  • section 398(3) of the Kolkata Municipal Corporation Act, 1980 (hereafter the Act)
  • Act embodies provisions relating to Buildings. Section 392,
  • section 4(1) of the Land Acquisition Act, 1894
  • provisions of section 398(3),
  • provision of section 398(3)
  • section 397. Section 398,
  • Schedule VII. Rule 15
  • provision [Rule 15(3)].
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Judges
Acts
  • section 398(3) of the Kolkata Municipal Corporation Act, 1980 (hereafter the Act)
  • Act embodies provisions relating to Buildings. Section 392,
  • section 4(1) of the Land Acquisition Act, 1894
  • provisions of section 398(3),
  • provision of section 398(3)
  • section 397. Section 398,
  • Schedule VII. Rule 15
  • provision [Rule 15(3)].
Smart Summary

Structured Summary of the Opinion

Factual and Procedural Background

The Kolkata Municipal Corporation (the Corporation) sanctioned a building permit in favour of the petitioner for premises No. 23A/660, Diamond Harbour Road, Kolkata (building permit No. BS-124) on 28.10.1999; the permit was stated to be valid until 27.10.2004. The petitioner says he intended to start construction on 20.3.2003 but was prevented by the police and accordingly filed a writ petition (W.P. 5188(W) of 2003). On 22.4.2003 a learned Judge granted the petitioner liberty to carry on construction strictly in accordance with the sanctioned plan until further orders and allowed the petitioner to seek police protection; the order recorded that pendency of the writ would not prevent the Corporation from proceeding with acquisition proposals or taking steps in accordance with law.

On 25.4.2003 the Executive Engineer (Building), Borough No. X, wrote to the petitioner informing him that the Corporation had taken steps to acquire the premises for a park and therefore it was "prudent to withhold the building sanction plan" and no construction would be allowed. A notice under section 4(1) of the Land Acquisition Act, 1894 was issued on 23.10.2003; the petitioner filed an objection. By a letter dated 8.12.2004 the Government requested dropping the acquisition proceeding and later (letter of 21.7.2005) the Land Acquisition Collector confirmed no further acquisition proposal had been received.

The petitioner made representations to the Mayor on 7.7.2005 and 11.8.2006 seeking permission to resume construction (excluding the period of withholding by the Executive Engineer) and to revive/extend the building plan. The Corporation did not act, and the petitioner sought judicial directions to set aside the 25.4.2003 withholding notice and to revive the sanctioned building plan dated 28.10.1999.

Legal Issues Presented

  1. Whether the building permit issued on 28.10.1999, valid on its face until 27.10.2004, had lapsed by operation of law because the petitioner failed to commence construction and/or to give the required notice within the statutory period (as provided in section 398 of the Kolkata Municipal Corporation Act, 1980 and related rules), entitling the Corporation to deny further reliance on that permit.
  2. Whether the Executive Engineer's order dated 25.4.2003 withholding operation of the building plan could revive or preserve a building permit that the Corporation contends had lapsed under the statute.
  3. Whether, if the permit had lapsed, the petitioner was entitled to revalidation/extension of that permit or was obliged to apply afresh for sanction under the statutory procedure.

Arguments of the Parties

Petitioner's Arguments (Mr. Ali)

  • The building plan does not lapse automatically merely because construction was not commenced within two years; the plan subsists until the stated period of validity (five years) and the statute requires that if one intends to raise construction after two years, the person must inform the Corporation—he relied on this to argue the plan remained valid.
  • The letter of the Executive Engineer dated 25.4.2003 withholding operation of the plan had not been recalled and therefore the plan could not be said to have lapsed.
  • The petitioner asked the Court to direct the Corporation to permit construction after excluding the period of withholding and alternatively to revive the building plan by granting an extension.

Corporation's Arguments (Mr. Ghosh)

  • Relying on section 398(3) of the Kolkata Municipal Corporation Act, 1980, the Corporation contended that because the petitioner did not commence construction within two years of sanction, the permit stood lapsed.
  • Alternatively, since no application for revalidation or extension was made before the permit's expiry on 27.10.2004, the question of revalidation/extension does not arise and the petitioner must apply for a fresh sanction if he intends to build.
  • The petitioner was therefore not entitled to the reliefs sought.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
AIR 1966 SC 529: Martin Burn Ltd. v. Corporation Of Calcutta Principle that courts must give effect to clear statutory provisions even if the result is harsh; courts cannot ignore or override the statutory language to relieve distress caused by its operation. The Court invoked this authority to support applying the clear wording of section 398(3) literally and to decline to override the operation of the statute in order to grant relief by revalidating or extending a permit that had lapsed by operation of law.

Court's Reasoning and Analysis

The Court examined the relevant statutory framework in Chapter XXII of the Kolkata Municipal Corporation Act, 1980 (provisions relating to buildings) and Chapter III of the Building Rules, 1990:

  • The Court identified key statutory provisions: section 392 (prohibits erection without sanction), section 393 (application procedure), section 395 (purpose specification), section 396 (sanction/provisional sanction/refusal), section 397 (cancellation in certain conditions), section 398 (procedures after sanction, including notice requirements and consequences of not commencing within two years), and section 399 (power to specify completion period).
  • It also relied on Rule 15 of the Building Rules (which provides that a building permit, subject to section 398(3), shall be valid for a minimum period of five years) and Rule 21 (which prescribes notification of proposed commencement within two years and the effect if commencement does not occur within 15 days of the notified date).

Turning to the facts, the Court noted:

  • The permit was issued on 28.10.1999 and professed validity until 27.10.2004; however, the petitioner did not notify his intention to commence erection within the statutory period—there was no evidence that the required notice (referred to in the opinion as under section 398(4)) was given within the relevant initial period, and his stated intention to commence on 20.3.2003 was well beyond two years from the date of sanction.
  • Although the Executive Engineer's letter of 25.4.2003 withheld operation of the building plan and prohibited construction, the core question was whether the building permit had already lapsed by operation of law because of the petitioner's failure to notify/commence within two years and thereby trigger section 398(3)'s requirement of a fresh sanction.

On construction of the statutory language, the Court applied the literal rule of interpretation where language is clear and unambiguous. The Court construed section 398(3) and Rule 15(3) together and held:

  • When a building permit is issued for a five-year period, but the person favoured by the permit neither commences construction within two years nor notifies an intention to commence within that period, the permit "exhausts itself by passage of time" and the statute requires that a fresh sanction must be obtained under section 398(3) for any subsequent attempt to erect the building.
  • If a notice of intention to commence had been given within two years, the petitioner could have relied on the proviso to Rule 21 to preserve the permit until its expiry, but the petitioner failed to serve such a notice and cannot now seek revalidation or extension of a permit that has lapsed by operation of law.
  • The Executive Engineer's order of 25.4.2003 withholding the plan could not lawfully revive or prolong a permit that had lapsed by operation of statute; any public authority act contrary to the statutory provisions cannot vest enforceable rights and is non est (of no legal effect).

The Court invoked Martin Burn Ltd. v. Corporation Of Calcutta to underscore that the Court cannot disregard clear statutory language even if the result causes hardship; it therefore declined to give the petitioner relief by way of revalidation or exclusion of the withholding period from computation to save the permit.

Finally, in light of the correspondence indicating that acquisition proceedings had been dropped, the Court observed that the petitioner remains free to apply afresh for sanction under section 393 and that appropriate action should follow in accordance with law if such a notice is given.

Holding and Implications

Holding:

The writ petition was disposed of; the Court held that the building permit had lapsed by operation of law because the petitioner did not notify or commence erection within the statutory period, and the Executive Engineer's order dated 25.4.2003 could not revive a permit that had lapsed. The Executive Engineer's order was declared non est.

Implications and direct consequences:

  • Direct effect on the parties: The petitioner is not entitled to revalidation or extension of the lapsed building permit and must follow the statutory procedure afresh—specifically, he may apply for fresh sanction by giving notice under section 393 of the Act; if he does so, the Corporation must take appropriate action according to law.
  • No broader legal change was announced by the Court beyond application of existing statutory provisions and established principles of statutory construction; the opinion enforces literal application of the relevant provisions and does not purport to lay down a new precedent beyond applying settled principles (the Court explicitly applied a cited Supreme Court authority to support this approach).

Disposition

The writ petition was disposed of in accordance with the reasons stated. There was no order as to costs. The Court authorized urgent certified copy within three days upon requisition.

This summary is drawn exclusively from the provided opinion. No information beyond the opinion's text has been added.

    Achintya Ghosh v. State Of West Bengal & Ors.

    1. The Kolkata Municipal Corporation (hereafter the Corporation) sanctioned a building permit in favour of the petitioner for the purpose of raising construction on premises No. 23A/660, Diamond Harbour Road, Kolkata (hereafter the said premises) vide No. BS-124 on 28.10.1999 The plan was valid till 27.10.04 It is the case of the petitioner that on 20.3.03 he intended to start construction said premises but was prevented from doing so by the concerned police authorities. Being aggrieved thereby, he had preferred a writ petition before this Hon'ble Court being W.P 5188(W) of 2003. On 22.4.03, a learned Judge of this Court for reasons recorded in the order granted liberty to the petitioner to carry on construction work at the premises in question strictly in accordance with the sanctioned building plan until further orders. The petitioner was also given liberty to seek assistance from the police for protection of his life and property as well as the safety and security of the labours who would be engaged in construction work. The police authorities were directed to render adequate police assistance, if sought for. However, it was recorded that pendency of the writ petition would not prevent the Corporation from proceeding with the proposal for acquisition of the said premises and/or to take any further step in respect of the construction work thereat in accordance with law.

    2. Immediately after the aforesaid order was passed, the Executive Engineer (Building), Borough No. X of the Corporation vide his letter dated 25.4.03 informed the petitioner that the Corporation had already taken steps for acquisition of the said premises for a park and hence it was felt “prudent to withhold the building sanction plan vide No. 124 (B-X)/99-2000 dated 28.10.99 for the time being and no construction work will be allowed on the abovenoted premises”. According to the petitioner, this letter was served on him on 25.4.03 when he had been to the said premises for the purpose of raising construction in terms of the sanctioned building plan. As a consequence, the petitioner could not raise construction. This was followed by a notice under section 4(1) of the Land Acquisition Act, 1894 dated 23.10.2003 issued to the petitioner by the 1st Land Acquisition Collector, Calcutta pursuant whereto the petitioner filed an objection. However, by letter dated 8.12.04 written by the Assistant Secretary to the Government of West Bengal, Land and Land Reforms Department, the 1 Land Acquisition Collector, Calcutta was requested to drop the land acquisition proceeding initiated for acquisition of the said premises and an action taken report was directed to be submitted. This was followed up by a letter of the Land Acquisition Collector dated 21.7.05 whereby he confirmed to the petitioner's lawyer that no proposal to initiate further land acquisition proceeding for acquiring the said premises had been received by his office.

    3. These facts in the background, the petitioner vide his representations dated 7.7.05 and 11.8.06 had requested the Mayor of the Corporation to permit him to resume construction excluding the time for which operation of the building plan was withheld by the order dated 25.4.03 issued by the Executive Engineer and also to revive the building plan by granting extension thereof. No action having been taken by the Corporation, the petitioner has approached this Court with the prayer to direct the Corporation authorities not to give effect to the impugned notice dated 25.4.03 issued by the Executive Engineer and also for rescission, cancellation and/or setting aside of the same and to revive the sanctioned building plan dated 28.10.99

    4. Mr. Ali, learned Senior Counsel appearing for the petitioner submitted that undisputedly the building plan which was to remain valid till 27.10.04 was not allowed to be operative with effect from 25.4.03 and, therefore, this Court ought to direct the Corporation to permit the petitioner to raise construction on the basis thereof after excluding the period during which operation of the same was withheld upon setting aside of the order dated 25.4.03 and/or in the alternative to direct the Corporation to revive the building plan by granting suitable extension. According to him, the petitioner was resisted from raising construction on the ground that the Corporation intended to use the said premises for constructing a park but such proposal not having materialized, the petitioner ought not to be penalized for no fault of his. He, accordingly, urged this Court to grant relief(s) as prayed for.

    5. Mr. Ghosh, learned Counsel for the Corporation vehemently opposed the petition. He referred to section 398(3) of the Kolkata Municipal Corporation Act, 1980 (hereafter the Act) and submitted that the petitioner not having commenced construction at the said premises in terms of the building permit within two years of such sanction, it stood lapsed. Alternatively it is his further submission that since the petitioner did not apply for revalidation and/or extension of the permit prior to its expiry on 27.10.04, question of grant of revalidation/extension of the same does not and cannot arise and the petitioner has to apply for fresh sanction if he intends to raise construction. According to him, the petitioner is not entitled to any relief whatsoever.

    6. In reply, Mr. Ali submitted that even if one does not commence construction within two years from date of sanction, the plan does not lapse automatically as contended by Mr. Ghosh. According to him, the plan subsists till the period of its validity and requirement of the statute is that if anyone intends to raise construction after two years of sanction he must inform the Corporation intending to commence construction and the provisions of section 398 would have application in such a case. It is his further submission that question of the plan lapsing on expiry of five years from the date of its sanction as contended by Mr. Ghosh, is absolutely misconceived inasmuch as the letter dated 25.4.03 withholding the operation of the plan is yet to be recalled and, therefore, it cannot be said that the plan has lapsed by operation of law.

    7. This Court has considered the rival submissions at the bar. Before this Court proceeds to decide the issues raised herein, a close look at the statutory provisions, to the extent relevant herein, would be profitable.

    8. Chapter XXII of the Act embodies provisions relating to “Buildings”. Section 392, inter alia, prohibits erection of a building without sanction of the Municipal Commissioner. In terms of section 393, a person who intends to erect a building is obliged to apply for sanction to the Municipal Commissioner by giving a notice in writing of his intention and containing relevant information in a prescribed form. The notice is to be accompanied by such documents and plans as may be prescribed. Section 395 requires the person intending to build to specify the purpose for which the building is to be used. Section 396 of the Act provides for sanction or provisional sanction to be granted by the Municipal Commissioner or his refusal to sanction erection of a building. Cancellation of sanction is permitted under certain conditions in terms of section 397. Section 398, inter alia, permits erection of a building after sanction has been given by the Municipal Commissioner as well as steps to be taken by the person intending to build in the event sanction is not refused by the Municipal Commissioner within the specified time. It also obliges a person, who has not commenced erection of the building within two years of the sanction, to give a notice under section 393 for fresh sanction and provides for applicability of the provisions of this section in relation to such notice as they applied in relation to the original notice. Lastly, the provision requires the person intending to build to give a notice of proposed date of commencement of erection and that if commencement does not take place within 15 days of the notified date, to give a fresh notice in this behalf. Section 399 empowers the Municipal Commissioner (when sanctioning the erection of a building) to specify a reasonable period within which erection thereof is to be completed, and that if erection is not completed within the period specified, erection shall not be continued except without a fresh sanction or within such extended period as may be allowed by him.

    9. Chapter III of the Building Rules, 1990 (hereafter the rules) framed under the Act lays down procedure for sanction for erection of a building. It obliges a person intending to build to issue notice in writing to the Municipal Commissioner in the form as specified in Schedule I thereto. This notice is to be accompanied by other documents required under the rules, viz. key plan, site plan, building plan etc. Power of the Municipal Commissioner to issue sanction or provisional sanction or to refuse sanction is contained in Rule 13. In the event the Municipal Commissioner sanctions or decides to provisionally sanction the erection of a building, he shall issue a building permit in the form as specified in Schedule VI and in case of refusal, communication has to be issued in the form as specified in Schedule VII. Rule 15 provides that a building permit, subject to provisions of section 398(3), shall be valid for a minimum period of 5 years from date of issue thereof. Rule 21 lays down that proposed date of commencement of erection has to be notified in the form as specified in Schedule IX within two years from date of issue of the building permit but not less than seven days before commencement. However, in terms of the proviso thereto, if during the validity of the building permit erection does not commence within fifteen days of the notified date, the notice shall be deemed not to have been given and a fresh notice shall be necessary if the validity of the building permit has not expired.

    10. It would therefore appear that the aforesaid statutory provisions are regulatory in nature for the purpose of controlled erection of buildings in the city of Kolkata and, therefore, a construction of the relevant statutory provisions has to be made in such manner so as to give effect to the legislative intent.

    11. It is not in dispute that building permit was sanctioned in favour of the petitioner by the Municipal Commissioner on 28.11.1999 and was valid till 27.10.2004 However, there is nothing on record to establish that within two weeks from date of issuance of the building permit, the petitioner had notified his intention of commencing erection in terms thereof as is required by section 398(4) of the Act. From the petitioner's own showing, he intended to commence construction on 20.3.2003, i.e well beyond two years from date of sanction of the building permit.

    12. True it is that by the letter dated 25.4.2003 the building plan was withheld for the time being and construction work was prohibited thereby. But the question which arises for a decision on facts and in the circumstances of this case is whether on the failure of the petitioners to commence construction within 27.10.2001, i.e two years from date of issuance of the building permit, the building permit lapsed by operation of law as contended by Mr. Ghosh though the building permit was initially valid for a period of five years from date of issue thereof, i.e till 27.10.2004 This question has to be answered keeping in mind the provisions of section 393/398/399 of the Act read with Rule 15 of the rules.

    13. The building permit has not been annexed to the present petition. However, the Corporation in its counter-affidavit has not disputed the assertion of the petitioner that it was valid till 27.10.2004 Issuance of building permit and its validity is regulated by section 399 of the Act read with Rule 15 of the rules. As has been noted above, section 399 empowers the Municipal Commissioner to specify period within which erection has to be completed. In terms thereof and in exercise of power conferred by Rule 15(3), the building permit had been issued which was to remain valid for five years from date thereof, but such validity of the building permit is subject to the provision of section 398(3) according to the same provision [Rule 15(3)]. When the language of the statute is clear and admits of no ambiguity, it has to be read literally and the words used by the legislature have to be given their ordinary, natural and grammatical meaning irrespective of its consequences is the cardinal rule of construction of statutes. To the mind of this Court, once a building permit is issued for a period of five years and the person favoured with the building permit does neither commence construction within two years from the date of its issuance nor even notifies his intention to commence erection within two years, he cannot after lapse of the said period of two years raise any construction on the basis of the building permit because it exhausts itself by passage of time and in terms of sub-section (3) of section 398 of the Act, a fresh sanction has to be applied for from the Municipal Commissioner and provisions of section 398 is made applicable in relation to a notice for fresh sanction as it applied in relation to the original notice. What section 398 further envisages is that only upon a fresh sanction granted by the Municipal Commissioner a person intending to build can commence erection of the building in accordance therewith and in the process he would be bound not to contravene any of the provisions of the Act or the rules framed thereunder or any other law in force for the time being. If only the petitioner had notified his intention to commence erection on a particular date within 27.10.2001, i.e two years from issuance of the building permit and even if he had not commenced erection on the date notified, proviso to Rule 21 could have been availed of by him, for, in such case the permit would not have lapsed and would have remained valid till its expiry as specified under Rule 15(3). Non-issuance of any notice notifying intention to commence erection within two years of issuance of the building permit proves fatal for the petitioner and the position cannot be retrieved for no law permits him to pray for extension/revalidation of a lapsed permit. It is understandably true that having obtained a building permit from the Municipal Commissioner, it would amount to some hardship for the petitioner to repeat the process of obtaining sanction once again. However, law is well-settled to the effect that result flowing from a statutory provision is never an evil and Court has no power to ignore that provision to relieve what it considers a distress resulting from its operation; whether the Court likes the result or not, the statute has to be given effect to (See AIR 1966 SC 529: Martin Burn Ltd. v. Corporation Of Calcutta). In view thereof, the conclusion is inevitable that unless and until a fresh sanction is obtained by the petitioner from the Municipal Commissioner by repeating the procedure as laid down in the statutory provisions referred to above for the purpose of obtention of sanction and commencement of erection, he is not legally entitled to reap the fruits of the building permit sanctioned on 28.10.1999 The language of section 398(3) of the Act is clear and admits of no ambiguity and on literal construction thereof, the contention of Mr. Ghosh is upheld.

    14. The submission of Mr. Ali that the very fact that the Executive Engineer of the Corporation by the notice dated 25.4.2003 had withheld the building plan establishes that the building permit was valid and did not lapse cannot be of any assistance to the petitioner. Since the petitioner had not commenced construction within two years, the building permit by operation of law had lapsed and the same could not have been given a fresh lease of life by an order passed by the Executive Engineer. Any action of a public authority which is palpably contrary to the provisions of law cannot vest a citizen with an enforceable right. The said order for all intents and purposes is non est and is declared so.

    15. However, having regard to the correspondences exchanged between the petitioner and the Government, it appears to be clear that the said premises is no longer required to be acquired for the purpose of a park and, therefore, this Court holds that it would now be open to the petitioner to apply for fresh sanction of the Municipal Commissioner by giving notice under section 393 of the Act for erecting a building on it and if such notice is given, appropriate action in accordance with law shall follow.

    16. The writ petition stands disposed of with the aforesaid observations. However, there shall be no order as to costs.

    17. Urgent photostat certified copy of this judgment, if applied for, be furnished to the applicant within 3 days from the date of putting in requisites therefor.

    Dipankar Datta, J.:

    Writ petition disposed of.