, before the tender was submitted. While discussing this matter, the Court has made certain general observations with regard to their not having been scored out as alleged by the plaintiff.

    The issue under which this matter has been discussed covered only clause 25-A and, therefore, the observations with regard to the other clauses cannot be considered to be final at this stage. The Court will be in a better position than the arbitrator to decide whether clauses 12, 13 and 25 wore so scored out or not. Furthermore, the allegations on which the suit is founded are such that complicated questions of law and fact are bound to arise which can be appropriately decided by a Court only.

    8. For the reasons given above, the appeal fails and is dismissed. In the circumstances or the case, however, I leave the parties to bear their own costs in this Court. The parties are directed to appear before the Court below on 24-11-1958 for further proceedings.

    Use AI to get other relevant cases.

    Comments

    The State Of Punjab, v. Jawahar Mal & Sons,
    (Oct 29, 1958)