  • SECTION 5 LIMITATION ACT 1963
  • sub-rules (1) and (2) of Rule 3A of Order 41 of the Code
  • provisions of Order 41, Rule 3A of the Code
  • Order 41, Rule 3A of the Civil P.C 1908
  • provisions of Order 41, Rule 3A of Code
  • S. 3 of the Limitation Act.
  • S. 5 of the Limitation Act
  • S. 5 of Limitation Act
  • Amending Act of 1976
  • Rule 11 or Rule 13,
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • SECTION 5 LIMITATION ACT 1963
  • sub-rules (1) and (2) of Rule 3A of Order 41 of the Code
  • provisions of Order 41, Rule 3A of the Code
  • Order 41, Rule 3A of the Civil P.C 1908
  • provisions of Order 41, Rule 3A of Code
  • S. 3 of the Limitation Act.
  • S. 5 of the Limitation Act
  • S. 5 of Limitation Act
  • Amending Act of 1976
  • Rule 11 or Rule 13,
Smart Summary

Structured Summary of the Opinion

Factual and Procedural Background

The petitioner (plaintiff in Title Suit No. 46 of 1987) instituted a suit in the Court of the Subordinate Judge, Titilagarh, seeking declaration of his right, title and interest over the suit land and permanent injunction against the opposite parties. The opposite parties filed a written statement and evidence was adduced by both sides. The trial Court decreed the suit in favour of the petitioner.

Opposite party No. 1 (Orissa Forest Corporation Ltd.) filed Title Appeal No. 19/12 of 1991-93 in the Court of the learned Additional District Judge, Titilagarh, after the prescribed period of limitation. An application under Section 5 of the Limitation Act, 1963 for condonation of delay was presented; the learned Additional District Judge condoned the delay and admitted the appeal for hearing on merits. The present civil revision challenges that order of condonation of delay.

Legal Issues Presented

  1. Whether the requirements of Order 41, Rule 3A(1) of the Civil Procedure Code (i.e., that a time-barred appeal be accompanied by an application for condonation of delay supported by affidavit) are mandatory in a manner that non-compliance must result in dismissal of the appeal, or directory so that the defect can be remedied.
  2. Whether the learned Additional District Judge erred in condoning the delay in filing Title Appeal No. 19/12 of 1991-93 despite the fact the application for condonation was originally not accompanied by the affidavit required by Order 41, Rule 3A(1).
  3. Whether the petitioner is entitled to costs because of the inconvenience caused by the delayed presentation of the appeal, and if so, what costs should be awarded.

Arguments of the Parties

Petitioner's Arguments (Counsel: M.S. Mishra)

  • Order 41, Rule 3A of the Code mandates that an affidavit must accompany an application for condonation of delay; this requirement was not met initially and is mandatory.
  • The affidavit filed subsequently does not cure the initial defect in the application.
  • The grounds advanced in support of the condonation application were prima facie untenable.
  • The petitioner has been prejudiced by the delayed presentation of the appeal and, at minimum, costs should have been awarded to mitigate that prejudice.

Opposite Party No. 1 / Corporation's Arguments

  • The provisions of Order 41, Rule 3A are not mandatory in the sense argued by the petitioner; they are directory and allow for approval of an affidavit filed subsequently.
  • Since genuine grounds were shown for condonation, the learned Additional District Judge acted within his jurisdiction and in accordance with law in condoning the delay.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Maya Devi v. M.K. Krishna Bhattathiri, AIR 1981 Kerala 240 Support for the view that procedural defects relating to R.3A can be treated so as to advance justice (as cited among other High Court decisions). Referenced as part of judicial support for permitting remedial action and not treating R.3A non-compliance as mandating outright dismissal.
State of Bihar v. Ray Chandi Nath Sahay, AIR 1983 Patna 139 Supportive authority on handling of procedure regarding limitation and R.3A. Used to show that other High Courts have adopted an approach permitting remediation of defects and considering merits.
M. Das Gupta v. Prakash K. Shah, AIR 1984 Bom 390 Authority indicating flexibility in dealing with procedural non-compliance relating to appeals and limitation. Invoked to corroborate the view that R.3A should not be construed to impose a drastic penalty in all cases of non-compliance.
State of Karnataka v. Nagappa, AIR 1986 Karnataka 199 Another High Court decision cited in support of remedial and justice-oriented approach to R.3A non-compliance. Relied upon to show consistent judicial approach across High Courts favouring opportunity to cure defects.
Dilabar v. Sulabha, AIR 1986 Orissa 38 Local High Court decision emphasizing that courts are not powerless where memorandum of appeal is not accompanied by condonation application or by an affidavit; interpretation should advance justice. Directly relied on by this Court to support its view that R.3A non-compliance does not render the Court powerless and that remedial opportunities should be afforded.
Krishnaswami v. Ramaswami, AIR 1917 PC 179 (Privy Council) Disapproval of admitting appeals subject to later decision on limitation; stressed expediency of determining limitation at admission stage. Cited for legislative history and rationale: R.3A was inserted to secure final determination of limitation issue at the stage of admission, preventing lingering doubt.
Anantnag (Collector, Land Acquisition) v. Mst. Katiji, AIR 1987 SC 1353 Principle that Section 5 of the Limitation Act confers power to condone delay so courts can do substantial justice; courts should apply law to subserve justice. Used to show higher court authority for a liberal but meaningful application of Section 5, supporting remedial approach to limitation issues.

Court's Reasoning and Analysis

The Court examined sub-rules (1) and (2) of Order 41, Rule 3A inserted by the Amending Act of 1976. It noted the legislative purpose: to prescribe a procedure for final determination of the question of limitation at the stage of admission of appeals so that the question does not remain lingering. A combined reading of Rule 3A(1) and (2) shows that an appellant cannot insist on the hearing of a time-barred appeal unless an application for condonation (supported by affidavit) is decided.

However, the Court distinguished between procedural mandate and a penal consequence. It observed that while Rule 3A(1) requires filing an affidavit with the condonation application, the rule neither expressly nor contextually imposes that the consequence of non-compliance must be dismissal of the appeal without opportunity to remedy. The Court treated R.3A(1) as procedural, intended to facilitate administration of justice rather than to operate as a punitive provision designed to defeat access to justice.

The Court set out the appropriate course where an appeal is presented without the accompanying application/affidavit: regard the presentation as defective for non-compliance and afford the appellant a reasonable opportunity to remedy the defect, rather than dismissing the appeal in limine. If the defect is remedied within the time allowed, the remedying relates back to the original date of presentation and the appeal should be treated as properly presented. If the appellant fails to remedy the defect despite opportunity, dismissal is appropriate.

Applying these principles to the case at hand, the Court noted that although the application was not originally accompanied by the affidavit, the affidavit was subsequently filed. On that basis the learned Additional District Judge was justified in treating the application as in accordance with law and in dealing with it on merits. The Court further found that the reasons advanced by the Corporation for condonation could not be termed unreasonable or unacceptable so as to warrant interference under Section 115 of the Code.

While upholding the validity of the condonation in this case, the Court balanced fairness and prejudice: it accepted that petitioner suffered inconvenience from the delay and therefore was entitled to costs.

Holding and Implications

Holding: The Civil Revision was disposed of by the Court upholding the manner in which the learned Additional District Judge dealt with the condonation application (i.e., treating the subsequently filed affidavit and application as in accordance with law and condoning the delay), subject to the payment of costs by opposite party No. 1 (the Corporation).

Direct Implications for the Parties:

  • The order of the learned Additional District Judge condoning the delay in Title Appeal No. 19/12 of 1991-93 stands; the appeal may be taken up for hearing on merits provided the condition set by this Court is complied with.
  • The Orissa Forest Corporation Ltd. (opposite party No. 1) is directed to pay Rs. 500/- as costs to the learned counsel for the petitioner within one month. A receipt evidencing payment must be filed before the learned Additional District Judge, Titilagarh. Only upon filing of that receipt will the appeal be taken up for hearing on merits; the order operates only if costs are timely paid.
  • The record (LCR) is to be sent back to the trial Court forthwith; the Civil Revision is disposed of accordingly.

Broader implications: The opinion applies and reiterates existing principles regarding Order 41, Rule 3A and the remedial role of Section 5 of the Limitation Act as explained through cited authorities. The Court did not purport to lay down a novel precedent; rather it applied established principles to the facts before it and emphasised a procedure that favours remediation of procedural defects where justice so requires.

    Rajkumar Jindal v. Orissa Forest Corporation And Another Opposite Parties.

    1. Petitioner, plaintiff in title Suit No. 46 of 1987 challenges the order for condonation of delay in presentation of appeal by the opposite parties (defendants in the suit) before the learned Addl. District Judge, Titilagarh.

    2. Background facts sans unnecessary details are as follows:

    Petitioner as plaintiff had filed the aforesaid suit in the Court of Subordinate Judge, Titilagarh with a prayer to declare his right, title and interest over the case land and for permanent injunction against the opposite parties on several grounds. The present opposite parties appeared in the suit and filed written statement denying the assertions made in the plaint. Evidence was adduced by the parties and on perusal and consideration thereof, the suit was decreed in favour of petitioner. Title Appeal No. 19/12 of 1991-93 was filed by opposite party No. 1 in the Court of learned Addl. District Judge. Titilagarh. Undisputedly, the same was filed beyond the time prescribed for preferring appeal. An application under Section 5 of the Limitation Act, 1963 (in short ‘Limitation Act’) was filed stating that on account of unavoidable difficulties there was delayed presentation of the appeal. On consideration of the grounds taken, delay was condoned and appeal was admitted for hearing on merits. Condonation of delay is the subject-matter of challenge in this application.

    3. Mr. M.S Mishra, learned counsel appearing for petitioner has urged that application for condonation of delay did not meet the requirements of Order 41, Rule 3A of the Civil P.C 1908 (in short, the ‘Code’) and therefore, the same should not have been acted upon. Elaborating it is stated that the aforesaid provision mandates an affidavit to accompany a petition for condonation for delay, which was not filed. Even though it was subsequently filed, that did not cure initial defect in the application. It is further urged that prima facie untenable grounds were taken in support of the application for condonation. It is further urged that petitioner has been prejudiced because of delayed action and even if it is accepted that delay was to be condoned, costs should have been awarded to mitigate the difficulties Learned counsel for the Orissa Forest Corporation Ltd. (hereinafter referred to as ‘Corporation’). (opposite party No. 1) on the other hand supported the order of learned Addl. District Judge. According to him, provisions of Order 41, Rule 3A of Code are not mandatory and even if affidavit was filed subseqeuntly, that was to be taken note of. It is further stated that on genuine grounds condonation of delay was sought for and learned Addl. District Judge has acted perfectly within his jurisdiction and in accordance with law.

    4. In order to appreciate rival contentions, provision an contained in sub-rules (1) and (2) of Rule 3A of Order 41 of the Code are to be noted. The same reads as follows:

    “3A. Application for condonation of delay — (1) When an appeal is presented after the expiry of the period of limitation specified therefor, it shall be accompanied by an application supported by affidavit setting forth the facts on which the appellant relies to satisfy the Court that he had sufficient cause for not preferring the appeal within such period.

    (2) If the Court sees no reason to reject the application without the issue of notice to the respondent, notice thereof shall be issued to the respondent and the matter shall be finally decided by the Court before it proceeds to deal with the appeal under Rule 11 or Rule 13, as the case may be.

    The pivotal question is whether provisions of Order 41, Rule 3A of the Code are mandatory as contended by the petitioner or directory as urged by Corporation. The said rule has been inserted by Amending Act of 1976 in order to prescribe a procedure for securing final determination of the question as to limitation even at the stage of admission of appeal. A combined reading of Rule 3A(1) and (2) makes it manifest that the purpose of requiring the filing of an application for condonation of delay under Rule 3 A(1) along with the time barred appeal is mandatory in the sense that the appellant cannot without such application being decided insist upon the Court to hear his time barred appeal. That was the very purpose sought to be achieved by the insertion of R. 3A(1) and (2), as becomes clear from the legislative history of R. 3A. So penalty of rejection or dismissal of a time barred appeal for non-compliance of the requirement of R. 3A(1) in envisaged therein. Thus when R. 3A(1) neither expressly nor contextually indicates that its non-compliance should as a penalty entail dismissal of the time barred appeal, its operation cannot be regarded as bringing about impliedly such drastic result. Rule 3A(1) being procedural is intended to and in the administration of justice and cannot be construed as implying the award of a severe penalty for its non-compliance. A Court before whom a time barred appeal comes up for hearing with no application along with it under S. 5 of Limitation Act for condonation of delay has to necessarily dissmiss it not because of non-compliance with R. 3A(1) but because of operation of S. 3 of the Act. An appeal preferred after the prescribed period shall be dismissed because of the bar of limitation imposed by S. 3 of the Limitation Act. Therefore, what a Court should do when a time barred appeal is presented before it without being accompanied by an application for condonation of delay is to regard such presentation as defective for non-compliance of R. 3A(1) and to afford to the appellant a reasonable opportunity to remedy the defect instead of dismissing the appeal outright or in limine. If the appellant disregards the opportunity afforded, the Court should dismiss the appeal. When the defect is remedied within the time allowed by the Court, the appeal should be regarded as one properly presented as on the date of its original presentation in that remedying of such procedural defect necessarily relates back to the date of original presentation of the appeal. My view receives support from decisions of not only various other High Courts i.e Kerala, Patna, Bombay and Karnataka High Courts in Maya Devi v. M.K Krishna Bhattathiri, AIR 1981 Kerala 240, State of Bihar v. Ray Chandi Nath Sahay, AIR 1983 Patna 139, M. Das Gupta… v. Prakash K. Shah…., AIR 1984 Bom 390 and State of Karnataka v. Nagappa, AIR 1986 Karnataka 199, but also decision of this Court in Dilabar v. Sulabha, AIR 1986 Orissa 38. As observed by this Court in Dilabar's case (supra) it cannot be said that in every timbe-barred appeal, where the memorandum of appeal is not accompanied by application for condonation of delay or accompanied by an application not supported by an affidavit, the Court is altogether powerless to consider the matter. Such an interpretation would defeat the very purpose i.e advancing the cause of justice, for which all procedural laws are framed. The object of inserting R. 3A(1) in O. 41 was to put an end to the practice of admitting of appeal subject to the decision on question of limitation. This practice was disapproved by the Privy Council in Krishnaswami v. Ramaswami, AIR 1917 PC 179 and it stressed the expediency of adopting a procedure under which the final determination of question as to limitation would be possible before admission of the appeal. Therefore with a view to see that the question of limitation does not remain lingering the provision of R. 3A of O. 41 has been inserted. The Law Commission of India in its Twenty-seventh Report (Page 237) referred to decision of the Privy Council in Krishnaswami's case, AIR 1917 PC 179 (supra) as noticed in its earlier report (Fourteenth Report) and laid strss on the expediency of adopting a procedure for securing at the stage of admission, the final determination, after due notice of the question of limitation affecting the competence of the appeal, and suggested insertion of proposed R. 3A of the Code for the purpose. That is how R. 3A was enacted. Appellate Court has no jurisdiction to defer question of limitation to be considered at the time of hearing, and to admit the appeal. The language of the Rule leaves no room for doubt that question of limitation is to be decided before the appeal is heard under R. 11 for admission.

    A Code of Procedure must be regarded as such. It is procedure, something designated to facilitate justice and further its ends not a penal enactment for punishment and penalties; not a thing designed to trip people up. Too technical construction of a provision that leaves no room for reasonable elasticity of interpretation should be guarded against (provided that justice is done to both sides) lest the very means designed for the furtherance of justice be used to frustrate it. A party cannot be refused just relief merely because of some mistake, negligence, inadvertence of even infraction of rules of procedure. A procedural step which facilitates hearing of appeal cannot impede access to justice. As observed by Apex Court in Collector, Land Acquisition, Anantnag v. Mst. Katiji, AIR 1987 SC 1353 legislature has conferred power to condone delay by enacting S. 5 of the Limitation Act in order to enable Courts to do substantial justice to the parties by disposing of matter on merits. Courts are to apply law in a meaningful manner which subserves ends of justice. Though a justifiable liberal approach in matters of limitation is necessary, at the same time no letharjic inaction is to be encouraged. That would also frustrate ends of justice. When substantial justice and technical considerations are pitted against each other, the former has to be preferred. A litigant does not stand to benefit by resorting to delay. In fact he runs a serious risk. There is no presumption that delay is occasioned deliberately, or on account of culpable negligence, or on account of mala fides.

    5. In the case at hand, admittedly application originally was not accompanied by an affidavit. But records show that subsequently the affidavit was filed. Learned Addl. District Judge was therefore, justified in treating the application for condonation to be in accordance with law, and in dealing with it. The reasons indicated by the Corporation in support of the application for condonation cannot be termed to be unreasonable or unacceptable so as to warrant interference, while exercising power under S. 115 of the Code.

    6. But as rightly submitted by learned Counsel for petitioner, inconvenience was caused to petitioner for delayed presentation of appeal, and he is entitled to costs. The opposite party No. 1 Corporation is a corporate body. It acts through its officer as it has no mind of its own. But when a period of limitation is prescribed, all possible efforts are to be made to take steps within the time stipulated. Ends of justice would be best served, if the opposite party No. 1 Corporation pays costs. Considering the extent of delay and nature of dispute involved. I direct the Corporation to pay a sum of Rs. 500/- (Five hundred as costs), to be paid to the learned counsel for petitioner in this Court within a month from today. Receipt however shall be filed before learned Addl. District Judge, Titilagarh. If such receipt is filed, appeal shall be taken up for hearing on merits. This order shall operate only if costs are paid within the time stipulated.

    The Civil Revision is disposed of accordingly.

    Send back the LCR forthwith.

    Order accordingly.

    Use AI to get other relevant cases.

    Comments

    Rajkumar Jindal v. Orissa Forest Corporation And Another Opposite Parties.
    (Apr 3, 1995)