  • section 230A, permission from the Urban Land Ceiling & Regulation Authority
  • Order 39 Rules 1 & 2) and I.A No. 6782/98 (Under Order 39 Rule 4).2.
  • Section 230A, from the Urban Land Ceiling and Regulation
  • Order 39, Rule 4 CPC
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • section 230A, permission from the Urban Land Ceiling & Regulation Authority
  • Order 39 Rules 1 & 2) and I.A No. 6782/98 (Under Order 39 Rule 4).2.
  • Section 230A, from the Urban Land Ceiling and Regulation
  • Order 39, Rule 4 CPC
Smart Summary

Summary of the Opinion (Dalveer Bhandari, J.)

Factual and Procedural Background

The suit was registered on 14 July 1998. On that date, while issuing summons to the defendants, the Court granted an ad interim ex parte injunction restraining Defendant No. 1 from selling the property in question to Defendant No. 4. The injunction application later came up for confirmation/vacation after service on the defendants. The defendants filed written statements and a reply to the plaintiff's interlocutory application; the plaintiff filed a reply to the defendants' application under Order 39 Rule 4 CPC.

The dispute concerns the proposed sale of freehold property bearing No. 43, Friends Colony (East), New Delhi (3860 sq. yds., with buildings) from Defendants Nos. 1–3 to the plaintiff (J.K. Industries Ltd.). The plaintiff sent an offer by letter dated 15 April 1998 proposing purchase at Rs. 13.5 crores (later revised to Rs. 14 crores), subject to the defendants obtaining necessary permissions (including under Chapter XXC of the Income Tax Act and Section 230A, and from the Urban Land Ceiling & Regulation Authority) and producing relevant documents. The defendants replied by a letter dated 24 April 1998 accepting the revised price of Rs. 14 crores with conditions about payment (10% on signing the agreement; balance 90% within three months after agreement). The plaintiff alleges these communications, plus the subsequent exchange of documents and correspondence (including a letter of 26 May 1998), show a concluded contract, and seeks confirmation of the injunction. The defendants contest that a concluded contract exists and maintain the matter remained in negotiation.

Legal Issues Presented

  1. Whether, on the materials before the Court (notably the letters of 15.4.1998, 24.4.1998 and 26.5.1998 and the documents exchanged), a concluded contract between the plaintiff and the defendants had come into existence.
  2. Whether the ad interim ex parte injunction granted restraining Defendant No. 1 from selling the property should be confirmed or vacated pending the suit.
  3. Whether the balance of convenience and the prospect of irreparable injury favored confirmation of the injunction.

Arguments of the Parties

Plaintiff's Arguments (as advanced by Mr. Rohtagi and Mr. O.P. Khaitan)

  • The offer by the plaintiff dated 15.4.1998 was accepted by defendants by the letter dated 24.4.1998 (which confirmed Rs. 14 crores and payment terms), and thereafter parties finalised the draft Agreement for Sale at a meeting — thus a concluded contract existed and only formal documentation remained.
  • The defendants furnished copies of extensive property documents in response to the plaintiff's offer, which supports that the offer was accepted and the contract was concluded.
  • The plaintiff was ready and willing to perform (earnest money available; money lying idle), and all material and essential terms (price, area, payment timing) were agreed.
  • If defendants were permitted to sell/dispose of the property after the concluded contract, irreparable harm to the plaintiff would result and the suit's purpose would be vitiated; hence injunction should be confirmed.
  • Relied on precedents (J.K Rajgarhia v. Dr. Ravi Singh; Kollipara Sriramulu v. T. Aswathanarayana; Ram Krishan Singhal v. Executive Engineer) to submit that reference to execution of a formal document does not defeat a binding agreement where parties intended to be bound.

Defendants' Arguments (as advanced by Mr. Sethi and Mr. V.N. Kaura)

  • There was no concluded contract; the parties were at the negotiation stage and the correspondence amounted at best to a counter-offer or conditional acceptance.
  • The total area mentioned (3860 sq. yds.) included an excess area subject to urban land ceiling (360 sq. metres noted as in ceiling), which the defendants could not validly sell — this calls into question the existence of a concluded contract for the entire area.
  • Material terms differed between the letters: the plaintiff's letter said balance 90% to be paid at time of execution of the agreement, while the defendant's acceptance required outright payment of 90% within three months after the agreement — showing material disagreement on terms.
  • It was not decided in whose favour the conveyance would be executed; no clear authorization of particular trustees to act was shown (trust matters), and even a concluded contract does not automatically entitle the plaintiff to specific performance — relief is discretionary.
  • Relied on precedents (Shamjibhai v. Jagoo Hemchand; Ganesh Shet v. Dr. C.S.G.K. Setty; R. Venugopala Naidu v. Venkatarayulu Charities) to support that (i) sale contracts commonly have stages and a formal document may be intended as a crucial stage, and (ii) relief may be refused in trust/public charitable trust contexts or where no proper authorization exists.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
J.K. Rajgarhia v. Dr. Ravi Singh & Ors., 1995 (34) DRJ 199 Examines whether intention to execute a formal document is a condition precedent or merely an intention to formalise an already concluded agreement; focus on parties' intention and whether any material term was left for negotiation. Relied upon by the plaintiff's counsel; the principle was considered by the Court in assessing whether a concluded contract existed on the facts before it.
Kollipara Sriramulu v. T. Aswathanarayana & Others, 1968 (3) SCR 387 States that reference to a future formal contract does not prevent existence of a binding agreement unless the parties clearly intended not to be bound until a formal contract was signed; the question turns on parties' intention and circumstances. Relied upon by the plaintiff's counsel; the Court considered this principle in deciding that a prima facie binding agreement existed for the purposes of interim relief.
Ram Krishan Singhal v. Executive Engineer, (1991) 1 Arbitration Law Reporter 154 Holds that formal signing is not necessary for a contract to be concluded and that contracts can be formed by exchange of letters. Cited by the plaintiff's counsel; the Court considered the proposition that an exchange of letters could constitute a binding contract when evaluating the prima facie case.
Shamjibhai v. Jagoo Hemchand & Others, AIR 1952 Nagpur 220 Explains the three stages commonly present in land sale negotiations: (1) negotiation, (2) agreement (possibly reduced to writing but with intention not to be bound till formal document), (3) execution of formal document; which stage is binding depends on construction of facts. Relied upon by the defendants' counsel to argue that the case remained in the negotiation stage; the Court considered this framework in evaluating competing contentions on whether binding agreement existed.
Ganesh Shet v. Dr. C.S.G.K. Setty & Ors., (1988) 5 SCC 381 Authority on formation of contracts and the significance of parties' intention concerning formal documentation. Cited by the defendants' counsel; the Court took into account the authority while assessing whether parties intended to be bound prior to execution of a formal agreement.
R. Venugopala Naidu & Others v. Venkatarayulu Charities & Others, AIR 1990 SC 444 Concerns discretionary reliefs (such as specific performance or injunction) in the context of trusts and charitable bodies, touching on trustees' authority and court discretion. Cited by Defendant No. 4's counsel to underline discretionary nature of relief in trust contexts; the Court considered this submission in the balance of arguments but granted interim relief on prima facie considerations.

Court's Reasoning and Analysis

The Court examined the sequence of communications and materials placed before it: the plaintiff's offer dated 15.4.1998, the defendants' reply dated 24.4.1998 accepting Rs. 14 crores with stated payment conditions, the production by defendants of copies of relevant property documents, and the plaintiff's subsequent letter dated 26.5.1998 stating that the draft Agreement for Sale had been discussed in detail and finalised.

The Court addressed the key factual and legal contentions advanced by both sides:

  • For the plaintiff, the exchange of letters, the defendants' provision of the property-related documents, and the meeting where the draft agreement was finalised evidenced that all material terms had been agreed and that only formal documentation remained to be executed.
  • For the defendants, material disputes remained (e.g., differences in the timing of payment of the balance 90%, the question of saleability of an excess area subject to urban land ceiling, and uncertainty as to in whose favour the conveyance would be executed), and the correspondence could be a counter-offer or conditional acceptance rather than a final acceptance.

The Court considered the authorities cited by both sides regarding when a contract is to be treated as concluded in the face of references to a future formal document. Applying those principles to the materials before it, the Court found that, on the totality of circumstances and at the prima facie stage, the evidence favored the plaintiff: the parties had agreed on the price and other material terms, the defendants furnished documents, and the plaintiff had demonstrated willingness and ability to perform (earnest money available).

On balance, the Court concluded that a strong prima facie case had been made out by the plaintiff and that the balance of convenience lay in the plaintiff's favour. The Court therefore decided that the ad interim ex parte injunction should be confirmed pending the suit.

Holding and Implications

Holding:

The ad interim ex parte injunction is confirmed for the pendency of the suit; the plaintiff's injunction application is allowed and disposed of, and the defendants' application under Order 39, Rule 4 CPC is dismissed.

Direct consequences and procedural directions:

  • The defendants are restrained as per the confirmed injunction (the original injunction had restrained Defendant No. 1 from selling the property to Defendant No. 4).
  • The defendants' application under Order 39 Rule 4 CPC is dismissed; the parties are directed to bear their own costs.
  • The parties are permitted to file additional documents within four weeks. The suit is to be listed for admission/denial of documents before the Joint Registrar on 21 July 1999, and the Joint Registrar is directed to place the matter before the Court for framing of issues immediately after admission/denial is concluded.

The opinion does not announce a broad new precedent; its effect as recorded is the confirmation of interim relief on the facts and prima facie assessment before the Court.

    J.K. Industries Limited v. International Cooperative Alliance Domus Trust

    Dalveer Bhandari, J.— This order will dispose of IA No. 5583/98 (Under Order 39 Rules 1 & 2) and I.A No. 6782/98 (Under Order 39 Rule 4).

    2. The suit was registered on 14th July, 1998 and on that date while issuing summons to the defendants this Court also granted ad interim ex parte injunction restraining defendant No. 1 from selling the property in question to the defendant No. 4. This injunction application has now come up after the service of the defendants for confirmation/vacation of the injunction order. The defendants have filed a written statement and reply to I.A No. 5583/93 and the plaintiff has filed reply to I.A No. 6782/98.

    3. The plaintiff agreed to purchase the property bearing No. 43, Friends Colony (East), New Delhi from defendants Nos. 1 to 3 for a sale consideration of Rs. 13.5 crores for the entire plot area measuring 3860 Sq. Yds. alongwith all the buildings and structure constructed thereon subject to the defendants obtaining necessary permission under Chapter XXC of the Income Tax Act and permission from the Income Tax Authority under Section 230A, from the Urban Land Ceiling and Regulation Authority. It is the further case of the plaintiff that by a letter dated 15.4.1998, the terms of sale were conveyed to defendants Nos. 1 to 3. The letter dated 15.4.1998 reads as under:

    J.K INDUSTRIES LIMITED

    3, Bahadurshah Zafar Marg,

    New Delhi-110002

    April 15, 1998.

    Fax Msg Fax No. 6835568

    M/s International Co-operative Alliance

    Bonow House,

    43, Friends Colony (East)

    New Delhi-110065.

    Kind Attn.: Mr. Guo Yong Kang

    Dy. Regional Director.

    Dear Sirs,

    Re: Freehold property bearing No. 43 Friends Colony (East),New Delhi-110065 admeasuring 3860 Sq. Yds. alongwith Buildings and other structures constructed thereon.

    Please refer to the discussion we had with your Mr. Kang this morning. We are in principle agreeable to purchase the aforementioned property for a total consideration of Rs. 13.5 Crore (Thirteen and half crore) for the entire plot Area of 3860 Sq. Yds. alongwith all Building and structures constructed thereon subject to inter alia, the following conditions:

    1. That you shall make out a good and marketable title in respect of the said property free from all encumbrances, liens and lis pendence

    2. You shall obtain all necessary permissions and approvals including the permission from the appropriate Authority under Chapter XXC of the Income Tax Act, permission from the Income Tax Authority under section 230a, permission from the urban land ceiling & regulation authority and any other authority that may be necessary for selling the same to us.

    3. We confirm that the entire payment to you would be by cheque.

    4. We confirm that we would pay 10% of the total consideration amount at the time of signing the Agreement for Sale Balance 90% would be paid at the time of Conveyance in our favour alongwith vacant physical possession.

    5. You shall discharge all liability in respect of the said property till the date of conclusion of transfer.

    6. That if there are more than one authorised nominees of the trust, the agreement and the sale deed will be signed by all the authorised persons, on the above terms.

    We hope that, the above offer is acceptable to I.C.A Please convey your acceptance to finalise the terms of Agreement for Sale and time schedule for completing the entire transaction.

    In case the offer is acceptable, please furnish copies of all relevant documents and papers relating to the said property including Court papers, if any, to us for our perusal and verification.

    Thanking you,

    Yours faithfully,

    D.C Jain

    Authorised Signatory”

    4. The substance of this letter is that the plaintiff agreed to purchase the property in question for Rs. 13.5 Crores which of course was later on changed to Rs. 14 Crores. The entire area of 3860 Sq. Yds. is mentioned in the letter. It is also mentioned that the defendants shall obtain necessary permission and approval from the concerned authorities for sale of the property in question.

    5. It is also indicated that 10 per cent of the sale consideration amount shall be paid at the time of signing the agreement for sale and 90 per cent would be paid at the time of conveyance in favour of the plaintiff alongwith the vacant physical possession. In the letter it is mentioned that in case the offer is accepted to defendant Nos. 1 to 3 then they were required to furnish all relevant documents and papers relating to the said property including court papers for perusal and verification.

    6. It is further alleged by the plaintiff that in response to the offer of the plaintiff dated 15.4.1998 the defendant Nos. 1 to 3 accepted the same vide its letter dated 24.4.1998 The letter reads as under:

    ICA DOMUS TRUST

    (DR. BONOW MEMORIAL TRUST)

    Regd. Office: Bonow House,

    43, Friends Colony (East),

    New Delhi-110065. India.

    URGENT

    24th April, 1998.

    Fax: 91-113322059

    Messrs J.K Industries Limited,

    3, Bahadurshah Zafar Marg,

    New Delhi-10 002.

    Kind Attn.: Mr. D.C Jain, Vice President (Operations P & B).

    Dear Sirs,

    Sale of Bonow House, 43 Friends Colony (East), New Delhi-65.

    Further to the discussions with Mr. Guo Yong Kang, Deputy Regional Director, had with you on the 21st and 24th April, 1998 and your revised offer on your letter of 15th April, we wish to confirm that your final offer at Rs. 14 crores (Rupees Fourteen crores) is acceptable to us with the conditions that 10% down payment will be made by you at the time of signing the agreement and the balance 90% should be paid outright within three months after the agreement is signed.

    The draft of the agreement can be mutually discussed and finalised in early May 1998 in the presence of our legal advisers.

    Thanking you,

    Yours faithfully,

    Robby Tulus

    Authorised Representative of ICA DOMUS TRUST”

    7. In the said letter defendant Nos. 1 to 3 had mentioned that they (defendant Nos. 1 to 3) confirmed the final offer of Rs. 14 crores with the condition the 10 per cent down payment will be made by the plaintiff at the time of signing the agreement and the 90 per cent should be paid outright within three months from the agreement and the draft of the agreement was to be finalised in early May, 1998. According to Mr. Rohtagi, the learned Senior Counsel appearing for the plaintiff, the letter dated 24.4.1998 is clear acceptance of the offer dated 15.4.1998 sent by the plaintiff to the defendant in which it is also indicated that “this has reference to your letter dated 24.4.1998 confirming sale of the above property to us”. It is also mentioned in the letter that we have discussed in detail the draft agreement for sale and the same was finalised.

    8. Mr. Rohtagi submitted that in pursuance to the offer of the plaintiff vide letter dated 15.4.1998 the defendant has furnished copies of all relevant documents and papers relating to the said property which are as follows:

    1. Photocopy of the Board Resolution dated 22nd April, 1997 authorising Mr. Bobby Tulus and Mr. D.C Vishwanath with fair type copy.

    2. Photocopy of the order of the Competent Authority dated 6.3.1987 with fair type Copy.

    3. Photocopy of the notification dated 8.4.1987 issued by the Competent Authority with fair type copy.

    4. Photocopy of the Notification dated 8.4.1987 as published in the Delhi Gazettes.

    5. Photocopy of the Notification dated 22.5.1987 notifying that the excess land shall be deemed to have been acquired by the Delhi administration with effect from 21.6.1987 with fair type copy.

    6. Photocopy of the Application for permission to transfer of property No. 43 in favour of National Cooperative Development Corporation alongwith annexures.

    7. Photocopy of the Sale deed dated 11th/19th September, 1967 executed between Srenska Enterprenad Alticboiaget (SENTAB) and ICA Domus Limited.

    8. Photocopy of the Conveyance deed dated 25th September, 1962 between Mr. D.D Kapila & Inter Continent (Tranvancore) (P) Ltd.

    9. Photocopy of the House Tax Receipt dated 6th September, 1985 for Rs. 12,758/-

    10. Photocopy of the Sale Deed dated 2nd July, 1965 executed between Intercontinent (Tranvancore) (P) Ltd. N.D and Srenska Enterprenad Aktieboiaget (SENTAB) Bombay.

    11. Photocopy of the Settlement deed dated 31st July, 1990 by ICA Domus Ltd. in favour of ICA Domus Trust.

    12. Photocopy of the Power of Attorney dated 27th July, 1977 executed by ICA Domus Ltd. in favour of Mr. Rajaguru Bandara Rajaguru as the lawful attorney of the company.

    13. Photocopy of the Registered Sale Deed dated 15.9.1995 entered in between Nathuran Friends Colony Co-operative House Building Society Ltd. and Mr. D.D Kapila.

    14. Photocopy of the Agreement to sell dated 19th March, 1951 entered into between Friends Colony Co-operative House Building Society Ltd. and Shri D.D Kapila.”

    9. Mr. Rohtagi, the learned counsel for the plaintiff submitted that this fact further goes to show that the offer of the plaintiff was accepted by the defendant No. 1 and only formal documentation remained to be done. Otherwise, the defendant would not have furnished all these documents to the plaintiff. Mr. Rohtagi also submitted that the plaintiff was willing to perform his part of the contract and earnest money was readily available with the plaintiff. He also submitted that all material and essential terms were agreed between the parties and consequently the plaintiff's offer was accepted by the defendants and there was a concluded contract with the defendants and only formal documents had to be executed. It is also submitted by the plaintiff that the sale price of the property was clearly mentioned; and the time was also indicated, It was further agreed that 10 per cent amount shall be paid at the time of signing of the agreement for the sale and the balance 90 per cent was to be given at the time of execution of the conveyance alongwith the vacant physical possession of the property in question.

    10. In this view of the matter, the offer given by the plaintiff was accepted and a concluded contract between the parties came into existence. It only required formal solemnisation of the agreement.

    11. Mr. Rohtagi further submitted that at this stage he has to show only a strong prima facie case in his favour.

    12. Mr. Rohtagi also submitted that in case the defendant Nos. 1 to 3 are permitted to sell or dispose of the property after the concluded contract with the plaintiff, then irreparable harm and injury would be caused to the plaintiff and the whole purpose of filing the suit shall be vitiated and it would be virtually impossible to retrieve the property in question, whereas the defendants shall not be put to any irreparable harm or injury.

    13. Mr. Rohatgi submitted that in this view of the matter, the injunction granted in favour of the plaintiff be confirmed. Mr. Rohtagi placed reliance on the decided case of this Court J.K Rajgarhia. v. Dr. Ravi Singh & Ors.; reported in 1995 (34) DRJ 199. The facts of this case are quite akin to the facts of the case at hand. The relevant observation of the Court reads as under:

    “What is more material than the expression of desire by the parties to resort to a formal document, is the intention of the parties behind the expression of that desire. Was the desire to execute further contract a condition or term of the bargain or a mere expression of parties wish to formalise what had already been agreed upon? This would be the real question and to answer it one must know as to whether a material term had been left out for future negotiations between the parties or not.”

    According to Mr. Rohtagi, if this principle is applied in the present case, then it is clear that all material terms were agreed between the parties and nothing was left for the negotiations between them except to give formal shape to the agreement.

    14. Mr. Rohtagi submitted that in this view of the matter, there is acceptance of prima facie case in his favour. He also submitted that the balance of convenience is also in favour of the plaintiff and non-grant of injunction would result in irreparable injury and harm to the plaintiff. Whereas grant of injunction would not prejudice the interests of the defendants to that extent. In view of all these factors, the injunction granted by this Court should be made absolute. He also placed reliance on Kollipara Sriramulu v. T. Aswathanarayana & Others; 1968 (3) SCR 387. In this case, their Lordships of the Supreme Court have held as under:

    “A mere reference to a future formal contract does not prevent the existence of a binding agreement between the parties unless the reference to a future contract is made in such terms as to show that the parties did not intend to be bound until a formal contract is signed. The question depends upon the intention of the parties and the special circumstances of each particular case. In the present case the evidence did not show that the drawing up of a written agreement was a pre-requisite to the coming into effect of the oral agreement.”

    Mr. Rohtagi submitted that in view of this judgment also the injunction has to be confirmed.

    15. Mr. Rohtagi also cited Ram Krishan Singhal v. Executive Engineer; (1991 (1) Arbitration Law Reporter 154.) In this case it is held:

    “It is not necessary that a formal contract should have been signed by both the parties before a contract could be concluded. A contract can come in to existence by exchange of letters. A written binding contract has come into existence between the parties and there exists arbitration clause governing the disputes arising out of the contract.”

    On the strength of this case also the injunction has to be confirmed.

    16. Mr. Sethi, the learned counsel appearing for defendant Nos. 1 and 2 submitted that there was no concluded contract between the parties and the matter was only at a negotiation stage. In this view of the matter, the plaintiff is not entitled to the injunction and this ad interim ex-parte injunction already granted is liable to be vacated.

    17. Mr. Sethi submitted that the total area of the land in question is 3860 Sq. Yds. whereas out of that 360 Sq. Metres is in ceiling and the defendants could not have sold this land to the plaintiff because it was an excess land. The plaintiff had mentioned about 3860 Sq. Yds in the offer dated 15.4.1998 Therefore, when the defendant could not sell the aforesaid area being an excess area, how could there be a concluded contract between the parties? He submitted that both the letters dated 15.4.1998 and the so called acceptance letter dated 24.4.1998 do not mention that the agreement will be executed with the plaintiff and his nominees. Whereas now the plaintiff is insisting that the agreement be executed with the plaintiff and his nominees.

    18. It is submitted that the letter dated 24.4.1998,at best can be considered as a counter offer from the side of the defendants or at the most a conditional acceptance of the contract but it cannot be termed as a concluded contract between the parties.

    19. Mr. Sethi mentioned that according to the letter of 15.4.98 the balance 90% amount was to be paid at the time of the execution of the agreement, whereas according to the letter dated 24.4.1998 the balance 90% amount had to be paid within three months of the execution of the agreement. Since the material terms were not accepted by the letter dated 24.4.1998, therefore, there is no question of a concluded contract between the parties.

    20. Mr. Sethi also submitted that it was also not decided by the defendants in whose favour the conveyance deed was to be executed. In these circumstances it cannot be said that there was a concluded contract between the parties. The whole matter between the parties was at a negotiation stage and the concluded contract never came into existence.

    21. He also referred to the letter dated 26.5.1998 sent by the plaintiff to the defendants. According to him, if this letter is comprehended properly then it gives a clear impression that there was no concluded contract between the parties.

    22. Mr. Sethi has filed a compilation of seven judgments but, during the course of arguments has placed reliance on two judgments only. He placed strong reliance on the Full Bench judgment Shamjibhai v. Jagoo Hemchand and others (AIR 1952 Nagpur 220). The relevant paras of this judgment read as under:—

    “(9) Many contracts, & particularly contracts for the sale & purchase of land, have three well defined stages, & it is always a matter for construction, when these three stages are present as to which the parties intended to be the crucial stage at which both sides are to be bound.

    (10) The first of these stages is the period of negotiation in which suggestion & counter-suggestions are bandied to & fro. Naturally this can either be oral or by letter. When this stage is concluded, we reach the second stage at which the parties have reached agreement. At this point they can either settle the matter finally or, as is more usual in contracts of this type, reduce their points of agreement to writing & agree to have them drawn up in a formal document by their legal advisers & agree not to be bound till they have signed that formal document. The execution of the formal document is the third stage. Which of these stages is intended to be the crucial one is a matter of construction & must depend on the facts of each particular case…..”

    23. Mr. Sethi also placed reliance on the Supreme Court judgment in the case of Ganesh Shet v. Dr. C.S.G.K Setty and others (1988) 5 S.C.C 381) to strengthen his submission.

    24. Mr. V.N Kaura, the learned counsel appearing for defendant No. 4 submitted that the Court should not grant any relief to the plaintiff. In case, the plaintiff's prayer is granted and injunction order is made absolute, then it would be disastrous for defendant No. 4. Therefore, the injunction order be vacated.

    25. Mr. Kaura also submitted that in matters pertaining to public charitable trusts, the trust can function only through its trustees. In the instant case, no particular trustee was authorised by any resolution to act on behalf of the trust. He also submitted that even in cases of concluded contracts, it is always discretionary for the Courts to grant a decree of specific performance. In the facts and circumstances of this case the plaintiff is not entitled to any injunction. Reference was also made to the judgment in R. Venugopala Naidu and others v. Venkatarayulu Charities and others (AIR 1990 SC 444).

    26. In the rejoinder, Mr. O.P Khaitan, counsel for the plaintiff, reiterated that there was a concluded contract between the parties and the injunction order should be confirmed, otherwise irreparable harm and injury would be caused to the plaintiff. The offer vide letter dated 15.4.1998 was clearly accepted by the defendants vide letter dated 24.4.1998 and thereafter again a letter dated 26.5.1998 was sent by the plaintiff to the defendants. All terms and conditions were agreed between the parties and a concluded contract came into existence and thereafter only a formal agreement remained to be executed.

    27. He submitted that 10% amount was to be paid at the time of signing the agreement and balance 90% at the time of execution of the conveyance in favour of the plaintiff. The plaintiff has always been ready and willing to pay these amounts. As a matter of fact, the money was lying idle with the plaintiff as was indicated in the letter dated 26.5.1998 Mr. Khaitan also submitted that at the time of executing the conveyance or within three months after the agreement is signed means one and the same thing. After 37(I) form of I.T Act is submitted it takes two months statutory period before the sanction is accorded and sometime is required thereafter for the execution of the conveyance deed. In these circumstances, three months time was specified. Therefore, according to the plaintiff three months after the agreement is signed or signing at the time of conveyance deed means one and the same thing.

    28. Mr. Khaitan submitted that the plaintiffs nominees were 100% subsidiaries of the plaintiff. He also submitted that vide resolution dated 22.4.1997 the trustees authorised Mr. Robby Tulus and Mr. G.I Vishwanath to take necessary steps to sell the “Bonow House” which is owned by the trust. Therefore, the defendants wrongly submitted that no one was authorised by the trust to take steps for the sale of the aforesaid house.

    29. Mr. Khaitan referred to the letter dated 26.5.1998 sent by the plaintiff to the defendant trust. All terms of the defendants were agreed and a concluded contract came into existence between the parties. The letter dated 26.5.1998 reads as under:—

    J.K Industries Ltd.

    3 Bahadurshah Zafar Marg,

    New Delhi-110 002

    26.5.1998

    M/s International Co-op Alliance

    Domus Trust,

    Bonow House,

    43 Friends Colony (East)

    New Delhi 110 065

    Kind Attn: Mr Robby Tulus/Mr. Guo Yong Kang

    Dear Sirs,

    This has reference to your letter of 24th April, 1998 confirming sale of the above property to us.

    At the meeting with you and your Counsel Mr. V.P Singh on 16th May 1998 in the Office of our Solicitors O.P Khaitan & Co., we have discussed in detail the draft Agreement for Sale and the same was finalised. The resolution of the Trust shown to our Solicitors was not satisfactory and the draft of the proper resolution was handed over to you which was also approved by your Counsel. We now await copy of the resolution of the Trust which, though already passed, has to be again passed in a proper form. We request you to compete the formalities and execute the Agreement as soon as possible since the amount of earnest money to be paid to you on signing the Agreement for Sale is lying idle with us.

    Looking forward to hear from you soonest.

    Thanking you,

    Yours faithfully,

    for J.K INDUSTRIES LIMITED

    D.C JAIN”

    30. In view of the aforesaid letter the negotiations between the parties were concluded and all terms and conditions of the contract were finally agreed between the parties and a concluded contract came into existence between the parties and nothing really remained except to execute the formal document. The plaintiff agreed to purchase the land on “as is where is basis” including 360 sq. yards of excess land for which notification was issued but not actually acquired. By the conduct of parties a concluded contract came into existence and nothing remained after the aforesaid letter of 26.5.1998 except execution of the formal document between the parties.

    31. On consideration of the totality of the circumstances of the case prima facie, I am of the considered opinion that the prima facie case is in the favour of the plaintiff and the balance of convenience is also clearly in favour of the plaintiff. Consequently, the ad interim ex parte injunction is liable to be confirmed during the pendency of the suit. The injunction application filed by the plaintiff is allowed and disposed of. The defendants' application under Order 39, Rule 4 CPC is accordingly dismissed. The parties are directed to bear their own costs.

    32. The parties would be at liberty to file additional documents within 4 weeks, and the suit be listed for admission/denial of documents before the Joint Registrar on 21.7.1999 The Joint Registrar is directed to place the matter before the Court for framing of Issues immediately after the admission/denial of documents is concluded.

    Use AI to get other relevant cases.

    Comments

    J.K. Industries Limited v. International Cooperative Alliance Domus Trust
    (Mar 19, 1999)