Smart Summary

Factual and Procedural Background

The Delhi Development Authority ("DDA") awarded a contract by Agreement No. 3.EE/CPD.VI/85-86 to M/s A.R. Khanna and Sons (the "Contractor") for construction of a Local Shopping Centre at Lawrence Road. The contract specified commencement on 26.3.85 and completion by 25.9.85, and required the Contractor to submit structural drawings within 15 days and to commence work only after approval of those drawings by the Engineer Incharge.

The Contractor submitted designs on 18.4.85. The Contractor alleges that the DDA did not approve the structural drawings during the contractual period, and only intimated on 13.11.85 (after the completion date had passed) that approved foundation plans could be collected and instructed the Contractor to commence immediately. The Contractor maintained that the time for completion had expired on 24.9.85 due to the DDA's delay and that, because of a substantial rise in material prices, it would not execute the work at the original rates but was willing to do so at 78% above the estimated cost. The DDA refused and threatened to get the work executed at the Contractor's risk and cost; the contract was ultimately rescinded on 24.6.86 and awarded to another contractor at 82% above estimated cost.

The Contractor raised disputes which were referred to sole arbitration (Arbitrator: Shri O.P. Mittal, Chief Engineer (Retired), CPWD). By an award dated 1.8.88 the arbitrator accepted the Contractor's claims and dismissed the DDA's counter-claim. The instant opinion records the Court's consideration of that arbitral award and makes the award a rule of the Court, directing interest on the awarded amount and decree to be drawn.

Legal Issues Presented

  1. Whether the arbitrator's findings and award (which held that the DDA breached the contract by failing to approve structural designs during the currency of the contract and awarded various sums to the Contractor) suffer from any error apparent on the face of the award or are so perverse as to justify judicial interference.
  2. Whether the arbitral award should be made a rule of the Court and, if so, whether interest should be granted on the awarded amount and from what date.

Arguments of the Parties

Claimant / Contractor (M/s A.R. Khanna and Sons) — Position and Contentions

  • The Contractor submitted structural designs on 18.4.85 but did not receive approval during the contractual period; therefore, the DDA's delay prevented commencement and completion within the stipulated time (expiry asserted as 24.9.85).
  • Because of an unprecedented rise in material prices, the Contractor refused to perform at the original rates and offered to perform the work at 78% above the previous estimated cost.
  • The Contractor claimed various heads of loss and expenditure made infructuous due to non-execution (earnest money/security deposit, preparation of drawings, dismantling of bore well, temporary stores, fencing, bricks loss, wages for Munshi and Chowkidar, etc.), and sought relief via arbitration.

Respondent / DDA — Position and Conduct as Recorded

  • The DDA did not approve the structural designs during the contract period but later intimated availability of approved foundation plans on 13.11.85 and directed immediate commencement.
  • The DDA threatened to get the work executed from another contractor at the risk and cost of the Contractor and ultimately rescinded the contract on 24.6.86, awarding the work to another contractor at a higher rate.
  • The DDA raised a counter-claim before the arbitrator, which the arbitrator dismissed (the opinion does not set out detailed legal arguments advanced by the DDA on the counter-claim).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
State of U.P. v. Allied Constructions, JT 2003 (7) SC 273 Articulates the limited scope of judicial interference with an arbitral award: courts should not reappraise evidence or interfere unless the award is based on a wrong proposition of law, is totally perverse, or contains an error apparent on the face of the record. The Court applied this principle to uphold the arbitrator's award, finding the arbitrator's view to be a plausible one and no perversity or error apparent on the face of the award; therefore the Court declined to disturb the award and made it a rule of Court.

Court's Reasoning and Analysis

The Court reviewed the factual findings by the arbitrator and the legal standard governing interference with arbitral awards.

  1. Factual summary accepted from the arbitrator: designs were submitted on 18.4.85 and the design calculations were received by DDA on 30.4.85. The work was administratively transferred between DDA divisions which delayed approval, and approved designs were not handed to the Contractor during the six-month construction period. On 13.11.85 the DDA told the Contractor to commence, but by then the Contractor had already taken steps to dismantle site installations and had notified the DDA of the expiry of the contractual completion date (24.9.85). The contract was rescinded on 24.6.86 and re-awarded after tender at 82% above estimated rates.
  2. The arbitrator concluded (and the Court recounts) that the Contractor was justified in refusing to complete the work at the original rate because the DDA breached the contract by not approving the structural designs within the contract period. The arbitrator also noted that the Contractor had offered to perform at 78% above original rates while the DDA later awarded the job at an even higher rate (82% above).
  3. The Court analyzed whether there was any ground to interfere with the arbitral award. It indicated the settled principle (citing State of U.P. v. Allied Constructions) that courts will not reappraise evidence or scrutinize the sufficiency of an arbitrator's reasons unless the award is perverse or contains an apparent error on its face.
  4. Applying that standard, the Court found two clear reasons given by the arbitrator for awarding the Contractor's claims: (i) DDA's delay in approving designs caused non-commencement during the contractual period, and (ii) the Contractor had offered to perform at a lower enhanced rate than that at which the DDA ultimately re-awarded the contract. The Court found these reasons non-perverse and plausible.
  5. As to Claim No. 8 (pendente lite interest), the opinion notes the general principle from higher authority that arbitrators are not competent to award pendente lite interest when the reference is not made through a court. The arbitrator's award on other heads was nevertheless sustained.
  6. On this basis, the Court concluded there was no infirmity in the award and proceeded to make the award a rule of the Court, awarding interest on the awarded amount at 6% per annum from the date of the award until realization and directing that a decree be drawn accordingly.

Holding and Implications

Holding: The arbitral award dated 1.8.88 in favour of the Contractor is upheld and made a rule of the Court; the suit is decreed.

Direct consequences and orders (as recorded in the opinion):

  • The Court sustained the arbitrator's awards on the various claims put forward by the Contractor (the opinion sets out the arbitrator's specific monetary awards under each claim).
  • The Contractor is entitled to interest on the awarded amount at 6% per annum from the date of the arbitral award until realization.
  • A decree is to be drawn in accordance with the award; the suit is decreed.

Broader implications:

The opinion applies established principles limiting court interference with arbitral awards (as cited from the Supreme Court). The opinion does not purport to lay down any new legal precedent; it enforces the existing arbitral award by making it a rule of Court and provides for interest and decree as a direct consequence for the parties.

Annex — Awards Noted by the Arbitrator (as recorded)

The arbitrator's awards (figures recorded in the opinion) included the following items (the Court sustained these awards):

  • Refund of earnest money/security deposit: Rs. 10,000/-
  • Preparation of drawings/details: Rs. 4,000/-
  • Dismantling of bore well/depreciation of pipes: Rs. 2,300/-
  • Dismantling of temporary store/depreciation of sheets/bricks etc.: Rs. 3,550/-
  • Dismantling of barbed wire fencing/depreciation: Rs. 2,650/-
  • Cartage and loss of bricks (83,460 carted; 15,000 lost/wastage): Rs. 10,340/-
  • Charges for Munshi and Chowkidar (reduced on assessment): Rs. 4,800/-
  • Claim for pendente lite interest: addressed by reference to authority that arbitrators cannot award pendente lite interest when reference is not through a court (the opinion records this legal position).

Note: This summary is prepared exclusively from the text of the provided opinion and does not add information beyond what the opinion itself contains.

    A.R Khanna And Sons v. Delhi Development Authority & Anr.

    Rekha Sharma, J.— The Delhi Development Authority (in short called DDA) vide Agreement No. 3.EE/CPD.VI/85-86 awarded the work of construction of Local Shopping Centre at Lawrence Road to M/s. A.R Khanna and Sons (hereinafter called the Contractor). It was stipulated in the agreement that the work was to commence on 26.3.85 and was to be completed by 25.9.85 It was also stipulated that the contractor was to submit structural drawings within 15 days of the award of the work and the work was to be commenced only after receiving approval of the structural drawings from the Engineer Incharge of the work.

    2. It is the case of the contractor that the designs were submitted to the DDA on 18.4.85 for approval but no approval of the same was received during the currency of contract. It was only on 13.11.85 after the date of completion of the work had expired that the DDA informed the contractor that approved foundation plans could be collected from its office and directed it to commence the work immediately. The contractor on being so informed intimated to the DDA that the stipulated time for completion of the work had expired on 24.9.85 for which the DDA alone was responsible because of the late approval of the structural designs at its end. The contractor also intimated that during all this period there had been an unprecedented rise in the prices of the material and therefore it was not willing to execute the work at old rates but was prepared to undertake the same at 78% above the previous estimated cost. This was not acceptable to the DDA. It threatened to get the work executed from elsewhere at the risk and cost of the contractor and gave effect to its threat on 24.6.86 by awarding the work to another contractor.

    3. Feeling aggrieved by the action of the DDA the contractor raised disputes which were referred to the sole arbitration of Shri O.P Mittal, Chief Engineer (Retired) CPWD who, vide his award dated 1.8.88, accepted the claims of the contractor and dismissed the counter-claim of the DDA which it had raised against the contractor.

    4. The arbitrator before giving his findings against the claim raised by the contractor gave a brief summary of facts which led to the cancellation of the contract. This is what the arbitrator said:

    According to the arbitrator the designs were submitted by the contractor on 18.4.85 and the design calculations were received by the DDA on 30.4.85 Originally the work was under DDA Division No. CPD. VI but subsequently orders were issued on 29.4.85 to transfer the work to Housing Division No. V of DDA. However, the actual transfer took place by about 30.5.85 Due to the fact that the work was transferred to another division the relevant action to approve the design was dislocated and during the entire period of six months of construction time the approved designs were not given to the contractor. On 13.11.85 the DDA intimated to the contractor that the approved foundation plans could be collected from its office and directed the contractor to commence the work immediately. Before this happened, on 9.11.85, the contractor had intimated to the Executive Engineer that the stipulated time for completion of the work had expired on 24.9.85 and the DDA was guilty of breach of contract in not approving the designs for the work. The contractor also intimated that he would commence dismantling of temporary stores constructed at site, the bore-well, the barbered wire fencing and remove other materials from 10.11.85 On 4.12.85 the contractor intimated to the DDA that the stipulated time for completion of work expired on 24.9.85 and it was the DDA which was responsible for breach of the contract. It further intimated that there was an unprecedented rise in the prices of materials and that it was prepared to commence the work at 78% above the estimated cost. On the other hand, the Executive Engineer served notices under Clause 3 of the contract and thereby threatened to get the work executed from another person at the risk and cost of the contractor. Ultimately the contract was rescinded on 24.6.86 and the work was awarded to another contactor at 82% above the estimated cost.

    5. Having noticed the above facts, the arbitrator came to the conclusion that the contractor was justified in not completing the work at the agreed rate as breach was committed by the DDA because of its failure to approve the structural designs during the currency of the contract. He also observed that the work was awarded to another contractor after call of open tenders at 82% above the estimated rates, whereas the contractor, was willing to perform the same contract at 39.38% above the estimated cost. Having so observed the arbitrator proceeded to accept the following claims of the contractor.

    Claim No. 1:

    6. Claimants claim Rs. 10,000/- towards refund of earnest money/security deposit.

    7. An amount of Rs. 10,000/- was deposited by the claimants as earnest money. The respondents have forfeited the above amount since the claimant did not execute the work. I have already decided that the breach was committed by the respondents and claimant was entitled to claim damages. I decide the forfeiture of the earnest money is not justified. The respondent should refund the amount of Rs. 10,000/- (Rupees ten thousand only) to the claimants. Claim No. 2. Claimants claim Rs. 5,100/- towards preparation of drawings/details.

    8. As per terms of the contract the claimants got the foundation and structural drawings prepared for the work from a structural Engineer. The expenditure became infructuous because the work was not executed. I decide the claim of the claimant is justified. I assess the justified amount to be Rs. 4,000/-. The respondents should pay an amount of Rs. 4,000/- (Rupees four thousand only) to the claimants against the above claim. Claim No. 3. Claimants claim Rs. 2,780/- towards dismantling of 80 ft. boring/depreciation of the pipes.

    9. For the execution of the work and obtaining construction water a bore well was provided by the claimant. This also became infructuous. I assess the claim is justified for Rs. 2,300/- only. I award the respondent should pay an amount of Rs. 2,300/- (Rupees two thousand three hundred only) to the claimants.

    Claim No. 4:

    10. Claimants claim Rs. 5,600/- towards dismentling of store/depreciation of the sheets/bricks, etc.

    11. For storing cement and for a temporary office at the site, temporary buildings were constructed by the claimants. The roof was provided in AC sheets. Since the work could not be executed the expenditure became infructuous. I assess the claim is justified for Rs. 3,550/-. I award the respondent should pay an amount of Rs. 3,550/- (Rupees three thousand five hundred fifty only) to the claimants.

    Claim No. 5:

    12. Claimants claim Rs. 2,650/- towards dismantling of barbed wire fencing depreciation of barbed wire.

    13. The place where the shopping centre was to be constructed was occupied by the vegetable sellers. The claimant was advised by the Executive Engineer to provide barbed wire fencing so that the construction may not be in interrupted by the vegetable sellers. Since the work was not executed the barbed wire fencing was dismantled and removed. The expenditure is justifiably claimed by the claimants. I assess and award that the respondents should pay an amount of Rs. 2,650/- (Rupees two thousand six hundred fifty only) to the claimants.

    Claim No. 6:

    14. Claimants claim Rs. 11,335/- towards cost of 83,000 bricks taken over back and 15,000 bricks because of wastage and theft.

    15. The claimant arranged about 1 lac bricks for the execution of the work. When the work could not be commenced, 83,460 bricks were carted to another work by the claimant. About 15,000 bricks were wasted. It is normal that when the bricks are obtained and stacked at site and later when these have to be again removed to another site about 15% bricks get broken into brick bats and are lost. I decide that the claimant is entitled to cartage of 83,460 bricks and the loss due to wastage of 15,000 bricks. I assess and decide that the claim is admissible for Rs. 10,340/- after allowing deduction for the residual value of brick-bats. The respondents should pay an amount of Rs. 10,340/- (Rupees ten thousand three hundred forty only) to the claimants.

    Claim No. 7:

    16. Claimants claim Rs. 9,000/- towards charges paid for Munshi and Chowkidar.

    17. The claim for employing Chowkidars and Munshi is justified. But the claimant should have economized on the cost due to Munshi when the work did not commence. I assess the claim is justified for Rs. 4,800/- only. I award the respondent should pay an amount of Rs. 4,800/- (Rupees four thousand eight hundred only) to the claimants.

    Claim No. 8:

    18. Claimants claim pendente lite interest.

    19. As per the latest decision of the Supreme Court the arbitrators are not competent to award pendente lite interest, when the case is referred not through the Court of law.

    20. This is an award which has been made under the Arbitration Act, 1940. It is well settled by a catena of judgments of the Supreme Court as well as by this Court that unless an error apparent on the face of the award is discernable from the award itself the Courts would be loathe to interfere in the same. It has also been held that if the award is a speaking award and the arbitrator has given his reasons for awarding what he has awarded the Courts will not go into the sufficiency of the reasons or even into the validity and legality of the reasons unless they are so perverse that no reasonable person would have arrived at the findings at which the arbitrator had arrived. I may in this context refer to the following paragraph from the judgment of the Apex Court State Of U.P v. Allied Constructions., JT 2003 (7) SC 273:

    “The arbitrator is a Judge chosen by the parties and his decision is final. The Court is precluded from reappraising the evidence. Even in a case where the award contains reasons, the interference therewith would still be not available within the jurisdiction of the Court unless, of course, the reasons are totally perverse or the judgment is based on a wrong proposition of law. An error apparent on the face of the records would not imply closer scrutiny of the merits of documents and material on record. Once it is found that the view of the arbitrator is a plausible one, the Court will refrain itself from interfering.”

    21. Here, is a case where the arbitrator has given two reasons for awarding the claims in favour of the contractor. Firstly, that it was because of the delay on the part of the DDA in not approving the designs that the contracted work could not be commenced during the currency of the contract period. And secondly, that the contractor nevertheless was prepared to undertake the work at 78% over and above the original rates to which the DDA did not agree but when it actually awarded the contract to another contractor it was at a higher rate than at which the contractor was prepared to execute the contract.

    22. I find no infirmity in the reasoning and consequently no error in the award. The award is thus made a rule of the Court. The contractor shall be entitled to interest on the awarded amount @ 6% per annum from the date of the award till realization. Decree be drawn accordingly.

    Suit decreed.