  • Section 16(d)/(e) of the CPC
  • Arbitration Act, 1996
  • Section 16(d)
  • Section 16(e)
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Section 16(d)/(e) of the CPC
  • Arbitration Act, 1996
  • Section 16(d)
  • Section 16(e)
Smart Summary

Factual and Procedural Background

The parties were parties to an agreement dated 10 August 2007 which provided for resolution of disputes under the Arbitration Act, 1996 with the arbitration proceedings to be held at Delhi. The respondent opposed the petition (including IA No. 691/2008 under Section 9 of the Act) on three grounds: (1) this court lacked territorial jurisdiction; (2) the agreement was unstamped and unregistered though claimed to be compulsorily registrable; and (3) the agreement had been abandoned by the parties. The petitioner's counsel stated that the petitioner was not claiming any rights in immovable property but was claiming breaches of contract and resultant losses. The matter proceeded on these contentions and the court made orders including the appointment of an arbitrator.

Legal Issues Presented

  1. Whether this court (Delhi) was the appropriate court to entertain the petition in view of the agreement and the location of the immovable property (jurisdictional question under Section 2(e) of the Arbitration Act and relevant authorities).
  2. Whether the agreement was unstamped and unregistered and, if so, whether it was compulsorily registrable and so liable to be impounded.
  3. Whether the agreement had been abandoned by the parties and, if that is so, whether that plea could be entertained at this stage.
  4. Whether the arbitration clause could be enforced despite alleged defects as to stamp or registration.

Arguments of the Parties

Respondent's Arguments

  • This court did not have territorial jurisdiction because the agreement related to development of the respondent's immovable property at Jammu and, accordingly, the appropriate court would be the court within whose jurisdiction the immovable property is situated (relying on Section 2(e) of the Arbitration Act and the dicta in Harshad Chimanlal Modi v. DLF Universal Ltd).
  • The agreement was unstamped and required compulsory registration; therefore it ought to be impounded.
  • The agreement had been abandoned by the parties, a contention challenging the continued validity of the agreement.
  • Section 16(d)/(e) of the CPC was invoked to support jurisdictional and substantive positions: Section 16(d) for determination of rights in property and Section 16(e) for compensation for wrong to immovable property.

Petitioner's Arguments

  • The petitioner was not claiming any rights in the immovable property; the claims were for breach of the agreement and consequent losses, not for rights in land or compensation for wrong to immovable property.
  • The agreement was executed at New Delhi and the parties had agreed to the venue of arbitration being New Delhi, making this court the appropriate court for adjudication of the breach of contract claims.
  • On the question of possession and registration, the petitioner stated that it had only put equipment on the property (disputing any admitted possession as owner or lessee that would render registration compulsory).
  • As to stamp duty/impounding, the petitioner undertook to deposit the maximum penalty (ten times) together with the deficiency in stamp duty with the Collector of Stamps within four weeks.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Harshad Chimanlal Modi v. DLF Universal Ltd (2005) 7 SCC 791 That the appropriate court to entertain certain petitions under the Arbitration Act may be the court within whose jurisdiction the immovable property is situated (territorial jurisdiction considerations). The court noted that, if the petitioner were claiming rights in the immovable property, then in view of this authority this court would not have jurisdiction; however the petitioner disavowed such property claims, altering the jurisdictional analysis.
Ansal Property and Industries Pvt Ltd v. Anand Nath MANU/DE/0824/1991 Characterisation of development agreements as agreements to sell in future; such agreements without delivery of possession do not require registration. The court relied on this precedent to hold that the development agreement in question was of the nature of an agreement to sell and did not compulsorily require registration where there was no delivery of possession.
N.I.I.T Institute of Information Technology v. West Star Construction Pvt Ltd MANU/DE/0485/2009 That an arbitration clause even in a lease deed requiring compulsory registration although not so registered can be implemented. The court referred to this Division Bench decision to support the proposition that an arbitration clause can be implemented despite defects as to compulsory registration of the underlying instrument.

Court's Reasoning and Analysis

The court proceeded step-by-step through the objections raised by the respondent.

  1. Jurisdiction: The court recognised the respondent's submission that, if the petitioner claimed rights in immovable property, the appropriate court would be the court where the property is situated (citing Harshad). However, the petitioner expressly stated it was not claiming any rights in immovable property but only breach of contract and consequent losses. Given that admission, the court found that Section 16(d) of the Code of Civil Procedure (for determination of rights in property) did not apply; the petitioner's claims were not for rights in immovable property nor for compensation for wrong to immovable property, so Section 16(e) similarly did not apply to convert the forum into the property court.
  2. Venue and proper court: The agreement recorded that it was executed at New Delhi and the parties had agreed on New Delhi as the venue of arbitration. On that basis, the court concluded that it would be the appropriate court to adjudicate the breach of contract claims in respect of the arbitration petition.
  3. Registration and stamp: The court analysed the nature of the agreement as a development agreement. Relying on Ansal Property and Industries and noting the petitioner's representation that there was no delivery of possession (petitioner only placed equipment on the property), the court held that the agreement was in the nature of an agreement to sell and did not require compulsory registration. The court also treated the impounding/stamping objection: the stamp duty payable on such an agreement was Rs 50, and the petitioner offered to deposit the maximum penalty (ten times) together with any deficiency in stamp duty with the Collector of Stamps within four weeks.
  4. Enforceability of arbitration clause: The court observed authority (N.I.I.T. decision) supporting that an arbitration clause can be implemented even where the underlying instrument may require registration but is not registered. This supported permitting arbitration to proceed.
  5. Abandonment plea: The court held that the plea that the agreement had been abandoned was a merits question that could not be gone into at this interlocutory stage; there was no material before the court to entertain that plea at this stage.
  6. As a consequence of the above reasoning, the court directed appointment of an arbitrator and set ancillary directions concerning fee fixation, cost-bearing, compliance with stamp duty penalties and an initial date for appearance before the arbitrator.

Holding and Implications

Core Ruling: The court appointed Justice Anil Dev Singh (Retd) as the arbitrator to adjudicate the disputes and differences in terms of the arbitration clause contained in the agreement, limited to the statement made by the petitioner's counsel.

Directions and immediate consequences:

  • The parties were directed to consult with the arbitrator to fix the arbitrator's fee and other expenses, to be borne equally by the parties subject to the award as to costs.
  • The petitioner was ordered to deposit with the Collector of Stamps within four weeks the stamp duty deficiency together with the maximum penalty (ten times), the court having noted the stamp duty payable on such an agreement as Rs 50.
  • The parties were directed to appear before the arbitrator (on prior appointment) on 23 October 2009.
  • The court declined to decide on the abandonment plea at this stage, treating it as a merits issue unsuitable for interlocutory determination.

Broader implications: The opinion applied existing precedents to the facts before it to permit arbitration to proceed and did not purport to lay down any new legal principle. The direct effect is the appointment of the arbitrator and the procedural directions listed above.

To access the original judgment, please Sign In or Subscribe.

    M/S Zoom Motels Pvt Ltd. Petitioner v. M/S Sheranwali Hotels & Resorts Ltd

    Rajiv Sahai Endlaw, J.:—The parties are admittedly the parties to an agreement dated 10th August, 2007 providing for resolution of disputes under the Arbitration Act, 1996 with the arbitration proceedings to be held at Delhi.

    2. The counsel for the respondent has opposed the petition on three grounds. Firstly on the ground of this court being not the appropriate court having territorial jurisdiction to entertain this petition; secondly on the ground of agreement aforesaid being unstamped and unregistered while being required to be compulsorily registered; and, thirdly on the ground of the agreement having been abandoned by the parties. As far as the first of the aforesaid pleas is concerned, it is contended that the agreement was for development of the immovable property of the respondent at Jammu by the petitioner in consideration of the petitioner having certain rights in the said property, post development. It is further contended that from the IA. No. 691/2008, under Section 9 of the Act filed by the petitioner in these proceedings, it appears that the petitioner is claiming rights in the property and is claiming appointment of arbitrator for adjudication of the said rights. The contention is that the appropriate court within the meaning of Section 2(e) of the Act to entertain this petition would be the court within whose jurisdiction the immovable property is situated.

    3. If that be the position, undoubtedly in view of the dicta in Harshad Chimanlal Modi v. DLF Universal Ltd(2005) 7 SCC 791 this court would not have jurisdiction. However, the counsel for the petitioner states that he is not claiming any rights in the immovable property and the claims of the petitioner against the respondent, of which arbitration is sought are for breach of agreement by the respondent and consequent losses suffered by the petitioner.

    4. Faced with the aforesaid, the counsel for the respondent has contended that Section 16(d)/(e) of the CPC would still apply. Section 16(d) is for determination of rights in property and Section 16(e) for compensation for wrong to immovable property. The counsel for the petitioner having stated that no claims in immovable property situated outside the jurisdiction of this court are claimed, Section 16(d) does not apply. The claims of the petitioner for breach of contract would not be for compensation for wrong to immovable property.

    5. Else the agreement itself states that the same is executed at New Delhi and the parties had also agreed to the venue of arbitration at New Delhi. This court would thus be the appropriate court for the adjudication of the claims for breach of contract.

    6. The counsel for the respondent has next contended that the agreement ought to be impounded, being unstamped. Though it is contended that it is compulsorily registrable but neither is it the case that the possession of the property in part performance of the agreement has been delivered to the petitioner either as owner or as a lessee nor is any clause of the agreement found to be such as requires registration. The agreement is a development agreement. The true nature and purport of such an agreement has been adjudicated by this court in Ansal Property and Industries Pvt Ltd v. Anand Nath MANU/DE/0824/1991. It has been held that such agreements are to exchange in future and are in the nature of agreements to sell. An agreement to sell without delivery of possession does not require registration. The counsel for the respondent states that though the petitioner claims to be in possession, the respondent does not admit the same; the counsel for the petitioner states that petitioner's case is of only having put its equipment on the property. Such an agreement does not require registration compulsorily. Even otherwise Division Bench of this court has held in N.I.I.T Institute of Information Technology v. West Star Construction Pvt Ltd MANU/DE/0485/2009 that an arbitration clause even in a lease deed requiring compulsory registration although not so registered can be implemented.

    7. As far as the request for impounding is concerned, stamp duty payable on an agreement of such nature is Rs 50/- and the counsel for the petitioner states that he shall deposit the maximum penalty. i.e ten times together with the deficiency in stamp duty with the Collector of Stamps within four weeks of today.

    8. As far as the plea of the agreement being abandoned is concerned that is on the merits of the dispute and cannot be gone into at this stage. There is no material before this court on the basis of which the said plea can be entertained at this stage.

    9. Accordingly, Justice Anil Dev Singh (Retd) is appointed as the arbitrator to adjudicate the disputes and differences in terms of the arbitration clause contained in the agreement aforesaid and further limited to the statement aforesaid of the counsel for the petitioner. The counsel for the parties to fix the fee and other expenses of the arbitrator in consultation with the arbitrator and to bear the same equally subject to award as to costs. The parties to appear before the arbitrator with prior appointment on 23rd October, 2009.

    RAJIV SAHAI ENDLAW, J.