AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Section 41 of the Indian Arbitration Act (hereinafter referred to as the Act), read with Order 39, Rules 1 and 2, C.P.C.
  • Order 19, Rule 2, C.P.C.
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Section 41 of the Indian Arbitration Act (hereinafter referred to as the Act), read with Order 39, Rules 1 and 2, C.P.C.
  • Order 19, Rule 2, C.P.C.
Smart Summary

Factual and Procedural Background

The revision petition arises from an order dated 9-8-1984 passed by the VI Additional Judge to the District Judge, Indore, disposing of an application under Section 41 of the Indian Arbitration Act, read with Order 39, Rules 1 and 2, C.P.C. The petitioner, a registered contractor firm, entered into a contract for construction of inner and service roads in Indira Complex, Naulakha, Indore. Initially, the work was to be done by the Indore Municipal Corporation but was later entrusted to the Indore Development Authority under State Government directions.

The petitioner received payment for the first running bill but was refused payment for the second running bill and was asked to stop work pending higher authority orders. Despite repeated attempts by the petitioner to resume work, the stipulated contract period expired and the Indore Municipal Corporation unilaterally terminated the contract on 23-11-1982 without giving the petitioner an opportunity to be heard. The petitioner then served a notice invoking the arbitration clause of the contract. Subsequently, two arbitrators were appointed and accepted by the petitioner.

Meanwhile, the Indore Development Authority issued a notice calling for fresh tenders for the work. The petitioner moved the lower court for an injunction restraining the respondents from opening or accepting tenders. The lower court initially granted an ex parte injunction but later dismissed the application as not maintainable under Section 41 of the Arbitration Act. The petitioner challenged this dismissal by filing the present revision petition.

Legal Issues Presented

  1. Whether a valid arbitration agreement exists between the parties under the contract and related correspondence.
  2. Whether the unilateral termination of the contract by the Indore Municipal Corporation was legally valid.
  3. Whether the petitioner is entitled to interim relief in the form of injunction under Section 41 of the Arbitration Act pending arbitration proceedings.
  4. Whether the trial court erred in dismissing the application for injunction on the ground of no prima facie case and misconstruing the scope of Section 41 of the Act.
  5. Whether the non-joinder of the Indore Municipal Corporation as a party affects the maintainability of the petitioner's claim.
  6. Whether delay in approaching the court disentitles the petitioner from seeking interim relief.

Arguments of the Parties

Petitioner's Arguments

  • The trial court misconstrued the scope of Section 41 of the Arbitration Act.
  • The contract cannot be unilaterally terminated; such termination is illegal and the contract subsists.
  • The trial court improperly went into the merits of the case instead of leaving it to the arbitrators.
  • The arbitration clause was accepted by both parties, indicating an intention to arbitrate disputes.
  • The petitioner was entitled to a fair opportunity to present its case before the arbitrators.
  • Delay in approaching the court is not significant as the petitioner had been corresponding and the delay was caused by the respondents.
  • The Indore Development Authority stepped into the shoes of the Indore Municipal Corporation, thus the contract dispute remains valid.

Respondents' Arguments

  • No valid subsisting contract exists between the petitioner and the respondents.
  • Even if the letter dated 14-6-1983 constitutes an arbitration agreement, the dispute is not of such a nature to warrant interim injunction.
  • The dispute is essentially between the petitioner and the Indore Municipal Corporation, which is not a party to the current proceedings.
  • The cause suffers from non-joinder of necessary parties.
  • The petitioner delayed in approaching the court and is thus disentitled to equitable relief.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Union of India v. D. N. Revri & Co., AIR 1976 SC 2257 Interpretation of arbitration agreements to give efficacy to contracts rather than invalidate them. The court relied on this precedent to affirm that the letter dated 14-6-1983 and its acceptance constituted a valid arbitration agreement.
Ranjit Chandra Mitter v. Union of India, AIR 1963 Cal 594 Whether interim relief under Section 41 of the Arbitration Act can be granted in absence of a valid arbitration agreement or pending arbitration proceedings. The trial court relied on this case to deny injunction; however, the revision court found this reliance erroneous and distinguished it.
Union of India v. Raman Iron Foundry, AIR 1974 SC 1265 The Court's power to grant interim injunctions under Section 41 of the Arbitration Act in relation to arbitration proceedings. The court cited this Supreme Court decision to hold that interim injunction can be granted in relation to arbitration proceedings, not necessarily pending before the court.
Debendra Nath Singha v. Dwijendra Nath, AIR 1970 Cal 255 Interpretation of Section 41(b) of the Arbitration Act concerning interim relief. The court noted this case as part of a line of authority supporting a broader interpretation of arbitration proceedings for granting injunctions.
Maheshwari & Co. (Pvt.) Ltd. v. Corporation of Calcutta, AIR 1975 Cal 165 Scope of interim injunction under Section 41 of the Arbitration Act. Used to support the proposition that interim relief can be granted in arbitration proceedings not necessarily pending in court.
Daulat Ram v. Shriram, AIR 1964 Madh Pra 219 Clarification that arbitration proceedings under Section 41(b) of the Act are not confined to court pending matters. The court relied on this to reject the trial court's narrow reading of Section 41(b) and to uphold the petitioner's entitlement to interim relief.

Court's Reasoning and Analysis

The court began by examining the existence of an arbitration agreement, concluding that the letter dated 14-6-1983 and the petitioner's acceptance dated 2-7-1983 constituted a valid arbitration agreement under Section 2(a) of the Arbitration Act. The court rejected the respondents' narrow and technical interpretation of the letter as a mere gesture of goodwill, emphasizing the Supreme Court's guidance to interpret arbitration agreements to uphold their efficacy.

Regarding the scope of the dispute and non-joinder of the Indore Municipal Corporation, the court held that the actual scope of the dispute is a matter for the arbitrators and that non-joinder was not fatal as no relief was sought against the Municipal Corporation.

The court dismissed the objection of delay in approaching the court, noting that the petitioner had been actively corresponding and that the delay was attributable to the respondents. The court observed that the respondents, as a statutory body, should have accounted for the arbitration process before inviting tenders.

In addressing the trial court's reliance on Ranjit Chandra Mitter, the court found the trial court erred by interpreting "arbitration proceedings" as only pending court proceedings, whereas the legislative intent and Supreme Court decisions support a broader interpretation allowing interim relief in arbitration proceedings not before the court.

The court concluded that the petitioner had a prima facie case and was entitled to ad interim relief under Section 41 of the Arbitration Act. The trial court's dismissal of the application was based on an erroneous approach and failure to apply binding precedents.

Holding and Implications

The revision petition is allowed and the order dated 9-8-1984 passed by the trial court is quashed. The respondents are restrained from proceeding with the work that is the subject matter of the arbitration agreement.

The court awarded costs and directed payment of counsel's fee. The decision directly affects the parties by reinstating the petitioner's right to seek arbitration and interim relief, and restrains the respondents from continuing the tender process. No new precedent was set, but the court reaffirmed established principles regarding the interpretation of arbitration agreements and the scope of interim relief under Section 41 of the Arbitration Act.

    Taj Builders, Indore v. Indore Development Authority, Indore And Another Opposite Party.

    1. This revision petition arises out of an order dt. 9-8-1984, passed by the VI Additional Judge to the court of the District Judge, Indore thereby disposing of an application under Section 41 of the Indian Arbitration Act (hereinafter referred to as the Act), read with Order 39, Rules 1 and 2, C.P.C.

    2. Facts necessary' for disposal of this revision petition, stated in brief, are that the petitioner-firm is a registered contractor. The firm had entered into a contract for construction of inner roads and service roads in the Indira Complex, Naulakha, Indore. Initially this work was to be carried out by the Indore Municipal Corporation, but it appears that eventually the work was entrusted to the Indore Development Authority, Indore, under the directions of the State Government.

    3. The petitioner's grievance is that the Indore Municipal Corporation having paid the first running bill, amounting to Rs. 3,97,945.80 paise, refused to pay the second running bill, amounting to Rs. 1,95,580.86p as submitted by it and the petitioner firm was asked to stop the work, which was to be resumed only on obtaining order from the higher authorities. The petitioner contends that it approached several times through letters expressing its intent to complete the work, but it was not allowed to complete the same. In the meanwhile the stipulated time for completion of work of the contract expired and the Indore Municipal Corporation acting unilaterally, without affording any opportunity to the petitioner terminated the contract on 23-11-1982. The petitioner thereafter served a notice, calling upon the Indore Municipal Corporation to come to arbitration in view of Clause 47 of the contract. The work, as has been stated above, was entrusted to the Indore Development Authority under orders of the State Government about four months after the notice dt. 1-1-1983, served by the petitioner on the administrator of the Indore Municipal Corporation. By this notice the petitioner made it clear that the notice be treated under the arbitration clause for appointment of an Arbitrator. In pursuance to this notice two Arbitrators were appointed, vide letter dt. 14-6-1983. The petitioner by its reply dt. 2-7-1983 agreed to the appointment of the Arbitrators and craved for a fair opportunity to put forth its case before the Arbitrators.

    4. In the meantime the Indore Development Authority issued a notice, calling for fresh tenders in respect of the work, which was to be completed by the petitioner. The tenders were to be received till 25-5-1984, but the petitioner on 24-5-1984 moved the lower court with an application under Section 41 of the Act, read with Order 39, Rules 1 and 2, C.P.C. and the lower court holding that the petitioner was entitled to an ex parte injunction, passed an order restraining the respondents from opening and accepting any tender in respect of the work, which was the subject-matter of the petitioner's contract.

    5. On 1-6-1984 the respondents made their appearance and submitted reply to the aforesaid application preferred by the petitioner. This reply is signed by the attorney, Shri Manoharlal Mootha, who has also sworn an affidavit in support of the reply. It appears from the record that on 9-7-1984 an application under Order 19, Rule 2, C.P.C. was preferred by the petitioner for permission to cross-examine the deponent Manoharlal Mootha on his affidavit, but this application was rejected by the trial court. The petitioner had also submitted a rejoinder to the reply Filed by the respondents. It was allowed to be taken on record. The trial Court after hearing the learned counsel for the parties, dismissed the application as not maintainable under Section 41 of the Act. It is against this order that the petitioner has come up in revision before this court.

    6. Shri Chaphekar, learned counsel for the petitioner, appearing with Shri Sanyal has contended that the trial court has misconstrued the scope of Section 41 of the Act. He further contends that a contract cannot be put to an end in an unilateral manner, as was done by the Indore Municipal Corporation, According to him there is still subsisting valid contract and a unilateral termination of the same is illegal. Such unilateral termination of contract cannot be accorded any legal sanction, as has been erroneously done by the trial court. He has pointedly referred to paras 5 and 7 of the trial courts' order and submitted that the trial court has palpably gone wrong in interpreting Section 41 of the Act. His further contention is that it was not open to the trial court at that stage to go into the merits of the case and decide the validity of the agreement. In fact, these were questions, which pre-eminently fell within the scope of arbitration, to be decided by the Arbitrators. According to the learned counsel, the trial court in going into such questions has virtually usurped the function of the Arbitrators. The learned counsel has referred to para 4 of the respondents' reply, filed before the trial court. According to him in fact there was no dispute about acceptance of the arbitration Clause. Naturally, as a result of a gesture of good-will or otherwise in any event even according to the respondents an arbitration was contemplated, provided for and in fact offered to the petitioner, who accepted the same.

    7. Shri Bagadia, learnd counsel appearing for the respondents, has contended firstly, that there is no valid subsisting contract between the petitioner and the respondents; secondly, if the letter dt. 14-6-1983 is held to have constituted an arbitration agreement, even then the extent and scope of the dispute between the parties is not such as to entitle the petitioner to a relief of ah ad interim injunction, and lastly, he submits that the dispute, if any, is essentially between the contractor-petitioner and the Indore Municipal Corporation, and the respondent-Indore Development Authority does not figure at any stage anywhere. His other submissions, which are of a technical nature, are that the cause suffers from non-joinder of parties and the petitioner is guilty of delay in approaching the court, which by itself is sufficient to disentitle him from seeking an equitable relief of injunction.

    8. The first question, which falls for consideration, in the light of the argument advanced by the learned counsel for the respondents is whether there is an arbitration agreement. The material available on record is a letter dt. 14-6-1983, with a copy endorsed to the present applicant and the reply dt. 2-7-1983, in which the applicant made a categorical statement accepting the arbitration of the Arbitrators. The 'arbitration agreement' has been defined in Section 2(a) of the Act, thus :

    "Section 2(a).-- "arbitration agreement" means a written agreement to submit present or future differences to arbitration, whether an arbitrator is named therein or not."

    A mere perusal of the letter, referred to above, and the reply thereto by the applicant is sufficient to establish the existence of an arbitration agreement. It cannot be interpreted in a manner to annul the effect of the letter and its acceptance. In fact the Supreme Court in Union of India v. D. N. Revri & Co. AIR, 1976 SC 2257 has propounded the interpretation in such a manner as to give efficacy to the contract rather than to invalidate it. The narrow technical approach is not proper and the interpretation sought to be put by the respondents is technical and narrow. At one stage of the arguments it was submitted by the learned counsel for the respondetns that at best this letter can be construed as the respondents' gesture of good-will. Even assuming it to be so far the sake of argument, the legal effect of the letter cannot be avoided or escaped by the respondents. It is, therefore, held that the letter dt. 14-6-1983 and its categorical acceptance by the applicant by its reply dt. 2-7-1983 results in an arbitration agreement, even if the term 'arbitration agreement' is strictly construed.

    9. The next submission made on behalf of the respondents is with regard to the scope of the dispute and in this behalf it is submitted that the dispute, if any, essentially lies between the applicant and the Municipal Corporation, Indore, which has not been joined as a party. Shri Chaphekar, learned counsel for the applicant on the other hand has submitted that the actual scope of dispute is a matter which falls essentially within the domain of functioning of the Arbitrators and at this stage it cannot be gone into. So far as the respondents' technical objection about the non-joinder of the Municipal Corporation, Indore, as a party is concerned Shri Chaphekar's reply is that as no relief is sought against the Municipal Corporation, Indore, it is not necessary to implead the Municipal Corporation as a party. There is substance in Shri Chaphekar's argument. Once the valid arbitration agreement comes into existence, the differences which exist between the parties can be resorted to by reference to the arbitration, which in fact has been proposed by the respondents themselves.

    10. There is yet another objection of delay in approaching the court. The applicant had been corresponding with the Corporation authorities and the respondents and (during) the time lost after the acceptance conveyed by the applicant, at no point of time was it indicated by the applicant that the respondents are not prepared for arbitration, as was proposed by them. Therefore, the delay, if any, is of no consequence. In fact the proposed Arbitrators are the Government Officers of the respondents' choice and having obtained the acceptance of the applicant, if the matters have not moved any further, the applicant cannot be blamed for the time lapsed in between. While inviting tenders, in all fairness it would be legitimately expected of the respondents, a statutory body, to have taken into consideration the steps which it was required to take in pursuance of the letter proposing appointment of Arbitrators and its acceptance by the applicant. In this view of the matter it is submitted on behalf of the applicant by Shri Chaphekar that the situation is self created one by the respondents. Therefore, on mere ground of delay the applicant cannot be denied the relief which he had sought.

    11. Relying on the case of Ranjit Chandra Mitter v. Union of India, AIR 1963 Cal 594, it is submitted on behalf of the respondents that the applicant is not entitled to any interim relief under Section 41 of the Act, inasmuch as there is no valid arbitration agreement or arbitration proceeding subsisting between the parties. Shri Chaphekar on the other hand submits that a unilateral termination of contract cannot be recognised in law. There is, according to him, a subsisting valid agreement and the Indore Development Authority because of the intervention of the State Government has stepped into the shoes of the Indore Municipal Corporation. With reference to paras 4, 5 and 7 of the impugned order he has tried to point out that the work is already done by the applicant prior to 23-11-1982, when the Corporation unilaterally terminated the contract; yet the contract exists and the dispute relating to the work already done still exists, as is clear from the letter dt. 14-6-1983 proposing appointment of Arbitrators. It is clear that as a result of this subsisting dispute even the respondent Authority was also finding it difficult to make further progress in the work. As a result of the recommendation of an advisory Committee, appointed to advice in the matter of Indira complex, it was decided by the respondents to resolve this dispute by resort to the arbitration, proposing the Collector and the Superintending Engineer as the two Arbitrators. This statement contained in the letter clearly goes to show that the dispute existed between the parties, which required to be resolved and was proposed to be resolved by appointment of Arbitrators and in fact two Arbitrators were proposed by the respondents.

    12. The trial court has negatived the existence of a prima faice case in favour of the applicant mainly basing its reasoning on the case of Ranjit Chandra Mitter (AIR 1963 Cal 594) (supra). Shri Chaphekar, learned counsel for the applicant, has vehemently assailed this finding. His contention is that the trial court has erroneously read 'pending arbitration proceedings' although Section 41(b) of the Act provides merely 'arbitration proceedings'. His submission is that it cannot be read as a 'pending arbitration proceeding'. Shri Chaphekar's contention deserves to be upheld. The provisions of Section 41(b) of the Act came up for consideration before the Supreme Court in Union Of India v. Raman Iron Foundry ., AIR 1974 SC 1265 and the Supreme Court held that the Court has power to issue interim injunction but such interim injunction can only be for the purpose of and in relation to arbitration proceedings. This court is constrained to observe that the trial court has ignored the decisions of this court and the Supreme Court while adhering to the aforesaid Calcutta view in the case of Ranjit Chandra Mitter (supra), while in subsequent decisions of the same High Court in Debendra Nath Singha v. Dwijendra Nath, AIR 1970 Cal 255 and Maheshwari & Co. (Pvt.) Ltd. v. Corporation of Calcutta, AIR 1975 Cal 165, a different view has been taken. This Court in Daulat Ram v. Shriram, AIR 1964 Madh Pra 219 has held that the arbitration proceedings contemplated by Section 41(b) of the Act are not confined to cases in which arbitration proceedings are pending before the court and the power can be exercised in other arbitration proceedings started out of the court. In this connection it would not be out of place to trace and refer to the Legislative intent, which is clear from the fact that expression "arbitration proceedings" has been substituted in Section 41(b) of the Act for the words "reference" in order to cover the various kinds of proceedings, which the Act contemplates. Surely enough the intention of the Legislature by effecting this amendment was to include within the scope of Clause (b) of Section 41, all those proceedings, which are held in pursuance of an arbitration agreement, whether with or without intervention of the Court. Thus, the order under revision cannot be allowed to stand as it has basically proceeded on an erroneous approach on the part of the trial court without applying its mind to the numerous authorities of this court and the Supreme Court, interpreting Section 41(b) of the Act.

    13. The trial court has refused leave to the applicant-petitioner mainly on the ground that it has no prima facie case, which is as has been held here to before not the correct position emerging from the facts of the case. This court has held that a party having a prima facie case is entitled to an ad interim relief of injunction unless the facts otherwise warrant. No material is placed on record so as to disentitle the applicant from claiming the relief in substance.

    14. For the reasons aforesaid, this revision petition succeeds and is accordingly allowed with costs throughout. The order dt. 9-8-1984, passed by the trial court is quashed and the respondents are restrained from proceeding with the work in any manner, which is the subject-matter of the arbitration agreement. Counsel's fee shall be Rs. 250/-, if certified. In the circumstances this court can only hope that the parties concerned shall co-operate in expeditious disposal of the arbitration.

    Use AI to get other relevant cases.

    Comments

    Taj Builders, Indore v. Indore Development Authority, Indore And Another Opposite Party.
    (Oct 19, 1984)