Factual and Procedural Background

The petitioner is the Bhubaneswar City Distribution Division represented through its Executive Engineer, Electrical Grid Corporation of Orissa Limited, Bhubaneswar. The petitioner filed a writ application under Articles 226 and 227 of the Constitution of India challenging an order (Annexure-5) passed by the Regional Provident Fund Commissioner, Orissa, Bhubaneswar under section 14-B of the Employees' Provident Funds & Miscellaneous Provisions Act, 1952. The impugned order imposed damages totaling Rs. 10,80,725/- for delayed payment of statutory dues for the periods 1986-87, 1987-88, 1988-89, 1989-90 and 1990-91.

The petition raised multiple contentions about procedural defects, delay in initiation of proceedings, the legal basis for levy of damages under section 14-B, arbitrariness of the rate imposed, and the effect of a Government letter (No.1107 dated 28-1-1997) which, it was said, excluded the Orissa State Electricity Board from the purview of the Act with effect from 1-4-1990.

The Regional Provident Fund Commissioner had disposed of two P.D. cases (P.D. Case Nos. 197 of 1994 and 132 of 1994-95) by the impugned order. The High Court considered rival contentions, addressed the scope and application of section 14-B, reviewed the procedure followed, and issued directions including quashing parts of the impugned order, recalculation of damages at a specified rate for a specified period, and directions on refund and interest. The writ application was allowed and there was no order as to costs.

Legal Issues Presented

  1. Whether the petitioner was denied a reasonable opportunity of being heard in respect of the alleged delayed payment for the period 1986-87 when Annexure-2 did not mention that period.
  2. Whether the entire proceeding leading to the impugned order was vitiated by unreasonable delay in initiation of proceedings under section 14-B (i.e., whether proceedings were initiated within a reasonable period).
  3. Whether delayed payment of statutory dues ipso facto attracts levy of damages under section 14-B or whether the Commissioner must consider sufficient cause for delay before levying damages.
  4. Whether the damages were levied arbitrarily and without following any principled rate or guideline.
  5. Whether the Government decision communicated by letter No.1107 dated 28-1-1997 (excluding the Orissa State Electricity Board from the purview of the Act with effect from 1-4-1990) precluded levy of damages on the petitioner with effect from that date.

Arguments of the Parties

Petitioner's Arguments (as advanced by Shri Nayak)

  • The petitioner was not given a reasonable opportunity of being heard for the period 1986-87 because Annexure-2 did not include that allegation, yet the impugned order imposed damages for that period.
  • The entire proceeding is vitiated because it was not initiated within a reasonable period.
  • Delayed payment does not ipso-facto attract damages under section 14-B; the Commissioner failed to give specific reasons for levying damages.
  • The damages were levied arbitrarily without adherence to any principle.
  • By reason of the Government letter No.1107 dated 28-1-1997 excluding the Orissa State Electricity Board from the Act with effect from 1-4-1990, no damages can be levied on the petitioner with effect from 1-4-1990.

Opposite Parties' Arguments (as advanced by Shri Samal)

  • Although Annexure-2 did not mention the 1986-87 period, the petitioner was issued a show cause notice for that period in P.D. Case No.197 of 1994 and submitted a reply, indicating the petitioner had reasonable opportunity of hearing; the impugned order disposed of both P.D. Case Nos. 197 of 1994 and 132 of 1994-95.
  • The Act does not prescribe any limitation period for initiation of proceedings under section 14-B; an affidavit dated 29-8-1997 stated that proceedings were initiated soon after the default was detected.
  • The petitioner, having defaulted in payments, is statutorily liable to pay damages.
  • The damages were levied as per the prescribed rate.
  • The State Government's decision excluding the petitioner from the purview of the Act is not final and may be challenged by the opposite parties in an appropriate forum.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court addressed each contention in turn and explained the legal reasoning it applied to the facts before it:

  1. On the procedural/hearing complaint (contention (i)), the court found that the petitioner had been given notice in P.D. Case No.197 of 1994 for the 1986-87 period and had submitted its reply. The impugned order disposed of both P.D. Case Nos. 197 of 1994 and 132 of 1994-95. Given this factual position, the court held the petitioner's contention that it was not heard on 1986-87 had no merit.
  2. On delay in initiation (contention (ii)), the court acknowledged that the Act contains no statutory limitation for initiation of proceedings under section 14-B and that where a statute is silent power should be exercised within a reasonable period; what is reasonable depends on facts and circumstances. The court noted the Commissioner's affidavit (dated 29-8-1997) averring that no unreasonable delay occurred, that defaults and failure to submit statutory forms led to early detection, and that administrative constraints (one Commissioner for the entire State and over five thousand establishments) were relevant. Nonetheless the court stated it was not inclined to investigate further whether an unreasonable delay occurred for reasons given subsequently in the judgment.
  3. On whether delayed payment automatically attracts damages (contention (iii)), the court reviewed section 14-B and emphasised that the provision requires the employer be given a reasonable opportunity of being heard before damages are levied and that delayed payment does not ipso-facto attract damages. If an employer furnishes sufficient cause, the authority may refrain from levying damages. The court observed that the Commissioner had recorded that the establishment defaulted "without any valid reason," and that the petitioner's explanation (that centralised payment scheme introduced operational difficulties which made delay unavoidable) did not appear to have been considered by the Commissioner.
  4. On arbitrariness of rate (contention (iv)), the court examined the detailed break-up of damages showing imposition of 25% of arrears per annum for delays ranging from six days to 562 days. The court described such imposition as "evidently arbitrary." The court referred to the insertion of paragraph 32-A vide C.S.R. No.521 dated 16-8-1991 (with effect from 1-9-1991), which prescribes specific percentage rates based on duration of default (17%, 22%, 27%, 37% per annum for increasing durations). Although the provision was noted as not strictly applicable to the present case, the court held that it indicated the Government's intention that rates should not be arbitrary. Taking into account that the Act is a beneficial legislation and to avoid further litigation, the court concluded that the petitioner was liable to pay damages at the rate of 17% per annum on the arrears.
  5. On the effect of the Government letter excluding the erstwhile Orissa State Electricity Board from the Act (contention (v)), the court examined Government letter No.1107 dated 28-1-1997 showing that, following a direction issued by the Supreme Court, the Government decided that with effect from 1-4-1990 the provisions of the Act were not applicable to the erstwhile Orissa State Electricity Board. The court treated the decision as final for the present proceedings because the opposite parties had not challenged it in any court. Consequently, the court quashed the impugned order insofar as it related to levy of damages from 1-4-1990 to February 1991.
  6. Remedies and directions: the court quashed the impugned order (Annexure-5) and the calculation sheets (Annexure-6 series). It directed the Commissioner (opposite party No.2) to recalculate damages for the period from March 1986 to 31-3-1990 at the rate of 17% per annum and pass appropriate order under section 14-B. The court further directed that if, on recalculation, any excess amount had been deposited by the petitioner, the Commissioner must refund the excess together with interest as required under paragraph 60(2)(b) of the Employees' Provident Funds Scheme, 1952. The Commissioner was to complete the exercise within two months of receipt of the order.

Holding and Implications

Core Holding: The writ application was allowed; the impugned order (Annexure-5) and the associated calculation sheets (Annexure-6 series) were quashed in part and remitted for recalculation and re-determination in accordance with the court's directions.

Practical consequences and immediate effects:

  • The Commissioner is directed to recalculate damages for the period from March 1986 to 31-3-1990 at the rate of 17% per annum on the arrears and to pass appropriate orders under section 14-B of the Act.
  • The portion of the impugned order imposing damages from 1-4-1990 to February 1991 was quashed because the Government decision (letter No.1107 dated 28-1-1997) excluded the erstwhile Orissa State Electricity Board from the purview of the Act with effect from 1-4-1990 and that decision had not been challenged by the opposite parties.
  • If recalculation shows any excess amount was deposited by the petitioner, the Commissioner must refund the amount due together with interest as determined under paragraph 60(2)(b) of the Employees' Provident Funds Scheme, 1952; the Commissioner must complete this exercise within two months of receipt of the court's order.
  • The writ application was allowed and there was no order as to costs.

Broader implications: The opinion does not purport to lay down a novel legal principle or binding precedent beyond the application of section 14-B and the administrative directions relied on; the court applied established principles (reasonable opportunity to be heard; that delayed payment does not automatically attract damages; and that arbitrary rates are impermissible) to the facts and remitted the matter for recalculation. The opinion did not cite any judicial precedents.

    Bhubaneswar City Distribution Division v. Union Of India

    R.K Patra, J.:— The Bhubaneswar City Distribution Division represented through its Executive Engineer, Electrical Grid Corporation of Orissa Limited, Bhubaneswar is the petitioner. It has filed this application under Articles 226 and 227 of the Constitution of India challenging the order at Annexure-5 passed by the Regional Provident Fund Commissioner, Orissa, Bhubaneswar under section 14-B of the Employees' Provident Funds & Miscellaneous Provisions Act, 1952 (in short, ‘the Act’) laying damages on it amounting to Rs. 10,80,725/- for the delayed payment of the statutory dues for the periods 1986-87, 1987-88, 1988-89, 1989-90 and 1990-91.

    2. Shri Nayak, learned counsel for the petitioner raises the following contentions in support of the application:—

    (i) The petitioner was not given reasonable opportunity of being heard in respect of the delayed payment of dues for the period 1986-87 in as much as in the show cause notice at Annexure-2 there was no such allegation but in the impugned order damage has been imposed for the said period.

    (ii) The entire proceeding leading to the passing of the impugned order is vitiated as it was not initiated within a reasonable period.

    (iii) Delayed payment of the statutory dues ipso-facto does not invite levy of damages under section 14-B of the Act and the Commissioner in the impugned order has not given any specific reason for levy of the damages.

    (iv) The damages have been levied arbitrarily without following any principle.

    (v) In any event, with effect from 1-4-1990 no damages can be levied on the petitioner in view of the Government decision communicated in letter No, 1107 dated 28-1-1997 at Annexure-1 excluding the Orissa State Electricity Board from the purview of the Act.

    3. Shri Samal, learned counsel appearing for the opposite parties contends as follows:—

    (i) Although in the show cause notice at Annexure-2, there was no mention of delayed payment of dues for the period 1986-87, the petitioner was issued with the show cause notice for the said period in P.D Case No. 197 of 1994 to which the petitioner submitted its show cause reply which indicates that the petitioner was given reasonable opportunity of hearing in respect of the delayed payment of dues for the period 1986-87 and by the impugned order, the Commissioner has disposed of both the cases i.e P.D Case Nos. 197 of 1994 for the period 1986-87 and 132 of 1994-95 relating to other periods.

    (ii) The Act has not provided any period of limitation for initiation of the proceeding under section 14-B of the Act and the affidavit dated 29-8-1997 filed in the case on behalf of the Commissioner would show that the proceeding was initiated soon-after the default was detected.

    (iii) The petitioner having defaulted in making payments is statutorily liable to pay damages.

    (iv) The damages have been levied as per the prescribed rate.

    (v) The State Government's decision excluding the petitioner from the purview of the Act is not final as the opposite parties may challenge the same in appropriate forum.

    4. We have carefully considered the rival contentions of the counsel for the parties.

    5. Contention No. (i):— So far as the grievance of the petitioner that in the show cause notice at Annexure-2, there was no allegation of non-payment/delayed payment of the dues for the period 1986-87 is concerned, we may state that the petitioner was admittedly given notice to show cause for the said period in P.D Case No. 197 of 1994. The petitioner had also submitted his reply in the said case. By the impugned order, the Commissioner has disposed of two cases, i.e P.D Case Nos. 197 of 1994 and 132 of 1994-95. In view of this factual position, the contention of Shri Nayak on this score has no merit.

    6. Contention No. (ii):— It is true that under the Act, there is no provision prescribing any period of limitation for initiation of proceeding for levy of damages under section 14-B of the Act. The law seems to be fairly settled that even though the statute does not provide for any limitation for exercise of power, the same should be exercised within a reasonable period. What would be the reasonable period would depend upon the facts and circumstances of each case. In the case at hand, in the affidavit dated 29-8-1997 it has been pleaded on behalf of the Commissioner that no un-reasonable delay had occurred in initiating the proceedings in as much as the petitioner not only defaulted in making the payments but also defaulted submitting the statutory forms which resulted in early detection. Besides this, for the entire State, there is one Commissioner functioning under the Act and there are more than five thousand establishments covered under the E.P.F Scheme.

    7. We are, however, not inclined to probe if un-reasonable delay had occurred in initiating the proceedings against the petitioner for the reasons mentioned hereinafter.

    8. Contention (iii):—Section 14-B of the Act clearly provides that where an employer makes default in the payment of any contribution required under the Act, the Commissioner may recover from the employer by way of penalty of such damages provided that before levying and recovering of such damages, the employer shall be given a reasonable opportunity of being heard. A bare reading of the provision would indicate that delayed payment of the statutory dues as it had occurred in the present case, does not ipso-facto invite levy of damages. If the employer furnishes sufficient cause for the delay, the designated authority in a given case may not levy damages. In the impugned order, the Commissioner in paragraph-5 has observed “that the establishment had defaulted in payment of statutory dues without any valid reason”.

    9. Shri Nayak, learned counsel for the petitioner submits that earlier different divisions were depositing the employees and employers share with the Commissioner within the time stipulated but subsequently when the centralised payment scheme was introduced, the divisions could not deposit the share and as such, delay in deposit was unavoidable and was not intentional. This plea taken by the petitioner does not seem to have been considered by the Commissioner as is evident from the impugned order.

    10. Contention No. (iv)—The break-up of damages levied on the petitioner (vide enclosure to Annexure-5 series) would show that for the period of delay ranging from six days to 562 days (from March, 1986 to March, 1990), 25% of arrears per annum has been imposed as penal damage. It is evidently arbitrary. May it be stated that previously damages were being imposed at a rate basing on circulars issued by the Commissioner under which damages up-to 100% was impossible. Such imposition being arbitrary, as there was no clear guideline paragraph 32-A has been inserted vide C.S.R No. 521 dated 16-8-1991 (wide effect from 1-9-1991) clearly indicating that damages may be recovered from the employer at the rates given below:

    “Period of default Rate of damages (percentage of arrears per annum) (a) Less than two months Seventeen (b) Two months and above but less than four months. Twenty-two (c) Four months and above but less than six months Twenty-seven (d) Six months and above Thirty-seven”.

    11. The aforesaid provision though is not strictly applicable to the case at hand, it indicates the mind of the Government that the rate of damages should not be arbitrary. On the facts and circumstances of this case and keeping in view that the Act is a beneficial legislation for the employees in factories and establishments covered under the Act and to avoid further litigation between the parties, we are inclined to hold that the petitioner is liable to pay damages at the rate of 17% per annum on the percentage of arrears.

    12. Contention No. (v):— The Government letter No. 1107 dated 28-1-1997 at Annexure-1 shows that on the direction issued by the Supreme Court, the Government decided that with effect from 1-4-1990 the provisions of the Act are not applicable to the erstwhile Orissa State Electricity Board. The said decision has to be taken as final since the opposite parties have not yet challenged the same in any court of law. This being the position, the impugned order so far as it relates to leavy of damages from 1-4-1990 to February, 1991 is liable to be quashed. We order accordingly.

    13. In the result, the impugned order at Annexure-5 and the calculation sheets at Annexure-6 series are quashed. The Commissioner - opp. party No. 2 is directed to recalculate the damages for the period from March, 1986 to 31-3-1990 at the rate of 17% per annum keeping in view the observations made above and pass appropriate order under section 14-B of the Act. As already stated, with effect from 1-6-1990 as the petitioner's establishment is excluded from the purview of the Commissioner is not competent to pass any order datermining liability under section 14-B of the Act with effect from that date so long as the Government decision communicated in letter No. 1107 dated 28-1-1997 at Annexure-1 stands un-reversed by the competent court of law.

    14. Shri Nayak submits that if re-calculation is made afresh pursuant to this order, the Commissioner may have to refund to the petitioner the excess amount deposited by it and as required under paragraph 60(2)(b) of the Employees Provident Funds Schems, 1952, interest is payable on the said amount of retund by the Commissioner. Shri Samal contends that no interest is payable on such claim of refund. We do not find any substance in the objection of Shri Samal in view of the clear provision of the liability of the Commissioner to pay interest. Therefore, in the event it is ultimately found that the petitioner is entitled to refund, the Commissioner will pass appropriate order as required under paragraph 60 of the Employees' Provident Funds Scheme, 1952 and refund the amount found due together with the interest so determined. The Commissioner will complete this exercise within two months of receipt of this order.

    15. The writ application is accordingly allowed. There would be no order as to costs.

    16. Pradipta Ray, J.:— I agree.

    Writ application allowed.