AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
Smart Summary

Factual and Procedural Background

On 14 April 1952 the Government awarded a lump-sum contract (Rs. 23,49,000) for construction of a bridge on the Narmada near Mortakka to M/s Umraosingh & Company (the contractors). The original contract required completion within 24 months but contemplated extensions for alterations, inclement weather and other causes beyond the contractors' control; Clause 17 contained a detailed arbitration provision for disputes arising under the contract.

A supplementary agreement dated 19 January 1954 extended time to 31 May 1956 and promised a bonus of Rs. 1,00,000 if the works were completed within the extended time; otherwise the principal agreement would operate as if the supplementary agreement had never been made. The supplementary agreement did not include or incorporate a specific arbitration clause.

The works were ultimately completed by 28 February 1958 after further extensions. The contractors presented eleven items of additional claims after completion; the Government rejected those claims and counter-claimed for supervision charges. The dispute was referred to arbitration under Clause 17 and two arbitrators (P.N. Bhalla and G.L. Sharma) made an award dated 28 October 1960 (published 31 October 1960). The arbitrators allowed most claims in specified amounts totaling Rs. 5,63,581, rejected one claim, and awarded interest at 6% per annum if the award was not paid within two months; they also apportioned costs.

The contractors applied on 2 November 1960 under Section 14 of the Arbitration Act, 1940, to file the award in Court. The Government objected. The Additional District Judge, Khandwa, by order dated 26 September 1964, upheld the award only for Claim Nos. 1 and 10 (Rs. 50,000 and Rs. 1,00,000 respectively), set aside the remainder (including interest), and declined interest; his reasoning relied on finding an error apparent on the face of the award that allowed him to examine the merits of the claims.

The contractors filed First Appeal No. 9 of 1965 in this Court seeking restoration of the entire award. The Government filed Miscellaneous (First) Appeal No. 60 of 1965 seeking to set the entire award aside. The present opinion disposes of both appeals.

Legal Issues Presented

  1. Whether the arbitrators had jurisdiction to award interest where none of the claims referred to them included a claim for interest, and whether the arbitrators' award of future interest was within jurisdiction.
  2. Whether an error apparent on the face of the award limited to the interest portion entitled the court below to examine the merits of all claims and set aside the whole award.
  3. Whether the arbitrators committed an error apparent on the face of the award in allowing the substantive claims (i.e., whether the grants contradicted a correct construction of the contract).
  4. Whether the arbitration clause in the original contract covered the eleven claims submitted (i.e., whether the arbitrators had jurisdiction over Claims Nos. 1 to 9 and 11).
  5. Whether Claim No. 10 (bonus under the supplementary agreement) fell within the jurisdiction of the arbitrators, given that the supplementary agreement did not incorporate the arbitration clause of the principal contract.
  6. Whether the contractors were duly authorised to file the award in Court.
  7. Whether the reference to arbitration was a valid joint reference made by the Executive Engineer and the contractors as required by Clause 17.

Arguments of the Parties

Government's Arguments (as presented by the learned Advocate-General)

  • The arbitrators had no jurisdiction to award interest because none of the submissions to arbitration included a claim for interest.
  • The error apparent on the face of the award (the interest portion) permitted the Additional District Judge to examine and set aside the entire award on the merits.
  • The arbitrators misconstrued the contract in allowing the substantive claims (Claims Nos. 2–9 and 11), which, on proper construction, could not have been allowed—this constituted an error apparent on the face of the award.
  • Some items (specifically Items Nos. 2, 3, 4 and 7) fell outside the arbitration clause because they were covered by Clause 1 of the contract and thus excluded.
  • The contractors were not properly authorised to file the award in Court; any authority to file should have been specifically alleged and proved.
  • The reference submitted to arbitration was not a valid joint reference by the Executive Engineer and the contractors.

Contractors' Arguments / Position (as reflected in the opinion)

  • The claims were properly referred to arbitration under Clause 17 because they involved additions to the contract price due to delay, altered works, or other matters arising under or out of the contract.
  • The supplementary agreement's bonus clause gave rise to a claim which the arbitrators nevertheless allowed; contractors proceeded under the award and filed it in Court.
  • The arbitrators had authorised the contractors (through their partner/agent Lala Banarasilal) to file the original award in Court; this was asserted in the Section 14 application.
  • Both the Executive Engineer and Superintending Engineer actively participated in arbitration proceedings without objection, demonstrating a consensual reference to arbitration.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court in This Opinion
Seth Thawardas Pherumal v. Union of India, AIR 1955 SC 468 Held that arbitrators lacked power to award interest after the award where interest was not part of the submission; Section 34 CPC does not apply to arbitrators. The Court applied this as the controlling principle for denying the arbitrators' award of future interest, because none of the claims referred included interest and the reference was not of "all matters in difference".
Firm Madanlal Roshanlal v. Hukumchand Mills, AIR 1967 SC 1030 Qualified Thawardas: where dispute as to interest is referred, arbitrator may award interest; if “all matters in difference” are referred, interest may be allowed analogous to Section 34. Used to explain the qualification to Thawardas; Court concluded those qualifications did not apply here because interest was not referred and the reference was not broadly worded.
Union of India v. Bungo Steel Furniture (P.) Ltd., AIR 1967 SC 378 / AIR 1967 SC 1032 Affirms that arbitrators may decide interest when it is part of the reference; also that arbitrators are not bound to record reasons and absence of reasons normally prevents finding an error on the face of the award. The Court relied on this authority to hold that the award's allowance of interest was beyond jurisdiction and to state that absence of reasons in an award prevents finding an error apparent on its face as to construction.
Stan of M.P. v. S. and S. (P.) Ltd., (1972) 1 SCC 702 : AIR 1972 SC 1507 Further authority addressing arbitrator's power to award interest when interest is part of the reference. Cited to show the line of authority that qualified Thawardas and to explain when interest may properly be awarded by arbitrators.
U.G.V.E.S Co. v. U.P.E Board, (1973) 1 SCC 254 : AIR 1973 SC 683 Discusses separability of invalid portions of an award and whether an error apparent on the face of part of an award permits remitting or setting aside the whole award. The Court applied the separability principle from this line of authority to hold that the award's defective interest portion was severable and the remainder should stand.
Chandris v. Isbrandtsen-Moller Co., (1951) 1 KB 240 English Court of Appeal authority: where reference is of “all matters in difference,” arbitrator may allow interest. Referred to as an example supporting the proposition that broadly worded references can include interest; the Court used it in discussing limits of Thawardas.
Champsey Bhara v. Jivraj Bulloo, 1923 All ER Rep 235 : AIR 1923 PC 66 Privy Council: definition of “error in law apparent on the face of the award” — there must be in the award (or incorporated document) a legal proposition which is the basis of the award and is erroneous. Relied upon to explain the narrow meaning of “error apparent on the face of the award” and to reject the Government's contention that mere mistake of law/fact by arbitrators suffices to set aside an award.
Giacomo Coats Fu Andrea v. British Italian Trading Co., (1962) 2 All ER 53 Test for when a contract (or clause) is incorporated into an award: whether the arbitrator comes to a finding on the wording of the contract. Applied to conclude that because the award here contained no reference to contract terms or reasons, the contract was not incorporated and no error of construction could be found on the face of the award.
Blaiber & Co. Ltd. v. Leopold Newporne (London) Ltd., (1953) 2 Lloyd's Rep 427 Quoted formulation (via Denning, L.J.) on implied incorporation: if the arbitrator says “On the wording of this clause I hold…”, that clause is incorporated. Used to explain the accepted test for incorporation of contract terms into an award; Court found no such incorporation in the instant award.
Allen Berry & Co. v. Union of India, (1971) 1 SCC 295 : AIR 1971 SC 696 Discusses cases on “error apparent on the face of the award” and approves Diplock L.J.'s test regarding incorporation and findings on contract wording. Relied on to affirm that mere reference to the contract in an award is insufficient to permit examination of contract construction by the Court; the award must show a finding on the wording.
Babu Ram v. Nanhemal, C.A. No. 107 of 1966 (decision referenced, 5-12-1968) Authority cited for restricting the principle of reading contracts into awards; court should not extend the rule of incorporation. Cited to support the position that incorporation of contract terms into an award is not to be extended; the award in the present case did not incorporate contract terms.
A.M. Mair & Co. v. Gordhandas Sagarmull, AIR 1951 SC 9 Holds that disputes requiring recourse to the contract are disputes under or arising out of the contract and thus fall within arbitration clauses. Applied to conclude that the contractors' substantive claims (except the bonus under the separate supplementary agreement) required recourse to the contract and so fell within Clause 17.
Heyman v. Darwins Ltd., 1942 AC 356 : 111 LJ KB 241 Quoted for the test: “If a party has to have recourse to the contract, that dispute is a dispute under the contract.” Used to reinforce the test for whether a dispute arises out of the contract and is therefore arbitrable under the arbitration clause.
Union of India v. S.T. and C. Co., AIR 1969 SC 488 Test: whether recourse to the contract is necessary to determine a party's claim; if so, the matter is within the arbitration clause. Applied to conclude that because Government resisted claims by reference to contract terms, recourse to the contract was necessary and the arbitrators had jurisdiction over those claims.
Kumbha Mawji v. Union of India, AIR 1953 SC 313 Addressed requirements for proof of authority to file awards in Court (referred to by Government). Cited by the Advocate-General; Court examined the Section 14 application and evidence and found contractors were authorised to file the award, rejecting the Government's contention.
Alopi Prashad v. Union of India, AIR 1960 SC 588 Example of a speaking award where reference to contract terms and findings permitted examination for errors of law on the face of the award. Cited by the Advocate-General; Court distinguished it because the instant award gave no reasons and contained no reference to contract terms, so Alopi Prashad was not applicable.
State of Madhya Pradesh v. R.N. Ghanekar & Co., Misc. (First) Appeal No. 17 of 1969 (decided 11-4-1972) Division Bench decision referenced regarding inference of error on face of award even without express reference to contract clauses. Court observed that the Division Bench could not lay down a proposition contrary to Supreme Court decisions; it found nothing in that decision to support the Advocate-General's position.

Court's Reasoning and Analysis

The Court addressed the questions in a structured sequence and applied the authorities set out above.

Interest awarded by the arbitrators: The Court began by observing the general rule from Seth Thawardas that an arbitrator is not a "Court" under the CPC and cannot award interest after the award unless the dispute as to interest was referred or the reference was broadly worded ("all matters in difference"). The Court noted subsequent authorities (Firm Madanlal Roshanlal, Union of India v. Bungo Steel Furniture, Stan of M.P.) that limited Thawardas by holding that where interest is part of the reference or the reference is all-encompassing, the arbitrator may award interest analogously to Section 34 CPC. Applying these principles, the Court found that in the present case none of the claims referred included interest and the referral was limited to specific matters (not "all matters in difference"); therefore Thawardas applied and the arbitrators exceeded their jurisdiction in awarding future interest. The Additional District Judge was therefore right in holding the award bad insofar as it allowed interest.

Whether the court below could examine the merits because of an error apparent: The Court held that the Additional District Judge erred in using the interest error as a basis to examine and set aside the whole award. The Court applied the separability principle (as discussed in Russell on Arbitration and U.G.V.E.S Co. v. U.P.E Board): where the bad portion of an award is separable from the rest, the valid residue should be upheld. Here, the interest portion was clearly separable and did not render the remainder invalid; there is no principle allowing a court to examine the merits of the entire award merely because a separable portion is defective.

Error apparent on the face of the award as to construction of the contract: The Advocate-General argued that the arbitrators misconstrued the contract and therefore the award contained errors apparent on its face. The Court reviewed authorities (Champsey Bhara, Giacomo Coats Fu Andrea, Diplock L.J.'s test, Allen Berry) and reiterated the narrow meaning of "error apparent on the face of the award." The test requires that the award itself (or a document incorporated into it) show a legal proposition or an express finding on the wording of the contract that is erroneous. The Court observed that the present award contained no reasons, no reference to contractual clauses and did not incorporate the contract; it only stated amounts awarded on each claim. Consequently, it was impossible to hold there was an error of law on the face of the award relating to contract construction. The Advocate-General's reliance on speaking awards (e.g., Alopi Prashad) was rejected because those cases involved awards with reasons and references to contract terms, unlike the instant award.

Jurisdiction under Clause 17 for substantive claims (Claims Nos. 1–9 and 11): The Court examined Clause 17, noting its wide wording permitting reference of disputes about additions to the contract amount arising from delay, directions/requisitions involving increased cost, disputes as to construction, or "any other matter or thing arising under or out of this contract," except as to matters left to the sole decision of the E.E. The Court applied the test from A.M. Mair and Union of India v. S.T. & C. Co. — whether recourse to the contract is necessary to decide the claim. Because the Government's resistances to the contractors' claims invoked the terms of the contract (as evidenced by the Executive Engineer's notes, Ex. P-4), recourse to the contract was necessary. Therefore Claims Nos. 1–9 and 11 fell within the arbitration clause and the arbitrators had jurisdiction to decide them. The Court rejected the Advocate-General's narrower reading that Items 2, 3, 4 and 7 were excluded by Clause 1, pointing out Clause 1 did not confer a decision/requisition power on the Executive Engineer relevant to exclusion.

Claim No. 10 (bonus under supplementary agreement): The Court held Claim No. 10 arose under the supplementary agreement dated 19 January 1954, which did not contain or incorporate an arbitration clause and did not make the arbitration clause of the principal agreement applicable. The bonus clause was independent and was not incorporated into the original contract. The settled rule that an arbitration clause in the original contract does not cover disputes arising under a fresh or subsidiary contract was applied (citing Seth Thawardas). Therefore Claim No. 10 was outside the arbitrators' jurisdiction.

Authority to file the award: The Court considered the argument that the contractors were not authorised to file the award. The Section 14 application averred that the original award "received by the petitioner from the arbitrators" was submitted; both arbitrators testified that the original award had been handed to Lala Banarasilal (partner/agent) with authority to file in Court. Although the Superintending Engineer and Executive Engineer denied witnessing such authorisation, the Court preferred the arbitrators' evidence and the fact an original was handed to Banarasilal (and a copy to the Superintending Engineer) supported the arbitrators' account. The Court therefore rejected the contention that the contractors lacked authority to file.

Validity of the reference (whether a joint reference existed): The Court treated the question as one of fact that should have been raised earlier. No formal challenge was made at the proper stage below. The Court reviewed the papers produced by the arbitrators (Ex. P-4), noted the claim statement signed by the Executive Engineer, the contractors' Appendix I, the Executive Engineer's notes, and records showing the Superintending Engineer and Executive Engineer appeared and participated throughout without objection. The Superintending Engineer had nominated one arbitrator and the contractors had nominated the other, and both parties participated in proceedings. On these facts the Court concluded there was a valid reference made in the manner envisaged by Clause 17.

Result of the analysis: The Court concluded that only the portions of the award dealing with future interest and Claim No. 10 (the bonus) were invalid for lack of jurisdiction; the rest of the award was valid and must be upheld because the invalid portions are separable.

Holding and Implications

Holding: First Appeal No. 9 of 1965 is partly allowed. The award is set aside in so far as it relates to Claim No. 10 (the Rs. 1,00,000 bonus under the supplementary agreement) and future interest awarded by the arbitrators. In all other respects the award is upheld.

Consequential orders and direct effects:

  • The contractors are entitled to receive Rs. 4,63,581 from the Government under the award (this is the award amount after excluding Claim No. 10 and the portion of interest set aside).
  • In place of the decree passed by the Additional District Judge, there shall be a decree for Rs. 4,63,581 against the Government.
  • The contractors are entitled to interest at the rate of three percent per annum on this amount from 26 September 1964 (the date of the decree passed by the Additional District Judge) under Section 29 of the Arbitration Act.
  • The contractors shall get proportional costs of both Courts; the Government will bear its own costs throughout.
  • Miscellaneous (First) Appeal No. 60 of 1965 (filed by the State) is dismissed without order as to costs.

Implications beyond the parties:

This opinion applies established principles concerning (a) the limited circumstances in which an arbitrator may award interest after an award, (b) the narrow meaning of "error apparent on the face of the award," (c) the requirements for incorporation of contract terms into an award, and (d) separability of invalid portions of awards. The opinion does not purport to create a novel precedent but applies and reconciles existing authorities to the facts before the Court.

    M/S. Umraosingh And Co., Mahanagar, Lucknow (U.P) v. The State Of M.P And Others

    Singh, J.:— This judgment shall also dispose of Miscellaneous (First) Appeal No. 60 of 1965.

    2. The facts giving rise to these appeals are that on 14th April, 1952 contract for construction of a bridge on Narmada near Mortakka was granted by the Government to M/s. Umraosingh and Company, which is a partnership firm and shall hereinafter be referred to as the contractors. The contract was for a lump sum payment of Rs. 23,49,000/-. According to clause (13) of the Contract, the works were to be completed within 24 months. Extension of time was, however, contemplated on account of works being altered, varied or added to or on account of any delay by reason of inclement weather or causes beyond the control of the contractors. The contract contained an arbitration clause which reads as follows:

    “17. Provided always that in case any question, dispute or difference shall arise between the E.E and the contractors:

    as to what additions, if any, ought in fairness to be made to the amount of the contract by reason of the works being delayed through no fault of the contractors or by reason or on account of any directions or requisitions of the E.E involving increased cost to the contractors beyond the cost properly attending the carrying out of the contract according to the true intent and meaning of the signed drawings and specification; or as to the works having been duly completed; or

    as to the construction of these presents; or as to any other matter or thing arising under or out of this contract, except as to matters left during the progress of the works to the sole decision or requisition of the E.E under clauses Nos. 1, 4, 8 and 9, or in case the contractors shall be dissatisfied with any certificate of the E.E under clause 6 or under the provision in clause 13 or in case he shall withhold or not give any certificate to which they may be entitled; or

    as to the right of the contractors to receive any compensation; or

    as to the amount of such compensation payable to them under clause 18;

    then such question, dispute or difference or such certificate or the value or matter which should be certified as the case may be, is to be from time to time submitted to the arbitration of a tribunal composed of one arbitrator nominated by the contractors and one arbitrator nominated by the S.E In the event of a disagreement between the arbitrators on any matter or matters, such matter or matters shall be referred to an umpire to be nominated by the C.E and the award of such arbitrators or the umpire is to be final and where necessary to be equivalent to a certificate of the E.E and the contractors are to be paid accordingly.

    3. The works were not completed within 24 months and there was a supplementary agreement between the contractors and the Government on 19th January, 1954 by which the time was extended upto 31st May, 1956. This agreement proceeds upon the premise that the works could not be completed within 24 months because of circumstances over which the contractors had no control. By this agreement the Government promised to pay a bonus of rupees one lac in case the works were completed within the extended time. In all other respects the terms and conditions of the principal agreement remained in full force. The supplementary agreement, leaving aside its preamble, reads as follows:

    “1. Notwithstanding anything contained in condition 13 of the principal agreement, the contractor shall duly and properly complete and carry out the said work in every respect to the satisfaction of the Executive Engineer by a date not later than the 31st May, 1956 in strict conformity to and accordance with the terms, conditions and specifications in the principal agreement contained.

    2. Upon fulfilment and performance by the contractor of the conditions of clause 1 hereof but in no other case the Governor shall pay to the contractor a bonus of Rs. 1,00,000/- (one lakh) only in addition to the sum payable under the principal agreement.

    3. In the event of the failure of the contractor to fulfil and perform the conditions contained in clause 1 hereof the contractor shall be liable under and subject to the provisions in clause 13 and other clauses of the principal agreement contained as if this supplementary agreement had never been made and entered into by and between the parties and in all other respects and cases and save as modified hereby the terms and conditions of the principal agreement shall remain in full force and have full effect.”

    4. The works could not be completed even by 31st May, 1956. It appears that there was some alteration in design, which was not sanctioned by the Government of India till October, 1956. The time for completion of the works was further extended upto 28th February, 1958. The works were completed within this period. After completion of the works, the contractors claimed additional payment under eleven items. The Government did not accept these items of claim of the contractors and counter-claimed for supervision charges. The dispute was referred to arbitration of two arbitrators viz. Shri P.N Bhalla and Shri G.L Sharma. The arbitrators, on 28th October, 1960, made an award, which was published on 31st October, 1960. The contractors' claim under item No. 6 was disallowed, but their other claims were allowed to the extent of Rs. 5,63,581/. The arbitrators also allowed interest on this amount at the rate of six per cent per annum after expiry of two months from the date of award in case of non-payment of the amount by the Government. The counter-claim of the Government was disallowed. The award reads as follows:

    “We, Prem Nath Bhalla and Ganeshilal Sharma, nominated respectively by the parties, entered into the Arbitration. We inspected the work, had several meetings and have gone through the written notes, pleadings, verbal representations and arguments at length and have also examined several documents.

    2. The Public Works Department was represented by Shri G.L Kumar, Superintending Engineer (B. and R.) Indore Circle, Indore, and Shri L.H Bhatia, Executive Engineer, West Nimar Division Khargone. The contractors were represented by Shri Umrao Singh and Shri Krishna partners of Messrs. Umrao Singh and Co.

    3. We hereby make and publish this Award in writing of and concerning the matters referred to us. Our Award against each individual claim is as follows:

    Claim No. 1 : Extra work done due to change in design in Pier No. 4 : In respect of this claim of Rs. 3,68,906/- made by the contractors, we award a sum of Rs. 50,000/- (Rs. fifty thousand only).

    Claim No. 2: Increased cost of labour from June, 1956 till actual completion: In respect of the claim of Rs. 4,23,000/- (later modified to Rs. 4,71,443/-) we award a sum of Rs. 2,07,900/- (Rs. two lacs seven thousand and nine hundred only).

    Claim No. 3: Increase in the cost of steel for the work: In respect of the claim of Rs. 1,81,717/- we award a sum of Rs. 73,269/- (Rs. seventy three thousand two hundred and sixty nine only).

    Claim No. 4: Difference of price of cement due to increase: In respect of the claim of Rs. 1,27,586/- we award a sum of Rs. 18,286/- (Rs. eighteen thousand two hundred and eighty six only).

    Claim No. 5 : Royalty paid on sand : In respect of the claim of Rs. 80,000/- we award a sum of Rs. 32,521/- (Rs. thirty two thousand five hundred and twenty one only).

    Claim No. 6 : Royalty paid on stone : We reject this claim of Rs. 12,000/-.

    Claim No. 7 : Non-supply of steel and cement in 1954: In respect of the claim of Rs. 1,00,000/- we award a sum of Rs. 15,000/- (Rs. fifteen thousand only).

    Claim No. 8: Compensation for loss of materials during floods of 1956 while concreting Arch No. 13: In respect of the claim of Rs. 21,920/- we award a sum of Rs. 10,428/- (Rs. ten thousand four hundred and twenty eight only).

    Claim No. 9: Claim for work redone after collapse of Arch No. 12: In respect of the claim of Rs. 81,488/- we award a sum of Rs. 40,500/- (Rs. forty thousand five hundred only).

    Claim No. 10 : Bonus: In respect of the claim of Rs. 1,00,000/- we award the amount of Rs. 1,00,000/- (Rs. one lac only).

    Claim No. 11 : Cartage of cement and steel: In respect of this claim (figure not given) we award a sum of Rs. 15,677/- (Rs. fifteen thousand six hundred and seventy seven only).

    Supervision Charges: The counter claim of supervision charges made by the Department for supply of cement and steel is rejected and no claim against the contractors is admitted.

    4. Total Award: Our total award against all the claims is Rs. 5,63,581/- (Rs. five lacs sixty three thousand five hundred and eighty one only), which sum shall be paid by the Public Works Department (B. and R.) Madhya Pradesh to Messrs. Umrao Singh and Co. in full settlement of all their claims.

    If the above amount of the award is not paid within two months of the date of the award, interest at the rate of 6% per annum shall be paid to Messrs. Umrao Singh and Co. by the Public Works Department (B. and R.) Madhya Pradesh from the date of the award to the date of the payment in addition to the amount of the award.

    The cost of the Award comprising of the fees of both the arbitrators plus their travelling and other expenses as well as the cost of the stamp paper and legal charges which is Rs. 23,219.14 (Rs. twenty three thousand two hundred and nineteen np. fourteen) shall be shared equally by the two parties.”

    5. The contractors made an application on 2nd November, 1960 under Section 14 of the Arbitration Act, 1940, and filed the original award along with this application. Objections were taken to the award by the Government. These objections were decided by the Additional District Judge, Khandwa, by his order dated 26th September, 1964. The award was upheld with respect to claim No. 1 for Rs. 50,000/- and claim No. 10 for Rs. 1,00,000/-. The award was, however, set aside with respect to claims Nos. 2 to 9 and 11 and interest was also disallowed. The Additional District Judge came to the conclusion that there was an error apparent on the face of the award in the matter of grant of interest and this error enabled him to examine the merits of all the claims. After examining the merits of the claims in accordance with the terms of the contract, he came to the conclusion that only claims Nos. 1 and 10 could be allowed by the arbitrators and the rest of the claims were not justified on the basis of the terms of the contract. It is on this reasoning that the award was upheld in so far as claims No. 1 and 10 were concerned and was set aside with respect to the other claims. It is against this order that the contractors have filed First Appeal No. 9 of 1965 in this Court in which they pray that the entire award be restored. The Government's appeal against the order of the Additional District Judge is Miscellaneous (First) Appeal No. 60 of 1965. In this appeal it is prayed that the entire award be set aside. The first question to be seen is whether the arbitrators were right in awarding interest. None of the claims referred to the arbitrators included a claim for interest. Section 34 of the CPC, does not apply to arbitration proceedings. In Seth Thawardas Pherumal v. Union Of India, AIR 1955 SC 468 it was observed as follows:

    “It was suggested that at least interest from the date of “suit could be awarded on the analogy of Section 34 of the CPC, 1908. But Section 34 does not apply because an arbitrator is not a “Court” within the meaning of the Code nor does the Code apply to arbitrators, and, but for Section 34, even a Court would not have the power to give interest after the suit. This was, therefore, also rightly struck out from the award.”

    6. The view taken in Thawardas's case has been modified to some extent in subsequent cases viz. Firm Madanlal Roshanlal v. Hukumchand Mills, AIR 1967 SC 1030, Union of India v. Bungo Steel Furniture, AIR 1967 SC 1032 and Stan of M.P v. S. and S. (P.) Ltd., (1972) 1 SCC 702 : AIR 1972 SC 1507. In all these cases it has been pointed out that Thawardas's case does not deal with the question whether the arbitrator can award interest subsequent to the passing of the award, if the claim regarding interest was referred to the arbitrator. It has also been pointed out in these cases that if a dispute as to interest is referred to arbitration, it is an implied term of the reference that the arbitrator will decide the dispute according to existing law and give such relief with regard to interest as the Court would give if it decided the dispute. On this basis it has been held that the principle of Section 34 will be applicable in such cases and the arbitrator will have jurisdiction to allow interest subsequent to the passing of the award. These cases also point out that if the reference is of “all matters in difference” the arbitrator may allow interest as was held by the Court of Appeal in Chandris v. Isbrandtsen-Moller Co., (1951) 1 KB 240. The position, therefore, is that if there is a dispute as to interest which is referred to arbitration or if all matters in difference are referred to arbitration, the arbitrator may award interest on principles analogous to Section 34 of the Code. But if the reference does not include a dispute as to interest or if it is not so widely worded as to include “all matters in difference” it appears that Thawardas's case will still prevail and the arbitrator will have no jurisdiction to allow interest after the date of the award. In the instant case the claims referred to arbitrators did not include any dispute as to interest. Further, the reference was not of “all matters in difference” but only of specific matters. In the circumstances, Thawardas's case was applicable and the arbitrators exceeded their jurisdiction in awarding interest. The learned Additional District Judge was, in our opinion, right in holding that the award was bad with respect to interest. The learned Additional District Judge was, in our opinion, right in holding that the award was bad with respect to interest.

    7. The next question is whether the Additional District Judge was right in examining all the claims on merits, simply on the ground that the award was erroneous on the face of it to the extent it allowed interest. In our opinion, the learned Additional District Judge was clearly wrong in this matter. According to his findings the only error apparent on the face of the award was with regard to interest. This error made the award invalid in respect of interest, but this portion of the award was severable from the rest of it. The law in this respect is that if the bad portion of the award is separable, the award will be held good for the residue; whereas, if the two are inseparable, the award is altogether avoided; (See Russell on Arbitration, Eighteenth Edition, pp. 399, 400, 401 and U.G.V.E.S Co. v. U.P.E Board, (1973) 1 SCC 254 : AIR 1973 SC 683 at p. 688 para. 25). Now, in the instant case that portion of the award which allowed future interest was clearly separable and, therefore, the rest of the award could not be held to be invalid. There is no principle of law that if a portion of an award which is clearly separable is found to be defective because of an error apparent on its face, the Court gets jurisdiction of examining the merits of the entire award. Indeed, the learned Advocate-General did not support the order of the Additional District Judge on this ground. We need not, therefore, pursue this matter any further.

    8. The learned Advocate-General, however, argued that the award in respect of all the items suffered from error apparent on the face of the award. His argument is that the claims laid by the contractors could not have been allowed on a proper construction of the terms of the contract and as the claims have been allowed by the arbitrators it must be held that they misconstrued the terms of the contract, which is an error apparent on the face of the award. In our opinion, there is no substance in this argument. It is well settled that an award made by an arbitrator cannot be set aside on the ground that he has committed mistakes in law and fact; it can only be set aside if the error in law appears on the face of the award. In Champsey Bhara v. Jivraj Bulloo, 1923 All ER Rep 235 : (AIR 1923 PC 66) it has been held by the Privy Council that an error in law on the face of an award means that there is to be found in the award, or a document actually incorporated therein, as, for instance, a note appended by the arbitrator stating the reasons for his judgment, some legal proposition which is the basis of the award and is erroneous. It was further held that the award will stand unless, on the face of it, the arbitrator has tied himself down to some legal proposition, which, when examined, appears to be unsound. In this connection questions have often arisen as to when a contract, the construction of which is necessary for deciding the matters, in dispute, can be said to be incorporated into an award. This matter was examined by the Court of Appeal in Giacomo Coats Fu Andrea v. British Italian Trading Co., (1962) 2 All ER 53 where Diplock, L.J, after examining all the relevant authorities, observed as follows:

    “It seems to me, therefore, that, on the cases, there is none which compels us to hold that a mere reference to the contract in the award entitles us to look at the contract. It may be that in particular cases a specific reference to a particular clause of a contract may incorporate the contract, or that clause of it, in the award. I think that we are driven back to first principles in this matter, namely, that an award can only be set aside for error which is on its face. It is true that an award can incorporate another document so as to entitle one to read that document as part of the award and, by reading them together, find an error on the face of the award. But the question whether a contract, or a clause in a contract, is incorporated in the award is a question of construction of the award. It seems to me that the test is put as conveniently as it can be in the words of Denning, L.J, which I have already cited from Blaiber and Co. Ltd. v. Leopold Newporne (London) Ltd., (1953) 2 Lloyd's Rep 427 at p. 429.

    “As I read the cases, if the arbitrator says: ‘On the wording of this clause I ‘hold’ so and so, then that clause is impliedly incorporated into the award because he invites the reading of it.”

    9. The question what is an error apparent on the face of the award has been considered by the Supreme Court in a number of cases. All these cases are discussed in Allen Berry and Co. v. Union of India, (1971) 1 SCC 295 : AIR 1971 SC 696. The Supreme Court has approved the test laid down by Diplock, L.J, in Giacomo Costa etc. v. British Italian, (1962-2 All ER 53) (supra). The test in the words of their Lordships is as follows:

    “The question whether a contract or a clause of it is incorporated in the award is a question of construction of the award. The test is, does the arbitrator come to a finding on the wording of the contract. If he does, he can be said to have impliedly incorporated the contract or a clause in it whichever be the case. But a mere general reference to the contract in the award is not to be held as incorporating it. The principle of reading contracts or other documents into the award is not to be encouraged or extended, (see Babu Ram v. Nanhemal, C.A No. 107 of 1966, D/- 5-12-1968 (SC)). The rule thus is that as the parties choose their own arbitrator to be the Judge in the dispute between them, they cannot, when the award is good on the face of it, object to the decision either upon the law or the facts. Therefore, even when an arbitrator commits a mistake either in law or in fact in determining the matters referred to him, but such mistake does not appear on the face of the award or in a document appended to or incorporated in it so as to form part of it, the award will neither be remitted nor set aside notwithstanding the mistake.”

    10. A reading of all these authorities goes to show that before it can be concluded that the award discloses an error apparent on its face relating to construction of a clause or term in the contract, the award must contain reference to the clause or term and a finding as to its meaning. Unless that is shown, it cannot be said that the arbitrator has come to a finding on the wording of the contract which is an error apparent on its face. When there is absolutely no reference to the contract or its terms and when the award contains no reasons, it is impossible to hold that there is an error apparent on the face of the award. Indeed, the Supreme Court in Bungo Steel Furniture (P.) Ltd. v. Union of India, AIR 1967 SC 378 at p. 382 clearly laid down that it was well settled principle that an arbitrator was not bound to record his reasons or state the principles of law on which he had proceeded, and that it is only when the arbitrator proceeds to give his reasons or to lay down the principles on which he has arrived at his decisions that the Court is competent to examine whether he has proceeded contrary to law and is entitled to interfere if such error in law is apparent on the face of the award. This view was reiterated in Firm Madanlal Roshanlal v. Hukumchand Mills, AIR 1967 SC 1030 and Union of India v. Bungo Steel Furniture, AIR 1967 SC 1032. In Firm Madanlal Roshanlal's case the award gave no reasons. In negativing the contention that there was an error of law on the face of the award, the Court observed as follows:

    “In the present case, the arbitrator gave no reason for the award. We do not find in the award any legal proposition which is the basis of the award, far less a legal proposition which is erroneous. It is not possible to say from the award that the arbitrator was under a misconception of law. The contention that there are errors of law on the face of the award is rejected.”

    11. We have already quoted the award in the instant case. The award does not refer to the contract or to any of its terms. It does not give any reasons; it only awards a particular sum against each item of claim. In the absence of any reference to the contract or to its terms and in the absence of any reasons contained in the award, it is not possible to hold that there is an error of law apparent on the face of the award relating to the construction of any of the terms of the contract. The learned Advocate-General referred to us Seth Thawardas Pherumal v. Union Of India, AIR 1955 SC 468, Alopi Prashad v. Union of India, AIR 1960 SC 588 and U.G.V.E.S Co. v. U.P.E Board, (1973) 1 SCC 254 : AIR 1973 SC 683. But in these cases the awards were speaking awards containing references to the terms of the contracts and also the findings of the arbitrators on those terms. That being not the position in the instant case, these cases are not applicable. The learned Advocate-General also referred to a Division Bench decision of this Court in State of Madhya Pradesh v. R.N Ghanekar and CO., Bombay, Misc. (First) Appeal No. 17 of 1969, decided on 11-4-1972 (Madh Pra) for the proposition that even when there is no reference to any term of the contract and no finding as to its meaning, still it is open to infer an error apparent on the face of the award. This decision quotes extensively from the Supreme Court cases referred to by us earlier. The learned Judges of the Division Bench could not have laid down any proposition contrary to the Supreme Court decisions and we do not find anything in this decision which can support the contention of the learned Advocate-General.

    12. The learned Advocate-General then argued that all the claims referred to the arbitrators were beyond the purview of Clause 17 of the contract. We have already quoted Clause 17, which is the arbitration clause. This clause is worded in very wide language. It permits reference of any dispute as to what additions ought in fairness to be made to the amount of the contract by reason of the works being delayed through no fault of the contractors, or by reason of or on account of any directions or requisitions of the E.E involving increased cost to the contractors. It also permits reference of a dispute as to the construction of the contract. Further, it permits reference when the dispute is as to any other matter or thing arising under or out of the contract, except as to matters left during the progress of the works to the sole decision or requisition of the E.E under clauses Nos. 1, 4, 8 and 9. Now, a look at the claims, except claim No. 10, laid by the contractors will show that they claimed all these items as additional payment for construction of the bridge on the ground that there was a change in the original design requiring extra work and also on the ground that works were delayed for reasons beyond the control of the contractors. These claims can reasonably fall within the First sub-clause of Clause 17. They will also fall within the Third sub-clause, which permits reference of any dispute “as to any other matter or thing arising under or out of this contract.” Arbitration clauses containing similar words have been construed by the Supreme Court. In A.M Mair and Co. v. Gordhandas Sagarmull, AIR 1951 SC 9 the Supreme Court, in this context, observed as follows:

    “A dispute, the determination of which turns on the true construction of the contract, would also seem to be a dispute, under or arising out of or concerning the contract. In a passage quoted in Heyman v. Darwins Ltd., 1942 AC 356 : 111 LJ KB 241 Lord Dunedin propounds the test thus “If a party has to have recourse to the contract, that dispute is a dispute under the contract.” Here, the respondents must have recourse to the contract to establish their case and, therefore, it is a dispute falling within the arbitration clause.”

    13. Again in Union of India v. S.T and C. Co., AIR 1969 SC 488 the same test was laid down for determining whether a dispute was one arising out of the contract. Their Lordships said:

    “The test for determining the question is whether recourse to the contract by which both the parties are bound is necessary for the purpose of determining whether the claim of respondent firm is justified or otherwise. If it is necessary to take recourse to the terms of the contract for the purpose of deciding the matter in dispute, it must be held that the matter is within the scope of the arbitration clause and the arbitrators have jurisdiction to decide this case.”

    14. Now, in the instant case, it is clear from the stand taken on behalf of the Government in answer to the claims of the contractors that claims were resisted on the ground that they were not tenable on a proper construction of the terms of the contract. Reference in this connection may be made to the notes and comments of the Executive Engineer answering the claims of the contractors which are contained in File No. 1, marked as Ex. P-4. As the Government resisted the claims of the contractors on the basis of the terms of the contract, recourse to the contract, was necessary for deciding the dispute between the parties. Thus the dispute pertaining to the claims of the contractors related to “any other matter or thing arising under or out of the contract,” and fell within the arbitration clause. It was submitted by the learned Advocate-General that Items Nos. 2, 3, 4 and 7 of the claims were outside the said words in the arbitration clause, because they were covered by clause 1 of the contract. There is no substance in this argument. What is excluded is a decision or requisition of the Executive Engineer under clause 1. A perusal of clause 1 of the contract will show that no power of decision or requisition is conferred on the Executive Engineer by that clause. Apart from other matters, clause 1 provides that any discrepancy between the drawings and specifications shall be decided by the S.E There is no reference to Executive Engineer in this clause. Claims Nos. 2, 3, 4 and 7, therefore, cannot be excluded from the arbitration clause. The learned Advocate-General has not relied upon any other exception contained in the arbitration clause and we need not refer to that. In our opinion, therefore, Claims Nos. 1 to 9 and 11 were within the arbitration clause and the arbitrators had jurisdiction to decide these claims. We may mention here that the jurisdiction of the arbitrators to decide these claims was not challenged in the Court of the Additional District Judge.

    15. As regards Claim No. 10, it relates to claim of bonus of Rs. one lac under the supplementary agreement. It will be recalled that under the original contract there was no provision for bonus. By clause 1 of the supplementary agreement which was made on 19th January, 1954, which we have earlier quoted, time for completing the works was extended upto 31st May, 1956. It was further provided in clause 2 that upon fulfilment and performance by the contractors of the conditions of clause 1, but in no other case, the Governor shall pay to the contractors a bonus of Rs. 1,00,000/- in addition to the sum payable under the principal agreement. Clause 3 then provided as to what will happen in case the contractors failed to perform the conditions contained in clause 1 i.e to complete the works by 31st May, 1956. In that event, the principal agreement was to be operative as if the supplementary agreement had never been made. It is pertinent to note that the supplementary agreement does not contain any arbitration clause and it also does not make applicable the arbitration clause contained in the original contract for resolving of any dispute arising under the supplementary agreement. The clause pertaining to bonus was an entirely independent clause and it is difficult to accept the suggestion that this clause got incorporated in the original contract. In our opinion, therefore, the claim relating to bonus of rupees one lac arose under the supplementary agreement and not under the original contract. As the arbitration clause of the original contract had not been made applicable for resolving of disputes under the supplementary agreement, it follows that a claim relating to bonus of rupees one lac could not be referred to arbitration. The rule is well settled that if the parties enter into a fresh contract or a subsidiary contract in addition to the original contract, the arbitration clause in the original contract cannot cover disputes arising out of subsidiary contract or a fresh contract, (See Seth Thawardas Pherumal v. Union Of India, AIR 1955 SC 468 at p. 477). Applying this principle, it has to be held that claim No. 10 regarding bonus of rupees one lac was outside the jurisdiction of the arbitrators.

    16. It was next contended by the learned Advocate-General that the contractors had no authority to file the award themselves. It is not disputed before us that it was competent for the arbitrators to authorise the contractors to file the award in Court. What is argued is that the authority to file the award must be specifically alleged and proved. Reference in this connection is made to Kumbha Mawji v. Union of India, AIR 1953 SC 313. In the application made under Section 14 of the Arbitration Act the contractors in paragraph 8 stated as follows:

    “That the original award received by the petitioner from the arbitrators for filing herein this Court is submitted herewith.”

    17. It is implicit in this averment that the contractors were authorised by the arbitrators to file the award in Court. Evidence was also led on this point. Both the arbitrators viz. G.L Sharma (P.W 1) and P.N Bhalla (P.W 2) stated in their evidence that the original of the award was given to Lala Banarasilal, who is the partner and agent of the contractors, authorising him to file the same in Court on behalf of the arbitrators. The award was signed on 28th October, 1960. It was published on 31st October, 1960 at Mortakka in presence of Banarasilal for the contractors and the Superintending Engineer and the Executive Engineer for the Government. G.L Kumar (D.W 1), the Superintending Engineer, and Laxmandas (D.W 2), the Executive Engineer, have no doubt stated that in their presence the arbitrators did not authorise Lala Banarasilal to file the award in Court. But having read the evidence of all these witnesses, we have no hesitation in believing the arbitrators. The fact that original award was admittedly handed over to Lala Banarasilal and a copy of it to the Superintending Engineer supports the statements of the arbitrators that they authorised the contractors to file the award in Court. The application under Section 14 of the Act was made on behalf of the contractors by Lala Banarasilal as agent and partner, and the award was filed in Court along with this application. We reject the contention that the contractors were not authorised to file the award.

    18. The learned Advocate-General lastly argued that the reference made to the arbitrators was not a joint reference by the contractors and the Executive Engineer and, therefore, the reference was invalid. It may here be stated that no objection was raised as to the existence or validity of the reference in the objections filed on behalf of the State before the Additional District Judge. There was no issue on that point. It, however, appears that at the time of arguments before the Additional District Judge the point was raised that the papers submitted by the arbitrators do not disclose a valid reference. But even at that stage the objection in the present form was not raised. The question whether the Executive Engineer and the Contractors had made a joint reference to the arbitrators is a question of fact and should have been raised at the proper stage. It cannot be decided off-hand without giving opportunity to the parties to lead evidence. In this connection the learned Advocate-General applied on 22nd February, 1974 for proving by secondary evidence Letter No. 745.GD dated 10th February, 1960 purporting to have been written by the Superintending Engineer to the arbitrators. No copy of this letter was filed before us and the learned Advocate-General admitted before us that he did not know what was contained in the letter and he was not in a position to say whether that letter, if proved, would show that the reference was not consented to by the Executive Engineer and the contractors. By an order passed on 22nd February, 1974 we rejected the application for producing the additional evidence as, in our opinion, the conditions mentioned in O. 41, R. 27 of the CPC for production of additional evidence were not satisfied. However, we have seen the papers contained in file No. 1 sent by the arbitrators which is marked as Ex. P-4. The first document in this file is the statement showing all the eleven items of claim of the contractors. This document is signed by the Executive Engineer. The grounds on which these claims were laid by the contractors are contained in a separate document which is marked as Appendix I. This is signed by the contractors. Notes on the claims of the contractors and the comments of the Executive Engineer are contained in a separate document. This document is signed by the Executive Engineer. File No. 2 shows that the Superintending Engineer appointed Shri P.N Bhalla, retired Superintending Engineer, as an arbitrator. This file further shows that Shri G.L Sharma Superintending Engineer of Uttar Pradesh, was appointed an arbitrator by the contractors. Another fact which appears from the award and the proceedings sent by the arbitrators is that the Superintending Engineer and the Executive Engineer throughout appeared before the arbitrators and took part in the proceedings without any objection. From all these papers it is quite clear that a dispute had arisen between the Executive Engineer and the contractors in respect of the eleven claims submitted by the latter and both these parties agreed that this dispute be decided by a reference to arbitrators under Clause 17 of the contract. Consequently, the Superintending Engineer, as envisaged by Clause 17, nominated one arbitrator and the contractors also nominated one arbitrator and then the matters in dispute were submitted to them for decision. Both the parties took part in the proceedings before the arbitrators without any objection. On these facts, we are clearly of opinion that there was a valid reference to the arbitrators by the Executive Engineer and the contractors in the manner envisaged by Clause 17 of the contract.

    19. As a result of the aforesaid discussion, our conclusion is that the award was bad in respect of future interest and also in respect of claim No. 10 regarding bonus. In all other respects the award was valid.

    20. As the invalid portions of the award were separable, the rest of the award must be upheld. We are also of opinion that the contractors must be allowed interest at three per cent from the date of the decree of the Additional District Judge under Section 29 of the Act.

    21. First Appeal No. 9 of 1965 is partly allowed. The award in so far as it relates to claim No. 10 and future interest is set aside. In all other respects it is upheld. The contractors shall be entitled to receive Rs. 4,63,581/- from the Government under the award. In place of the decree passed by the Additional District Judge there shall be a decree for Rs. 4,63,581/- against the Government. The contractors shall also be entitled to interest at the rate of three per cent on this amount from 26th September, 1964, the date of the decree passed by the Additional District Judge. The contractors shall get proportional costs of both the Courts. The Government will bear its own costs throughout. Miscellaneous (First) Appeal No. 60 of 1965 filed by the State is dismissed without any order as to costs.

    22. Order accordingly.

    Use AI to get other relevant cases.

    Comments

    M/S. Umraosingh And Co., Mahanagar, Lucknow (U.P) v. The State Of M.P And Others
    (May 1, 1974)