Judgment Summary — Valmiki J. Mehta, J. (Oral) — I.A No. 252/1998 & CS(OS) No. 674A/1997

Factual and Procedural Background

The proceedings arise from objections under Sections 30 and 33 of the Arbitration Act, 1940 to an arbitral Award dated 14.3.1997. The underlying dispute concerned construction of 410 "Janta Houses" at Peera Garhi, New Delhi. The original work was awarded to the petitioner by letter dated 14.9.1983 with a stipulated completion date of 24.9.1983. Because the work remained incomplete, the balance work, valued at Rs. 33,292/-, was the subject of a supplementary agreement dated 31.8.1988 prescribing nine months for completion. The balance work was ultimately completed on 20.3.1993. The petitioner filed claims in 1994; the Arbitrator dismissed those claims as time-barred on the ground that the original contract had closed when the supplementary agreement was entered into in 1988. A final bill dated 18.1.1994, however, was submitted and described as a consolidated bill referring to both the original (1983) and supplementary (1988) agreements and mentioning completion/closure as 20.3.1993.

Legal Issues Presented

  1. Whether the Arbitrator was correct in holding that the petitioner's claims arising under the original contract (dated 14.9.1983) were barred by limitation because, according to the Arbitrator, the original contract had been closed when the supplementary agreement was executed on 31.8.1988.
  2. If the Arbitrator's conclusion on limitation is incorrect, whether the Court should remit the matter to the Arbitrator for re-determination or whether the Court itself may consider the merits of the claims while hearing objections under Sections 30 and 33 of the Arbitration Act, 1940 (and whether the Court may invoke inherent powers under Section 151 CPC to decide merits given the specific procedural history and delay).

Arguments of the Parties

Objector / Petitioner

  • Challenged the Award that dismissed his 1994 claims as time-barred, contending that disputes under the original agreement of 14.9.1983 continued because the supplementary agreement of 31.8.1988 used the expression "provisional closure" (not plain "closure"), so disputes survived until completion of the balance work on 20.3.1993.
  • Relied heavily on the final bill dated 18.1.1994, contending it was a consolidated bill for work done under both the original and supplementary agreements and that it mentioned the date of closure as 20.3.1993.
  • Argued (through counsel) that arbitrators are experts and that detailed evidence is not necessary for such monetary claims to be allowed by an arbitrator.

Respondent / Non-objector

  • Contended that two views were possible regarding the term "provisional closure" in the supplementary agreement, and that the Arbitrator legitimately adopted the view that the original contract was closed on 31.8.1988 — thus claims had to be filed within three years from that date.
  • Argued that where two views are possible, the Court would not interfere with the Arbitrator's decision on objections under Sections 30 and 33, and thus the Arbitrator's conclusion on limitation was justified.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
K.P. Poulose v. State of Kerala, (1975) 2 SCC 326 Referenced regarding misconduct of arbitrator/proceedings when relevant documents are not considered. The court held that the Arbitrator had mis-conducted himself by not considering the admitted final bill dated 18.1.1994 and invoked the principle in K.P. Poulose to set aside the Arbitrator's finding on limitation.
Godhra Electricity Company v. State of Gujarat, AIR 1975 SC 32 Principle that how parties understand contract terms is manifested by their actions under the contract. The court cited this to support the proposition that conduct and documents (such as the final bill) illuminate the parties' understanding of closure and completion dates.
Evidence Act, 1872 (principles) Principles of burden and discharge of proof in civil proceedings are applicable to arbitration proceedings. The court applied basic Evidence Act principles to conclude that the claimant failed to discharge the onus of proof for the large monetary claims; mere pleadings without supporting evidence are insufficient.
Union of India v. Madhya Pradesh Export Corporation Ltd., 1998 (Suppl.) Arb.LR 618 Authority cited by objector to argue that the Court should not decide issues on merits (context in the opinion: modification/correction of Awards). The court distinguished this authority: it found the cited judgment related to modification/correction and not to the present situation where delay and lack of evidence justified the Court deciding merits rather than remitting the matter.
Padma Sundra Rao v. State of Tamil Nadu, 2002 (3) SCC 533 Principle that a case's ratio must be read with reference to the particular facts; a single differing fact may produce a different outcome. The court relied on this to explain that precedents must be applied in light of the facts of each case and thus the objector's reliance on other decisions did not make them applicable here.

Court's Reasoning and Analysis

The court proceeded in two main analytical stages: (A) the question of limitation and the correctness of the Arbitrator's finding; and (B) whether to remit the matter to the Arbitrator or decide the merits itself.

(A) Limitation — why the Arbitrator's conclusion was set aside

  • The court examined the final bill dated 18.1.1994, which expressly referenced both the original (1983) and supplementary (1988) agreements and stated a date of closure/completion as 20.3.1993. The final bill was an admitted, later document which indicated a consolidated accounting for both contracts.
  • The Arbitrator had relied on the earlier supplementary agreement of 31.8.1988 (which used the term "provisional closure") and concluded claims under the original contract were barred by limitation from that earlier date. However, the Arbitrator did not consider the vital subsequent document (the final bill of 18.1.1994).
  • By failing to consider that admitted document, the Arbitrator mis-conducted himself. The court invoked K.P. Poulose to support the view that such failure to consider crucial material warranted setting aside the Arbitrator's conclusion on limitation.
  • The court therefore held that the Arbitrator's finding that claims under the 1983 contract were time-barred was incorrect and unlawful because it ignored the later, relevant final bill which reflected closure as 20.3.1993.

(B) Whether to remit or decide merits — reasons for deciding merits

  • The court considered whether it should remit the case to the Arbitrator for re-determination under Sections 30 and 33 of the Arbitration Act, 1940. It recognized that in some cases involving detailed factual inquiry, remittal is appropriate.
  • However, given the exceptional procedural history — the age of the contract (over 26 years) and the long pendency (work completed more than 16 years earlier, objections filed in 1997) — the court concluded that remittal would serve no useful purpose where conclusions were obvious from the arbitration record.
  • The court invoked its inherent power under Section 151 CPC to examine merits in the present circumstances to prevent further wasteful delay and to do justice, noting that long pendency itself constitutes prejudice that ought to be addressed.

(C) Merits — why the claims failed on evidence

  • The court observed that the monetary claims allowed by the Arbitrator were disproportionately high relative to the contract values (main contract Rs. 3,89,688 and supplementary Rs. 33,292) and included large heads such as Rs. 5,00,000 for overheads, Rs. 3,15,000 for idle labour damages, and Rs. 1,25,000 for increased cost of materials and labour.
  • The claimant failed to provide any meaningful breakup of claims between the original and supplementary contract periods; counsel for the objector candidly admitted no breakup existed, and that the claims were conjoint spanning 1983–1993.
  • The court rejected the objector's counsel's submission that arbitrators' expertise relieved the claimant of producing evidence. The court held that basic principles of the Evidence Act, 1872 (burden/discharge of proof on balance of probabilities) apply in arbitration as in ordinary civil proceedings.
  • Because there was essentially no evidence before the Arbitrator to discharge the onus for the large monetary claims, the court concluded the claimant had miserably failed to prove the claims and that they were liable to be dismissed on merits.

(D) Conclusion of the analysis

  • Although the court held for the record that the Arbitrator was incorrect in dismissing claims on limitation, after examining the arbitration record and evidence (or lack thereof) the court found that the claims failed on merits.
  • Therefore the court did not remit the matter to the Arbitrator; it dismissed the objection petition and made the Award the rule of the Court.
  • The court considered the objector's reliance on Union of India v. Madhya Pradesh Export Corporation Ltd. and distinguished it on its facts and scope (modification/correction versus deciding merits), and relied on Padma Sundra Rao to emphasize that precedent must be applied in the context of differing facts.

Holding and Implications

Holding: The court reached a two-part conclusion: first, it held that the Arbitrator's finding that the claims under the 1983 contract were time-barred was incorrect because the Arbitrator failed to consider the admitted final bill (18.1.1994) that indicated closure on 20.3.1993. Second, having examined the merits, the court held that the claimant failed to discharge the burden of proof for the large monetary claims and therefore the objection petition is ultimately dismissed and the Award is made the rule of the Court.

Direct effect on the parties: The objections under Sections 30 and 33 are allowed "for the record" as to the limitation issue but are ultimately dismissed on merits; consequently, the arbitral Award stands and is made the rule of the Court. The parties were left to bear their own costs (no costs were imposed).

Broader implications: The opinion applies established principles (importance of contemporaneous documents reflecting parties' conduct; applicability of ordinary Evidence Act principles to arbitration; courts may, in appropriate cases and exercising inherent powers, decide merits rather than remit to arbitrators where remittal would serve no purpose). The judgment does not state that it creates a new, general precedent beyond its application to the facts of this case.

To access the original judgment, please Sign In or Subscribe.

    Prominent Electric Works v. Delhi Development Authority & Ors.

    Valmiki J. Mehta, J. (Oral)

    I.A No. 252/1998 and CS(OS) No. 674A/1997

    These are the objections filed by the petitioner under Sections 30 and 33 of the Arbitration Act, 1940 against the Award dated 14.3.1997 The award arises on account of the disputes which arose between the parties with respect to the work of construction of 410 Janta Houses for harijans and landless persons at Peera Garhi, New Delhi.

    2. The facts of this case are that the work was awarded to the petitioner vide letter dated 14.9.1983 which prescribed the stipulated date of completion as 24.9.1983 Since the work could not be completed even well after 24.9.1983, the work in question was broken up with respect to the balance work which was of the amount of Rs. 33,292/-. For this balance work of Rs. 33,292/-, a supplementary agreement dated 31.8.1988 was entered into between the parties which prescribed the period for completion of work to be nine months. The work was however completed on 20.3.1993

    3. The counsel for the objector/petitioner has challenged the award whereby his claims filed in 1994 have been dismissed as being time barred, because claims filed were with respect to the main contract dated 14.9.1983 and which was already closed when the supplementary agreement dated 31.8.1988 was entered into between the parties. The counsel for the objector has referred to the agreement dated 31.8.1988 which uses instead of word ‘closure’, the expression “provisional closure”. The counsel for the objector therefore contended that all the disputes under the original agreement dated 14.9.1983 continued to survive right till the end when the balance work under the supplementary agreement was ultimately completed on 20.3.1993 The counsel for the objector/petitioner has also very heavily relied upon the final bill dated 18.1.1994 The counsel relying on this final bill has pointed out that this is a consolidated bill for work done both as per the original agreement as also the supplementary agreement. He has further referred to the fact that in the supplementary agreement dated 31.8.1988 there is no date mentioned for completion of work under the contract dated 14.9.1983 Per contra the counsel for the non-objector, however, urges that two views are possible for this expression ‘provisional closure’ as used in the letter dated 31.8.1988 She has further urged that one of the acceptable views can certainly be as held by the Arbitrator that the original contract was closed whereby the claims under the same ought to have been filed when the same was closed in 1988 and not in 1994 and only the balance work remained to be performed by means of the fresh agreement titled as supplementary agreement thereby nothing remained to be done under the original agreement, and this Court while hearing objections under Sections 30 and 33, has repeatedly held that it will not interfere with the Award if two views are possible. Consequently, the Arbitrator having taken one view which shows that the first contract was closed when the supplementary agreement was signed on 31.8.1988, claims had to be filed within three years from that date so far as the claims under the first contract and which admittedly was not done. It was, therefore, urged that the conclusion on the issue of limitation as held by the Arbitrator, therefore, is clearly justified.

    4. I feel that the contention of the objector is correct and merits acceptance. In the final bill dated 18.1.1994, there is a specific mention of the actual date of completion of work, which was not mentioned in the Supplementary Agreement dated 31.8.1988, and, which final bill is with reference not only to the original agreement of 1983 but also for the supplementary agreement dated 31.8.1988 This final bill also while referring to both the contracts mentions the date of closure not as the date of the supplementary agreement dated 31.8.1988 but 20.3.1993 which is inclusive of the work completed after the supplementary agreement dated 31.8.1988 A reference to the final bill and the entries contained therein does definitely show that it was a consolidated bill for both the agreements and since it was a consolidated bill for both the contracts, it refers to payments made under the first contract also. Consequently the Arbitrator so far as having determined the issue that the claims for the agreement which began in 1983 are barred by limitation does not appear to be correct considering the fact of this admitted document being the final bill. The Arbitrator has while arriving at the conclusion that the claims are barred by limitation has referred to the supplementary agreement which is the document earlier in point of time dated 31.8.1988, but has not referred to the vital, crucial and admitted later document being the final bill dated 18.1.1994 By not considering this most relevant document, the Arbitrator has mis-conducted himself and the proceedings as per K.P Poulose v. State of Kerala, (1975) 2 SCC 326. How the parties understand the terms of a contract is best understood by their actions in terms of such a contract (vide Godhra Electricity Company v. State of Gujrat, AIR 1975 SC 32). I consequently hold that the findings of the Arbitrator of the claims being time barred are illegal and hence liable to be set aside. The objections are therefore allowed, though for the record only, as the objections have to be ultimately dismissed as held by me later in this judgment.

    5. The issue which now I have to consider is what to do in a very old case like the present one where the contract is more than 26 years old and work under which contract was duly completed more than 16 years from today. Once the issue of limitation is decided in favour of the petitioner/objector, and it is held that the Arbitrator was not justified in dismissing the claims on the ground that the same were barred by the limitation, the issue is that while hearing objections under Sections 30 and 33 of the Arbitration Act, 1940 is it necessary for the Court to necessarily remit the matter back to the Arbitrator for redetermination or can the Court look into the merits of the disputes itself for arriving at a final decision itself I am of the opinion that in a particular case where detailed and lengthy arguments on many issues are required, many documents are to be looked into, detailed evidence has to be considered, that case may be a case where the matter may have to be remitted, but, is it so required also in such a case where it is obvious from the facts as pleaded and the evidence as led that remission would serve no purpose inasmuch as the conclusions which are to be arrived at are obvious from the arbitration record. I am of the firm opinion that this Court can, in such a latter scenario, the Court can as well look into the issue with respect to the merits of the claims which are made since not much time is to be taken for arriving at a decision on those issues. Every civil court has inherent power under Section 151 CPC to do justice and I, therefore, invoke this power in the facts and circumstances of this case. Accordingly, in view of the fact of the pendency of these disputes since the last over 16 years and the objections itself having been filed in the year 1997 i.e more than 12 years back and the state of the pleadings and evidence as led before the Arbitrator, I have persuaded myself to look into the issue as regards the merits of the claims which were made by the claimant before the Arbitrator. Long pendency of litigation itself is a prejudice which ought to be addressed.

    6. The main claims which have been rejected by the Arbitrator, for the main contract of the value of Rs. 3,89,688/- and the supplementary agreement of the value of Rs. 33,292/-, are disproportionately high when compared to the value of the contracts. Some of the claims are:—a claim of Rs. 5,00,000/- for loss on account of overheads at site; at head office; alongwith loss and profits due to prolongation of the contract, a claim of Rs. 3,15,000/- as damages on account of idle labour and staff due to prolongation of work, a claim of Rs. 1,25,000/- on account of increase in cost of material and labour and so on. On looking at all these claims as per the claim petition, I enquired from the counsel for the objector that what is the break-up of these claims because no break-up of the same as relatable to which contract i.e they pertain to the period of the original contract period or the supplementary contract period and considering type/nature of the claims whether they have been effectively broken up for the two different periods and in what manner each of these claims is established and proved before the Arbitrator. The counsel for the objector in this regard has been very fair in stating that there is no break up available in the claim petition with regard to the different heads of claims or otherwise. The counsel for the objector said that the claims are conjoint claims for the complete period right from the work being awarded in 1983 till the same was completed in 1993. The next question then posed by me to the counsel for the objector is how and in what manner these claims have been substantiated by filing of the requisite evidence before the Arbitrator if the same have to be allowed. To this, the counsel says that arbitrators are experts in the field and no evidence is required and consequently, such claims can be regularly allowed by the Arbitrator.

    7. I do not agree at all with the contention which has been urged by counsel for the objector. Surely, mere statements contained in the statement of facts or pleadings without being supported by evidence cannot mean that in spite of the same having not been proved as required by the doctrine of discharge of onus on balance of probabilities, leave alone to the complete conviction of the Arbitrator, yet such status can still entitle the contractor/claimant to the damages as claimed. This argument urged by the objector is against all cannons of justice, equity, law and the principle of burden/discharge of proof. No doubt burden of proof in a civil case is on balance of probabilities but surely some reasonable amount of evidence has to be there on the basis of which an Arbitrator can make an honest guess work for allowing the claims. It is not an argument available to the contractor/claimant to say that on the basis of very tennuous and almost non existent evidence, the Arbitrator is entitled to make a guess work merely because he is allegedly an expert in the field being an Engineer. The Arbitrator being an engineer cannot mean that basic minimum requirements of the Evidence Act have to be thrown to the winds when huge monetary liability by the Award can be fastened on to the opposite party. Surely basic and fundamental principles of Evidence Act, 1872 are applicable even to arbitration proceedings. I find that, and which could not be at all rebutted by the objector, that there is no evidence as available before the Arbitrator to discharge the onus of proof as required in a civil case. The claimant has therefore miserably failed to discharge the onus, which he has to, in order to succeed in establishing the claims. The claims, therefore, as filed are clearly liable to be dismissed.

    8. Accordingly, though the objection petition is allowed for the purpose of record in that it is held that the Arbitrator was not justified in holding the claims to be beyond limitation, however, having examined the merits of the matter with respect to the claims which were made before the Arbitrator, and the other details including the evidence. I am of the opinion that objection petition is liable to be dismissed and it is not required that the matter should be remitted to the Arbitrator for fresh consideration. Accordingly, the objection petition is dismissed and the Award is made the rule of the Court.

    9. At this stage, the counsel for the objector has relied upon Union of India v. Madhya Pradesh Export Corporation Ltd., 1998 (Suppl.) Arb.LR 618 to contend that this Court should not decide the issue on merits. I find that the said judgment is only with respect to modification or correction of the Award and not with respect to the fact whether if on account of delays caused by long pendency of cases and the lack of evidence a Court cannot and shall not look into the case on merits and it is necessary that an exercise in futility should and ought to be resorted to by referring the matter back to the Arbitrator though the same will serve no purpose because the claims in no circumstances are at all proved as the onus to prove the claims has not even been the least bit discharged.

    The Supreme Court in the Constitution Bench case reported as Padma Sundra Rao v. State of Tamil Nadu, 2002 (3) SCC 533 has held that the ratio of a case has to be read with reference to the facts of each particular case and even a single fact which is different may make a difference to the ratio. Thus on the facts of the present case I do not find the judgment cited by the Objector is applicable.

    10. Ordinarily, I would have imposed costs for disposal of the objections, however, since objections are for the purpose of record qua the issue of limitation allowed, but since ultimately the objections are being dismissed because I am not remitting back to the Arbitrator, I am not imposing costs in the matter and leave the parties to bear their own costs.