  • Sections 14/17 of the Arbitration Act
  • Sections 30/33 of the Arbitration Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Sections 14/17 of the Arbitration Act
  • Sections 30/33 of the Arbitration Act
Smart Summary

Factual and Procedural Background

The petitioner’s tender dated 8.8.1979 for the construction of the Maternity Center at 48, Babar Road, New Delhi was accepted by the respondent, resulting in Agreement No. 7.ME (C-11)/79-80. The work was to commence on 15.9.1979 and be completed by 14.7.1980, but was actually completed on 17.9.1981. A security deposit of Rs. 24,567 was retained by the department. Disputes arising from the agreement were referred to arbitration, with the arbitrator delivering an award on 20.7.1992, granting the claimant/contractor Rs. 1,06,148.92 inclusive of pendente lite interest and additional interest at 15% per annum. The award was filed on 17.12.1992. The petitioner sought to make the award a rule of the Court under Sections 14 and 17 of the Arbitration Act, while the respondent NDMC filed objections under Sections 30 and 33 of the Act, which were opposed by the petitioner.

Legal Issues Presented

  1. Whether the arbitrator’s award on various claims made by the contractor, including claims for non-reimbursement of expenses, unwarranted reduction in agreement rates, escalation in cost due to delay, and withheld payments, was legally valid and free from illegality.
  2. Whether the rate of pendente lite interest awarded by the arbitrator was reasonable and justified.
  3. Whether the award should be made a rule of the Court with or without modification.

Arguments of the Parties

Petitioner’s Arguments

  • The petitioner filed an application under Sections 14 and 17 of the Arbitration Act to make the arbitrator’s award a rule of the Court.
  • The petitioner opposed the respondent’s objections to the award.
  • The petitioner contended that the delay in completing the work was due to breaches by the respondent.

Respondent’s Arguments

  • The respondent NDMC filed objections under Sections 30 and 33 of the Arbitration Act against the award.
  • The respondent was aggrieved particularly by claims Nos. 7, 10, 11, and 13 in the award.
  • The respondent contended that the rates were paid as per agreement and that the contractor was solely responsible for delay in completion of the contract.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Secy. Irrigation Deptt. Govt. of Orissa v. G.C Rai (1992) 1 SCC 508 Arbitrator’s power to award interest Confirmed that arbitrators have discretion to award interest in absence of contrary agreement.
Sudhir Bros. v. DDA (1996) 1 SCC 32 Arbitrator’s power to award interest Supported the discretionary power of arbitrator to grant interest.
Board Of Trustees For The Port Of Calcutta v. Engineers-De-Space-Age (1996) 1 SCC 516 Arbitrator’s power to award interest Reinforced the principle of arbitrator’s discretion in awarding interest.
State of Orissa v. B.N Agarwala (1997) 2 SCC 469 Arbitrator’s discretionary power to award interest Affirmed arbitrator’s authority to award interest unless agreement provides otherwise.
Ram Nath International Construction Pvt. Ltd. v. State Of U.P. (1997) 11 SCC 645 Discretionary power of arbitrator to award interest Held that awarding interest is within arbitrator’s discretion in absence of contrary stipulation.

Court's Reasoning and Analysis

The court examined each contested claim in the arbitrator’s award. For Claim No. 7 (foundation stone ceremony expenses), the arbitrator’s reduction of the claim due to lack of details was upheld as not illegal. For Claim No. 10 (unwarranted reduction in agreement rates), the court found the arbitrator’s acceptance of the contractor’s claim justified based on record materials. Regarding Claim No. 11 (escalation due to delay), the arbitrator reasonably reduced the claim after considering insufficient details and mutual responsibility for delay, supported by documentary evidence of delayed supply of drawings by the respondent. The court accepted the arbitrator’s apportionment of responsibility and the resulting award amount. For Claim Nos. 13 and 14 (wrongfully withheld payments), the arbitrator’s award including interest was supported by established precedent confirming arbitrators’ discretionary power to award interest. However, the court found the pendente lite interest rate of 33% per annum excessive and reduced it to 18% per annum as a reasonable rate. The court thus partly allowed the respondent’s objection on this point and otherwise dismissed all other objections, making the award a rule of the Court with the modification. The court also directed interest at 12% per annum from the date of decree till realization and ordered parties to bear their own costs.

Holding and Implications

The Court upheld the arbitrator’s award with a modification reducing the pendente lite interest rate from 33% to 18% per annum, and made the award a rule of the Court.

The direct consequence is that the claimant/contractor is entitled to recover the awarded sums along with interest at 18% per annum pendente lite and 12% per annum post-decree interest until realization. The parties bear their own costs. No new legal precedent was established; the decision primarily confirms the arbitrator’s discretion in awarding interest and the court’s supervisory role in moderating excessive interest rates.

    G.S Kalra v. New Delhi Municipal Committee And Another.

    M.S.A Siddiqui, J.— For the construction of the Maternity Center at 48, Babar Road, New Delhi, petitioner's tender dated 8.8.1979 was accepted by the respondent. An agreement No. 7.ME (C-11)/79-80 to that affect was executed between the parties. In terms of the agreement the work was to start on 15.9.1979 and was to be completed on 14.7.1980 But the work was completed on 17.9.1981 By way of security deposit a sum of Rs. 24567 remained deposited with the department. However, differences and disputes between the parties in respect of the said agreement were referred to the arbitrator, who gave his award on 20.7.92 The arbitrator has awarded a sum of Rs. 1,06,148.92 inclusive of pendente lite interest to the claimant/contractor. In addition, the arbitrator has also awarded interest @ Rs. 15% on the said amount. On 17.12.1992 arbitrator filed his award. Notice of filing of award was given to the parties. While the petitioner filed an application under Sections 14/17 of the Arbitration Act for making the award a rule of the Court, the respondent NDMC filed objections under Sections 30/33 of the Arbitration Act against the award, which have been opposed by the petitioner.

    2. The respondent is mainly aggrieved by the award under the claims No. 7, 10, 11 and 13.

    Claim No. 7:—The claimant/contractor preferred a claim of Rs. 15000/- on account of non re-imbursement of expenditure incurred on foundation stone ceremony. According to the arbitrator, the respondent had not denied the said claim. However, the arbitrator has reduced the claim to Rs. 2000/- on the ground of non-furnishing of details by the claimant/contractor. I do not find any illegality in the award under the said claim.

    3. Claim No. 10:—The claimant/contractor claimed a sum of Rs. 3,092.29 on account of unwarranted reduction in agreement rates. Learned counsel for the respondent contended that the rates had been worked out and paid to the contract as per relevant clause of the agreement. On a consideration of the material on record, the arbitrator came to the conclusion that the payment was made at the reduced rates as per details in Annexure J which was wholly unjustified. The arbitrator, therefore, allowed the said claim of the contractor. The arbitrator has assigned valid reasons for accepting the said claim of the contractor. In my opinion, the award under this head does not suffer from any illegality.

    4. Claim No. 11:—The contractor claimed a sum of Rs. 1,15,725/- on account of escalation in cost of material and labour for work done during extended period of the contract. The arbitrator has reduced the claim to Rs. 21714/- on the following grounds:

    (i) The claimant has not furnished the details of the price escalation of various items of material and labour.

    (ii) A compensation for delay in completion of work has been levied @ 2%. However, this is not the full in quantum as per agreement. This shows that causes for delay are attributable to both claimant and respondent. Under the circumstances an escalation @ 6% of Rs. 3,61,904/- which comes to Rs. 21,714/- is considered just and reasonable.

    5. It is undisputed that as per agreement, the work was to start on 15.9.1979 and was to be completed on 14.7.1980 However, the work was completed on 17.9.1981 There was, thus, overrunning of the contract for a period of nearly 14 months. Learned counsel for the contractor contended that completion of the work was delayed due to certain breaches committed by the respondent. On the contrary, learned counsel for the respondent submitted that the contractor was solely responsible for delayed performance of the contract. In this context, I may usefully refer to the respondent's Letter No. ME (C-11)/1802-5.D, dated 26.7.1980 (Annexure A(4) which shows that the following architectural and structural drawings were supplied to the contractor on the dates indicated against them:—

    (i) architectural drawings 6 Nos. 23.10.1979

    (ii) Structural drawing 2 Nos. 28.10.1979

    (iii) Structural drawing of col.1 No. 7.1.1980

    (iv) Structural drawings of slab and beams at I and IInd floor and structural designer of left pit 11.2.1980

    6. The letter further shows that drawing No. CA 2232 for steel windows etc, was sent on 26.7.1980 with an assurance to send other relevant drawings in due course. The contents of the said letter to a great extent probabilise the case of the contractor that the work was delayed due to non-furnishing of the complete drawings of the work by the respondent within a reasonable time. However, the arbitrator has held that only 30% of the work was done within the stipulated period and both the parties were responsible for delayed performance of the contract. Taking into consideration of the said fact, the arbitrator has awarded a sum of Rs. 21,714/- to the contractor. Having regard to the facts and circumstances of the case, no fault can be found with the said award of the arbitrator.

    7. Claim Nos. 13 and 14:—The arbitrator has awarded a sum of Rs. 26,337.63 to the contractor on the ground that some of the payments had been wrongfully withheld by the respondent. The arbitrator has also awarded future interest @ 15% per annum on the sum of the award. It is now well settled that the arbitrator has the power to award interest. (Secy. Irrigation Deptt. Govt. of Orissa v. G.C Rai (1992) 1 SCC 508; Sudhir Bros. v. DDA (1996) 1 SCC 32; Board Of Trustees For The Port Of Calcutta v. Engineers-De-Space-Age (1996) 1 SCC 516; State of Orissa v. B.N Agarwala (1997) 2 SCC 469. In Ram Nath International Construction Pvt. Ltd. v. State Of U.P. (1997) 11 SCC 645, it was held that the power to award interest is a discretionary power of arbitrator which can be exercised in absence of any stipulation to the contrary in the agreement between the parties.

    8. The arbitrator has awarded a sum of Rs. 79,811 to the claimant. In addition, the arbitrator has also awarded interest pendente lite @ 33% per annum amounting to Rs. 26,337.26 and future interest @ 18% per annum. In my opinion, the award of interest pendente lite @ 33% appears to be excessive. The reasonable rate of interest pendente lite should be 18% per annum. Consequently, the award of interest pendente lite is reduced to 18% per annum.

    9. For the foregoing reasons, the objection of the respondent against the award of pen-dente lite interest is partly allowed and the award is modified to the extent indicated above. Remaining objections against the award are disallowed. With the aforesaid modification in the award, it is made a rule of the Court. In addition, the claimant/contractor shall also be entitled to recover interest @ 12% per annum on the sum of the award from the date of decree till realisation. Parties shall bear their own costs. A decree be drawn up accordingly.

    Use AI to get other relevant cases.

    Comments

    G.S Kalra v. New Delhi Municipal Committee And Another.
    (Jul 1, 1999)