Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • S. 4, sub-section (1);xxxxxxxxxxxx(2)
  • Court Sections 20, 21 and 22
  • sub-section (1) of Section 23,
  • sub section (2) of Section 23
  • sub section (1) of Section 4
  • LAND ACQUISITION ACT 1894
  • acquisition.4. Section 24
  • LAND ACQUISITION ACT
  • S. 4, sub-section (1)5.
  • S. 17 sub-section (4)
  • S. 4(1) and the Act
  • Section 4(1)7.
  • Section 4(1)
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • S. 4, sub-section (1);xxxxxxxxxxxx(2)
  • Court Sections 20, 21 and 22
  • sub-section (1) of Section 23,
  • sub section (2) of Section 23
  • sub section (1) of Section 4
  • LAND ACQUISITION ACT 1894
  • acquisition.4. Section 24
  • LAND ACQUISITION ACT
  • S. 4, sub-section (1)5.
  • S. 17 sub-section (4)
  • S. 4(1) and the Act
  • Section 4(1)7.
  • Section 4(1)
Smart Summary

Case Summary — Bhagwati, J.

Factual and Procedural Background

The Government of Kutch took possession on 19 November 1949 of a plot of land (Survey No. 010 on Bhachau–Rahapar Road) belonging to the respondent limited company, which conducted ginning and related businesses. The possession was taken under an arrangement that the Government would give the respondent other land in exchange, but no notification under Section 4(1) of the Land Acquisition Act, 1894, was issued at that time and no formal acquisition proceedings had been initiated under the Act. The Government constructed a State Guest House and a Court House on the land. Later, because it could not provide acceptable exchange land, the Government issued a notification under Section 6 declaring the land needed for a public purpose, and the Deputy Collector proceeded under the Act (notices under Section 9, inquiry and award under Section 11 dated 22 April 1957).

The Collector's award valued the land as agricultural and fixed an aggregate compensation of Rs. 5,075-44 nP (including compensation for a well and pipeline and 15% solatium). The respondent applied for a reference under Section 18. In the Reference the respondent initially contested area (later abandoned) and challenged the compensation. The District Judge accepted that the land's market value at the date of the Section 6 notification should be applied and, taking a market value of Rs. 3 per square yard, awarded Rs. 1,00,000-8-0 for the land; with well/pipeline and 15% solatium the total awarded was Rs. 1,20,094-8-0 with interest and proportionate costs. The State appealed against that order.

Legal Issues Presented

  1. Whether, under the Land Acquisition Act, 1894, compensation for acquisition must be determined on the basis of the market value of the land at the date of publication of the notification under Section 4(1), and thus whether a reference under Section 18 can result in compensation based on a later Section 6 notification where no Section 4(1) notification was issued.
  2. Whether, assuming compensation could properly be determined on the date of the Section 6 notification in the absence of a Section 4(1) notification, the District Judge's higher award of compensation for the land was supported by satisfactory evidence (a merits question raised by the State).

Arguments of the Parties

Appellant (State) — Advocate General

  • Preliminary contention: The statutory machinery for determining compensation under the Land Acquisition Act requires valuation based on market value at the date of the notification under Section 4(1). Since no Section 4(1) notification was issued in this case, the District Judge erred in awarding compensation based on the date of the Section 6 notification; the Reference should have been rejected.
  • Merits contention: Even if valuation at the Section 6 notification date were permissible, the evidence did not justify the higher compensation awarded by the District Judge; there was no satisfactory evidence entitling the respondent to more than the Collector's award.

Respondent

  • Contended that because no notification under Section 4(1) had been issued, the respondent was entitled to claim compensation on the basis of the market value of the land as of the date of the Section 6 notification. Before the District Judge the respondent claimed Rs. 6 per square yard (as a building-site) and later relied on a rate of Rs. 3 per square yard accepted by the District Judge; the measurement objection was abandoned.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court undertook a statutory construction of the Land Acquisition Act, 1894, focusing on the sequence and content of Parts II and III (acquisition and reference). The court observed that the Act contemplates two distinct notifications in the acquisition process: (a) a notification under Section 4(1) — the introductory, exploratory step that initiates acquisition proceedings (including the opportunity to object under Section 5-A) — and (b) a subsequent notification under Section 6 declaring that the land is needed for a public purpose.

The court emphasized that Section 11 requires the Collector, when making an award, to enquire into "the value of the land at the date of the publication of the notification under Section 4, subsection (1)" and that Section 23 expressly directs the Court on reference to take into consideration "the market value of the land at the date of the publication of the notification under Section 4, subsection (1)". Section 23(2) further makes clear that the solatium (15%) is to be calculated on that market value. Section 24 excludes from consideration improvements or outlays made after the date of the Section 4(1) notification without the Collector’s sanction.

From these provisions the court drew the following conclusions:

  • The Section 4(1) notification is an essential, mandatory first step in the Act's acquisition machinery and fixes the crucial date for valuation; it cannot be dispensed with by inference or bypassed except as expressly provided by the Act (the court noted that even where certain inquiries may be dispensed with under Section 17 in emergencies, the Section 4(1) notification itself cannot be dispensed with).
  • Both the Collector and the Court, when exercising statutory jurisdiction under the Act, are confined to the date prescribed by the statute (the date of Section 4(1) publication) for determining market value and, therefore, cannot lawfully base awards on market value at a different date such as the date of a Section 6 notification.
  • Because the Act contains no provision for the situation where no Section 4(1) notification was issued, the statutory machinery for determining compensation under the Act cannot be applied in such a case; to allow valuation on another date would be to exceed the authority conferred by the Act.

Applying this reasoning to the present facts — where no Section 4(1) notification had ever been published and the only relevant notification was under Section 6 — the court held that the Collector and the District Judge could not determine compensation under the Act (that is, the reference should have been rejected because the Act's valuation date was absent). Because the court accepted the preliminary contention of the State, it did not address the second, merits-based contention as it was unnecessary to resolve the appeal.

Holding and Implications

Holding: The court allowed the appeal and set aside the District Judge's order awarding compensation.

Core Ruling: The machinery of the Land Acquisition Act, 1894, for determining compensation requires valuation at the market value on the date of publication of the notification under Section 4(1); where no Section 4(1) notification has been issued, compensation cannot be determined under that statutory machinery based on a later Section 6 notification. Accordingly, the Reference under Section 18 should have been rejected in the present case.

Direct implications for the parties: The respondent's award of Rs. 1,20,094-8-0 (and associated interest and costs ordered by the District Judge) was set aside. The appeal was allowed and there was no order as to costs of the appeal.

Broader implications: The opinion limits the ability of the Collector or the Court, exercising jurisdiction under the Act, to adopt any valuation date other than that fixed by Section 4(1). The court did not state or assert that it was laying down any new judicial principle beyond interpreting and enforcing the Act's express provisions; the decision operates to deny the application of the Act's reference machinery where the mandatory Section 4(1) notification is absent. The opinion does not discuss or decide alternative remedies the respondent might pursue outside the Act.

Decision rendered by Bhagwati, J.: Appeal allowed.

    State Of Bombay v. Chatrabhuj Nenshi .

    Bhagwati, J.:— This appeal is directed against in order made by the District Judge, Kutch in Land Acquisition Reference No 1 of 1958 awarding a total compensation of Rs. 1,20,094-8-0 to the respondent for acquisition of a piece of land bearing Survey No 010 situate on the Bhachau Rahapar Road in Kutch District the land belonged to the respondent which is a Limited Company carrying on business inter alia of ginning cotton and it was taken possession of by the Government of Kutch on 19th November, 1949 under an arrangement that some other land suitable for the requirements of the respondent would be given by the Government of Kutch to the respondent in exchange for the land so taken over At this lime the Land Acquisition Act, 1894. was in force in Kutch but no notification under Section 4(1) was issued by the Government of Kutch in respect of the land and no proceedings were adopted under the Act for acquisition of the land the possession of the land was taken by the Government of Kutch for construction of the State Guest House and the Court house for the Subordinate Judge at Bhachau and these buildings ‘were construe led on the land after possession of the land was taken, though no steps were taken to vest the title to the land in the Government of Kutch either by a conveyance from the respondent or by acquisition. It appears that the Government of Kutch was not in a position to Rive to the respondent in exchange equivalent land acceptable to the respondent and the arrangement upon which the land was originally taken over by the Government of Kutch, therefore, fell through but by this time the Government of Kutch had already constructed buildings on the land and the Government of Kutch, therefore, issued a notification under Section 6 of the Act declaring that the land was needed for a public purpose. The notification directed the Deputy Collector in charge of the Eastern Sub-division under S. 7 to take order for acquisition of the land. The Deputy Collector accordingly issued the necessary notices under S. 9 and after holding the prescribed inquiry made an award dated 22nd April, 1957 under S. 11 determining the true area of the land as 6 acres and 35½ gunthas and awarding as and by way of compensation Rs. 585-44 nP. for the land valuing it as agricultural land and Rs. 3,828 for the well and pipeline in the land and Rs 662 as 15 percent solatium under S. 23(2) making in all an aggregate sum of Rs. 5,075-44 nP. The respondent was dissatisfied with this award & he, therefore, applied to the Deputy Collector to make a reference and the Deputy Collector accordingly made a reference to the District Court under S. 18 of the Act. The respondent raised a twofold objection against the award in the Reference the first objection was as regards the measurement of the land. The respondent's contention was that the true area of the land was 8 acres and 28 gunthas and not 6 acres and 35½ gunthas as found by the Deputy Collector. This contention was, however, given up at the hearing of the Reference and the true area of the land was accepted as 6 acres and 35½ gunthas. The other objection was to the amount of compensation both in respect of the land as also in respect of the well and pipeline. But so far as the well and pipeline were concerned, no evidence was led on behalf of the respondent to show that the valuation of Rs. 3,828 made by the Overseer of the Public Works Department was erroneous and the learned District Judge, therefore, negatived the objection in so far as it related to the amount of compensation in respect of the well and pipeline the objection as to the amount of compensation in respect of the land was however, found by the learned District Judge to be well founded the respondent had claimed before the Deputy Collector compensation at the rate of Rs 6 per square yard on the basis that the land was a building-site but the Deputy Collector had proceeded to award compensation on the basis that the land was agricultural land. The same claim of Rs 6 per square yard was repealed before the learned District Judge and it was contended that the rate of Rs 6 per square yard represented the market value of the land on the date of the notification under Section 6 on the basis of the land being a building-site and since there was no notification under Section 4(1), the respondent was entitled to claim compensation on the basis of the market value of the land on the date of the notification under Section 6. It was not disputed on behalf of the State that the respondent was entitled to compensation on the basis of the market value of the land at the date of the notification under Section 6 and the learned District Judge, after considering the evidence on record, came to the conclusion that the market value of the land at the date of the notification under Section 6 should be taken to be Rs. 3 per square yard and on that basis the learned District Judge awarded compensation of Rs. 1,00,000-8-0 for the land. Adding to this the amount of compensation in respect of the well and pipeline and 15 per cent solatium the learned District Judge came to the conclusion that the respondent was entitled to claim Rs. 1,20,094-8-0 as compensation and he accordingly made an order awarding the said amount as compensation together with interest thereon at the rate of 6 per cent per annum from 1st February, 1955 being the date of the notification under Section 6 and proportionate costs the State thereupon preferred (he present appeal in this Court.

    2. The learned Advocate General appealing on behalf of the State advanced broadly two contentions in support of the appeal. The first was a contention of a preliminary nature and it raised a question of some importance the contention was that under the machinery provided by the Land Acquisition Act for determination of compensation for acquisition of land, compensation could be determined only on the basis of the market value of the land at the date of the notification under Section 4(1) and the learned District Judge has, therefore, in error in awarding compensation on the basis of the market value of the land at the date of the notification under Section 6. The learned District Judge, it was argued, should have held that since in the present case there was no notification under Section 4(1), it was not possible to determine the amount of compensation pay able for the land under the machinery of the Land Acquisition Act and the Reference should, therefore have been rejected by the learned District Judge the second contention was directed to the merits of the case and it was urged that even if the learned District Judge was, in the absence of notification under Section 4(1), entitled to award compensation on the basis of the market value of the land at the date of the notification under Section 6, the compensation awarded by the learned District Judge-was not at all justified by the evidence on record and as a matter of fact there was no satisfactory evidence which would entitle the respondent to claim higher compensation than that awarded by the Deputy Collector. This second contention would become necessary to be considered only if the first contention were decided against the State, but in our opinion the first contention is well-founded and if is, therefore, not necessary to go into the evidence for the purpose of deciding the validity of the second contention. Let us examine the first contention. In order to appreciate this contention it is necessary to examine briefly the scheme as appearing from the various provisions of the Act. The preamble of the Act shows that it is an Act to amend the law for the acquisition of land needed for public purposes and for companies and for determining the amount of compensation to be made on account of such acquisition. Part I of the Act contain sections of a preliminary nature dealing with subjects such as extent and commencement and definitions. Then comes Part II which is headed “Acquisition” and which sets out the procedure to be followed in effecting acquisition of land. The first step which is required to be taken is the issue of a notification under sub section (1) of Section 4 That sub-section provides that whenever it appears to the appropriate Government that land in any locality is needed or is likely to be needed for any public purpose, a notification to that effect shall be published in the Official Gazette on the issue of the notification under Section 4(1) steps are taken to enter upon and survey the land and take all other actions necessary to decide whether the land is fit for the purpose for which it is needed and in that connection Section 5-A provides that any person interested in the land may, within thirty days after the issue of the notification, object to the acquisition of the land Every objection under Section 5-A is required to be made to the Collector in writing and that section enacts that the Collector shall after hearing all objections and after making such further inquiry, if any, as he thinks necessary, submit the case for the decision of the appropriate Government, together with a report containing his recommendations on the objections and the decision of the Government on the objections shall be final. Section 6 then provides for the issue of a notification declaring that the land is needed for a public purpose or for a company. The notification under Section 6 is made conclusive evidence that the land is needed for a public purpose or for a Company, as the case may be, and Section 7 declares that on such notification being issued the appropriate Government shall direct the Collector to lake order for acquisition of the land. Section 8 requires the Collector to cause the land to be marked out measured, and planned and Section 9 says that the Collector shall then cause public notices to be given to persons interested in the land stating that the Government intends to take possession of the land and that claims to compensation for all interests in the land may be made to him. Section 10 empowers the Collector to require and enforce the making of statements as to names of persons possessing interest in the land and the nature of such interest with the object of enabling the Collector to make a proper award determining compensation to be paid for acquisition of the land and apportioning such compensation amongst persons interested in the land Section 11 is a little important and we would prefer to set it out in full rather than give a mere gist of it in our own words that section runs as follows:

    “11. Enquiry and award by Collector: On the day so fixed, or on any other day to which the enquiry has been adjourned, the Collector shall proceed to enquire into the objections (if any) which any person interested has stated pursuant to a notice given under Section 9 to the measurements made under Section 8, and into the value of the land at the date of the publication of the notification under Section 4, subsection (1), and into the respective interests of the persons claiming the compensation, and shall make an award under his hand of—

    (i) the true area of the land;

    (ii) the compensation which in his opinion should be allowed for the land; and

    (iii) the apportionment of the said compensation among all the persons known or believed to be interested in the land, of whom or of whose claims, he has information, whether or not they have respectively appeared before him.”

    3. The award made by the Collector is declared by S. 12 to be final and conclusive evidence as between the Collector and the persons interested, of the true area and value of the land and the apportionment of the compensation among the persons interested. Sections 13 and 14 deal merely with the powers of the Collector while holding the inquiry and are not material for the purpose of the present discussion Section 15 enacts that in determining the amount of compensation, the Collector shall be guided by the provisions contained in Ss 23 and 24. After the Collector has made the award, he may lake possession of the land and on possession being taken, the land vests absolutely in the Government free from all encumbrances Section 17 confers power on the Government in cases of urgency, to direct the Collector to take possession of any waste or arable land needed for public purposes or for a company even before any award has been made and in such cases, on possession being taken, the land vests absolutely in the Government free from all encumbrances. That section also authorizes the appropriate Government to dispense with the inquiry under S. 5-A in certain cases Here ends Part II Part III deals with the subject of reference to Court and procedure on such reference Section 18 which is the first section in Part III provides that any person interested who has not accepted the award may, by written application to the Collector, require that the matter be referred by the Collector for the determination of the Court, whether his objection be to the measurement of the land, the amount of the compensation, the persons to whom it is payable or the apportionment of the compensation among the persons interested Section 19 specifies the particulars which are required to be set out by the Collector in making a reference to the Court Sections 20, 21 and 22 deal with certain matters of detail in regard to the Reference which have no bearing on the question before us. Then comes S. 23 which is a very important and relevant section. The material part of that section reads as follows:

    “23. Matters to be considered in determining compensation: (1) In determining the amount of compensation to be awarded for land acquired under this Act, the Court shall take info consideration—

    first, the market value of the land at the date of the publication of the notification under S. 4, sub-section (1);

    xxxxxx

    xxxxxx

    (2) In addition to the market value of the land, as above provided, the Court shall in every case award a sum of fifteen per centum on such market-value, in consideration of the compulsory nature of the acquisition.”

    4. Section 24 lays down what matters must not be taken into account by the Court in determining compensation and one of those matters is that set out in the seventh clause of the section, namely:

    “any outlay or improvements on, or disposal of, the land acquired, commenced, made or affected without the sanction of the Collector after the date of the publication of the notification under S. 4, sub-section (1)”

    5. Then follow Ss 25 to 28 which lay down certain rules as to amount of compensation and make provision for award of costs and interest These are the relevant sections of the Act which we will have to bear in mind while examining the validity of the contention urged on behalf of the State.

    6. Now it is clear from the summary of the Section which we have given above that the Act contemplates two notifications to he issued by the Government as essential steps in acquisition of land; one being a notification under S. 4(1) and the other being a notification under S. 6. The notification under S. 4(1) precedes the notification under S. 6 and it constitutes the first step in the process of acquisition It is undoubtedly true that the notification under S. 4(1) is merely an introductory measure exploratory in character and having no consequence beyond initiating a proposal for acquisition of land but none-the-less it constitutes an essential step which must needs be taken before acquisition of any land can be effected It is significant that in cases covered by S. 17 sub-section (4) an inquiry under S. 5-A may be dispensed with but there can be no dispensing with the notification under S. 4(1) and that notification must be issued before any further step is taken in the matters of acquisition of land. Since the issue of the notification under S. 4(1) is the first step in the process of acquisition of land and is a step which would necessarily be taken in all cases of acquisition of land, the date of that notification is taken as the date at which the value of the land must be determined for the purpose of ascertaining the amount of compensation awardable for acquisition of land. Section 11 which we have reproduced above in terms provides that the Collector for the purpose of making his award determining the amount of compensation which in his opinion should be allowed for the land shall enquire into the value of the land at the date of the publication of the notification under S. 4(1). It is on the basis of the value of the land at the date of the notification under S. 4(1) that the Collector is required to determine compensation which should be awarded for acquisition of the land. The scope of the inquiry to be made by the Collector is restricted to ascertainment of the value of the land at the date of the notification under S. 4(1) and he cannot transgress that limit and enquire into the value of the land at any other date and award compensation on that basis. Now the award of the Collector is merely in the nature of a proposal by the Government and the persons interested in the land may accept it or may prefer to take the matter to Court by way of Reference. When the matter is taken to the Court by way of Reference, the Court would then have to determine the amount of compensation which should be awarded to the applicant for acquisition of the land. Now obviously the scope of the inquiry before the Court cannot be any wider or any different from the scope of the enquiry before the Collector & it would, therefore, be reasonable to conclude that the Court would also have to enquire into the value of the land at the date of the notification under S. 4(1) and award compensation on that basis But this is not a matter left to be gathered by implication We find that it is expressly provided in S. 23 that in determining the amount of compensation to be awarded for the land, the Court shall lake into consideration the market value of the land at the date of the publication of the notification under S. 4(1). It is an injunction issued to the Court by the legislature that the Court must lake into consideration the market value of the land at the date of the notification under S. 4(1) in deter-mining the amount of compensation in the face of this provision it is difficult to see how it can be urged that the Court may, in a possible case, take into consideration the market value of the land at some date oilier than the date of the notification under S. 4(1). The argument urged on behalf of the respondent was that all that S. 23 requires the Court to do is to take the market value of the land at the date of the notification under S. 4(1) into consideration; it does not say that the Court shall determine the amount of compensation on the basis of the market value of the land at the date of the notification under S. 4(1) or that the market value of the land at the date of the notification under S. 4(1) shall be the amount of compensation. But this argument is wholly devoid of merit and is based on what we may term legal casuistry. As the preamble of the Act shows, the Act was passed inter alia for determining the amount of compensation to be made on account of acquisition of land and S. 23 is one of the sections laying down the principles for determining the amount of compensation to be paid for acquisition of land the various clauses of S. 28 set out the matters which must be considered by the Court in determining the amount of compensation so that they are provided for in the amount of compensation which is awarded by the Court. One of the matters is the market value of the land at the date of the notification under S. 4(1) and it is that market value and no other which must be taken into account when the Court determines what is the amount of compensation which must be awarded for the land. To accept the contention urged on behalf of the respondent would mean that the Court would be at large in determining the amount of compensation and the principles for deter mining the amount of compensation laid down in Sec. 23 would have no compulsive force the true meaning of sub-section (1) of Section 23, we think, is that the amount of compensation to be awarded for the land shall consist of various components and one of the components shall be the market value of the land at the date of the notification under Section 4(1). This view which we are taking is considerably reinforced by reference to sub section (2) of Section 23 which says that in addition to the market value of the land as above provided, the Court shall in every case award a sum of 16 per cent of such market value as solatium. Sub-section (2) clearly shows that under sub-section (1) the Court is to award the market value of the land at the date of the notification under Section 4(1) and in addition to that market value the Court must also award 15 per cent of such market value as solatium Section 24 also emphasizes that the crucial date which is required to be taken into account is the date of the notification under Section 4(1) for it says that in determining the amount of compensation the Court shall not take into account any outlay or improvements, on or disposal of, the land acquired, commenced made or effected without the sanction of the Collector after the date of the publication of the notification under Section 4(1) It is, therefore, clear that the Collector making an inquiry under S. 11 as also the Court hearing a reference under S. 18 can award compensation only on the basis of the market value of the land at the date of the notification under Section 4(1)

    7. The question then is what is to happen if in a given case no notification under Section 4(1) has been issued by the Government and the only notification issued is that under Section 6? Now, as we have pointed out above the Act does not contemplate any such situation and it is, therefore, natural that there is no provision in the Act dealing with such a situation If there is no notification under Section 4(1) the machinery provided by the Land Acquisition Act for determination of compensation for acquisition of the land obviously cannot apply Neither the Collector nor the Court can take into account the market value of the land at any other date on the ground that there is no notification under S. 4(1) and consequently it is not possible to take into account the market value of the land at the date of such notification the Court as well as the Collector can not travel outside the limits placed upon the exercise of their jurisdiction and determine the amount of compensation on the basis of the market value of the land at a date other than that provided in S. 11 or S. 23. The Collector and the Court are exercising the jurisdiction conferred upon them by the Act and if the Act directs in positive mandatory terms that in determining the amount of compensation the Collector and the Court shall take into account the market value of the land at the date of the notification under S. 4(1), the Collector and the Court cannot take into account the market value of the land on any other date To do so would be to act beyond the authority conferred by the Act It may be that in a given case where no notification under S. 4(1) has been issued, it may not be possible to determine the amount of compensation payable fur the acquisition of the land by resort to the machinery provided by the Act, but that difficulty or hardship should not induce us to take a view which is not warranted by the language of the various provisions of the Act and which flies in the face of Ss 11 and 23. The difficulty arises in such a case because the Act does not contemplate acquisition with out issue of a notification under S. 4(1) and the Act has, therefore, not provided any machinery for determination of compensation for acquisition of land in such a case the respondent may be able to successfully contend that the acquisition is bad since it is not initiated by a notification under S. 4(1) or the respondent may be able to claim compensation by pursuing any other remedy available to him but we are not concerned with that. The only question is whether the respondent can claim compensation by availing himself of the machinery provided by the Land Acquisition Act and on that question we do not think we can give an answer in favour of the respondent Since there is no notification under S. 4(1) in the present case, it is not possible to determine the amount of compensation payable for acquisition of the land under the machinery provided by the Land Acquisition Act and the learned District Judge should have, therefore, rejected the reference.

    8. The result, therefore, is that the appeal is allowed and the order passed by the learned District Judge awarding compensation to the respondent is set aside. There will be no order as to costs of the appeal

    AJ/VRB/R.G.D

    9. Appeal allowed.