  • Sections 4, 6 and 17 of the Land Acquisition Act, 1894 (hereinafter
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Sections 4, 6 and 17 of the Land Acquisition Act, 1894 (hereinafter
Smart Summary

Factual and Procedural Background

The appellants owned land measuring approximately 55 bighas and 6 biswas in Village Sabhapur, which was acquired under notifications issued pursuant to Sections 4, 6, and 17 of the Land Acquisition Act, 1894. The Land Acquisition Collector passed an Award on 19.09.1986, granting compensation at Rs. 12,000 per bigha. Dissatisfied parties sought a reference, resulting in a judgment dated 11.03.1993 by the Additional District Judge, which increased the compensation to Rs. 21,500 per bigha. The appellants filed an appeal against this order, but it was delayed and accompanied by an application for condonation of delay. This application was dismissed for non-prosecution in 1994, leading to dismissal of the appeal.

For nearly a decade, the appellants took no action until 2004, when they became aware of the dismissal and engaged new counsel. Subsequent applications were filed for condonation of delay, restoration of the appeal, and impleadment of the legal heirs of a deceased appellant. These applications faced procedural delays and deficiencies but were eventually listed before the Court.

Legal Issues Presented

  1. Whether the delay in filing the appeal and subsequent applications for restoration and impleadment should be condoned.
  2. Whether the appeal should be restored and allowed on merits despite procedural lapses.
  3. Determination of the appropriate quantum of compensation payable to the appellants for the acquired land.
  4. Whether the appellants are entitled to interest on the compensation amount during the period of delay in prosecution.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court analyzed the procedural history and noted the appellants' failure to prosecute the appeal timely, resulting in dismissal for non-prosecution. It acknowledged the appellants' long period of inaction but considered that the delay in filing the original appeal was not excessive. The Court emphasized that any negligence by prior counsel was a matter for the appellants to address separately. Importantly, the Court was persuaded by the fact that the quantum of compensation had been subsequently determined by this Court at Rs. 27,000 per bigha, which favored the appellants.

The Court therefore exercised its discretion to condone the delay in prosecuting the appeal and related applications. It imposed costs on the appellants for delay in restoration but allowed the appeal to proceed on merits. The Court further conditioned that the appellants would not claim interest on the compensation amount for the period from three months after the impugned decree till the date of this judgment.

Holding and Implications

The Court allowed the appeal and related applications for condonation of delay and restoration.

The appeal was allowed in terms of the enhanced compensation fixed at Rs. 27,000 per bigha. The appellants were directed to bear costs for the delay in restoration, and they waived any claim to interest on compensation for the period of delay. The parties were left to bear their own costs otherwise. No new precedent was established; the decision primarily restored the appellants' right to compensation with conditions reflecting procedural lapses and equitable considerations.

    Yad Ram & Ors v. Union Of India & Anr

    B.C Patel, C.J (Oral):— The land of the appellants measuring approximately 55 bighas and 6 biswas located in Village Sabhapur was acquired in pursuance to the notification dated 10.08.1983 issued under Sections 4, 6 and 17 of the Land Acquisition Act, 1894 (hereinafter to be referred to as, ‘the said Act’).

    2. The Award was passed by the Land Acquisition Collector on 19.09.1986 in terms whereof the appellants were held entitled to compensation @ Rs. 12,000/- per bigha. The parties aggrieved by the said Award sought a reference, which was decided in terms of the impugned judgment of learned Additional District Judge dated 11.03.1993

    3. It may be noticed that there were some inter-se disputes between the parties about the respective shares, which, however, stood determined in pursuance to the reference made under Section 30/31 of the said Act.

    4. In terms of the impugned judgment and decree, the rate of compensation was determined at Rs. 21,500/- per bigha. The appellants, still aggrieved by the order of the Reference Court, preferred the present appeal.

    5. The appeal was filed beyond time and, thus, along with the appeal, an application being CM No. 1347/1993 was filed for condonation of delay in filing the appeal. The appeal was listed on 14.09.1993 when notice was issued in the application for condonation of delay. The respondents were served for the next date of 07.02.1994 and time was granted to the respondents to file reply. No reply was, however, filed and the application was listed on 24.08.1994 On the said date, neither counsel for the appellant nor counsel for the respondent appeared even at the second call and, thus, CM No. 1347/1993 was dismissed for non-prosecution. The result of dismissal of the application was that the appeal was consequently dismissed.

    6. There was silence on the part of the appellants for almost a decade and it appears that only when the issue of compensation in respect of the same very Award was determined in RFA No. 545/1993 titled ‘Mangal Singh v. Union of India’ decided on 18.03.2004 that the appellants apparently sought to take steps as to why they were not being paid the amount. It is stated at that stage that the appellants came to know of dismissal of the appeal for non-prosecution and the counsel appearing for the appellants never informed the appellants about the same nor did the counsel chose to appear on the date fixed. A new counsel was appointed to find out the facts and thereafter moved the applications in the year 2004 for condonation of delay in moving the application for restoration of the appeal, the application for restoration of the appeal, the application for impleadment of legal heirs of one of the appellants Shri Brahm Pal, who was since deceased having passed away on 13.09.1998 and for condonation of delay in moving the application for impleadment of legal heirs.

    7. The matter did not rest at this since no steps were even taken to prosecute these applications as a result of which the matter was listed before the Court on 26.07.2004 The appellants were directed to take steps within a week, failing which the matter would automatically stand dismissed. It is only thereafter the steps were taken. There was some deficiency in the court fee filed thereafter. It is all these applications and the RFA which have now been listed before the Court.

    8. A perusal of the explanation given in these applications really gives no justification for the manner in which the appeal and the applications have been prosecuted. If the appellants are aggrieved by the manner of prosecution of the appeal and the application, it was for the appellants to take steps against the person who was negligent in this behalf. The only factor, which weighs with us, is that undoubtedly the appellants have affixed court fee and filed the appeal, which itself was not within time, but the delay is not inordinate in filing the appeal. The quantum of compensation now stands determined by this Court at Rs. 27,000/- per bigha. It is this factor, which is persuading us to pass the orders in this matter as hereinafter, especially in view of the fact that learned counsel for the appellants states that the appellants be burdened with some costs and the appellants will not claim any interest for the period the appellants have failed to prosecute the appeal, which is from the original date till date.

    9. In view of the aforesaid, CM No. 1347/1993 for delay in prosecuting the appeal is allowed and the delay is condoned.

    10. CM No. 4332/2004 being the application for delay in filing the application for restoration is also allowed subject to payment of Rs. 5,000/- as costs to Delhi High Court Bar Association for Law Library.

    11. CM No. 4333/2004 being the application for restoration of the appeal to its original number is also allowed.

    12. In view of the demise of Shri Brahm Pal, one of the appellants, on 13.09.1998, CM No. 6352/2004 is allowed as the same is supported by the affidavits and the death certificate of the deceased. All the legal heirs mentioned in para 2 of the application are brought on record. The delay in filing this application stands condoned and the application being CM No. 6353/2004 also stands allowed.

    13. Amended memo of parties be filed within 3 days.

    14. CM No. 1348/1993 also stands allowed subject to just exceptions.

    15. In so far as RFA is concerned, the appeal is allowed in terms of the judgment in Mangal Singh's case (supra) determining the compensation @ Rs. 27,000/- per bigha subject to the condition that the appellants shall not be entitled to interest from the date of expiry of three months from the impugned judgment and decree till date.

    16. The appeal is accordingly allowed leaving the parties to bear their own costs.