  • S. 17(4) and S. 5-A of the Land Acquisition Act. He referred to Exts. P1, P2, P4, P5 and P10 in W.P (C). No. 8453 of 2008, R. 6 of the Land Acquisition (Kerala) Rules
  • Ss. 4(1), 5A and 17(4) of the Land Acquisition Act.
  • LAND ACQUISITION ACT
  • S. 6(3) of the Land Acquisition Act.
  • LAND ACQUISITION ACT
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • S. 17(4) and S. 5-A of the Land Acquisition Act. He referred to Exts. P1, P2, P4, P5 and P10 in W.P (C). No. 8453 of 2008, R. 6 of the Land Acquisition (Kerala) Rules
  • Ss. 4(1), 5A and 17(4) of the Land Acquisition Act.
  • LAND ACQUISITION ACT
  • S. 6(3) of the Land Acquisition Act.
  • LAND ACQUISITION ACT
Smart Summary

Structured Summary of the Opinion

Factual and Procedural Background

Multiple writ petitions challenge land acquisition proceedings for expansion of Infopark. In W.P.(C) No. 8453 of 2008 there are eight petitioners whose lands are proposed to be acquired. Respondents include the State of Kerala, Ministry of Industries & Commerce (Government of India), Deputy Commissioner Land Revenue, District Collector, Special Tahsildar (LA), M/s. Infopark and the I.T. Secretary (additional respondent). The petitions raise objections to notifications and the acquisition process (including dispensation of enquiry under Section 5A and validity of Section 4(1) notifications) and allege, among other things, that the acquisition is actually for a private company (Smart City Infrastructure Pvt. Ltd.) rather than for Infopark.

Counsel for petitioners and respondents made extensive oral and written submissions and placed documents and several authorities before the court. The court examined documentary material including an agreement (Ext. P10), counter-affidavit (notably paragraph 16), S.R.O. No. 1743/89 and the file of the Land Revenue Commissioner. The court considered legal challenges to the initiation and form of acquisition proceedings and whether enquiry under S.5A should be dispensed with.

Legal Issues Presented

  1. Whether the acquisition is genuinely for the public purpose of extending Infopark or primarily for a private company (Smart City), and if the latter, whether the urgency provisions and procedure invoked are impermissible.
  2. Whether enquiry under Section 5A of the Land Acquisition Act can be dispensed with (i.e., the validity of invoking the urgency clause and the need for a reasoned order or materials to support subjective satisfaction).
  3. Whether the notifications under Section 4(1) are valid when issued by the Land Acquisition Officer / appointed Tahsildar rather than by the Government or District Collector.
  4. Whether declaration under Section 6 (and the presumption of "conclusive evidence" that land is needed for public purpose) can be judicially reviewed in the absence of proved mala fides or colourable exercise of power.
  5. Whether the special procedure in Chapter VII / Part VII of the Land Acquisition Act applies (i.e., when acquisition is truly for the benefit of a company/joint venture) and if so, whether the general notifications are invalid.

Arguments of the Parties

Petitioners' Arguments

  • The acquisition is not genuinely for Infopark but for Smart City Infrastructure Pvt. Ltd., a private company; hence the urgency clause cannot be invoked.
  • If acquisition is for a company, the procedure under Chapter VII (Part VII) of the Land Acquisition Act must be followed and notifications under the general provisions are invalid.
  • Dispensation of enquiry under Section 5A is not warranted; there is no urgency that cannot brook even 30 days.
  • The Section 4(1) notification itself is bad because it was issued by the Land Acquisition Officer (or a Tahsildar) and not by the Government (or not in the proper authority name), challenging the competence/authority to issue notifications.
  • There are allegations of mala fides (faintly pleaded) concerning the acquisition process.

Respondents' / Requisitioning Authority's Arguments (State, Infopark, Government Pleader)

  • Infopark and State representatives submitted that the acquisition is for extension of Infopark Phase-II; only a strip of land is to be leased as a connective corridor to the Smart City project and Infopark will remain owner.
  • Many landowners have accepted DLPC (District Level Price Committee) rates; negotiations by the District Collector are underway and compromises are likely.
  • The Land Acquisition Officer had been properly authorized — the Government issued S.R.O. appointing Special Tahsildars to perform Collector functions under the Land Acquisition Act within the district; accordingly, notifications by those appointed officers are valid.
  • The Land Revenue Commissioner had materials before him to form subjective satisfaction to dispense with enquiry under Section 5A; a reasoned order is not strictly necessary so long as there were materials demonstrating application of mind.
  • Declaration under Section 6 is to be regarded as conclusive evidence of public purpose unless mala fides or colourable exercise of power is proved; such mala fides were not satisfactorily pleaded or established.
  • Infopark indicated willingness to allow enquiry under Section 5A in respect of petitioners if conducted within a set timeframe (30 days as proposed by counsel for Infopark).

Table of Precedents Cited

Precedent Rule or Principle Cited For (as stated in the opinion) Application by the Court (based on the opinion)
Union of India v. Mukesh Hans The judgment was cited by petitioners in relation to Section 5A/dispensation of enquiry. The court notes this authority was relied upon by petitioners but also notes it was subsequently distinguished by Sheikhar Hotels Gulmohar Enclave.
Pankajakshy v. State Of Kerala The opinion records citation of this Court's judgment; specific principle relied upon is not detailed in the provided opinion. Listed among authorities cited by counsel; no distinct application stated beyond being cited.
Sheikhar Hotels Gulmohar Enclave v. State of U.P. (JT 2008 (7) SC 120) Used to distinguish Mukesh Hans in relation to Section 5A and dispensation of enquiry. The court accepted that Mukesh Hans was distinguished by this later decision and relied on the later approach regarding dispensation of enquiry.
Munshi Singh v. U.O.I (1973) 2 SCC 337 Cited by counsel; the specific rule or principle is not spelled out in the opinion. Included in the list of authorities relied upon by counsel; the opinion does not state a specific application.
Samuel v. Secretary to Government (2002 (2) KLT 339) Cited by counsel; specific principle not detailed in the opinion. Listed among authorities relied on by petitioners' counsel; no discrete application noted in the opinion.
Hamdardh Dawakahana v. U.O.I (AIR 1960 SC 554) Cited by counsel; specific principle not detailed in the opinion. Mentioned among various Supreme Court decisions cited; no specific use recorded.
Air India v. Nergesh Meerza (1981) 4 SCC 335 : AIR 1981 SC 1829 Cited by counsel; specific principle not detailed in the opinion. Cited in hearings; no explicit doctrinal application recorded in the opinion.
A.N. Parasuraman v. State of T.N (1989) 4 SCC 683 Cited by counsel; specific principle not detailed in the opinion. Listed among authorities; no specific application stated.
Stare of Punjab v. Khan Chand ((1974) 1 SCC 549 : AIR 1974 SC 543) Cited by counsel; specific principle not detailed in the opinion. Mentioned in the list of cases cited; no further application recorded.
Keshavananda Bharati v. State of Kerala (1973) 4 SCC 225 Cited by counsel; specific principle not detailed in the opinion. Referred to by counsel among many constitutional and statutory authorities; no specific application in reasoning recorded.
Lingappa Pochenna Appelwar v. State of Maharashtra (1985) 1 SCC 479 Cited by counsel; specific principle not detailed in the opinion. Included in the list of authorities cited; no distinct role in the court's analysis as recorded.
Dalmia Cement (Bharat) Ltd. v. U.O.I (1996) 10 SCC 104 Cited by counsel; specific principle not detailed in the opinion. Mentioned among the cases cited before the court; no particular application specified.
Atamprakash v. State of Haryana (1986) 2 SCC 249 Cited by counsel; specific principle not detailed in the opinion. Listed as cited authority; no explicit use described in the opinion.
S.A Iwardas v. Government of A.P (AIR 1995 A.P 71) Cited by counsel; specific principle not detailed in the opinion. Mentioned among authorities; no detailed application recorded.
Somawanti v. State of Punjab (AIR 1963 SC 151) Held that the expression "conclusive evidence" (in Section 6 context) means conclusive proof; court cannot go behind the declaration unless mala fides or colourable exercise of power is alleged and proved. The court relied on this principle to treat the declaration under Section 6 as conclusive evidence of public purpose, subject to allegations of mala fides being properly pleaded and proved.
Girias Investment (P) Ltd. v. State of Karnataka (JT 2008 (4) SC 242) Authority for the proposition that allegations of mala fides require proper pleading and that persons attributed with mala fides must be impleaded or given an opportunity to meet allegations. The court referred to this authority to reject faint allegations of mala fides that were not properly pleaded or targeted at individuals impleaded in their personal capacity.
Sooraram Pratap Reddy v. District Collector, Ranga Reddy Distt (JT 2008 (9) SCC 622) The Supreme Court repelled contention that acquisition for a joint venture/company necessarily requires the Chapter VII procedure; applied where state equity was 26% and foreign company's 74%. The court found the Sooraram Pratap Reddy reasoning applicable: even if acquisition is related to Smart City (with similar equity participation), it does not make the general acquisition proceedings invalid.
Union of India v. Praveen Gupta (1997) 9 SCC 78 : AIR 1997 SC 170 Cited by counsel; specific principle not detailed in the opinion. Listed among relied authorities; no particular application recorded in the opinion text.
Chameli Singh v. State of U.P (1996) 2 SCC 549 : AIR 1996 SC 1051 Cited by counsel; specific principle not detailed in the opinion. Included in the list of cases relied upon by respondents; the opinion does not detail a specific application.
Division Bench judgment in W.P.(C) No. 3149 of 2006 (this Court) Held that acquisition for Infopark is for a public purpose. The court noted that a Division Bench had previously held acquisition for Infopark to be for public purpose and relied on that position in submissions for the requisitioning authority.

Court's Reasoning and Analysis

The court reviewed factual materials and legal authorities and proceeded through the following steps (as reported in the opinion):

  1. Examination of the nature and purpose of acquisition: The court considered the petitioners' contention that acquisition was for Smart City (a private company) and referred explicitly to Ext. P10 (the agreement between Government of Kerala, Infopark, Teacom and Smart City) and the counter-affidavit of the I.T. Secretary (paragraph 16). The counter-affidavit stated the acquisition is for extension of Infopark Phase-II and that only a strip would be leased to Smart City while Infopark would remain owner. The court accepted the I.T. Secretary's contention.
  2. Application of precedent on acquisitions involving companies/joint ventures: The court applied and relied upon Sooraram Pratap Reddy (JT 2008 (9) SCC 622), where the Supreme Court repelled the argument that acquisition for a joint venture necessarily triggers Chapter VII procedure; the court found that the rationale in that decision applied to the present matter (including the similarity of equity participation percentages noted by counsel).
  3. Review of authority to initiate acquisition and sufficiency of appointments: The court considered S.R.O. No. 1743/89 and the District Collector's letter and referred to Section 6(3) of the Land Acquisition Act. It accepted that the Government had appointed Special Tahsildars as Collectors under the Act (S.R.O. No. 7143/89 was made available), and pointed to the statutory definition of "Collector" in Section 3(c) which includes officers specially appointed by the appropriate Government to perform Collector functions. On that basis, the court found no reason to hold the Section 4(1) notification invalid merely because it was issued by an appointed officer or because the District Collector's use of the word "appointed" in his letter was a misnomer; the explanation was accepted.
  4. Dispensation of enquiry under Section 5A: The court addressed the contention that dispensing with enquiry under S.5A required a reasoned order. It observed that although Mukesh Hans was cited for petitioners, that decision was distinguished by the later Sheikhar Hotels Gulmohar Enclave decision. The court stated that a reasoned order is not always necessary when dispensing with S.5A; what is necessary is that there must have been some materials before the competent authority which could lead to a subjective satisfaction regarding urgency, and that the competent authority (here the Land Revenue Commissioner) applied his mind. The court inspected the file of the Land Revenue Commissioner (as directed) and found that materials were present from which subjective satisfaction could have arisen.
  5. Section 6 declaration and "conclusive evidence": The court relied on Somawanti (AIR 1963 SC 151) for the proposition that a declaration under Section 6 is conclusive evidence (i.e., conclusive proof) of public purpose and that courts cannot ordinarily go behind such declaration unless mala fides or colourable exercise of power is alleged and proved. The court found only faint allegations of mala fides in the petitions, which did not merit consideration because the persons attributed with mala fides were not impleaded in their personal capacity nor given opportunity to meet such allegations (citing Girias Investment).
  6. Conclusion on merits: On the cumulative assessment of the documents, statutory appointments, and precedents, the court concluded that the principal legal arguments of the petitioners on the validity of the acquisition and on the competence of authorities were unsustainable.
  7. Exercising equitable discretion: Despite concluding that the petitions should have been dismissed, the court took into account Infopark's willingness (through counsel P.A. Ahammed) to allow enquiry under S.5A for the petitioners' properties and, in exercise of its discretion, directed that S.5A enquiries be conducted for petitioners who had already submitted objections to Section 4(1) notification, with specific timelines and procedural directions.

Holding and Implications

Holding:

The court disposed of the writ petitions by issuing directions rather than dismissing them outright. The core orders are summarized as follows:

  • The Land Acquisition Officer is directed to conduct enquiry under Section 5A of the Land Acquisition Act in respect of the properties belonging to the petitioners in these Writ Petitions only, provided objections have already been submitted by them to the notification under Section 4(1).
  • The enquiry is to be completed within one month of the Land Acquisition Officer receiving a copy of the judgment, ensuring hearing opportunities to objecting petitioners.
  • After enquiry, the Land Acquisition Officer must forward his report and recommendations regarding the objections to the Land Revenue Commissioner.
  • The Land Revenue Commissioner is to take a fresh decision and issue the declaration under Section 6 based on those recommendations within two weeks of receiving the report.
  • To give effect to these directions, the declaration under Section 6 already issued will be kept in abeyance for a period of six weeks from the date of the judgment insofar as it pertains to properties belonging to the petitioners in these cases.

Implications:

  • The direct effect is that eligible petitioners (those who filed objections to the Section 4(1) notification) will receive S.5A enquiries and hearings within the court-directed timeframe; the acquisition process for their properties is temporarily stayed in the form of abeyance of the Section 6 declaration for six weeks.
  • The court did not purport to set aside the acquisition generally nor to pronounce a broad new legal doctrine beyond applying existing precedents (including Sooraram Pratap Reddy and Somawanti) as recorded in the opinion. The opinion's disposition is a case-specific order directing enquiry and further administrative decision-making within fixed timelines.

Note: This summary is limited to and strictly reflects the material and reasoning set out in the provided opinion. No information beyond the text of that opinion has been introduced.

    Johnson Mathew v. State Of Kerala

    1. All these Writ Petitions are filed challenging land acquisition proceedings for the purpose of expansion of Infopark. There are eight petitioners in W.P(C). No. 8453 of 2008 whose lands are proposed to be acquired. The respondents in that Writ Petition are State of Kerala (R1), The Director, Ministry of Industries & Commerce, Government of India (R2), The Deputy Commissioner Land Revenue (R3), The District Collector (R4), The Special Tahsildar (LA) R5, M/s. Infopark (R6) and I.T Secretary (Addl. R7). The prayers in this Writ Petition are:

    2. Sri. V.R Venkitakrishnan, senior counsel addressed me extensively on behalf of the petitioner in W.P(C). No. 9735 of 2008. The learned senior counsel referred to S. 17(4) and S. 5-A of the Land Acquisition Act. He referred to Exts. P1, P2, P4, P5 and P10 in W.P (C). No. 8453 of 2008, R. 6 of the Land Acquisition (Kerala) Rules and to sub-r. (3) of R. 6. The learned senior counsel referred to the pleadings in the various Writ Petitions. He relied on the judgment of the Supreme Court in Union of India v. Mukesh Hans (2004 (3) KLT 462 (SC)) and also on the judgment of this Court in Pankajakshy v. State Of Kerala (1990 (1) KLT 776). It was Advocate Sri. G. Krishnakumar who addressed me on behalf of the petitioners in W.P(C). No. 25104 of 2008. Mr. Krishnakumar also addressed me very strenuously and extensively. The learned counsel referred to Ss. 4(1), 5A and 17(4) of the Land Acquisition Act. He referred to the judgment of the Supreme Court reported in Sheikhar Hotels Gulmohar Enclave, (JT 2008 (7) SC 120), a judgment which was cited by the Senior Government Pleader Mr. Anilkumar and also to the judgment of the Supreme Court in Munshi Singh v. U.O.I ((1973) 2 SCC 337) and judgment of this Court in Samuel v. Secretary to Government (2002 (2) KLT 339). Judgments of the Supreme Court in Hamdardh Dawakahana v. U.O.I, (AIR 1960 SC 554), Air India v. Nergesh Meerza, ((1981) 4 SCC 335 : AIR 1981 SC 1829), A.N Parasuraman v. State of T.N; (1989) 4 SCC 683) and in Stare of Punjab v. Khan Chand, ((1974) 1 SCC 549 : AIR 1974 SC 543) were a few of the decisions which were cited before me by Mr. Krishnakumar. Sri. Krishnakumar in his submissions referred also to Keshavananda Bharati v. State of Kerala, ((1973) 4 SCC 225), Lingappa Pochenna Appelwar v. State of Maharashtra, ((1985) 1 SCC 479), Dalmia Cement (Bharat) Ltd. v. U.O.I, ((1996) 10 SCC 104), Atamprakash v. State of Haryana ((1986) 2 SCC 249), S.A Iwardas v. Government of A.P (AIR 1995 A.P 71) etc. Sri. P.A Ahammed, Standing Counsel for Infopark was able to meet the submissions of the learned counsel for the petitioners to a considerable extent. He submitted that only a small percentage of the total number of land owners whose properties are being acquired for this purpose figure as petitioners before this court. DLPC rates have been accepted by most of the land owners. The District Collector is holding negotiations with the land owners and it is likely that a compromise will be arrived at, according to him.

    3. Meeting the argument that the Land Acquisition Officer has not been duly authorised to initiate the acquisition proceedings in this case Mr. D. Anilkumar, learned Senior Government Pleader placed before me a copy of S.R.O No. 1743/89 dated 21.8.1989 He also placed before me a copy of the District Collector's letter. He referred to S. 6(3) of the Land Acquisition Act. He relied on the judgment of the Supreme Court in Somawanti v. State of Punjab (AIR 1963 SC 151), Girias Investment (P) Ltd. v. State of Karnataka, (JT 2008 (4) SC 242), Sooraram Pratap Reddy v. District Collector, Ranga Reddy Distt. (JT 2008 (9) SCC 622) (a decision which was relied on by Mr. P.A Ahammed also), Sheikar Hotels Gulmohar Enclave v. State of U.P (JT 2008 (7) SC 120) corresponding to (2008 (8) SCALE 322), Union of India v. Praveen Gupta ((1997) 9 SCC 78 : AIR 1997 SC 170), Chameli Singh v. State of U.P ((1996) 2 SCC 549 : AIR 1996 SC 1051) etc.

    4. Sri. P.A Ahammed placed before me a copy of the judgment of a Division Bench of this Court in W.P(C). No. 3149 of 2006, whereby the Division Bench has held that acquisition for Infopark is for a public purpose. Mr. P.A Ahammed towards the end of his submissions agreed that an enquiry under S. 5A can be conducted in respect of the persons who figure as petitioners in these Writ Petitions provided a time frame of 30 days is set by this court for completing that enquiry. According to him, considering the strategic position which the city of Kochi occupies it is extremely urgent that Infopark is extended and more and more I.T Companies come over to Kochi utilising the infrastructural facilities which will be offered by the expanded Infopark. Any delay in the matter may result in Kochi failing in the stiff competition the city is facing from other I.T Cities like Hyderabad, Bangalore, Purie and Chennai.

    5. The argument of Sri. V.R Venkitakrishnan, learned senior counsel was that the acquisition is not for Infopark, but it is really intended for Smart City Infrastructure Private Limited which is a company registered under the Companies Act. According to him, it is a private company and therefore the urgency clause under the Land Acquisition Act cannot be invoked. His further argument was that in acquisition for the purpose of a company, the procedure prescribed under Chapter VII of the Land Acquisition Act will have to be followed and therefore the notifications issued under the general provisions of the L.A Act will be bad in law. He argued that dispensation of enquiry under S. 5A is not warranted in as much as there is no such urgency in this case which cannot brook delay of even 30 days. The contention of the learned senior Counsel Sri. K.P Dandapani who appeared for the Writ Petitioners in W.P(C). No. 8453 of 2008 were similar to those addressed by learned senior counsel Sri. V.R Venkitakrishnan. One of the main contentions urged by Sri. G. Krishnakumar, learned counsel for the Writ Petitioner in W.P(C). No. 25104 of 2008 was that the notification under S. 4(1) itself is bad since the same is issued by the L.A Officer and not by the Government.

    6. Sri. K.V Sohan, learned counsel for the petitioner in W.P(C). No. 2655 of 2008 adopted the contentions raised by the counsel for the petitioners in other cases. He argued that the notification under S. 4(1) issued by the L.A Officer is bad since as much as the notification should have been issued by the Government.

    7. I have considered the rival submissions of Sri. V.R Venkitakrishnan, learned senior counsel in support of his contention that the acquisition is for the purpose of Smart City and not for Infopark, referred to Ext. P10 agreement executed between the Government of Kerala, Infopark, Teacom and Smart City. It is specifically stated in the counter affidavit filed on behalf of the I.T Secretary at paragraph 16 that the present acquisition is for extension of Infopark Phase-11 and only a strip of land is intended for providing a connective corridor to the Smart City Project area. It is stated that even this piece of land will be given only on lease to the Smart City and that Infopark will continue to be the owner of the property. The contention raised by the I.T Secretary is acceptable. It follows that the contentions raised by the petitioners that the acquisition is for a company and that the emergency provisions cannot be attracted and that the procedure under Part VII should be followed, are unsustainable. Even if it is assumed that the acquisition is for the purpose of Smart City then also it cannot be said that the present proceedings are bad. This position has been explained by the Supreme Court in the judgment reported in Sooraram Pratap Reddy v. District Collector Ranga Reddy Distt. (JT 2008 (9) SC 622). That was a case where acquisition was for a joint venture company between the State of Andhra Pradesh and a foreign company. The equity participation by the State of Andhra Pradesh in that case in the joint venture company was only 26% while that of the foreign company was 74%. It was contended that the acquisition is for a company and therefore the procedure contemplated under Chap. VII of the Land Acquisition Act are to be followed. The Supreme Court repelled this contention. In the case of Smart City also the equity participation of the Government of Kerala is 26% and that of the foreign company is 74%. The judgment of the Supreme Court applies to this case also and therefore the contention raised by the petitioners in this regard, at any rate, has to fail.

    8. As regards the challenge against dispensation of enquiry under S. 5A, learned counsel for the petitioners relied on the judgment of the Supreme Court in Union of India v. Mukesh Hans (2004 (3) KLT 462 SC). The Supreme Court distinguished the above decision in a later decision reported in Sheikhar Hotels Gulmohar Enclave v. State of U.P (JT 2008 (7) SC 120). Even otherwise the position was always trite and there is no need for passing a reasoned order while dispensing with the enquiry contemplated under S. 5A. What is necessary is that there must have been some materials on the basis of which a subjective satisfaction could have been arrived at by the competent authority regarding the urgency of the need and that the competent authority (in this case, the Land Revenue Commissioner) applied his mind to the materials available before him and also to the question whether the need is so urgent that the enquiry under S. 5A should be avoided. As directed by me the file maintained by the Land Revenue Commissioner was made available. The file disclosed that the Land Revenue Commissioner had materials before him on the basis of which he would have arrived at a subjective satisfaction that it is necessary to dispense with the enquiry under S. 5A.

    9. The argument of the learned senior Government Pleader that in this case declaration under S. 6 has been issued and such declaration is to be taken as conclusive evidence that the land is needed for a public purpose is supported by judicial authorities. The expression “conclusive evidence” was considered by the Supreme Court in Somawanti v. State of Punjab (AIR 1963 SC 151) and it has been held that conclusive evidence means, conclusive proof. The above judgment is also an authority for the proposition that unless mala fides or colourable exercise of power is alleged and proved the court making judicial review is not entitled to go behind the declaration under S. 6. In this case I find there is only a faint allegation of mala fides. Those allegations do not merit consideration since I find that the persons to whom mala fides are attributed are not impleaded in their personal capacity or are given an opportunity to meet the allegations (see the judgment of the Supreme Court in Girias Investment (P) Ltd. v. State of Karnataka, (JT 2008 (4) SC 242)). I am not impressed by the argument advanced by Mr. Krishnakumar and by Mr. Sohan that the notification under S. 4(1) is bad since the same is not issued by the Government. In S.R.O No. 7143/89, copy of which was made available to this Court, it is stated that the Government of Kerala has appointed Special Tahsildar, Cochin Refineries to perform the function of Collectors under the Land Acquisition Act within the area of Ernakulam Revenue District. The submission of the learned Government Pleader that similar notifications are issued by the Government appointing various Special Tahsildars as Collectors under the Land Acquisition Act was not disputed. I do not find any reason to reject the argument that when the Government appoints several Collectors under the L.A Act in a Revenue District it is the District Collector as the head of the district administration who allots work to various Collectors appointed by the Government. The learned Government Pleader would explain that the use of the word “appointed” by the District Collector in his letter dated 15.12.2005 bearing number C-10-20291/05 is a misnomer. The above explanation according to me is convincing. As per S. 4(1) of the Act the persons appointed as Collector are also entitled to issue notifications under S. 4(1). The word “Collector” is defined under S. 3(c) in the following terms:

    “The expression “Collector” means the Collector of district, and includes a Deputy Commissioner and any officer specially appointed by the appropriate Government to perform the functions of a Collector under this Act.”

    10. When the Government have properly appointed Tahsildars as Collectors under the Land Acquisition Act, District Collector's letter dated 15.12.2005 using the word “appointed” cannot be a consequence.

    11. Sri. G. Krishnakumar made very enthusiastic submissions on the basis of the grounds raised in his Writ Petition challenging the validity of various provisions of the Land Acquisition Act. Counsel however, fairly conceded towards the end of his submissions that in case this court becomes inclined to grant relief to the petitioner on the other grounds it is not necessary that this court decides the grounds of challenge against the provisions of the statute.

    12. The above discussions should have resulted in the dismissal of all these Writ Petitions. However, taking into accountthe submission Mr. P.A Ahammed, standing counsel for the requisitioning authority Infopark that Infopark does not have any serious objection to enquiry under S. 5A being conducted as regards the properties of the petitioners in these Writ Petitions I am inclined to dispose of these Writ Petitions issuing directions in that regard. The result of the Writ Petition therefore will be as follows:

    The Land Acquisition Officer is directed to conduct enquiry under S. 5A of the Land Acquisition Act in respect of the properties belonging to the petitioners in these Writ Petitions only, provided objections have been submitted by them already to the notification under S. 4(1). The enquiry to be conducted shall be completed within one month of receiving copy of this judgment since the objecting petitioners will have to be afforded a hearing opportunity. Once enquiry is completed, LA Officer will forward his report containing recommendations regarding the objections of the petitioners to the Land Revenue Commissioner. Land Revenue Commissioner will take fresh decision and issue declaration under S. 6, on the basis of such recommendations, within two weeks of receiving the report from the Land Acquisition Officer. Considering the above directions the declaration under S. 6 which is now issued will be kept in abeyance for a period of six weeks from today to the extent the same pertains to properties belonging to the petitioners in these cases.